This is a Statement of Work for the Tuskegee Airmen National Historic Site Control Tower and Observation Deck Rehabilitation project located in Tuskegee, Alabama. The National Park Service (NPS) is contracting for historical preservation work on a four-story brick masonry control tower constructed in 1942 at Hangar No. 2. The project has a 4-month (120-day) performance period beginning upon receipt of Notice to Proceed. The contractor must provide all materials, equipment, labor, and tools necessary to complete the work, which includes two primary tasks: repairing the leaking observation deck floor through surface cleaning, crack inspection, elastomeric roofing application, proper grading to ensure drainage to the southwest corner scupper, and concrete parapet cap sealing; and completely replacing the wooden fire escape system (two balconies and a ladder) using pressure-treated lumber matching existing dimensions and design specifications, with 4x4 anchoring members, 2x4 flooring, 2x2 spindles for railings, and exterior latex paint finish.
The contractor must comply with the Secretary of the Interior's Standards for Historic Preservation and OSHA, EPA, and applicable federal, state, and local regulations. All work must be performed Monday through Friday from 7:30 a.m. to 4:00 p.m. with daily notification to the Contracting Officer's Representative between 7:00 and 7:15 a.m. CST. Prior to Notice to Proceed, the contractor must submit a project-specific safety plan addressing heavy equipment operations, fall protection, public/visitor safety, traffic management, scaffolding, personal protective equipment, hazardous materials with Safety Data Sheets, emergency protocols, personnel training, and OSHA 300A summaries for the past three years. Additional required deliverables include proof of insurance and performance and payment bonding. Payment will be made upon submission of proper invoices for services rendered and accepted, with the government retaining the right to withhold partial payment for inadequate performance and withhold final payment until all remaining scope items are completed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NATIONAL PARK SERVICE
Region IR2
Tuskegee Institute / Tuskegee Airmen National Historic Site
PROJECT NAME:
TUAI Control Tower and Observation Deck Rehab
PMIS NO.:
349353
PEPC No.:
126701
Tuskegee Institute/Tuskegee Airmen National Historic Site
Tuskegee, AL 36088
Statement of Work
TABLE OF CONTENTS
1. Background
2. Objectives
3. Place of performance
4. Period of performance
5. Project Scope
6. Safety
7. Tasks
8. Delivery
9. Government-Furnished Property (GFP)
10. Security Considerations
11. Special Material Requirements
12. Other Unique Requirements and Considerations
13. Quality Assurance Requirement
14. Project Personnel
15. Invoices and Payments
1. BACKGROUND
Tuskegee Airmen National Historic Site (TUAI) is a unit of the National Park Service and is head quartered at 1616 Chappie James Ave. Tuskegee, AL. 36083 There are a total of 7 buildings and 2 hangers. The Hangar#2 is one of those buildings that has a Control Tower Observation Deck and Fire Escape that is emergency need of Rehab. The Historic Tuskegee Airmen Control Tower Observation Deck and Fire Escape needs repair due to the observation deck floor and fire escape has went through decay/ rotten and needs repair/rehabbed. The Tuskegee Airmen Control Tower at Moton Field observation deck floor is also leaking and requires repair. The fire escape system is constructed of wood material and includes two balconies and a ladder.
2. OBJECTIVES:
From Moton Field’s Control Tower, controllers directed flight operations and signaled landing instructions to pilots through a system of flashing colored lights. Dispatchers called cadets for their flights. The tower overlooked the busy – and noisy
– flow of aircraft, pedestrian, and vehicle traffic between two hangars.
The tower was where the dispatcher would look out on the field and call the cadets over the loudspeaker to tell them about their flight assignments. Also in that tower was a big chamber in which parachutes were hung to dry.
The four-story, brick masonry Control Tower stood at Hangar No. 2 northeast corner and was constructed in 1942. The original Hangar No. 2 burned in 1989 and was demolished. A replica of Hangar No. 2 was built in 2010. The control tower was restored during the 2010 construction project. The structures were reopened to the public in 2014.
