A04_ATTACHMENT_001_-_STATEMENT_OF_WORK.pdf

PDF 2 MB Posted

Attached to
MACA-REHAB ENTRANCE SIGNS/PARKING AREAS
Solicitation number
140P5326R0006
Issued by

About this file

Project Specifications Summary

This document is a 100% construction specification package for the Parking Lot and Monument Sign Renovations project at Mammoth Cave National Park in Mammoth Cave, Kentucky. The project is identified by PMIS Numbers 323725, 325833, 323722, 325832, 323654, and 325829, prepared by Walker Architects and HMB Professional Engineers, Inc. The specifications are organized into 16 divisions covering procurement, general requirements, concrete, masonry, metals, thermal and moisture protection, finishes, and civil work including earthwork, pavement, sidewalks, storm sewer, seeding, and erosion control.

The project requires comprehensive construction services including site preparation, demolition, concrete placement (cast-in-place and precast), masonry work, metal fabrications, exterior painting, asphalt concrete pavement installation with base and surface courses, concrete sidewalk and driveway construction, storm sewer pipeline installation with appurtenances, grading, and landscape restoration through seeding and sod installation. Key execution requirements include construction staking by a licensed Kentucky surveyor, quality testing and inspection during earthwork operations, compaction certification, mandrel testing of storm sewer lines, pavement smoothness verification using straightedges, protection and curing of concrete work, erosion control with immediate seeding and mulching, and final cleanup and restoration. The contractor bears responsibility for utility location and protection, dewatering, record documentation, shop drawing submissions with engineer approval before fabrication, and maintenance of all constructed surfaces through project warranty periods.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MAMMOTH CAVE NATIONAL PARK

MAMMOTH CAVE, KY

PARKING LOT AND MONUMENT SIGN RENOVATIONS

MACA

PMIS Number 323725, 325833

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE (NPS)

DENVER SERVICE CENTER (DSC)

323722, 325832 323654, 325829

WA22065-16 Mammoth Cave Monument Sign Renovations 100% Construction Documents May 24, 2024 Walker Architects

WA22065-16

Seals Page 00 0107 - 1

SECTION 00 0107

SEALS PAGE

ARCHITECT:

JOE WALKER, AIA

KY ARCHITECTURAL LICENSE NO: 8781

RESPONSIBLE FOR DIVISIONS 01-14 SECTIONS EXCEPT WHERE INDICATED AS PREPARED

BY OTHER DESIGN PROFESSIONALS OF RECORD.

CIVIL ENGINEER:

DAVID K. BROWN, PE

KY CIVIL ENGINEERING LICENSE NO: 34543

RESPONSIBLE FOR SECTIONS 01000 - 02999.

END OF SECTION

6/28/2024

100% Construction Documents

May 24, 2024

Walker Architects

WA22065-16

Table of Contents

00 0110 - 1

SECTION 00 0110

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

A. 00 0107 - Seals Page

B. 00 0110 - Table of Contents

SPECIFICATIONS

2.01 DIVISION 01 -- GENERAL REQUIREMENTS

A. 01 1000 - Summary

B. 01 2000 - Price and Payment Procedures

C. 01 2500 - Substitution Procedures

D. 01 3000 - Administrative Requirements

E. 01 3216 - Construction Progress Schedule

F. 01 4000 - Quality Requirements

G. 01 4216 - Definitions

H. 01 5000 - Temporary Facilities and Controls

I. 01 6000 - Product Requirements

J. 01 6116 - Volatile Organic Compound (VOC) Content Restrictions

K. 01 7000 - Execution and Closeout Requirements

L. 01 7419 - Construction Waste Management and Disposal

M. 01 7800 - Closeout Submittals

N. 01 7900 - Demonstration and Training

2.02 DIVISION 02 -- EXISTING CONDITIONS

A. 02 4100 - Demolition

2.03 DIVISION 03 -- CONCRETE

A. 03 3000 - Cast-in-Place Concrete

B. 03 4500 - Precast Architectural Concrete

2.04 DIVISION 04 -- MASONRY

A. 04 2000 - Unit Masonry

B. 04 4313 - Stone Masonry Veneer

2.05 DIVISION 05 -- METALS

A. 05 5000 - Metal Fabrications

2.06 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES (NOT USED)

2.07 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

A. 07 7000 - Fastener Schedule

B. 07 9200 - Joint Sealants

2.08 DIVISION 08 -- OPENINGS (NOT USED)

2.09 DIVISION 09 -- FINISHES

A. 09 9113 - Exterior Painting

100% Construction Documents

May 24, 2024

Walker Architects

WA22065-16

Table of Contents

00 0110 - 2

2.10 DIVISION 10 -- SPECIALTIES (NOT USED)

2.11 DIVISION 11 -- EQUIPMENT (NOT USED)

2.12 DIVISION 12 -- FURNISHINGS (NOT USED)

2.13 DIVISION 13 -- SPECIAL CONSTRUCTION (NOT USED)

2.14 DIVISION 14 -- CONVEYING EQUIPMENT (NOT USED)

2.15 DIVISION 21 -- FIRE SUPPRESSION (NOT USED)

2.16 DIVISION 22 -- PLUMBING (NOT USED)

2.17 DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC) (NOT USED)

2.18 DIVISION 25 -- INTEGRATED AUTOMATION (NOT USED)

2.19 DIVISION 26 – ELECTRICAL (NOT USED)

3.01 CIVIL SPECIFICATIONS

A. 01055 – Construction Staking

B. 01340 – Shop Drawings

C. 01562 – Dust Control

D. 01610 – Transportation & Handling

E. 01630 – Substitution and Options

F. 01710 – Cleaning

G. 01720 – Record Documents

H. 02010 – Subsurface Conditions

I. 02140 – Dewatering

J. 02200 – Earthwork

K. 02255 – Crushed Stone and Dense Graded Aggregate

L. 02510 – Asphalt Concrete Pavement

M. 02523 – Concrete Sidewalk and Driveway

N. 02720 – Storm Sewer

O. 02933 – Seeding

P. 02957 – Erosion Control & Stabilization

SECTION 01055

CONSTRUCTION STAKING

PART 1 GENERAL

1.1 SCOPE

A. Construction staking shall include all the surveying work required to layout the Work and control the location of the finished construction. The full responsibility for holding to grade shall rest upon the CONTRACTOR. All work under this Contract shall be constructed in accordance with the lines and grades on the Drawings or as given by the ENGINEER or OWNER.

