This document is a Contract Data Requirements List (DD Form 1423-1) for a 2D Scanner procurement by the Rock Island Arsenal. The CDRL outlines five specific data documentation requirements the contractor must provide:
- Installation and Preparation Documentation, which includes an Installation Documentation List, Tool List, Footprint Drawing, Electrical Schematic, and Equipment Identification details. 2. Maintenance Manual with Preventive Maintenance Procedures. 3. Operator Manual detailing safe operation procedures. 4. Pre-Shipment Testing Report. For each requirement, the contractor must submit both electronic (PDF, DXF, DOC, IGS formats) and paper copies, typically 60 calendar days prior to equipment delivery. The documentation must include comprehensive details such as standard and optional features, installation requirements, maintenance schedules, operational instructions, and technical specifications. All documentation is to be provided to the Rock Island Arsenal, specifically to the TARA-LGC department, Attention: Jeffery Merry, located in Building 220B, Room Plant Engineering.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DD Form 1423-1, SEP 97 (EG) (Computer Generated) PREVIOUS EDITIONS ARE OBSOLETE Page 1 of 8 Pages
C O N T R A C T D A T A R E Q U I R E M E N T S L I S T (1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
D. SYSTEM/ITEM
2D Scanner
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Installation Documentation List
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
7. DD250 REQ
9. DIST
STATEMENT
REQUIRED
10. FREQUENCY
SEE BLOCK 16
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
SEE BLOCK 16
a. ADDRESSEE Draft
Final
Reg Repro
16. REMARKS
The contractor shall provide a copy of this information in either electronic or paper format, a minimum of 60-calendar-days prior to delivery of equipment. The contractor shall provide a second copy of this information in electronic or paper format at the time of delivery of the equipment.
Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
A plainly visible cover sheet shall be provided with the Installation and Preparation Documentation package listing drawings and schematics required for installation.
PROVIDE COPIES, AS REQUESTED TO THE FOLLOWING:
Rock Island Arsenal
ATTN: TARA-LGC
Jeffery Merry Bldg 220B, Rm Plant Engineering Rock Island, IL 61299-6400
15. TOTAL
G. PREPARED BY
Tad Larson
H. DATE
24-April-2025
I. APPROVED BY
J. DATE
DD Form 1423-1, SEP 97 (EG) (Computer Generated) PREVIOUS EDITIONS ARE OBSOLETE Page 2 of 8 Pages
(1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Tool List
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
13. DATE OF SUBSEQUENT
SUBMISSION
SEE BLOCK 16
a. ADDRESSEE Draft
Final
Reg Repro
16. REMARKS
The contractor shall provide a copy of this information in either electronic or paper format, a minimum of 60-calendar-days prior to delivery of equipment. The contractor shall provide a second copy of this information in electronic or paper format at the time of delivery of the equipment.
Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and Microsoft Word (.doc).
An itemized list of all fixtures, tools, and equipment, whether special or not, required to install, align, and maintain the equipment in this purchase description. NOTE: The contractor is responsible for providing special/custom tools and equipment necessary for installation, moving, and/or set-up as part of the equipment.
ATTN: TARA-LGC
Jeffery Merry
Tad Larson
H. DATE
DD Form 1423-1, SEP 97 (EG) (Computer Generated) PREVIOUS EDITIONS ARE OBSOLETE Page 3 of 8 Pages
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Footprint Drawing
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
13. DATE OF SUBSEQUENT
SUBMISSION
SEE BLOCK 16
a. ADDRESSEE Draft
Final
Reg Repro
16. REMARKS
The contractor shall provide a copy of this information either in electronic or paper format, a minimum of 60-calendar-days prior to delivery of equipment. The contractor shall provide a second copy of this information in electronic or paper format at the time of delivery of the equipment.
Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and initial graphic exchange specification (.igs).
A dimensioned drawing shall be provided to accurately depict the layout of system, showing contours. It shall be fully dimensioned and include net operating clearance for moving components which travel beyond the gross contour. The drawing shall distinguish between the base of the equipment at floor level and the gross contour where it may overhang the base.
Location of access doors for servicing of the equipment shall also be designated.
ATTN: TARA-LGC
Jeffery Merry
Tad Larson
H. DATE
DD Form 1423-1, SEP 97 (EG) (Computer Generated) PREVIOUS EDITIONS ARE OBSOLETE Page 4 of 8 Pages
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Electrical Schematic
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
13. DATE OF SUBSEQUENT
SUBMISSION
SEE BLOCK 16
a. ADDRESSEE Draft
Final
Reg Repro
16. REMARKS
The contractor shall provide a copy of this information either in electronic or paper format, a minimum of 60-calendar-days prior to delivery of equipment. The contractor shall provide a second copy of this information in electronic or paper format at the time of delivery of the equipment.
Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and initial graphic exchange specification (.igs).
The equipment includes this type of utility and a complete system schematic is required. The capacity required at the point of first connection must be clearly stated.
ATTN: TARA-LGC
Jeffery Merry
Tad Larson
H. DATE
DD Form 1423-1, SEP 97 (EG) (Computer Generated) PREVIOUS EDITIONS ARE OBSOLETE Page 5 of 8 Pages
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing
2. TITLE OF DATA ITEM
Installation and Preparation Documentation
3. SUBTITLE
Equipment Identification
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
13. DATE OF SUBSEQUENT
SUBMISSION
SEE BLOCK 16
a. ADDRESSEE Draft
Final
Reg Repro
16. REMARKS
The contractor shall provide a copy of this information either in electronic or paper format, a minimum of 60-calendar-days prior to delivery of equipment.
