A04_PWS_Bassie_Spring_Enclosure_and_Development.docx

DOCX document 12 MB Posted

Attached to
BASSIE SPRING IMPROVEMENT PROJECT
Solicitation number
140L3926Q0049
Issued by

About this file

This is a Performance Work Statement (PWS) for the Bassie Spring Habitat Improvement Project, a habitat restoration initiative managed by the Bureau of Land Management in Churchill County, Nevada. The contractor must complete all work within 60 days of receiving notice to proceed, with project completion required by October 30, 2027. The project is located in the Desatoya Mountains near Fallon, Nevada, approximately two hours from the nearest full support community.

The contractor is responsible for furnishing all labor, tools, materials, and equipment to complete four primary components: removal and disposal of a defunct spring diversion structure, pipeline, and trough; installation of 650 feet of pipe rail fence to protect the spring riparian area; installation of a new spring diversion box with gravel pack, PVC pipe, float valve, and trough; and transportation of materials from the Carson City District Office to the project site. Specific construction requirements include steel pipe rail fence with top rails at 38.5 inches and bottom rails at 18.5 inches above ground, posts spaced 12 feet apart and set minimum 30 inches into the ground, a spring box installed below the spring head surrounded by pea-sized gravel pack, and 175 feet of one-inch PVC pipe buried at least 18 inches underground connecting to an approximately 625-gallon poly stock trough. The contractor must adhere to strict environmental and cultural resource protection standards, including weed control procedures, archaeological site avoidance, fire prevention protocols, and prohibition of ground blading or cross-country travel on muddy terrain. Payment will be made upon invoice submission for work completed to identified standards, with fencing invoicing to identify linear feet of fence constructed.

View the file

Other files

File Type Posted
Sol_140L3926Q0049.pdf PDF
B03_Davis-Bacon_Act_WD___NV20260070_dated_7_30_2026.pdf PDF
Bid_Schedule_L3926Q0049.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bassie Spring Habitat Improvement Performance Work Statement 7/1/2026

PURPOSE

Work performed under this project includes furnishing labor and equipment to implement the following components:

· Removal and disposal of defunct spring diversion structure, pipeline, and trough.

· Bassie Spring Fence: purchase and installation of 650 ft of pipe rail fence to protect the Spring riparian area from cattle and allow wildlife access.

· Purchase and installation of spring diversion box, gravel pack, PVC pipe, float valve, and new trough.

Additionally, this PWS includes transporting material from the Carson City District Office to the project site.

LOCATION, COORDINATES & ACCESSIBILITY

The project area is located in the Desatoya Mountains, in Churchill County, Nevada (Figure 1). The project is on land managed by the Bureau of Land Management.

Site
Coordinates (UTM’s 11

Datum NAD 1983) Legal Description

Bassie Spring
443810 m E 4367257 m N
SENE Section 01, Township 18 N,

Range 38 E

The nearest full support community to the project is Fallon, NV. Average travel time from Fallon to the project sites is ~2 hours. The Contractor shall be held liable and is responsible for any damages caused by their personnel and/or equipment to any improved and unimproved road, ditch, culverts, signs, or survey monuments.

BOUNDARIES/WORK LAYOUT

The Bureau of Land Management (BLM) will set flags or fence posts within site distance to give the Contractor lines and angles necessary to execute the work specified under contract award. The Contractor shall, immediately upon entering the project site for the purpose of beginning work, locate all reference marks and take such actions to prevent their destruction. Changes in the location or the construction of any portion of the fences can only be made if agreed upon by both the contractor and the Contracting Officer.

SCHEDULE/PROGRESS OF WORK

The period of performance will be 60 days from the notice to proceed, and all project activities should be completed before October 30, 2027. If work is scheduled to begin before September 1, 2027, provide the BLM Contracting Officer’s Representative with 14 days' notice before breaking ground to perform a migratory bird clearance survey. A mobilization plan and invoice for approval will be submitted to BLM no later than September 15, 2027.

PRE-WORK CONFERENCE

The Pre-Work Conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date, and place to review required work, project drawings, specifications, construction schedules, payroll, payments and administrative provisions of the contract. The Contractor and subcontractors or their authorized representatives and the persons responsible for coordination of the work shall be present at the meeting. The Contractor shall be prepared to present the work schedule and summarize and explain work procedures planned for the project. Should the contractor need to delay the project beyond what is presented in the pre-work conference, then the contractor should notify the Contract Officers Representative (COR) immediately.

Mobilization Plan A document outlining how equipment and personnel will access the site will be submitted to BLM for review.

Progress Meetings Progress meetings may be held at the project site, in Fallon or Carson City, NV or where necessary or as determined by the Contracting Officer (CO). Progress meetings may be requested by CO, COR, or the Contractor. The request shall state who should attend and include an agenda.