B. The OWNER will not provide benchmark or baseline adjacent to the work site.

The CONTRACTOR shall be responsible for setting BM and baseline and offsets from these points and all other layout, staking and all other surveying required for the Work.

C. The CONTRACTOR shall safeguard all points, stakes, grade marks, bench marks and monuments established on the Work, shall bear the cost of re-establishing same if disturbed and shall assume the entire expense of rectifying work improperly constructed due to failure to maintain and protect such established points, stakes and marks.

D. Measurement of quantities for payment purposes which are different from Drawing dimensions is included in the Work.

1.2 QUALITY ASSURANCE

A. The CONTRACTOR shall furnish documentation prepared by a surveyor currently registered in the State of Kentucky confirming that staking is being done to the lines and grades shown in the Contract Documents. This requires that the CONTRACTOR hire, at the CONTRACTOR's own expense, a currently registered surveyor, acceptable to the OWNER, to provide ongoing confirmation of construction staking.

B. Any deviations from the Drawings shall be confirmed by the ENGINEER prior to construction.

C. Written certification of sub-base grades by a licensed surveyor, is required.

E. Quantities for payments measured under this Contract shall be certified by the approved currently registered surveyor.

PART 2 PRODUCTS

2.1 EQUIPMENT

01055-2CONSTRUCTION STAKING

A. The CONTRACTOR shall furnish and use surveying equipment and supplies maintained in good working order.

PART 3 EXECUTION

3.1 FINAL GRADES

A. Any variance with plan grades shall be identified by the surveyor and confirmed by the ENGINEER.

3.2 STORM DRAINAGE

A. Storm drain lines and drainage structure bases shall be correctly located to yield the drainage structure top locations and orientations shown on the Drawings.

SECTION 01340

SHOP DRAWINGS AND PRODUCT DATA

PART 1 GENERAL

1.1 SCOPE

A. The work under this Section includes submittal to the Engineer of shop drawings, product data and samples required by the various sections of these Specifications.

B. Submittal Contents: The submittal contents required are specified in each section.

C. The following forms shall be used for all major components of the work:

1. Typical Maintenance Summary Form

2. Notice of Start of Manufacturing

3. Notice of Shipment of Equipment

4. Notice of Schedule Impact

The forms are included at the back of this section.

D. Definitions: Submittals are categorized as follows:

1. Shop Drawings

a. Shop drawings shall include technical data, drawings, diagrams, procedure and methodology, performance curves, schedules, templates, patterns, test reports, calculations, instructions, measurements and similar information as applicable to the specific item for which the shop drawing is prepared.

b. Provide newly-prepared information, on reproducible sheets, with graphic information at accurate scale (except as otherwise indicated) or appropriate number of prints hereof, with name or preparer (firm name) indicated. The Contract Drawings shall not be traced or reproduced by any method for use as or in lieu of detail shop drawings. Show dimensions and note which are based on field measurement. Identify materials and products in the work shown.

Indicate compliance with standards and special coordination requirements. Do not allow shop drawing copies without appropriate final "Action" markings by the Engineer to be used in connection with the Work.

c. Drawings shall be presented in a clear and thorough manner. Details shall be identified by reference to sheet and detail, specification section, schedule or room numbers shown on the Contract Drawings.

d. Minimum assembly drawings sheet size shall be 24 x 36-inches.

e. Minimum detail sheet size shall be 8-1/2 x 11-inches.

f. Minimum Scale:

(1) Assembly Drawings Sheet, Scale: 1-inch = 30 feet.

(2) Detail Sheet, Scale: 1/4-inch = 1 foot.

01340 - 2

2. Product Data

a. Product data includes standard printed information on materials, products and systems, not specially prepared for this Project, other than the designation of selections from among available choices printed therein.

b. Collect required data into one submittal for each unit of work or system and mark each copy to show which choices and options are applicable to the Project. Include manufacturer's standard printed recommendations for application and use, compliance with standards, application of labels and seals, notation of field measurements which have been checked and special coordination requirements.

3. Samples

a. Samples include both fabricated and un-fabricated physical examples of materials, products and units of work, both as complete units and as smaller portions of units of work, either for limited visual inspection or, where indicated, for more detailed testing and analysis.

b. Provide units identical with final condition of proposed materials or products for the work. Include "range" samples, not less than three units, where unavoidable variations must be expected, and describe or identify variations between units of each set. Provide full set of optional samples where the Engineer's selection is required. Prepare samples to match the Engineer's sample where indicated. Include information with each sample to show generic description, source or product name and manufacturer, limitations and compliance with standards. Samples are submitted for review and confirmation of color, pattern, texture and "kind" by the Engineer. Engineer will note "test" samples, except as otherwise indicated, for other requirements, which are the exclusive responsibility of the Contractor.

