A04_Attachment_0001_SOW_44016407.pdf

PDF 858 KB Posted

Attached to
Provide Debris Removal - CAHA Federal contract opportunity
Solicitation number
140P5125Q0022
Issued by
Department of the Interior National Park Service Southeast Region

About this file

This is a Scope of Work (SOW) for the removal of abandoned infrastructure at Cape Hatteras National Seashore in Rodanthe, North Carolina. The project requires a contractor to remove a 10'x20' in-ground concrete pool, 11 wood timber pilings (10-15 feet deep), and approximately 20-30 sandbags from a former residential property site. The work must be completed within 60 days of contract award, with the contractor commencing work within 21 days after award.

Key requirements include complete removal of all pool debris, pilings, and sandbags, with careful screening of the sand to ensure no small or medium-sized debris remains. The contractor must follow strict environmental and safety regulations, provide detailed submittals including a project schedule and safety plan, and restore the site to its natural beach condition without using any fill materials. The project aims to protect natural and cultural resources while improving safety and recreational use of the shoreline.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CAPE HATTERAS NATIONAL SEASHORE

Outer Banks Group

SCOPE OF WORK

REMOVAL OF ABANDONED POOL DEBRIS, PILINGS AND SANDBAGS

23273 MIDGETT’S MOBILE COURT, RODANTHE NC 27968

PMIS#349512A

[PMIS#349512A] Removal of Abandoned Pool Debris, Sandbags and Pilings P a g e | 2

1.0 INTRODUCTION

The National Park Service (NPS) Cape Hatteras National Seashore (CAHA) will be contracting the removal of sandbags, house foundation pilings and abandoned pool debris on the shoreline in Rodanthe, NC.

1.1 OBJECTIVE

The purpose of this project is to perform the removal of sandbags, pilings and associated pool remnants and restore the site to natural beach conditions.

• A site visit is recommended prior to submitting a proposal.

• The contractor shall be responsible for verifying all measurements and site conditions prior to submitting a proposal and ordering material required for removal.

• NPS provided documentation and pictures of the debris are for general reference only. Onsite conditions may vary.

1.2 LOCATION

Figure 1: Cape Hatteras National Seashore Map

[PMIS#349512A] Removal of Abandoned Pool Debris, Sandbags and Pilings P a g e | 3

Figure 2: Map Location 23273 Midgett’s Mobile Ct, Rodanthe, NC 27968

[PMIS#349512A] Removal of Abandoned Pool Debris, Sandbags and Pilings P a g e | 4

1.3 BACKGROUND AND EXISTING CONDITIONS

Beach erosion in recent history has resulted in an increase of infrastructure from houses and roads once abandoned from years of previous beach erosion on the seashore to be uncovered along Cape Hatteras National Seashore.

23273 Midgett’s Mobile Ct, Rodanthe, NC 27968 was located at the very end of a former existing road and is a location where a home once was. This location was confirmed to be on Cape Hatteras National Seashore property on 4/1/2025. The park boundary line does change between tide cycles, but at the time of confirmation the remnants of the house that remained on the seashore were located within the park boundary. The remnants of the house that remain behind that need to be removed and disposed include 11 pilings (a few are 100 yards to the north), approximately 20-30 sandbags and a 10’x20’ inground concrete pool.

[PMIS#349512A] Removal of Abandoned Pool Debris, Sandbags and Pilings P a g e | 5

There are no known active existing public utilities on this site to address prior to demolition.

Removal of these pilings and pool debris will provide for long term protection of natural and cultural resources, safety, and recreational use along the seashore.

2.0 PERIOD OF PERFORMANCE

The contractor shall commence work under this contract within twenty-one (21) days after the date of award. Removal and cleanup shall be completed within sixty (60) days of the contract award.

3.0 SCOPE OF WORK

This Statement of Work includes removing the debris of the 10’x 20’ inground concrete pool foundation, 11 wood timber pilings that are 10-15 feet deep in the sand and all sandbags on the shoreline (estimated to be 20 - 30 sandbags) and the hauling/disposal of the debris appropriately. Any discovered components of septic systems, piping, sandbags or other debris on the property will be removed completely as part of this project. All eleven timber piles will be removed fully, if they break, they must still be dug out and removed. Any remaining sandbags discovered while removing other items will also be removed completely as a part of this project. When all debris are removed completely, the ground will be graded level with surrounding grades. No fill materials will be used.

[PMIS#349512A] Removal of Abandoned Pool Debris, Sandbags and Pilings P a g e | 6

When disposing of any components of this debris removal, the contractor shall dispose of all items according to Federal, State, and local laws and ordinances. The contractor shall minimize the creation of deconstruction, and demolition waste where possible to protect and restore natural habitat and resources. Factors that contribute to waste such as over packaging, improper storage, ordering error, poor planning, breakage, mishandling, and contamination shall be minimized. The contractor shall provide a Waste Management Plan.

The contractor shall always keep the premises clean, free of accumulation of waste materials and rubbish, and the roads clean of all droppings from their trucks.

