This file contains site location maps, aerial imagery, diagrams and photos related to a Small Arms Firing Range (SAFR) at the Kulm Wildlife Management District (WMD) in North Dakota. The documentation provides detailed information about the firing range layout and specifications for remediation work.

The site maps and diagrams show a firing range with a 108-foot long backstop berm that is 38 feet wide at the base and 10 feet high. The shooting line is approximately 79 feet wide, with target boards positioned 75 feet from the shooting line and 6 feet from the face of the berm. The contractor is required to remove and test contaminated soil from the berm face (including 3 feet on either side of target boards), conduct grid sampling across 25 distinct areas of the range, recover bulk lead through sieving, and properly dispose of contaminated materials. The aerial imagery shows the range location relative to Kulm, ND and includes maintenance facilities and support structures visible in 2004 ground photos showing target frames and shooting positions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1 – Google Earth Location Map and Site Map

Attachment 2 – Range and Berm Plan and Elevations

Berm Plan (Not to Scale)

Back Stop - 108 Feet Length Estimated

Back Stop

38 Feet Base Estimated

Back Side of Berm Front of Berm

10 Feet Height Estimate

38 Feet At Base Estimate

The contractor shall assume the face of the berm is contaminated with lead including three feet on either side of the target boards. The contractor shall conduct testing to determine if additional soils on the edge are contaiminated.

The contractor will remove three feet from the face of the berm and recover bulk lead by sieve. Soils shall be tested to determine level of contamination and proper disposal. Bulk lead will be recycled.

After the first three feet of soil has been removed from the face of the berm, the contractor shall test the face of the berm to identify if additional material shall be removed. The contractor will provide a cubic yard cost for any additional soils that are required to be removed. Note: Follow-up sampling will be required if additional material is removed from the face.

Face of Berm

79 Feet Estimated Shooting Line

Contractor shall make a grid and conduct random sampling of shooting range for contamination. The grid area shall be a minimum of Twenty-Five (25) distinct areas sampled. The contractor will provide a proposed sampling plan. Note: The Target Board Line is wider than the 79-foot estimated shooting line.

6 Feet Estismate between Taret Boards and Face of Berm

Target Boards

75 Feet estimated distance

Shooting Line

Attachment 3 – Photos of Site from 2004