4. Miscellaneous submittals related directly to the Work (non-administrative) include warranties, maintenance agreements, workmanship bonds, project photographs, survey data and reports, physical work records, statements of applicability, quality testing and certifying reports, copies of industry standards, record drawings, field measurement data, operating and maintenance materials, overrun stock, security/protection/safety keys and similar information, devices and materials applicable to the Work but not processed as shop drawings, product data or samples.

1.2 SPECIFIC CATEGORY REQUIREMENTS

A. General: Except as otherwise indicated in the individual work sections, comply with general requirements specified herein for each indicated category of submittal.

Submittals shall contain:

1. The date of submittal and the dates of any previous submittals.

01340 - 3

2. The Project title.

3. Numerical submittal numbers, starting with 1.0, 2.0, etc. Revisions to be numbered 1.1, 1.2, etc.

4. The Names of:

a. Contractor

b. Supplier

c. Manufacturer

5. Identification of the product, with the Specification section number, permanent equipment tag numbers and applicable Drawing No.

6. Field dimensions clearly identified as such.

7. Relation to adjacent or critical features of the Work or materials.

8. Applicable standards, such as ASTM or Federal Specification numbers.

9. Notification to the Engineer in writing, at time of submissions, of any deviations on the submittals from requirements of the Contract Documents.

10. Identification of revisions on resubmittals.

11. An 8 x 3-inch blank space for Contractor and Engineer stamps.

12. Contractor's stamp, initialed or signed, certifying to review of submittal, verification of products, field measurements and field construction criteria and coordination of the information within the submittal with requirements of the Work and of Contract Documents.

13. Submittal sheets or drawings showing more than the particular item under consideration shall have all but the pertinent description of the item for which review is requested crossed out.

1.3 ROUTING OF SUBMITTALS

A. Submittals and routine correspondence shall be routed as follows:

1. Supplier to Contractor (through representative if applicable)

2. Contractor to Engineer

3. Engineer to Contractor

4. Contractor to Supplier

1.4 ADDRESS FOR COMMUNICATIONS

A. Engineer: HMB Professional Engineers, Inc.

3 HMB Circle, US 460 Frankfort, KY 40601

(502) 695-9800 FAX (502) 695-9810

01340 - 4

PART 2 PRODUCTS

2.1 SHOP DRAWINGS

A. Unless otherwise specifically directed by the Engineer, make all shop drawings accurately to a scale sufficiently large to show all pertinent features of the item and its method of connection to the Work.

B. Submit all shop assembly drawings, larger than 11 x 17-inches, in the form of one reproducible transparency with two opaque prints or bluelines.

C. Submit all shop drawings, 11 x 17-inches and smaller, in the form of six opaque prints or bluelines.

D. One reproducible for all submittals larger than 11 x 17-inches and no more than three prints of other submittals will be returned to the Contractor.

2.2 MANUFACTURER'S LITERATURE

A. Where content of submitted literature from manufacturers includes data not pertinent to this submittal clearly indicates which portion of the contents is being submitted for the Engineer's review.

B. Submit the number of copies which are required to be returned (not to exceed three) plus three copies which will be retained by the Engineer.

2.3 SAMPLES

A. Samples shall illustrate materials, equipment or workmanship and established standards by which completed work is judged.

B. Unless otherwise specifically directed by the Engineer, all samples shall be of the precise article proposed to be furnished.

C. Submit all samples in the quantity which is required to be returned plus one sample which will be retained by the Engineer.

2.4 COLORS

A. Unless the precise color and pattern is specifically described in the Contract Documents, wherever a choice of color or pattern is available in a specified product, submit accurate color charts and pattern charts to the Engineer for review and selection.

B. Unless all available colors and patterns have identical costs and identical wearing capabilities, and are identically suited to the installation, completely describes the relative costs and capabilities of each.

01340 - 5

PART 3 EXECUTION

3.1 CONTRACTOR'S COORDINATION OF SUBMITTALS

A. Prior to submittal for the Engineer's review, the Contractor shall use all means necessary to fully coordinate all material, including the following procedures:

1. Determine and verify all field dimensions and conditions, catalog numbers and similar data.

2. Coordinate as required with all trades and all public agencies involved.

3. Submit a written statement of review and compliance with the requirements of all applicable technical Specifications as well as the requirements of this Section.

4. Clearly indicate in a letter or memorandum on the manufacturer's or fabricator's letterhead, all deviations from the Contract Documents.

B. Each and every copy of the shop drawings and data shall bear the Contractor's stamp showing that they have been so checked. Shop drawings submitted to the Engineer without the Contractor's stamp will be returned to the Contractor for conformance with this requirement.

C. The Owner may backcharge the Contractor for costs associated with having to review a particular shop drawing, product data or sample more than two times to receive a "No Exceptions Taken" mark.

D. Grouping of Submittals

1. Unless otherwise specifically permitted by the Engineer, make all submittals in groups containing all associated items.

2. No review will be given to partial submittals of shop drawings for items which interconnect and/or are interdependent. It is the Contractor's responsibility to assemble the shop drawings for all such interconnecting and/or interdependent items, check them and then make one submittal to the Engineer along with Contractor's comments as to compliance, non-compliance or features requiring special attention.

E. Schedule of Submittals: Within 30 days of Contract award and prior to any shop drawing submittal, the Contractor shall submit a schedule showing the estimated date of submittal and the desired approval date for each shop drawing anticipated. A reasonable period shall be scheduled for review and comments. Time lost due to unacceptable submittals shall be the Contractor's responsibility and some time allowance for resubmittal shall be provided. The schedule shall provide for submittal of items which relate to one another to be submitted concurrently.

01340 - 6

3.2 TIMING OF SUBMITTALS

A. Make all submittals far enough in advance of scheduled dates for installation to provide all required time for reviews, for securing necessary approvals, for possible revision and resubmittal, and for placing orders and securing delivery.