The contractor shall operate only within the park property limits, which includes the property line for the house. For any additional space needs that cannot be achieved within the park property limits, the contractor shall provide requirements for space and the park will work with the county and or state or local homeowners to determine available areas.

3.1 Pre-Removal Inspection

To limit debris from entering the ocean or being washed down the seashore the COR must approve the method and route of removal for all items listed. No work shall begin until all necessary protective fencing, signing, and barricades have been approved by the COR in the field.

3.2 Remove Harmful Materials

All material identified as hazardous by the North Carolina Department of Environmental Quality (NCDEQ) or the Environmental Protection Agency (EPA) shall be disposed of in accordance with NCDEQ and EPA regulations.

3.3 Removal of Pool, Pilings, Sandbag and Remnants

The contractor shall remove:

• All remaining pieces of the pool.

• All pilings on site – 11 total pilings have been identified.

• All wastewater system components, if any are discovered onsite.

• All sandbags and remnants of any manmade debris.

The contractor shall remove all pieces of the pool. All concrete, tile, rebar, framing, and piping shall be removed.

The contractor shall remove all identified pilings. All lumber, bolts, brackets, and concrete shall be removed.

The contractor shall remove all components of any wastewater system component, if discovered onsite. All tanks, distribution boxes, grinders, piping, and drain field lines shall be removed.

The contractor shall remove all sandbags and remnant of any manmade debris. All sandbag material shall be removed. Any pipe, lumber, metal, asphalt paving, building block, brick, [PMIS#349512A] Removal of Abandoned Pool Debris, Sandbags and Pilings P a g e | 7 stone, concrete, and all scrap that is visible shall be removed. All foundation walls, piling, concrete blocks, or any other manmade structures discovered while removing the visible debris. The only thing left behind should be the sand.

No components shall be abandoned in place.

3.4 Post Removal Site Restoration

Debris from the home site shall be removed completely. The contractor shall screen the sand to ensure all small (6 inches to 10 inches in length/diameter) and medium (10 inches to 40 inches in length/diameter) sized pieces of debris are removed completely. Visual inspection will be conducted by the COR that debris has been removed completely at the pre-final inspection and final inspection.

The ground shall be graded level with surrounding grades. No fill materials will be used.

Upon completion of this contract the contractor shall remove all apparatus, tools, equipment, surplus materials, rubbish, etc. and shall leave the premises clean, neat, orderly, and otherwise in good condition, similar to the shoreline surrounding the existing properties.

4.0 OTHER REQUIREMENTS

4.1 Project Meetings, Scheduling and Coordination

A post award meeting will be required either by phone or on-site. The contractor shall have at least daily coordination and provide daily reporting of progress to the COR. Once the contractor has completed the demolition a pre-inspection shall be conducted with the COR.

Once all items (if any) identified in the pre-inspection are resolved, the contractor shall conduct a final inspection with the COR. The contractor shall provide all submittals referenced below in 4.5 Submittals, in accordance with their required timeframe.

4.2 Responsibility and Protection of Adjacent Property

The contractor shall be responsible, at their expense, to repair any damages to other properties that result from their actions.

4.3 Final Inspection and Acceptance

When all work of this contract has been completed and the cleanup performed, the COR will make the final inspection after receipt of a written request by the contractor. When all errors and omissions disclosed by the final inspection have been corrected, acceptance will be in writing, but until such acceptance, the contractor shall be responsible for the work covered by this contract.

4.4 Responsibility

[PMIS#349512A] Removal of Abandoned Pool Debris, Sandbags and Pilings P a g e | 8

The contractor shall direct, coordinate, and supervise all work under this contract. Likewise, the contractor shall inspect all equipment and apparatus engaged in this operation to assure its safe operations and will coordinate their activities through the COR.

4.5 Submittals

The intent is to provide an overall summary of the submittal requirements and not a comprehensive list. The requirements of the terms and conditions of the contract still apply regardless of what is shown on the submittal list.

Submittals required prior to pre-construction meeting and mobilization:

• Project Schedule

• Accident Prevention Plan/Safety Plan/Site Plan

• Demolition and Disposal Plan (must include at a minimum the below) o Equipment Placement/Storage Plan o Waste Management Plan o Routes of Travel Plan

• List of Subcontractors (if applicable)

Submittals required during demolition:

• Daily Reports

• Waste Material Dump Receipts

• Reuse/Salvage/Recycle Manifests/Invoices

• Project Schedule Updates or Changes

5.0 SAFETY

All work performed on government property will be accomplished in accordance with OSAH, EPA, Federal, State, and local regulations and requirements. Prior to starting work, the contractor shall submit an Accident Prevention Plan/Safety Plan for approval. The safety plan must address at a minimum the following:

• Heavy Equipment Operations

• Public/visitor Safety (barriers/signage, etc.)

• Personal Protective Equipment (PPE) to be used

• Emergency Response Protocols

• Personnel Training Requirements