This Performance Work Statement (PWS) details a contract for hurricane debris removal at the J.N. "Ding" Darling National Wildlife Refuge on Sanibel Island, Florida. The project involves removing approximately 4 acres of non-vegetative debris generated by Hurricane Ian in September 2022, with specific constraints due to the sensitive mangrove wetland ecosystem. The contractor must manually remove construction materials, building fragments, and household items without using heavy equipment, and stage debris at the designated Gavin Site before proper disposal.
The contract is a fixed-price, best-value task order with a 90-day performance period. Key requirements include 100% debris removal, minimal ecosystem damage, manual handling techniques, and strict adherence to environmental protection protocols. The contractor must provide all personnel, tools, and supplies, maintain a comprehensive quality control plan, and ensure crew consistency. Work will be conducted Monday through Friday between 7:00 am and 5:00 pm, with weekend work requiring advance permission. Payment will be held until final inspection confirms complete and satisfactory debris removal, with potential penalties for non-compliance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FS325Q0076_Amd_0001.pdf | ||
| PAST_EXPERIENCE_REFERENCES.pdf | ||
| Sol_140FS325Q0076.pdf | ||
| B03_-_WD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PWS-QAP_FY25 Debris removal Debris Removal
United States Department of the Interior
FWS J N DING DARLING NWR
1 WILDLIFE DRIVE
SANIBEL FL 33957-3032
Performance Work Statement
Work Requirements for Hurricane Debris Cleanup
I. GENERAL INFORMATION
1.1 General:
This is a non-personal services contract to remove hurricane generated debris on select areas of the J.N. “Ding”
Darling National Wildlife Refuge. Debris includes portions of buildings and roofs and other construction materials that are in sensitive ecosystems. The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and non-personal services necessary to perform work services as defined in this Performance Work Statement except; for those items specified as government furnished property and services. The Contractor shall perform to the standards in this contract.
1.2 Introduction:
The Contractor shall remove and lawfully dispose of disaster-generated debris (other than hazardous materials and household putrescible garbage) from public property and public rights-of-ways immediately after a hurricane or other disaster. Debris from mangrove wetlands must be removed to minimize further damage to the sensitive ecosystem, the contract may not utilize heavy equipment or vehicles to access the debris field. The contractor must be capable of assembling, directing, and managing a work force that can complete the debris management operations in ninety (90) days or less.
1.3 Period of Performance:
The period of performance shall complete all work within 90 days (3 month) following issuance of the contract.
1.4 Place of Performance:
The work will be conducted on the J.N. “Ding” Darling NWR Complex located near Fort Myers, Florida.
Specifically work will be conducted on Sanibel Island at the locations identified on the map in Figures 1 and 2.
1.5 Pre-bid Site Visit:
Potential bidders are strongly encouraged to attend a pre-bid site visit hosted by the refuge. The meeting place will occur at the refuge’s Administration Building located at 1 Wildlife Drive, Sanibel, FL 33957 followed by a visit to the specified work site and disposal staging site. Dates and Time for pre-bid site visit will be provided at a later time.
1.6 Type of Contract:
This is a Fixed Price-Best Value contract/task order.
1.7 Security Requirements: n/a
1.8 Physical Security:
The Contractor shall be responsible for safeguarding all government equipment, information, and property provided for Contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.
1.9 Key Control (if applicable):
The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer.
In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the
Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the payment due the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the payment due the Contractor.
The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the
Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.
1.10 Post Award Conference/Periodic Progress Meetings:
The Contractor agrees to attend any post award conference or progress meetings convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The
Contracting Officer, Contracting Officers Representative (COR), Government/Site Representative (GR/SR), and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance and/or status of work. At these meetings, the Contracting Officer will apprise the Contractor of how the government views the Contractor's performance and the Contractor will apprise the Government of problems being experienced, if any. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.11. Contracting Officer Representative (COR)/Government/SR Representative (GR/SR):
The COR/SR will be identified by either separate letter or other form of notification. The COR/GR monitors all technical aspects of the contract and assists in contract administration. The COR/GR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract; conduct scheduled and unscheduled inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, and specifications; monitor Contractor performance and notify both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property and provide site entry of Contractor personnel. A letter of designation issued to the
COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
1.12 Key Personnel:
The following personnel are considered key personnel by the government: Contract Manager/Administrator, Project
Manager/Supervisor and Crew Supervisor. The Contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the Contracting Officer. The contract manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The Contractor shall supply a Crew Supervisor that is dedicated for the duration of the project to maintain project consistency. Crew Supervisor should be on site at all times when crew personnel are working. The Crew Supervisor and Project Manager functions can be the same individual.