B. In scheduling, allow sufficient time for the Engineer's and FSD review following the receipt of the submittal.

3.3 REVIEWED SHOP DRAWINGS

A. Engineer Review

1. Allow a minimum of 14 days for the Engineer's initial processing of each submittal requiring review and response, except allow longer periods where processing must be delayed for coordination with subsequent submittals. The Engineer will advise the Contractor promptly when it is determined that a submittal being processed must be delayed for coordination. Allow a minimum of two weeks for reprocessing each submittal. Advise the Engineer on each submittal as to whether processing time is critical to progress of the Work, and therefore the Work would be expedited if processing time could be foreshortened.

2. Acceptable submittals will be marked "No Exceptions Taken". A minimum of three copies will be retained by the Engineer for Engineer's and the Owner's use and the remaining copies will be returned to the Contractor.

3. Submittals requiring minor corrections before the product is acceptable will be marked "Make Corrections Noted". The Contractor may order, fabricate and ship the items included in the submittals, provided the indicated corrections are made. Drawings must be resubmitted for review and marked "No Exceptions Taken" prior to installation or use of products.

4. Submittals marked "Amend and Resubmit" must be revised to reflect required changes and the initial review procedure repeated.

5. The "Rejected " notation is used to indicate products which are not acceptable. Upon return of a submittal so marked, the Contractor shall repeat the initial review procedure utilizing acceptable products.

6. Only three (3) copies of items marked "Amend and Resubmit" and "Rejected " will be reviewed and marked. One copy will be retained by the Engineer, one copy will be retained by the Owner and the other copy with all remaining unmarked copies will be returned to the Contractor for resubmittal.

B. No work or products shall be installed without a drawing or submittal bearing the "No Exceptions Taken" notation. The Contractor shall maintain at the job site a complete set of shop drawings bearing the Engineer's stamp.

C. Substitutions: In the event the Contractor obtains the Engineer's approval for the use of products other than those which are listed first in the Contract Documents, the Contractor shall, at the Contractor's own expense and using methods approved by the Engineer, make any changes to structures, piping and electrical work that may be necessary to accommodate these products.

01340 - 7

D. Use of the "No Exceptions Taken" notation on shop drawings or other submittals is general and shall not relieve the Contractor of the responsibility of furnishing products of the proper dimension, size, quality, quantity, materials and all performance characteristics, to efficiently perform the requirements and intent of the Contract Documents. The Engineer's review shall not relieve the Contractor of responsibility for errors of any kind on the shop drawings. Review is intended only to assure conformance with the design concept of the Project and compliance with the information given in the Contract Documents. The Contractor is responsible for dimensions to be confirmed and correlated at the job site. The Contractor is also responsible for information that pertains solely to the fabrication processes or to the technique of construction and for the coordination of the work of all trades.

3.4 RESUBMISSION REQUIREMENTS

A. Shop Drawings

1. Revise initial drawings as required and resubmit as specified for initial submittal, with the resubmittal number shown.

2. Indicate on drawings all changes which have been made other than those requested by the Engineer.

B. Project Data and Samples: Resubmit new data and samples as specified for initial submittal, with the resubmittal number shown.

SECTION 01562

DUST CONTROL

PART 1 GENERAL

1.1 SCOPE

A. Limit blowing dust caused by construction operations by applying water or employing other appropriate means or methods to maintain dust control, subject to the approval of the OWNER. This may require the use of a water wagon as needed to suppress dusty conditions.

1.2 PROTECTION OF ADJACENT PROPERTY

A. The Bidders shall visit the site and note the buildings, landscaping, roads, parking areas and other facilities near the Work site that may be damaged by their operations. The CONTRACTOR shall make adequate provision to fully protect the surrounding area and will be held fully responsible for all damages resulting from CONTRACTOR's operations.

B. Protect all existing facilities (indoors or out) from damage by dust, fumes, spray or spills (indoors or out). Protect motors, bearings, electrical gear, instrumentation and building or other surfaces from dirt, dust, welding fumes, paint spray, spills or droppings causing wear, corrosion, malfunction, failure or defacement by enclosure, sprinkling or other dust palliatives, masking and covering, exhausting or containment.

SECTION 01610

TRANSPORTATION AND HANDLING

PART 1 GENERAL

1.1 SCOPE

A. The CONTRACTOR shall provide transportation of all equipment, materials and products furnished under these Contract Documents to the Work site. In addition, the CONTRACTOR shall provide preparation for shipment, loading, unloading, handling and preparation for installation and all other work and incidental items necessary or convenient to the CONTRACTOR for the satisfactory prosecution and completion of the Work.

B. All equipment, materials and products damaged during transportation or handling shall be repaired or replaced by the CONTRACTOR at no additional cost to the Owner prior to being incorporated into the Work.

1.2 TRANSPORTATION

A. All equipment shall be suitably boxed, crated or otherwise protected during transportation.

B. Where equipment will be installed using existing cranes or hoisting equipment, the CONTRACTOR shall ensure that the weights of the assembled sections do not exceed the capacity of the cranes or hoisting equipment.

C. Small items and appurtenances such as gauges, valves, switches, instruments and probes which could be damaged during shipment shall be removed from the equipment prior to shipment, packaged and shipped separately. All openings shall be plugged or sealed to prevent the entrance of water or dirt.

1.3 HANDLING

A. All equipment, materials and products shall be carefully handled to prevent damage or excessive deflections during unloading or transportation.

B. Lifting and handling drawings and instructions furnished by the manufacturer or supplier shall be strictly followed. Eyebolts or lifting lugs furnished on the equipment shall be used in handling the equipment. Shafts and operating mechanisms shall not be used as lifting points. Spreader bars or lifting beams shall be used when the distance between lifting points exceeds that permitted by standard industry practice.

