This document summarizes an industry day presentation related to a federal contract opportunity for an Air Route Surveillance Radar version 4 replacement in Hawaii. The Air Force is seeking to replace the aging ARSR-4 radar system on Oahu with a new S-band radar to provide air traffic surveillance and missile defense capabilities. The acquisition will proceed in two phases, with the first being a competitive prototype demonstration by two vendors and the second involving rapid prototyping, testing and installation by a single downselected contractor. The industry day briefing provided an overview of radar requirements, the acquisition approach and schedule, as well as plans for product support and site implementation activities to integrate the new radar system into the National Airspace System. The Federal Aviation Administration will lead site selection and upgrades to power and communications infrastructure to enable operation of the replacement radar.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ARSR4R-HI Industry Day.pdf | ||
| Industry Day Welcome Package.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
D I G I T A L D I R E C T O R A T E
Air Route Surveillance Radar v4 Replacement
Hawaii (ARSR4R‐HI) Industry Day
Sueann Paradiso, PM (AFLCMC/HBA) 28‐29 November 2023
CUI
CUI
Controlled by: AFLCMC/HB Controlled by: AFLCMC/HBA CUI Category: BASIC Distribution/Dissemination Controls: Distribution D POC: Comm: Sueann Paradiso, sueann.paradiso@us.af.mil
Agenda
CUI
CUI
Admin/Safety Instructions/Security Opening Remarks Legal Disclaimer Contracting Officer Remarks Program Overview Logistics Strategy Break Site Implementation Overview Lunch One‐on‐One Sessions
UNCLASSIFIED
UNCLASSIFIED
Admin/Safety/Security
A
UNCLASSIFIED
Admin/Safety/Security
A
Overview
Jul 2022 DEPSECDEF Memo delegated lead acquisition to Air Force for ACMD‐H mission
Oct 2022 PDM I direction for replacement Radar on Oahu; ACMD and Air Traffic Control
Mar 2023: ACC/A5Y designated as Lead Command; PACAF as Lead Using Command
May 2023: SAF/AQX MFR: Candidate PEO Identification for Long‐Range Radar Replacement
May 2023: PEO Digital concurs as the conditional candidate PEO for ARSR4R‐HI
ARSR‐4 Site Oahu, HI (Mt Ka’ala) Notional 4 face array Legacy ARSR‐4
CUI
Requirements:
CONOPS (USAF) in work w/PACAF CONOPS (FAA) in work w/FAA Rapid Prototype Requirements Document (RPRD) planned by ACC/A5Y System Requirements Document in work w/Hanscom/FAA Site Requirements in work w/FAA
Key Requirements/Attributes (Notional):
S‐band Air Cruise Missile Defense/Air Traffic Surveillance Radar w/IFC per PDM
Detect, Track and support engagement of new threats
Non‐cooperative/cooperative target identification, e.g., IFF/SIF (Mode 5/S)
Weather Surveillance
Interface with External Systems: C2 PADS, FAA ATC, ICBS/IFCN, CEC
Cybersecurity (comply w/ NIST 800.53 rev 5 & Zero Trust Approach Exec Order)
Market Research Activities:
Sept 2023: Request for Information (RFI) Nov 2023: Industry Day Jan 2024: Market Research Report (internal DoD)
Continuing Resolution impacting funding for program
Status
Acquisition Approach (pre‐decisional)
CUI
CUI
Competitive approach: best value for best performance 2 Phases: Phase 1: Rqmnts/demo; Phase 2: NRE, test, install
Phase 1: compete for 2 vendors to develop requirements and execute an operational capability demonstration (a mix of M&S and Field Testing, for score); OTA contracts
Request cost proposal for Phase 2 Rapid Prototyping effort during execution of Phase 1
Down select to 1 vendor (best value cost/demo capability score) Phase 2: Rapid Prototyping C/A: NRE, design, test, deliver, install radar to Mt Ka’ala site; Initial Contractor Support (ICS); FAR Part 15 Contract type
Operational test and acceptance for IOC; post ICS‐ transition O&S to Long Range Radar National Defense Program Joint Program Office
Notional Schedule
Product Support Strategy
CUI
CUI
Assumption: National Defense Program Long Range Radar Joint Program Office (NDP LRR JPO) to execute maintenance & sustainment, as ARSR4’s currently are supported Plan to use current ARSR‐4 fleet support infrastructure FAA serves as primary/lead agency for:
Primary source of supply Source of repair Depot‐level for overall system Repairable LRUs
ARSR4R‐HI may include, as part of the contract action:
Spares Cataloging and Provisioning
Training Technical Data Two or more 1‐year options for Interim Contractor Support Handoff to NDP LRR JPO NLT 4QFY27
Additional product support requirements (TBD)
NAS Defense Programs
ARSR‐4 Replacement Hawaii Site Implementation Activities Initiative
Presented To: Industry Day Vendors
Distribution Statement D. Information contained in this briefing is provided for distribution authorized to the Department of Defense and U.S.