1.13 Identification of Contractor Employees:
All Contract personnel will be required to obtain and wear badges (or company attire indicating name of company) in performance of this service. Contractor must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.
1.14 Data Rights (if applicable):
The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the
Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.15 Special Considerations
The project work area is located in challenging environmental conditions due to the area being located within sensitive mangrove wetlands and is surrounded by mosquito ditches and associated dredge spoil mounds on 3 sides.
The debris field is approximately 4 acres in size and is characterized by extremely soft soils due to the wetland nature of the area and the mosquito ditches act as obstacles from getting any type of motorized machinery into the debris field for clean-up operations. Examples of such motorized equipment include but are not limited to skidsteers, excavators of all sizes, UTVs/ATVs, and loader backhoe machinery. In addition to the barriers created to access by the mosquito ditches the very soft soils also hinder any kind of motorized machinery from accessing the site without causing irreparable damages to these sensitive soils and habitats. These limitations shall be taken into consideration by any potential bidding vendors.
II. Background
2.1 The purpose of this Request for Proposal (RFP) is to obtain proposals from qualified firms who are interested in providing Hurricane Debris Removal and Disposal from sensitive ecosystems. The storm generated debris primarily consists of the destroyed walls, roof, and other construction type debris that was blown into the refuge by the winds generated by Hurricane Ian in September 2022. The debris was initially discovered by refuge staff utilizing commercially available satellite imagery. The furthest extent of this debris field is approximately 0.11 miles from -the initial access point along Sanibel-Captiva Road. The debris field is in sensitive mangrove wetlands and is only accessible by foot from the Sanibel Captiva Road to the south approximately 0.08 miles. These sensitive wetlands are characterized by soft, muddy soils, spoil piles from previous mosquito ditching efforts, and several narrow and shallow waterways that bisect access into the debris field. The access from the road is limited due to a public multiple use trail that is heavily utilized by pedestrian, bicycle, and City of Sanibel public works employees. The access trail to the debris field is located adjacent to the Island Water Association’s, a public utility, sewage lift station. Due to these listed site conditions the ability of utilizing any heavy equipment to access the debris field is nearly impossible and therefore these constraints should be considered when bidding on this project. Additionally, the heavily utilized public trail system that runs parallel to Sanibel Captiva Road will hinder the ability for the contractor to place dumpsters for debris removal efforts.
III. Scope
3.1 Objective: The Contractor will provide all labor, equipment, and materials to perform debris removal and disposal service at the J.N. Ding Darling National Wildlife Refuge (NWR). Debris located within 4 acres of mangrove wetlands must be removed to minimize further damage to the sensitive ecosystem, no vehicle or heavy equipment may be used to remove the debris. No known hazardous materials exist in the debris piles.
3.2 Location of the Debris: J.N. “Ding” Darling NWR– any units designated for Debris removal See Map on Figure
1. The overall goal of this effort will be to remove 100% of all non-vegetation hurricane debris such as construction materials and household items. The debris field is approximately 4 acres in size with the majority of the large debris in several concentrated locations and smaller debris scattered over the site. Specific location is 26.441127° -
82.098423°
3.3 Work to Be Performed: The contractor shall remove all non-vegetative construction/household debris from the delineated area as shown in Figure 1. The work performed shall include but not limited to the cutting/bucking of construction type debris such as rafters, walls, flooring joists, carpeting, roofing materials and other materials typically found in home construction to a size that is manageable to handle by hand. Other debris that may be encountered and shall be disposed of by the contractor include but not limited to furniture, buckets, and housewares.
The Contractor can use the Gavin Site (Fig. 2.0), located approximately 0.90 miles to the east of the debris field, to stage debris before being disposed of offsite.
IV. Applicable Directives
4.1 Contractor must comply 100% with the agreed-upon plan of work. The deliverables listed in this section are the minimum desired from the successful Proposer.
4.2 The Contractor shall provide a Mobilization plan and Operating Plan/schedule a separate attachment to its response to this RFP.