C. Under no circumstances shall equipment or products such as pipe, structural steel, castings, reinforcement, lumber, piles, poles, etc., be thrown or rolled off of trucks onto the ground.

D. Slings and chains shall be padded as required to prevent damage to protective coatings and finishes.

SECTION 01630

Substitutions and Options

PART 1 GENERAL

1.1 SCOPE

This Section outlines the restrictions and requirements for substitutions, product and manufacturer options, and construction method options.

1.2 DEFINITIONS

A. For the purposes of these Contract Documents, a "substitute item" shall be defined as one of the following:

1. A product or manufacturer offered as a replacement to a specified product or manufacturer.

2. A product or manufacturer offered in addition to a specified product or manufacturer.

B. For the purposes of these Contract Documents, a "substitute construction method" shall be defined as one of the following:

1. A mean, method, technique, sequence or procedure of construction offered as a replacement for a specified mean, method, technique, sequence or procedure of construction.

2. A mean, method, technique, sequence or procedure of construction offered in addition to a specified mean, method, technique, sequence or procedure of construction.

1.3 GENERAL

A. An item or construction method, which is offered where no specific product, manufacturer, mean, method, technique, sequence or procedure of construction is specified or shown on the Drawings, shall not be considered a substitute and shall be at the option of the CONTRACTOR, subject to the provisions in the Contract Documents for that item or construction method.

B. For products specified only by a referenced standard, the CONTRACTOR may select any product by any manufacturer, which meets the requirements of the Specifications, unless indicated otherwise in the Contract Documents.

01630-2

C. If the manufacturer is named on the Drawings or in the Specifications as an acceptable manufacturer, products of that manufacturer meeting all requirements of the Specifications and Drawings are acceptable.

D. Whenever the ENGINEER’S design is based on a specific product of a particular manufacturer, that manufacturer will be shown on the Drawings and/or listed first in the list of approved manufacturers in the Specifications. Any Bidder intending to furnish products of other than the first listed manufacturer, or furnish substitute items, shall

1. Verify that the item being furnished will fit in the space allowed, perform the same functions and have the same capabilities as the item specified.

2. Include in its Bid the cost of all accessory items which may be required by the other listed substitute product,

3. Include the cost of any architectural, structural, mechanical, piping, electrical or other modifications required, and

4. Include the cost of required additional work by the ENGINEER, if any, to accommodate the item.

1.4 APPROVALS

A. Approval, of a substitution as an acceptable manufacturer, of the ENGINEER is dependent on determination that the product offered

1. is essentially equal in function, performance, quality of manufacture, ease of maintenance, reliability, service life and other criteria to that on which the design is based, and

2. will require no major modifications to structures, electrical systems, control systems or piping systems.

1.5 SUBSTITUTIONS AND OPTIONS

A. See Bid Schedule for allowance of substitutions.

B. After Notice to Proceed

1. Substitute items will be considered for acceptable manufacturers in the Specification.

2. Where items are specified by referenced standard or specified as indicated in Article 1.3, Paragraph A. above, such items shall be submitted to the ENGINEER for review.

01630-3

3. The CONTRACTOR shall submit shop drawings on the substitute item for the ENGINEER’S review in accordance with the Section 01340.

C. Prior to Opening of Bids

1. No consideration or approvals will be made for products specified by a referenced standard, or specified as indicated in Article 1.3, Paragraph A.

above. Such consideration may occur only after the Notice to Proceed.

2. No consideration or approvals will be made for products being offered where the term "equal to" precedes the name of an approved product. Such substitution consideration may occur only after the Notice to Proceed.

SECTION 01710

CLEANING

PART 1 GENERAL

1.1 SCOPE

A. This Section covers the general cleaning which the Contractor shall be required to perform both during construction and before final acceptance of the Project unless otherwise shown on the Drawings or specified elsewhere in these Specifications.

1.2 QUALITY ASSURANCE

A. Daily, and more often if necessary, conduct inspections verifying that requirements of cleanliness are being met.

B. In addition to the standards described in this Section, comply with all pertinent requirements of governmental agencies having jurisdiction.

1.3 HAZARDOUS MATERIAL AND WASTE

A. The Contractor shall handle hazardous waste and materials in accordance with applicable local, state, and federal regulations. Waste shall also be disposed of in WFPA approved landfills as applicable.

B. The Contractor shall prevent accumulation of wastes which create hazardous conditions.

C. Burning or burying rubbish and waste materials on the site shall not be allowed.

D. Disposal of hazardous wastes or materials into sanitary or storm sewers shall not be allowed.

1.4 DISPOSAL OF SURPLUS MATERIALS

A. Unless otherwise shown on the Drawings, specified or directed, the Contractor shall legally dispose off the site all surplus materials and equipment from demolition and shall provide suitable off-site disposal site, or utilize a site designated by the Owner.

PART 2 PRODUCTS

2.1 CLEANING MATERIALS AND EQUIPMENT

A. Provide all required personnel, equipment and materials needed to maintain the specified standard of cleanliness.

01710-2

2.2 COMPATIBILITY

A. Use only the cleaning materials, methods and equipment which are compatible with the surface being cleaned, as recommended by the manufacturer of the material or as approved by the Engineer.

PART 3 EXECUTION

3.1 PROGRESS CLEANING

A. General

1. Do not allow the accumulation of scrap, debris, waste material and other items not required for construction of this Work.

2. At least each week, and more often if necessary, completely remove all scrap, debris and waste material from the job site.

3. Provide adequate storage for all items awaiting removal from the job site, observing all requirements for fire protection and protection of the environment.

B. Site

1. Daily, and more often if necessary, inspect the site and pick up all scrap, debris and waste material. Remove all such items to the place designated for their storage.

