A. 805 Mobilization.pdf
PDF 12 KB Posted
- Attached to
- Carson National Forest- Road 44B Maintenance
- Solicitation number
- 12363N23Q4010
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12363N23Q4010-amendment2.pdf | ||
| Picture3.png | PNG image | |
| 12363N23Q4010-amendmentextension.pdf | ||
| Picture2.png | PNG image | |
| Picture5.png | PNG image | |
| Picture1.png | PNG image | |
| Picture4.png | PNG image | |
| 12363N23Q4010-Amendment1.pdf | ||
| A. 837-1 Drainage Dip Maintenance.pdf | ||
| A. 834 Drainage Structure Maintenance.pdf | ||
| A. 839-Restore Drainage Function.pdf | ||
| E. WageDetermination.pdf | ||
| 12363N23Q4010 (1).pdf | ||
| A. 837 Drainage Dip Maintenance.pdf | ||
| B. Fire Plan.pdf | ||
| D. CAF NFSR 44B MAP 2022.pdf | ||
| A. 807 Equipment Rental.pdf | ||
| C. CAF NFSR 44B WORK LOCATION SPREADSHEET.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
805 MOBILIZATION / EQUIPMENT MOVING (10/16)
1. DESCRIPTION
This Section consists of one or more mobilizations of personnel, equipment, supplies, and incidentals to the project site, or sites listed in the Schedule of Items.
2. REQUIREMENT
a. Make equipment available for inspection before it is used on National Forest System lands.
b. Moving is complete, when the contractor has moved from the present work site to the ordered work site and returned to the previous location.
c. Equipment will be clean and weed free before it arrives on National Forest System lands.
3. LOCATION OF WORK
As specified on roads listed on the Road Listing, Shown on the Plans, or as ordered by the
Contracting Officer.
4. MEASUREMENT
Measurement under this Section will be made by the total number of units for each item listed in the Schedule of Items completed and accepted.
Mile: work activity will be measured along the shortest feasible route to the nearest one (1) mile, from the starting location of the move, to the ordered work site.
5. PAYMENT
a. The accepted quantities will be paid at the contract price per unit of measurement for the
Section 805 pay items listed in the schedule of items. Mobilization is complete when all equipment, personnel, and materials are moved to the project site and work has been started. Payment will be full compensation for the work prescribed in this Section.
Mobilization is incidental unless ordered for a specific project at a specific time.
b. Payment will be made under:
Pay Item Description Pay Unit
805 (1) Mobilization Mile