The observation deck floor is leaking and requires repair. The fire escape system is constructed of wood material and includes two balconies and a ladder that are anchored to the Control Tower with ¾” steel anchors. The fire escape has extensive rotten and will need to be completely replaced.
PROJECT PLANNING
An historical repair contractor will be needed to be appropriate for the project. All necessary tools, equipment and materials will be assembled and transported to a designated on-site staging area. This includes project pre-planning, the procurement of required materials, and an allowance for travel time for the crew from their respective shop facility to the project site.
A safety/hazard analysis will be conducted as part of this first task and will be supported with the preparation of a Safety Plan for all on-site activities that will be provided to TUAI prior to the beginning of the project. A pre-project safety briefing with project related personnel will occur.
Construction safety fencing will be installed around the defined work area as determined during project pre-planning. Parking, access, and egress areas will be established. Safety related signage will be posted.
Existing conditions, ongoing work, and completed preservation work will be documented through a combination of digital color photography, field sketches, and written narratives to include the timely submittal of Weekly Field Reports. Existing conditions will be documented prior to, and during project work. During project execution, representative samples of historic materials will be salvaged, inventoried, and tagged. The samples will be turned over to TUAI after the final inspection.
SCOPE OF WORK
The historical repair contractor will need a team of preservation specialists for the work identified in the following tasks. All preservation work and practices performed will comply with the Secretary of the Interior’s Standards for Historic Preservation. All salvageable fabric will be stabilized and reused whenever possible, with existing condition, initial design, and long-term maintenance in mind.
Task #1: Repair Control Tower Observation Deck
The historical repair contractor will clean the observation deck floor surface and inspect cracks and possible leaks. Any deficiencies found during visual inspection will be repaired by layering elastomeric roofing to seal the deficiencies. After the recommended cure time has elapsed, the crew will check and correct the grade of the deck surface to ensure flow to the scupper located in the southwest corner of the control tower observation deck by layering elastomeric roofing to fill the lows and creating proper flow. After recommended cure time, the entire deck surface will be coated with an elastomeric roofing system. The team will clean the concrete parapet cap with D2 and rinse with light pressure washing. The concrete parapet cap will then be sealed with an approved sealer to protect the cap and prevent water intrusion.
Task #2: Replace the Fire Escape
The historical repair contractor will remove and document the dimensions and design of the existing fire escape. The fire escape system includes two balconies and a ladder, constructed of nominal size, pressure treated, wood materials. The fire escape balconies and ladder will be constructed with kind materials matching the existing structure and dimensions. The balconies will be anchored to the structure with 4x4’s via existing ¾” anchor studs. The framework will be constructed with 4x4’s and flooring with 2x4’s. The railing will be crafted from 2x2 spindles with a 1” trim board on the interior top and bottom and the exterior top and bottom. A 2x6 outside band will be constructed to match the existing trim. The top rail will be a 4x6 with beveled edges. The ladder will be constructed with approved pressure treated lumber. The rails will be 4x4’s anchored to the wall via existing ¾” anchor studs at 2’ on center. The ladder rungs will be 2x4’s anchored to the 4x4’s at 12” on center. All lumber will be primed with a park approved primer and painted with an exterior grade latex paint.
3. PLACE OF PERFORMANCE:
• Tuskegee Airmen National Historic Site: 1616 Chappie James Venue, Tuskegee, Alabama 36083
The mailing address of the building associated with this contract is:
• Tuskegee Airmen National Historic Site – 1616 Chappie James Venue, Tuskegee, Alabama 36083
4. PERIOD OF PERFORMANCE:
All work specified herein shall commence after the notice to proceed is received from the Contracting Officer and completed within a 4-month (120-day) period.
4. PROJECT SCOPE
In accordance with the terms and conditions herein, the prime contractor or his sub-contractors shall perform the work of this contract for the National Park Service (NPS).
The contractor will complete the following items:
1. Contractor will provide all material, equipment, parts, and labor required to perform all the work of this contract.
2. All equipment, material and waste removed or generated by the work of this contract shall be properly disposed of offsite by the contractor.