2. Restack materials stored on site weekly.

3. At all times maintain the site in a neat and orderly condition which meets the approval of the Engineer.

3.2 FINAL CLEANING

A. General: Prior to completion of the Work, remove from the job site all tools, surplus materials, equipment, scrap, debris and waste. Conduct final progress cleaning as described in 3.01 above.

B. Site: Unless otherwise specifically directed by the Engineer, hose down all paved areas on the site and all public sidewalks directly adjacent to the site; rake clean other surfaces of the grounds. Completely remove all resultant debris.

C. Post-Construction Cleanup: All evidence of temporary construction facilities, haul roads, work areas, silt fences, structures, foundations of temporary structures, stockpiles of excess or waste materials, or any other evidence of construction, as directed by the Engineer.

D. Restoration of Landscape Damage: Any landscape feature damaged by the Contractor shall be restored as nearly as possible to its original condition at the Contractor's expense. The Engineer will decide what method of restoration shall be used.

01710-3

E. Timing: Schedule final cleaning as approved by the Engineer to enable the Owner to accept the Project.

3.3 CLEANING DURING OWNER'S OCCUPANCY

A. Should the Owner occupy the Work or any portion thereof prior to its completion by the Contractor and acceptance by the Owner, responsibilities for interim and final cleaning of the occupied spaces shall be as determined by the Engineer in accordance with the Supplementary Conditions of the Contract Documents.

SECTION 01720

RECORD DOCUMENTS

PART 1 GENERAL

1.1 SCOPE

A. The work under this Section includes, but is not necessarily limited to, the compiling, maintaining, recording and submitting of project record documents as herein specified.

B. Record documents include, but are not limited to:

1. Drawings;

2. Specifications;

3. Change orders and other modifications to the Contract;

4. ENGINEER field orders or written instructions, including Requests for

Information (RFI) and Clarification Memorandums;

5. Reviewed shop drawings, product data and samples;

6. Test records.

C. The CONTRACTOR shall maintain on the Project site throughout the Contract Time an up to date set of Record Drawings.

1.2 MAINTENANCE OF DOCUMENTS AND SAMPLES

A. Storage

1. Store documents and samples in the CONTRACTOR's field office, apart from documents used for construction.

2. Provide files and racks for storage of documents.

3. Provide locked cabinet or secure storage space for storage of samples.

B. File documents and samples in accordance with format of these Specifications.

C. Maintenance

1. Maintain documents in a clean, dry, legible condition and in good order.

2. Do not use record documents for construction purposes.

3. Maintain at the site for the OWNER one copy of all record documents.

D. Make documents and samples available at all times for inspection by ENGINEER.

E. Failure to maintain the Record Documents in a satisfactory manner may be cause for withholding of a certificate for payment.

1.3 QUALITY ASSURANCE

A. Unless noted otherwise, Record Drawings shall provide dimensions, distances and coordinates to the nearest 0.1 foot.

01720 - 2

B. Unless noted otherwise, Record Drawings shall provide elevations to the nearest

0.1 foot for all pertinent items constructed by the CONTRACTOR.

1.4 RECORDING

A. Label each document "PROJECT RECORD" in neat, large printed letters.

B. Recording

1. Record information concurrently with construction progress.

2. Do not conceal any work until required information is recorded.

1.5 RECORD DRAWINGS

A. Record Drawings shall be reproducible, shall have a title block indicating that the drawings are Record Drawings, the name of the company preparing the Record Drawings, and the date the Record Drawings were prepared. The CONTRACTOR will be provided paper sepias of the Drawings, or it may elect to provide reproducible drawings via another method. Reproducible shall be defined as being translucent so as to allow a blueline print to be produced.

B. Legibly mark drawings to record actual construction, including:

1. All Construction

a. Changes of dimension and detail.

b. Changes made by Requests for Information (RFI), field order, clarification memorandums or by change order.

c. Details not on original Drawings.

2. Site Improvements, Including Underground Utilities

a. Horizontal and vertical locations of all exposed and underground storm piping, utilities and appurtenances, both new facilities constructed and those utilities encountered, referenced to permanent surface improvements.

b. Location of and dimensions of roadways and parking areas, providing dimensions to back of curb when present.

c. The locations shall be referenced to at least two easily identifiable, permanent landmarks (e.g., power poles, valve markers, etc.) or benchmark..

1.6 SPECIFICATIONS

A. Legibly mark each section to record:

1. Manufacturer, trade name, catalog number, and supplier of each product and item of equipment installed.

01720 - 3

2. Changes made by Requests for Information (RFI), field order, clarification memorandums, or by change order.

1.7 SUBMITTAL

A. At contract closeout, deliver Record Documents to the ENGINEER for the

OWNER.

B. Accompany submittal with transmittal letter, in duplicate, containing:

1. Date

2. Project title and number

3. CONTRACTOR's name and address

4. Title and number of each record document

5. Signature of CONTRACTOR or CONTRACTOR's authorized representative

SECTION 02010

SUBSURFACE CONDITIONS

PART 1 GENERAL

1.1 DESCRIPTION

A. Investigation: The CONTRACTOR shall visit the site and become acquainted with site conditions. Prior to bidding, prospective CONTRACTORS may make their own site and subsurface investigations to satisfy themselves with site and subsurface conditions. The CONTRACTOR shall be responsible for obtaining rights of ingress and egress to private property for site and subsurface investigation and shall assume all responsibility for any damage to property caused as a result of the CONTRACTOR's investigation.