4.3 The Contractor shall provide all personnel, labor, equipment, supplies, transportation, tools, materials, supervision, and other non-personal services necessary to perform the requirements of this contract order and shall plan, schedule, coordinate, and ensure effective performance of required services for the entire duration of contract.
The Contractor will be responsible for all unloading/loading operations. Movement of equipment in and around the treatment locations will be the sole responsibility of the contract applicators. All personnel and equipment to be used will be appropriately licensed and certificated as appropriate for the work to be done. The Contractor will be responsible for providing sufficient equipment, fuel (for equipment), safety items, spill response kit, personnel and their subsistence needs during the project period, as well as checking all work sites for hazards of any type which could affect their ability to accomplish the treatment project. NOTE: The Contractor is responsible for clearing debris within the delineated treatment area as specified by the Government Site Representative/COR only. NOTE:
The Contracting Officer reserves the right to require the Contractor to replace any operating personnel, or equipment used in the performance of this Contract if the personnel, or equipment are violating, or have violated, any state or federal laws; or are unsafe; or for any valid reason. In this event, the Contractor shall as soon as reasonably possible, upon written or verbal notice (to be later reduced to writing) from the Contracting Officer, provide replacements satisfactory to the Contracting Officer at no additional cost.
4.4 The Contractor will provide USFWS with contact information for all ground personnel, vehicles, and equipment, identification information (including make, model, color, name of company, and contact information) at least 48 hours before implementation of the project.
4.5 The Contractor will supply equipment to hauling heavy debris from sensitive wetland habitats. *NOTE: All equipment and personnel must be able to work at a semi-remote and semi-primitive site (i.e., no electrical or water hookups, bathrooms, or other facilities available).
4.6 No heavy equipment will be allowed to operate within the refuge units. During periods of extended wet weather or in areas with saturated soils, equipment cannot cause ruts greater than 4 inches deep. If work is prohibited by the
USFWS due to extended wet weather, negotiations may be made to lengthen the contract period.
4.7 The Contractor shall avoid damage to native vegetation and wildlife other than what is necessary to safely and effectively remove the debris. The Contractor shall not collect, harass, harm, or molest native plants or wildlife.
The Contractor shall avoid damage to sensitive archaeological sites such as Native American middens and shell mounds. The Contractor must use tools such as chainsaw, power saws, rakes, and loppers to removed vegetation in accordance with an approved operating plan. The Contractor shall be held liable if damage was determined to be the fault of the Contractor (negligence), the result of improper techniques, or the result of Contractor controlled activities.
4.8 The Contractor shall be responsible for the removal of all trash and related equipment. The Contractor (or their representatives) will not litter and shall police and dispose of all litter at the end of each workday. Litter violations will be handled under Federal Code of Regulations 50CFR27.94(a), which carries fines ranging from $100.00 -
$500.00 per incident upon conviction.
4.9 Work performance shall be defined as 100% of identified non-vegetative debris within the 4 acre location for the
Acceptance Criteria (AC) achieved. If the AC is not met, it shall be the responsibility of the Contractor to sweep the area for additional debris until the control rate is achieved at no additional cost to the Government (FWS).
4.10 Public Safety: It shall be the responsibility of the Contractor to ensure the safety of the public when conducting all phases of the work specifications. Public safety must be ensured when removing debris. Refuges are heavily visited by the public. The Refuge shall advise the Contractor of any public use hazards. It shall be the ultimate responsibility of the Contractor to initiate operations. 4.11 All Contractor employees performing work directly onsite must adhere to all local regulations, rules, policies relating to the obtainment of proper clearances from various regulatory agencies. If applicable, the Contractor must complete background investigation, computer security, and records management training. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures including but limited to OSHA, 29 CFR 1910 (as applicable).
4.12 The Contractor is responsible for acquiring and maintaining all federal, state and local licenses, certification, and permits as or if determined to be required. The Contractor is required to submit a copy of the licenses to the
Contracting Officer prior to the pre-award meeting.
V. Performance Requirements
5.1.1 Remove 100% of non-vegetation debris as identified in the performance work statement and work requirements document and achieve no less than 100% of all construction and household debris.
5.1.2 The Contractor shall canvass 100% of the 4-acre area and remove 100% of all debris encountered. The Crew or Project Supervisor shall be responsible for notifying the COR/SR upon completion of the operation so that the area may be inspected.