3. The contractor shall verify the quantity of materials needed to complete the task identified in this
SOO.
4. Contractor will provide a work site and environment that is safe for employees, for visitors to the park, and NPS staff. If needed, the work area will be cordoned and secure.
5. All work will be performed Monday through Friday from 7:30 am until 4:00 pm. No work will be done on weekends or federal holidays without prior approval.
6. Contractor and employee parking and equipment storage areas will be designated by the park. No company signs shall be installed on government property. Smoking and eating will be performed in areas designated by the park. Employees shall always wear appropriate clothing.
7. Contractors will notify NPS staff of scheduled site visits to ensure access to secure areas.
6. SAFETY:
All work performed on government property will be accomplished in accordance with OSHA, EPA, Federal, State, and local regulations, and requirements. Prior to starting work on government property, the contractor will submit to Tuskegee National Historic Site for approval a copy of their company safety plan pertaining to this particular contract. Although not all inclusive, the safety plan must address at a minimum the following areas:
1) Heavy equipment operations (if required)
2) Fall Protection
3) Public/visitor safety (barriers/signage, etc…)
4) Traffic safety plan (if required)
5) Scaffold safety plan (if required)
6) Personal protective equipment to be used.
7) Hazardous materials (HAZMAT) to be used.
a. Copies of Safety Data Sheets (SDS) must be provided at the park
b. Storage of HAZMAT
8) Emergency response protocols
9) Personnel training requirements
10) OSHA DART rate
a. OSHA 300A Summary for last three years
Contractor shall use “green” products whenever possible, and all HAZMAT must be pre-approved for use by the TUAI Collateral Duty Safety Coordinator. The contractor will be responsible for the safety and security of the site to ensure unauthorized personnel (park visitors & employees) do not enter the construction area.
7. TASKS:
COMMUNICATION
A). Contractor shall notify the Contracting Officer’s Representative (COR) between 7:00 am CST and 7:15am CST am on the morning work will be performed or inform the COR why services cannot be performed that day.
B). Work shall be performed during daylight hours between 7:30 am CST and 4:00 pm CST Monday through Friday. Weekend and holiday work will not be permitted unless prior approval by the Contracting Officer
C). Schedule changes MUST be Approved through the Contracting Officer
SPECIFIC REQUIREMENTS
• The material installation methods will be consistent with the material manufacture requirements and construction industry standards.
• The asphalt shingles shall be architectural style shingles, fiberglass and match the existing color.
• Roof drip edge will be aluminum coated, Type F.
• Shingle and drip edge color will be approved by the COR.
GERERAL PROVISIONS
1. Pumphouse footprint = 144 square feet
2. Bath and Locker footprint = 1,760 square feet
3. Skyway Club footprint = 5,500 square feet
4. Dope Storage Station footprint = 144 square feet
5. Maintenance Shop footprint = 2,560 square feet
6. Fire BLDG footprint = 144 square feet
7. Storage BLDG footprint = 144 square feet
8. Visitor BLDG footprint = 144 square feet
WEATHER
The contractor shall notify the COR by 7:00 am CST of any intention to cancel work for the day due to the weather.
8. DELIVERY:
All deliverables required to complete this project will be delivered by the contractor.
• Asphalt shingle cut sheets.
• Roofing underlayment cut sheets.
• Safety plan
• Proof of Insurance
9. GOVERNMENT-FURNISHED PROPERTY, MATERIAL, EQUIPMENT, OR
INFORMATION (GFP, GFM, GFE, OR GFI):
• None
10. SECURITY:
The information developed under this Statement of Objectives is the property of the U.S. government and shall be kept in strict confidence. Proprietary or copyrighted material may not be included into the contract information unless otherwise approved in writing by the Contracting Officer.
11. SPECIAL MATERIAL REQUIREMENTS:
• The asphalt shingles shall be architectural style shingles.
• Roof drip- edge will be aluminum.
• Shingle and drip edge color will be approved by the COR.