B. A geotechnical investigation has NOT been performed on this site

SECTION 02140

DEWATERING

PART 1 GENERAL

1.1 SCOPE

A. This Section shall apply to all excavation, except trench excavation.

B. Construct all permanent work in areas free from water. Design, construct and maintain all dikes, levees, cofferdams and diversion and drainage channels as necessary to maintain the areas free from water and to protect the areas to be occupied by permanent work from water damage. Remove temporary works after they have served their purpose.

C. The CONTRACTOR shall be responsible for the stability of all temporary and permanent slopes, grades, foundations, materials and structures during the course of the Contract. Repair and replace all slopes, grades, foundations, materials and structures damaged by water, both surface and subsurface, to the lines, grades and conditions existing prior to the damage, at no additional cost to the OWNER.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 CARE OF WATER

A. Except where the excavated materials are designated as materials for permanent work, material from required excavation may be used for dikes, levees, cofferdams and other temporary backfill.

B. Furnish, install, maintain and operate necessary pumping and other equipment for dewatering the various parts of the work and for maintaining the foundation and other parts free from water as required for constructing each part of the work.

C. Install all drainage ditches, sumps and pumps to control excessive seepage on excavated slopes, to drain isolated zones with perched water tables and to drain impervious surfaces at final excavation elevation.

D. Dewater by means which will ensure dry excavations, preserve final lines and grades, do not disturb or displace adjacent soil.

E. All pumping and drainage shall be done with no damage to property or structures and without interference with the rights of the public, owners of private property, pedestrians, vehicular traffic or the work of other contractors, and in accordance with all pertinent laws, ordinances and regulations.

F. Do not overload or obstruct existing drainage facilities.

02140 - 2

DEWATERING

G. After they have served their purpose, remove all temporary protective work at a satisfactory time and in a satisfactory manner. All diversion channels and other temporary excavations in areas where the compacted fill or other structures will be constructed shall be cleaned out, backfilled and processed under the same Specifications as those governing the compacted fill.

H. When the temporary works will not adversely affect any item of permanent work or the planned usage of the Project, the CONTRACTOR may be permitted to leave such temporary works in place. In such instances, breeching of dikes, levees and cofferdams may be required.

3.2 DEWATERING

A. By the use of well points, pumps, tile drains or other approved methods, the CONTRACTOR shall prevent the accumulation of water in excavated areas.

Should water accumulate, it shall be promptly removed.

B. Excavations shall be continuously dewatered to maintain a ground water level no higher than three to four feet below the lowest point in the excavation.

Dewatering shall be accomplished well enough in advance of excavation to ensure that groundwater is already lowered prior to completing the final excavation to finish subgrade.

C. All destabilized subgrade conditions caused by inadequate or untimely dewatering operations shall be undercut and backfilled with suitable backfill material at no additional cost to the OWNER.

D. Piezometric observation wells are required to monitor the ground water level to insure proper dewatering prior to excavation below the static water table. The number of wells required will vary depending on the size and depth of structures.

SECTION 2200

EARTHWORK

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

A. Extent of earthwork is indicated on the Drawings.

1. Preparation of subgrade for building slabs, and pavements is included as part of this work.

2. Engineered fill course for support of building or parking lots is included as part of this work.

1.2 QUALITY ASSURANCE

A. Codes and Standards: Perform excavation work in compliance with applicable requirements of governing authorities having jurisdiction.

B. Testing and Inspection Services: CONTRACTOR will employ a testing laboratory to perform soil testing and inspection service for quality control testing during earthwork operations where necessary.

1.3 SUBMITTALS

A. Test Reports-Excavating

CONTRACTOR will employ a geotechnical engineering company to prepare all soil testing reports. ENGINEER must approve geotechnical engineering company.

All soil testing reports to be certified by a licensed geotechnical engineer.

1.4 JOB CONDITIONS

A. Site Information

1. Additional test borings and other exploratory operations may be made by Contractor at no cost to Owner.

B. Existing Utilities: Prior to commencement of work, the Contractor shall locate existing underground utilities in areas of the work. If utilities are to remain in place, provide adequate means of protection during earthwork operations.

C. Use of Explosives: The Contractor (or any of his subcontractors) shall not bring explosives onto site or use in work.

D. Protection of Persons and Property

1. Barricade open excavations occurring as part of this work and post with warning lights.

02200-2

a. Operate warning lights as recommended by authorities having jurisdiction.

2. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations.

PART 2 PRODUCTS

2.1 SOIL MATERIALS

A. Definitions

1. Satisfactory soil materials are defined as those complying with ASTM D2487 soil classification groups GW, GP, GM, SM, SW, SP, GC, SC, ML and CL.

2. Unsatisfactory soil materials are defined as those complying with ASTM D2487 soil classification groups MH, CH, OL, OH and PT.

3. Backfill and fill materials: Satisfactory soil materials free of debris, waste, frozen materials, vegetable, and other deleterious matter.

4. Engineered fill: (Refer to this Section, paragraph 3.7 A.1.)

PART 3 EXECUTION

3.1 STRIPPING AND TOPSOILING

A. Before excavation and grading is commenced for work described hereinafter, the material meeting the topsoil specification of these Specifications shall be removed from the areas affected and stockpiled. When final grading is accomplished, the topsoil shall be spread evenly over the excavated area. Rough grading above excavated areas shall have been carried approximately 6 inches below finished grade (except solid rock, where it shall be carried 12 inches below finished grade) and brought back up to grade with topsoil as set out herein. Additional topsoil may be used to top dress slopes.

B. After stripping at-grade areas and areas that are to receive structural fill, they shall be proof rolled. Proof rolling consist of applying repeated passages (4 to 5 passes) on the subgrade with a loaded dump truck or similar rubber tired vehicle.

Any materials judged to deflect excessively under the wheel loads should be undercut to more stable soil or as recommended by the Engineer.