5.1.3 Handling and Disposal: All debris shall be removed from the 4-acre location, staged on the refuge at the
Gavin Site (see Figure 2), and then hauled off and disposed of properly. The transport and legal disposal of this debris is the sole responsibility of the contractor and must comply with local and state regulations/ordinances.
5.1.4 Special Conditions: Weather and site conditions may interfere with the work completion schedule negotiated at the award conference. The Contracting Officer may halt work at any time upon written notice for conditions beyond the control of the contractor. If this result in significant time lost, the completion date for the project can be re-negotiated by the CO/COR/SR and the Contractor.
VI. Work time/Hours of duty
6.1 Work will not be performed on the following holidays: New Year's Day, Martin Luther King Jr. Day, President's Day, Memorial Day, Fourth of July, Labor Day, Columbus Day, Veteran's Day, Thanksgiving, and
Christmas.
6.2 Hours of Operation: The Contractor is responsible for conducting business, between the hours of 7:00 am and
5:00 pm, minimum of 40 hours/week, Monday thru Friday (lieu day) except Federal holidays or when the
Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Weekend work will require permission, in advance, from the site COR. The Contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential especially with regards to the Crew Supervisor.
VII. Supplies, Materials, Equipment, and Utilities
NOTE: As a government agency dedicated to “working with others to conserve, protect and enhance fish, wildlife, and plants and their habitats for the continuing benefit of the American people,” the U.S. Fish and Wildlife Service
(FWS) strives to incorporate the most ecologically sound and environmentally beneficial technologies, materials, and practices into all aspects of planning and operations. To help achieve this mission and meet Executive Orders
(EOs) and Department of the Interior (DOI) planning requirements, the FWS has implemented strategies to reduce the environmental impacts associated with procurement, lease acquisition, waste prevention and recycling, facility design, construction, operation and management, contracting and permitted commercial visitor services. These strategies have been collectively referred to as the FWS’s Green Procurement and Waste Prevention & Recycling
Program (Greening Program) and are a part of the FWS’s overall approach to environmental management.
7.1 Government-Furnished Property and Services. The Government will provide the Contractor with the following items:
7.1.1 Services/Supply: none
7.1.2 Facilities: none
7.1.3 Utilities: none
7.1.4 Equipment: none
7.1.5 Materials: none
7.2 Supplies, Materials, and Equipment: to be provided by the Contractor
VIII. Supervision
8.1 On-site Supervision: In order to ensure performance and accomplishment of the work as outlined herein, the
Contractor shall provide adequate and competent supervision at all times for all work to be accomplished by the
Contractor’s employees. An on-site supervisor, with the ability to speak and understand English clearly, and with the authority to act for the Contractor on a day-to-day basis and to sign inspection reports and all other correspondence on behalf of the Contractor, shall be present at the work site at all times when contract work is in progress, unless a contractor employee can act on the supervisor’s behalf. When contract work is in progress, supervisory personnel shall be available at all times to receive notices, reports, or requests from the Refuge Manager, COR/GR or his authorized representative. At no time shall Government representatives direct or supervise the activities of the
Contractor’s employees.
8.2. Supervisory Responsibilities. Supervisory responsibilities shall include, but shall not be limited to, the following:
8.2.1 Providing an adequate labor force; this includes the immediate replacement of personnel dismissed for cause or leaving employment of their own volition.
8.2.2 Ensuring that Contractor personnel are properly trained to perform their assigned work in a proper, safe, and efficient manner, and ensuring that the proper supplies, materials, and equipment are on hand.
8.2.3 Taking action to prevent general carelessness by employees and/or abuse of facilities or equipment.
8.2.4 Establishing an effective and comprehensive safety program.
8.2.5 Indoctrinating employees to report fire, hazardous conditions, maintenance deficiencies, and graffiti.
IX. Contractor Personnel Qualifications
9.1 Supervisory Personnel. All supervisory employees engaged in directing the work to be accomplished under this contract shall possess, at least with-in the last two years of recent, (within the past four years) experience in directing the subject service-type operations in a supervisory capacity for projects of the approximate size/scope under this contract.
X. Deliverables
Deliverables and Reports (Includes any hardware, software, or data items)
10.1 Frequent reporting/accounting of overall progress and (to-date) expenditures (i.e. 25%, 50%, 90%) or as determined by the Government/Site Representative.