• Flashing should be coated aluminum and be secured by a flashing cement in accordance with industry standards.
• Aluminum gutters,5” box,0.27 thick
• Gutter end cap, K type aluminum, 5”
• Aluminum downspouts, round, corrugated, 4” diameter, 0.25” thick.
• Gutter outlet, aluminum, 3”x4”
• Gutter sealant to be used to seal all joints by industry standards.
12. OTHER UNIQUE REQUIREMENTS:
N/A
13. QUALITY ASSURANCE REQUIREMENT:
THE CONTRACTOR SHALL DEVELOP AND MAINTAIN A QUALITY CONTROL
PROGRAM TO ENSURE SERVICES ARE PERFORMED IN ACCORDANCE WITH
COMMONLY ACCEPTED COMMERCIAL PRACTICES. THE CONTRACTOR SHALL
DEVELOP AND IMPLEMENT PROCEDURES TO IDENTIFY, PREVENT, AND
ENSURE NON-RECURRENCE OF DEFECTIVE SERVICES. AS A MINIMUM THE
CONTRACTOR SHALL DEVELOP QUALITY CONTROL PROCEDURES
ADDRESSING THE CRITICAL AREAS IDENTIFIED IN THIS STATEMENT OF
WORK. THE GOVERNMENT WILL PERIODICALLY EVALUATE THE
CONTRACTOR’S PERFORMANCE IN ACCORDANCE WITH THE STATEMENT OF
WORK.
Prior to issuance of Notice to Proceed, the Contractor shall be required to submit to the CO/COR the following items (Electronic submission in PDF or MS Office format is acceptable):
• Project Safety plan (Specific to Project)
• Proof of Insurance
• Performance and Payment Bonding
14. PROJECT PERSONNEL:
Contracting Officer (CO):
TBD
Contracting Officer Representative (COR):
TBD
Facility Manager:
TBD
15. INVOICES AND PAYMENTS:
52.232-1 PAYMENTS (APR 1984)
The Government shall pay the Contractor, upon the submission of proper invoices or vouchers, the prices stipulated in this contract for supplies delivered and accepted or services rendered and accepted, less any deductions provided in this contract. Unless otherwise specified in this contract, payment shall be made on partial deliveries accepted by the Government if—
(a) The amount due on the deliveries warrants it; or
(b) The Contractor requests it and the amount due on the deliveries is at least $1,000 or 50 percent of the total contract price.
(End of clause)
Adjustment for Inadequate Performance
• Well maintained buildings are the National Park Service’s goals. Routine inspection shall be performed to minimize work improperly performed. Such inspections are designed only to ensure that the NPS pays only for those services, which have been specified, and adequately completed by the contractor.
• In the event the contractor fails to successfully perform the required work, the National Park Service has the right to withhold partial payment.
• It is highly recommended for the contractor should make a sit visit prior to submitting a quote.
• In the event there are unforeseen remaining project items in the scope at the end of project completion date, there will be a Hold on the Final Payment until the Items are completed on a one-time extension made by the CO/COR over the project.
Pictures Below:
Map (Below)
| Project Name: |
| PMIS No.: |
| Statement of Work |
| TABLE OF CONTENTS |
| 1. Background |
| 2. OBJECTIVES: |
| Project Planning |
| Scope of Work |
| Task #1: Repair Control Tower Observation Deck |
| 3. Place of Performance: |
| 4. PERIOD of Performance: |
| 4. Project Scope |
| 6. Safety: |
| 7. Tasks: |
| 8. DELIVERY: |
| 9. GOVERNMENT-Furnished Property, Material, Equipment, or Information (GFP, GFM, GFE, or GFI): |
| 10. SECURITY: |
| 11. SPECIAL Material Requirements: |
| 12. OTHER Unique Requirements: |
| 13. QUALITY ASSURANCE Requirement: |
| The contractor shall develop and maintain a quality control program to ensure services are performed in accordance with commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent, and ensure non... |
| 14. PROJECT Personnel: |