3.2 EXCAVATION

A. Excavation includes excavation to subgrade elevations indicated including excavation of earth, rock and other debris. All excavation of materials will be

02200-3 unclassified and no additional payment will be made regardless of type material encountered.

B. The upper nine inches of soil exposed in cut sections shall be scarified and recompacted to create a blanket of less permeable material.

C. Rock Excavation

1. If rock is encountered, it shall be removed with hard rock removal methods, such as rock trenching, chemical fracturing or hoe-ramming. The small volume of rock generated from this process can be used in deeper fill areas on the site.

D. Unauthorized excavation consists of removal of materials beyond indicated subgrade elevations or dimensions without specific direction of Engineer.

Unauthorized excavation, as well as remedial work directed by Engineer, shall be at Contractor's expense.

E. Additional Excavation

1. When excavation has reached required subgrade elevations, notify the Engineer who will make an inspection of conditions.

a. If unsuitable bearing materials are encountered at required subgrade elevations, carry excavations deeper and replace excavated material as directed in writing by the Engineer.

b. Removal of unsuitable material and its replacement as directed will be paid on basis of Contract conditions relative to changes in work.

F. Stability of Excavations

1. Slope sides of excavations to comply with local codes and ordinances having jurisdiction. Shore and brace where sloping is not possible because of space restrictions or stability of material excavated.

2. Maintain sides and slopes of excavations in safe condition until completion of backfilling.

F. Dewatering: Refer to this Division, Section 02140 for dewatering requirements.

G. Material Storage

1. Stockpile satisfactory excavated materials where directed, until required for backfill or fill. Place, grade, and shape stockpiles for proper drainage.

a. Dispose of excess soil material and waste materials as herein specified.

H. Excavation for Structures

02200-4

1. Conform to elevations and dimensions shown within a tolerance of plus or minus 0.10 feet.

I. Excavation for Pavements

1. Cut surface under pavements to comply with cross-sections, elevations, and grades as shown.

J. Cold Weather Protection

1. Protect excavation bottoms against freezing when atmospheric temperature is less than 35°F (1°C).

3.3 COMPACTION

A. General

1. Control soil compaction during construction providing minimum percentage of density specified for each area classification indicated below.

a. Percentage of maximum density requirements: Compact soil to not less than the following percentages of maximum density for soils which exhibit a well-defined moisture density relationship (cohesive soils) determined in accordance with ASTM D698 and not less than the following percentages of relative density, determined in accordance ASTM D4253 and D4254, for soils which will not exhibit a well-defined moisture-density relationship (cohesionless soils).

b. Structures, building slabs and steps, pavements: Compact top 12 inches of subgrade and each layer of backfill or fill material at 95 percent standard proctor density.

c. Lawn or unpaved areas: Compact top 6 inches of subgrade and each layer of backfill or fill material at 90 percent standard proctor density.

d. Walkways: The testing frequency for density test performed a full time basis can be determined by the Geo-Tech representative based on the area to be tested, the grading equipment used and construction schedule. Test shall be performed at vertical intervals of 8 inch or less as the fill is being placed.

B. Moisture Control

1. The moisture content of the fill shall be maintained within 3 percent of the soil’s optimum moisture content even though compaction may be achieved at moisture contents outside the specified range.

2. Where subgrade or layer of soil material must be moisture conditioned before compaction, uniformly apply water to surface or subgrade, or layer

02200-5 of soil material, to prevent free water appearing on surface during or subsequent to compaction operations.

3. Remove and replace, or scarify and air dry, soil material that is too wet to permit compaction to specified density.

4. Soil material that has been removed because it is too wet to permit compaction may be stockpiled or spread and allowed to dry. Assist drying by discing, harrowing, or pulverizing until moisture content is reduced to a satisfactory value.

3.4 BACKFILL AND FILL

A. General

1. Place acceptable soil material in layers to required subgrade elevations, for each area classification listed below. Backfill material shall be no larger than the specified depth of the layer to be placed and/or compacted.

a. In excavations, use satisfactory excavated material.

b. Under grassed areas, use satisfactory excavated material.

c. Under proposed pavements, use satisfactory excavated material.

e. Under building slabs, use satisfactory excavated material.

B. Backfill excavations as promptly as work permits, but not until completion of the following:

1. Acceptance of construction below finish grade.

2. Inspection, testing, approval, and recording locations of underground utilities.

3. Removal of trash and debris.

C. Ground Surface Preparation

1. Remove vegetation, debris, unsatisfactory soil materials, obstructions, and deleterious materials from ground surface prior to placement of fills.

Plow, strip, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so that fill material will bond with existing surface.

2. When existing ground surface has a density less than that specified under "Compaction" for particular area classification, break up ground surface, pulverize, moisture condition to optimum moisture content, and compact to required depth and percentage of maximum density.

D. Placement and Compaction

1. Place backfill and fill materials in layers not more than 8 inches in loose depth for material compacted by heavy compaction equipment, and not more than 4 inches in loose depth for material compacted by hand-operated tampers. Crushed stone shall be installed in accordance with Section 02255.

02200-6

a. Before compaction, add moisture or aerate each layer as necessary to provide optimum moisture content. Compact each layer to required percentage of maximum dry density or relative dry density for each area classification. Do not place backfill or fill material on surfaces that are muddy, frozen, or contain frost or ice.

b. Place backfill and fill materials evenly adjacent to piping, or conduit to required elevations. Take care to prevent displacement of piping or conduit by carrying material uniformly around structure, piping, or conduit to approximately same elevation in each lift.

c. Observation of the structural fill placement and in-place density testing must be performed on fill sections as a check by the Geo- Tech representative.

d. Soil moisture content is to be kept near or just above the plastic limit where…

This is the start of the file's text. The full file is on GovTribe.