Final Inspection The final inspection will be held at the project site, as determined by the COR. The Contractor shall notify the COR in writing and by phone at least three working days before the completion date so the Government can schedule final inspection. The Contactor or the Contractor’s authorized representative shall be present during the final inspection. The Contractor shall be held liable and is responsible for any damages caused by their personnel and/or equipment to any improved and unimproved road, ditch, culverts, signs, or survey monuments.

CAMPING/STAGING

Camping will be allowed during project implementation at the project site or other location if approved by the COR. All fire regulations and permits shall be followed. All garbage and refuse shall be removed from the camp site by the contractor within one day of camp abandonment. Toilet facility requirements shall follow all Federal and State regulations. Final payment will be reserved subject to inspection of these sites.

CONTRACTOR FURNISHED ITEMS

The Contractor will provide all tools, material, equipment, and labor necessary to transport and complete the work as specified in the contract. This includes all fence material, spring box, PVC pipe, float valve, and trough. The Contractor shall be responsible for safely loading, transporting, and off-loading material at the project site in good working condition. The Contractor is liable for any loss or damage of materials during transport, and until the fences are constructed. The contractor will be responsible for disposing of scrap material. Extra material belongs to BLM and will be transported back to the Carson City District Office.

STATE OR FEDERAL AGENCY FURNISHED ITEMS

The BLM will install a wildlife escape ramp.

BASSIE SPRING EXCLOSURE CONSTRUCTION SPECIFICATIONS

Pipe Rail Fence:

Construction of steel pipe rail continuous enclosure fence (Figure 3). See attached document titled, Exhibit A_Typ Post and Rail Fence Drawing, for example.

Pipe Rails:

The top of the top rail should be installed 38.5 inches (±2 inches; no more than 40.5 inches and no less than 36.5 inches above ground). The top of the bottom rail must be installed 18.5 inches (±2 inches; no more than 20.5 inches and no less than 16.5 inches above ground).

Rails must be secured to each other and to post (i.e. couplers should join rails at posts and should not be installed free floating between posts).

Posts: Post should be spaced 12 feet apart (±1 ft) apart.

Posts shall be set 30 inches into the ground so that the top of the top rail will 38.5 inches (±2 inches; no more than 40.5 inches and no less than 36.5 inches) above ground. Pound, auger, drill, and/or concrete steel line posts into the ground a minimum of 28 inches deep.

If the post cannot be pounded to the specified 30 inches, then a hole must be dug and the post concreted with a minimum of one 60-pound bag of concrete and firmly seated in the ground at a depth no less than 18 inches. When the ground is too moist to allow for proper curing of concrete, a concrete forming tube will be used and filled with two 60-pound bags of concrete.

If the post must be cut due to a natural obstruction (rock), the post must be seated no less than 28 inches below the grounds surface and concreted flush to the grounds surface. If the necessary depth of 28 inches cannot be achieved, the contractor should use a rotary hammer to drill a hole 28 inches deep and approximately 2 inches in diameter to fit a piece of pipe that will support the post. This supporting pipe should have an outside diameter of no less than 1 5/8 inches and should be epoxied with masonry epoxy into the obstruction. The pipe supporting the post should rise 18.5 inches above the grounds surface and tech screwed to the respective post a minimum of 4 times using one inch tech screws.

Corner, end, and gate posts: All corners/angles, end posts, and gate posts will be concreted and firmly seated in the ground at a minimum of 30 inches. If the required depth of 30 inches cannot be achieved the post should be cut at a depth no less than 28 inches, so that the top of the bottom rail will achieve the correct 18.5-inch distance from the ground and concreted flush to the ground’s surface. Any open pipe ends will be capped permanently to prevent access to birds or other wildlife.

When angles are encountered that prevent rail from easily passing through line posts and terminating at corners two fence rail ends should be bolted together to produce an articulating joint/flexible elbow. These caps will be fastened to the two respective pipe rail ends with tech screws. All non-corner angles shall have 2 posts (one on each fence side) within 4 feet of ends/flexible elbow joint.

Water Crossings and depressions When encountering water crossings and depressions the post and rail should adhere to the standards described above (i.e. posts set 30” in ground, top rail = 38.5 inches, bottom rail = 18.5 inches), with continuous rail paralleling the ground so not to allow livestock under or over fence. Use articulating joint/flexible elbow when necessary. When water crossings and depressions are encountered that are either inundated with standing water or are expected to be inundated with standing water do not install posts in the water. If necessary, use additional posts on either side of the standing water to maintain spacing between posts of less than 12 ft.

Spring Development: Refer to Figure 2, Project Site Detail.