10.2 Coordination, application, and wrap-up meetings.
10.3 Work plan to include schedule.
10.4 Safety/spill response plan.
10.5 A government representative will inspect all areas periodically during the contract period and will perform a final inspection of all areas 30 days following treatments.
10.6 Copies of all task order invoices (signed by the Contractor Crew Supervisor/Site Manager) shall be submitted to the FWS Site Manager agreed upon by the Government and the Contractor. Invoices shall be submitted no more frequently than on a monthly basis.
DELIVERABLES SCHEDULE
(This technical exhibit lists any reports or documentation that are required as a deliverable and includes the frequency, # of copies, medium/format and who/where it is to be submitted. A deliverable is anything that can be physically delivered but may include non-physical things such as meeting minutes.)
Deliverable Frequency # of Copies Medium/Format Submit To
Routine reporting/accounting of progress and (to-date) expenditures
25%, 50%, 90%
1 Hard/soft copy in MS
Word or Excel format
Government
Representative/Manager
Daily logs to document work
Recorded daily;
submitted bi-weekly
1 Hard/soft copy in MS
Word or Excel format
Government
Representative/Manager
Coordination, application, and wrap-up meetings
As directed by the
COR/SR
n/a Meeting Government
Representative/Manager
XI. PRS Attachments/Technical Exhibit Listings
(The Contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.)
Performance Objective
(The Service required—usually a shall statement)
Standard Performance Threshold
(This is the maximum error rate. It could possibly be
“Zero deviation from standard”)
Method of
Surveillance
PRS # 1.
The Contractor shall comply with work production/work schedule(s) except for Excusable Delays.
Perform work as scheduled/workers onsite as scheduled.
100% compliance Daily log/100%
Inspection
PRS # 2
The Contractor shall comply with all work requirements and standards as indicated within the
Performance Work Statement and
Work Requirements document.
Adhering to all contract terms and conditions. No infractions.
100% compliance
100%
Inspection
PRS # 3
The Contractor shall remove
100% of non-vegetative debirs, Adhere to Performance Work Statement standards. No infractions.
100% compliance
100%
Inspection
PRS # 4
The Contractor shall not damage government resources, fish, wildlife, and/or property when onsite.
No reportable violations or carelessness 100% compliance 100%
Inspection
PRS # 5
The Contractor shall document, report and clean up, according to
State standards, and dispose of material, any chemical or fuel spills – a Spill Prevention and
Containment Plan must be present on site at all times.
Adhere to Performance Work Statement standards. No infractions. No reportable violations or carelessness
100% compliance 100%
Inspection
PRS # 6
The Contractor shall maintain
Crew Supv. and crew consistency.
Adhere to Performance Work Statement standards. No infractions.
100% compliance
100%
Inspection
PRS # 7
The Contractor shall implement
‘Decontamination’ (BMPs) protocols prior to and after completing work.
Adhere to Performance Work Statement standards. No infractions.
100% compliance
100%
Inspection
PRS # 8
The Contractor shall remove all trash (daily) and debris
(completion) generated during the execution of contract performance.
Adhere to Performance Work Statement standards. No infractions. No reportable violations or carelessness
100% compliance 100%
Inspection
PRS # 9
The Contractor shall maintain a
Quality Control Plan and immediately disclose/report any problems.
Quality Control Plan completed/enforced 100% compliance 100%
Inspection
XII. Quality Assurance Plan
11.1 The Contractor shall institute a complete quality-control program to ensure that the requirements of this contract are provided, as specified. The overall goal of the program should be to identify and correct any problems that may exist before they are identified by or reported to the Refuge Manager (RM), Contracting Officer’s
Representative (COR), or Government/Site Representative (GR/SR). This will aid in ensuring the contractor meets time schedules, adheres to standard commercial practices, and complies with the Performance Work Statement
(PWS) in an efficient, ethical, and productive manner. As a minimum, the program shall include:
11.1.1 An inspection system covering all the services required under Section V (Performance Requirements) with a comprehensive checklist to be used to inspect contract performance during scheduled and unscheduled inspections, and the name(s) of the individuals who will be performing the inspections.
11.1.2 A file of all inspections conducted by the Contractor and corrective actions taken (at Contractor’s expense).
This should include follow-up inspections to ensure that corrective action was appropriate, complete, and timely.
This documentation shall be organized in a logical manner, kept current, and made available to the COR or GR/SR and the Contracting Officer (CO) during the term of the contract.
