B09_AMENDMENT_P0002_0002.pdf

PDF 36 KB Posted

Attached to
AK-KODIAK ADMIN SITE-SOIL CLEAN-UP
Solicitation number
140FC126Q0023
Issued by

About this file

This is a Questions and Answers document for Amendment P0002 to the Kodiak Sheep Island Soil Clean Up contract. The document addresses five contractor inquiries regarding project requirements and specifications.

Key clarifications include: the period of performance extends from May 1, 2026 to August 30, 2027 (updated from the original June 30, 2026 end date); excavation restoration may be accomplished through sloping and grading without importing additional backfill, provided slopes remain below 10% and do not create hazards; compaction by placement equipment weight is acceptable rather than requiring in-situ testing to 95%; third-party utility locates are not necessary if the contractor conducts its own survey, with contractor responsibility for employee safety evaluation; and borings and wells may be located using GPS to submeter accuracy by field crew without requiring an Alaska Professional Land Surveyor to document final locations and elevations.

View the file

Other files

File Type Posted
Sol_140FC126Q0023_Amd_0002.pdf PDF
Sol_140FC126Q0023_Amd_0001.pdf PDF
B09_AMENDMENT_P0001_0001.pdf PDF
A04_PWS_UPDATED.pdf PDF
B03_WAGE_DETER_05-18-2026.pdf PDF
Sol_140FC126Q0023.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B09 AMENDMENT P0002-KODIAK SHEEP ISLAND SOIL CLEAN UP-QUESTION AND

ANSWERS

1. The SF1442 indicates a period of performance of 05/01/2026 – 06/30/2026. Please provide an update on the period of performance dates.

Answer: Thank you and POP end date is 8/30/2027

2. Is the requirement to import fill, or regrade removal areas without importing additional backfill?

Answer: Restoration of the excavation by sloping and grading the excavation limits would be acceptable. The restoration would need to ensure the slope is less than 10% and does not create a hazard.

3. Is in-situ compaction testing to 95% required or is compaction by the weight of placement equipment acceptable?

Answer: Compaction by the weight of placement equipment is acceptable.

4. Do to the remote location of this site and lack of infrastructure it is assumed no 3rd party locate is needed?

Answer: I am not aware of any infrastructure at this site. The contractor is required to protect their employees and shall take appropriate measures to ensure their safety.

Evaluation will be the responsibility of the contractor. If the contractor can conduct the survey, then a third party locate would not be necessary.

5. Can borings and wells be located via GPS to submeter accuracy by field crew, or is an AK PLS required to document final locations and elevations?

Answer: Yes, borings and wells can be located via GPS to submeter accuracy by field crew.