This document shall consist of the make & model of the equipment with a complete list of standard features, optional features being installed in order to meet the specification, and a list of optional features available for field installation but not included. Each section shall be clearly identified.
Also included will be any technical data or brochures applicable to the equipment being provided.
ATTN: TARA-LGC
Jeffery Merry
Tad Larson
H. DATE
DD Form 1423-1, SEP 97 (EG) (Computer Generated) PREVIOUS EDITIONS ARE OBSOLETE Page 6 of 8 Pages
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing
2. TITLE OF DATA ITEM
Maintenance Manual
3. SUBTITLE
Preventive Maintenance Procedure
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
13. DATE OF SUBSEQUENT
SUBMISSION
SEE BLOCK 16
a. ADDRESSEE Draft
Final
Reg Repro
16. REMARKS
The contractor shall provide (3) copies of this manual/information with delivery of the equipment. Of these, (2) will be paper, and (1) shall be electronic. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and initial graphic exchange specification (.igs).
This section of the documentation shall include: Daily Operator Checklist, Visual Inspections, and a Lubrication Schedule. Procedures and schedules for inspections, adjustments, cleaning, and component replacements.
ATTN: TARA-LGC
Jeffery Merry
Tad Larson
H. DATE
DD Form 1423-1, SEP 97 (EG) (Computer Generated) PREVIOUS EDITIONS ARE OBSOLETE Page 7 of 8 Pages
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing
2. TITLE OF DATA ITEM
Operator Manual
3. SUBTITLE
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
13. DATE OF SUBSEQUENT
SUBMISSION
SEE BLOCK 16
a. ADDRESSEE Draft
Final
Reg Repro
16. REMARKS
The contractor shall provide (3) copies of this manual/information with delivery of the equipment. Of these, (2) will be paper, and (1) shall be electronic. Acceptable electronic formats include acrobat files (.pdf), drawing exchange files (.dxf), and initial graphic exchange specification (.igs).
This section of the documentation shall include: Procedures for safe operation of the equipment in all modes. It shall include information necessary for performing all the operations and utilizing all the functions listed in the purchase description.
ATTN: TARA-LGC
Jeffery Merry
Tad Larson
H. DATE
DD Form 1423-1, SEP 97 (EG) (Computer Generated) PREVIOUS EDITIONS ARE OBSOLETE Page 8 of 8 Pages
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing
2. TITLE OF DATA ITEM
Pre-Shipment Testing Report
3. SUBTITLE
12. DATE OF FIRST SUBMISSION
SEE BLOCK 16
14. DISTRIBUTION
13. DATE OF SUBSEQUENT
SUBMISSION
SEE BLOCK 16
a. ADDRESSEE Draft
Final
Reg Repro
16. REMARKS
The contractor shall provide (1) copies of this information in paper format no later than 10-calendar-days prior to delivery of the equipment.
ATTN: TARA-LGC
Jeffery Merry
Tad Larson
H. DATE
| CONTRACT DATA REQUIREMENTS LIST |
| Form Approved |
| B. EXHIBIT |
| C. CATEGORY |
| E. CONTRACT/PR NO. |
| 001 |
| SEE BLOCK 16 |
| SEE BLOCK 16 |
| Draft |
| G. PREPARED BY |
| CONTRACT DATA REQUIREMENTS LIST |
| Form Approved |
| B. EXHIBIT |
| C. CATEGORY |
| E. CONTRACT/PR NO. |
| 001 |
| SEE BLOCK 16 |
| SEE BLOCK 16 |
| Draft |
| G. PREPARED BY |
| CONTRACT DATA REQUIREMENTS LIST |
| Form Approved |
| B. EXHIBIT |
| C. CATEGORY |
| E. CONTRACT/PR NO. |
| 001 |
| SEE BLOCK 16 |
| SEE BLOCK 16 |
| Draft |
| G. PREPARED BY |
| CONTRACT DATA REQUIREMENTS LIST |
| Form Approved |
| B. EXHIBIT |
| C. CATEGORY |
| E. CONTRACT/PR NO. |
| 001 |
| SEE BLOCK 16 |
| SEE BLOCK 16 |
| Draft |
| G. PREPARED BY |
| CONTRACT DATA REQUIREMENTS LIST |
| Form Approved |
| B. EXHIBIT |
| C. CATEGORY |
| E. CONTRACT/PR NO. |
| 001 |
| SEE BLOCK 16 |
| SEE BLOCK 16 |
| Draft |
| G. PREPARED BY |
| CONTRACT DATA REQUIREMENTS LIST |
| Form Approved |
| B. EXHIBIT |
| C. CATEGORY |
| E. CONTRACT/PR NO. |
| 002 |
| SEE BLOCK 16 |
| SEE BLOCK 16 |
| Draft |
| G. PREPARED BY |
| CONTRACT DATA REQUIREMENTS LIST |
| Form Approved |
| B. EXHIBIT |
| C. CATEGORY |
| E. CONTRACT/PR NO. |
| 003 |
| SEE BLOCK 16 |
| SEE BLOCK 16 |
| Draft |
| G. PREPARED BY |
| CONTRACT DATA REQUIREMENTS LIST |
| Form Approved |
| B. EXHIBIT |
| C. CATEGORY |
| E. CONTRACT/PR NO. |
| 005 |
| SEE BLOCK 16 |
| SEE BLOCK 16 |
| Draft |
| G. PREPARED BY |
File details come from the government source that posted it. Updated .