Spring Box Installation: Contractor will supply a spring box diversion structure, stock trough, 175 feet of 1” PVC pipe (including any necessary PVC couplers), float shut-off valve, and 2 cubic yards of pea gravel pack for the spring box. Contractor will install the spring box by digging it into the ground just below the spring head and filling and surrounding the box with a gravel (pea-sized) pack. The gravel pack will be placed at least one foot below the bottom of the spring box and at a one-foot radius surrounding the box on the uphill side. For an example spring box, see the Spring Development Kit Water Collection System – COMPLETE – Steep in the Woods and shown in the Spring Box Attachment. A spring diversion structure like this or approved equal is required.

Pipeline to Stock Trough: The 1” PVC pipe will be connected to the outlet port of the spring box, and the pipe will be run approximately 175 feet downhill to the trough. The spring box outlet port and pipeline will be installed below grade to prevent freezing. The pipe will be buried at least 18” below ground and connected to the inlet port on the bottom of the stock trough. The trough and pipeline shall be situated so that the inlet port to the trough is entirely below grade to prevent freezing. The trough will be placed downhill from the spring to the east, but on the west side of the two-track road (same side as the spring).

Stock Trough and Float Valve: The trough should be round, poly, 8’ diameter, approximately 625-gallon capacity, with inlet port on the bottom (Figure 4). A float valve will be installed on the stock trough inlet port to shut off flow when the water level reaches the fill line in the trough.

Environmental Considerations Blading or Scraping: No blading or scraping of the ground along the fence line or on any BLM administered land is permitted. Access roads shall not be constructed along fence lines or to the job sites, but overland travel along the fence line is permitted.

Rocky and Uneven Terrain: Rocky and uneven terrain exist along portions of the fence line, and it is recommended that interested vendors inspect the site before offering a quote.

Cross-Country Travel: No cross-country travel with motorized vehicles shall take place when ground is muddy causing ruts to form. The vendor shall repair all ruts and scarred ground created by construction, repair, or removal as directed by the Contracting Officer or the COR.

Specific areas may be flagged that designate sensitive areas due to archaeological sites, wildlife nesting areas, sensitive plant species, spring areas, etc. The Government may pose restrictions to other operations in these areas.

STANDARD OPERATING PROCEDURES

Weed Control - Contractor will ensure all vehicles moved onto public or private land are free of soil, seeds, and vegetative matter or other debris that could contain or hold seeds. Contractor will employ whatever cleaning methods are necessary to ensure compliance and will notify the BLM prior to moving vehicles. Notification will include identifying the location of the vehicle’s most recent operations.

Cultural Resource Protection - Locations of known historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology, and culture, such as settler or Indian artifacts need to be avoided by the Contractor. Because fragile and irreplaceable culture resources may be present in the area, project activities and any other action which cause disturbance of the earth's surface shall be limited to those areas approved by the BLM and by the state. Deviations from routes flagged or shown on the drawings are not allowable without prior approval of the project manager. The vendor shall ensure that the vendor, employees, or representatives do not collect archaeological artifacts. Should the condition of the cultural resources in the area be altered during construction due to unauthorized activity by the vendor or employees, the vendor shall be responsible for all costs of mitigating the cultural resources involved. If destruction of the archaeological sites is found to be occurring during the construction phase, work on the project shall be terminated until a data recovery plan is prepared and completed in accordance with the National Historic Preservation Act and the State Historic Preservation Office.

Fire Prevention/Suppression -Vegetation occurring in the Great Basin can be highly flammable. Under dry and windy weather conditions the potential for a fire to start is high. The risk of wildfire is year-round. Be extra careful when working on or around the dry grasses. Check under vehicles when parking off road.

The Contractor will, independently and in cooperation with the Government, take all reasonable action to prevent and suppress fires on the project. Independent initial action will be prompt and will include the use of all personnel and equipment available in the project area.

Emergency Reporting Requirements:

1. 911 (initial call for all emergencies)

2. Sierra Front Dispatch Center: 775-883-5995 (wildland fire emergency line)

Information needed in reporting a wildland fire would include: Location: Geographical reference and if possible, Latitude/longitude coordinates. Description on what the fire is doing size, spread, color of smoke, etc.

BLM may require emergency measures, including the necessary shutting down of equipment or portions of operations during periods of high fire danger.

The holder of this permit may be held liable for any and all costs should a wildland fire occur caused by the activities associated with the construction, maintenance, or operation of this project. Fire trespass action might be initiated, and wildfire suppression costs may be collected from the holder of this permit.

BID SUBMISSION

Please see attached Bid Schedule.

PAYMENT AND INVOICING

Payment will be made for work completed to identified standards and timeframes upon submitting an invoice to the BLM Contract Administrator. Fencing invoicing should identify the number of linear feet of fence constructed/installed.

Figure 1. Project site.

Figure 2. Project site detail.

Figure 3. Example of pipe rail fence to be installed at Haypress and Dalton Canyon..

image2.png image3.jpeg image4.png image1.png