11.1.4 When notified of a deficiency, items designated as unsatisfactory or below standard shall be re-performed by
Contactor at no additional cost to the Government. All corrective action must be completed by the next working day of notification of the deficiency. If not, a deduction may be made (as determined from the applicable month’s invoice). Failure for the Government to notify the Contractor of a deficiency does not relieve the Contractor of the obligation to perform services nor does it relieve the Contractor of the responsibility to ensure that quality control measures are adhered to for contract compliance.
11.2 Performance Indicators and Acceptable Quality Levels:
11.2.1 Comply with work production/work schedule(s) except for Excusable Delays. 100% compliance
11.2.2 Comply with all work requirements and standards as indicated within the PWS. 100% compliance
11.2.3 Comply with all Performance Requirements (PR) and PR Standards. 100% compliance
11.2.4 Comply with all contract terms and conditions. 100% compliance
11.2.5 Cause no damage to government resources, fish, wildlife, and/or property. 100% compliance with no deviations
11.2.6 Maintain safety of workers and work environment at all times. 100% compliance with no deviations
11.2.7 Maintain a Quality Control Plan and immediately disclose/report any problems. 100% compliance with no deviations
11.2.8 Ensure all equipment is in good working order during the entire period of performance and safeguard the use and storage of all chemicals. 100% compliance with no deviations
11.2.9 The Contractor shall Remove 100% of debris from the delineated project area as identified via maps 100% compliance with no deviations
11.2.10 The Contractor shall maintain crew continuity for the duration of the project. 100% compliance
11.2.11 The Contractor shall document, report, and clean up all spills, and dispose of any hazardous material including chemicals and fuels according to State standards. A Spill Prevention and Containment safety plan must be present on site at all times. 100% compliance
11.2.12 The Contractor shall complete and provide to the COR or GR/SR all Daily Report data sheets for the duration of the project. 100% compliance with no deviations
11.2.13 The Contractor shall remove all trash (daily) and debris (completion) generated during the execution of contract performance. 100% compliance
11.2.14 Additional Performance Requirement Standards other than those identified above may be listed in individual task orders. The Contractor agrees to perform to all work standards. 100% compliance.
11.3 Acceptance Criteria:
11.3.1 The task shall be considered completed following a thorough inspection of the delineated treatment area by the COR, or GR/SR, and only if it is determined that the Contractor removed 100% of all non-vegetative debris within the delineated treatment area, 100% of the treatment area. If determined that the Contractor did not remove or 100% of all debris following the initial event, any additional removal shall be performed at the Contractor’s expense. 100% compliance with no deviations
11.4 Surveillance Methods:
11.4.1 Regularly scheduled inspection/review of work
11.4.2 Unscheduled site inspections to document project progress
11.4.3 Inspection of materials, equipment, and chemicals. The CO/COR/SR reserves the right to inspect, at any time upon notice to the Contractor, the Contractor’s procedures, tools and equipment, and other ancillary equipment, and operating personnel. Inspection, however, shall not relieve the Contractor of any obligation or responsibilities, nor shall it transfer any liability to the Refuge.
11.4.4 Communication via electronic means: e-mail, text or telephone
11.4.5 Contractor logs and reports
11.5 Payment (s):
11.5.1 In general, entire payment will be held until final inspection (unless otherwise agreed upon by all parties at the pre-award conference with concurrence of the CO) by refuge staff to determine effects on target vegetation to ensure work standards and acceptance criteria have been achieved. Inspection by staff shall occur in 45 days or less, dependent upon weather. Following final inspection and concurrence of the COR or SR, the Contractor may submit their invoice for payment. If the Contractor is negligent in achieving desired acceptance standards, the Contractor shall implement re-treatments at their own expense within 2 months of notification by the COR/SR. Payment will be withheld until the desired results are achieved.
11.5.2 Partial payments, in certain circumstances, may be negotiable as determined by the Site Manager or COR with concurrence of the CO.
11.6 Incentives:
11.6.1 Non-compliance with the PWS or contract will result in negative performance evaluation/rating.
11.6.2 A positive performance rating will be given for overall satisfactory work and compliance related to the contract.
Figure 1. Map of Debris Clearing area.
Figure 2. Map of Debris removal area and Gavin Site staging area
Gavin Site Staging area
Debris removal site
File details come from the government source that posted it. Updated .