DoD contractors only. DIRECT MILITARY SUPPORT, 11/13/2023.
Other requests for this document must be referred to PEO Digital, HAB, ARSR4R-H PMO, Hanscom AFB.
11ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
• FAA NAS Defense Programs ̶ Implement the core infrastructure to integrate the ARSR‐4 replacement radar into the National Airspace System (NAS).
• This Initiative is called the Site Implementation activities ̶ Allows for the radar program to be “Power to Port”
• The initiative provides:
̶ Site Selection ̶ Chiller System ̶ Emergency/Standby Power System ̶ System Uninterruptable Power Supply ̶ Facility Power Upgrades ̶ NAS Communication Interface ̶ Site Preparations (Excavation and Demolition)
Project Charter
12ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
• 5 Phases:
Phase 1: Site Survey, Requirements and Approvals
Phase 2: Upgrade Facility Power at Mt Ka’ala, HI
Phase 3: Move Air to Ground (A/G) Radios and Relocate
Antenna Tower
Phase 4: Environmental Support System Engineering
Phase 5: Site Preparation
Implementation Approach
13ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
Phase 1 – Siting
• Preferred siting of replacement radar
• Conceptual layout of tower and environmental support systems
• Existing Air to Ground Radio’s and Antenna towers must be relocated and building demolished.
14ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
Phase 2 – Facility Power
• Facility Power transformer is currently rated for
500KVA
• Currently working with Hawaiian Electric Company (HECO) for current infrastructure maximum capabilities
15ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
Phase 3 – Tower & Radio’s
• New Air to Ground antenna tower will be installed between building 3 and 5.
• Antenna Cables will be routed to RML room inside Building 1
• RML room in Building 1 will be provisioned for the radio’s relocation
• Radios will be relocated once antenna’s, cabling and provisioning has been tested.
16ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
Phase 3 – Tower & Radio’s (con’t)
• Air to Ground Radio’s that will be relocated from building 2 to the RML room in Building 1.
• Proposed layout for Radio Racks in the RML Room
17ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
Phase 4 – Support Systems
• Conceptual Chiller
System key points:
• Modular
• Serviceability
• Minimal water usage
• Redundancy N+2
Note: Drawing not to scale and is meant to visualize concept.
18ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
Phase 4 – Support Systems (con’t)
• Conceptual
Emergency/Standby Power System, key points:
• Modular
• Serviceability
• 5 Day min
Continuous Run Time
• Redundancy N+1
19ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
Phase 4 – Support Systems (con’t)
• Conceptual
Uninterruptable Power Supply System, key points:
• Modular
• Serviceability
• Redundancy
20ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
Phase 5 – Site Preparations
• Air to Ground building 2 will be demolished
• Old Antenna towers will be removed
• Area will be excavated to accommodate support systems
21ARSR‐4 Replacement Hawaii (ARSR4R‐HI)
Phase 5 – Site Preparations (con’t)
• Old Antenna towers and footers will be removed
• Area will be excavated to accommodate support systems
Questions?