This document is a Record of Categorical Exclusion for the project to repair mechanical systems and building improvements at B103. The proposed action includes replacing deteriorating hydronic floor-mounted fan coil units, rooftop package units, mini-split AC units, and ceiling exhaust fans. The new work involves installing new ceiling cassette type fan coil units, modifying existing piping, installing new rooftop package units and mini-split AC units, and adding new ceiling exhaust fans. Additional tasks include providing a new dedicated outdoor air system (DOAS) unit, new LED lighting, and new ceiling tiles. The project must comply with various environmental requirements related to soil disturbance, historic preservation, stormwater, hazardous materials, and asbestos/lead. The project is located at the Naval Air Station Patuxent River Complex and will be performed under Solicitation Number N40080-24-R-3956.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B_103 Repair Mechanical Systems and Building Improvements
February 2024
RECORD OF CATEGORICAL EXCLUSION
SUBJECT OF THE PROPOSED ACTION:
DESCRIPTION OF THE PROPOSED ACTION:
Replace deteriorating (24) hydronic floor mounted fan coil units to include associated fittings, piping, valves, and accessories. (2) 7.5 ton rooftop package units to include associated ductwork, disconnect switches, circuit breakers, conduits, wirings, piping, valves, temperature controls, and accessories. (2) Mini-split type a/c unit to include associated disconnect switches, circuit breakers, conduits, wirings, piping and accessories located in IDF room and locker room. (3) Ceiling exhaust fans located in first floor toilet male and female rooms and weather office room– 104.
The new work includes the following:
1) Provide and install new (26) ceiling cassette type fan coil units to include associated fittings, valves, piping, insulation, hanger, support, digital control, and accessories.
2) Modify existing fan coil units piping as required for installation of new ceiling cassette type units. Remove unused piping, fittings, valves, and associated accessories. Where required, drywall is removed add layer of ½ rigid expanded polystyrene (EPS) foam.
3) Provide and install new ceiling exhaust fan in second floor room 205; shower and toilet rooms to include circuit breakers, conduits, wirings, and associated accessories.
4) Provide and install new dedicated outdoor air system (DOAS) unit to include associated ductwork, housekeeping pad, disconnect switch, circuit breakers, conduits, wirings, control, sensors, and accessories.
5) Provide and install new LED luminaires, LED emergency luminaire, and associated accessories in air operation spaces. Where required, relocate lighting fixtures as required for installation of new ceiling cassette type units.
6) Provide and install new ceiling tiles and associated accessories matching the existing patterns and finishes in air operation spaces.
7) Extend RTU#2 new ductwork to provide cooling and heating in room 232, 233, and 234.
Modify ductwork as required to meet requirements of this project.
8) Modify existing panels to adapt to the new DOAS unit and ceiling exhaust fans.
Existing electrical wiring may be reused if capacity is adequate.
Building will remain occupied during construction. Heating, cooling, and dehumidification will need to be maintained in the Air Traffic control operation room during this project.
February 2024
SUMMARY OF ADDITIONAL ENVIRONMENTAL REQUIREMENTS:
These action items must be added to the specifications section of the contract or resolved before contract award.
Soil Disturbance - Historic and Archaeological Resources
Carefully protect in-place and report immediately to the Contracting Officer historical and archaeological items or human skeletal remains discovered in the course of work. Upon discovery, notify the Contracting Officer or their representatives. Stop work in the immediate area of the discovery until directed by the Contracting Officer to resume work. If any artifacts or relics that are not obvious modern trash or debris, please call the Cultural Resources Program Manager. Please take a digital image of the items along with a location map, and email them to the Cultural Resources Program Manager as soon as possible. The Government retains ownership and control over historical and archaeological resources.
Program Manger Comments:
This project will not impact an archeology site or previously undisturbed soil. Therefore, no additional archeological surveys are required.
Historic Preservation
Although this project occurs on a historic building, the action is considered routine maintenance and repair and does not have an adverse effect on the building. Therefore, consultation with the State Historic Preservation Office is not required.
Soil Disturbance - Stormwater
Must provide the Stormwater Program Manager a map with dimensions of the new surface to track for Chesapeake Bay Total Maximum Daily Load (TMDL).
Project is still subject to proper Maryland Best Management Practices for sediment erosion control and stormwater management even though official MDE notification is not required.
Contact the Stormwater Program Manager if you have any questions.
Water - Wastewater
If any new drain lines are created, please ensure they do not drain to sanitation.
Solid Waste and Recycling
Contact the Environmental Compliance Branch Head with the list of items and quantities that can be recycled. The Contractor must provide copies of all weight and landfill tickets to the Environmental Specialist within five days after removal from base.
Per the installation’s Stormwater Pollution Prevention Plan, ensure any on site dumpster doors remain closed when not in use (i.e., doors should only be open when actively disposing). Dumpster should not be filled past capacity to ensure doors can be physically
February 2024 shut. If the dumpster is being stored on a vegetated surface, such as a grass lawn, the area must be reseeded and stabilized after the project is completed.
Environmental General Awareness Training
All NASPRC personnel (including military, civilian, and contractors) are required to take the Environmental General Awareness Training.
ECATTS is an online environmental training site that can be accessed from any computer with access to the internet (you do not need a CAC). Instructions for taking the Environmental General Awareness Training in ECATTS:
o Go to https://environmentaltraining.ecatts.com o In the “NEW USERS-Register Here” box in the center of the page, enter "navfac" as the registration password and click on Create an Account.
o Complete only required fields in the registration form (help available at 866-730-
4253). You will be asked to select a UIC code (the NASPRC UIC code is 47608). Do not select any of the “training selection” options. Scroll to the bottom of the page, agree to the terms of use by selecting the appropriate box, and click “register”.
o Once you are properly logged into the system, you should see a page with the “EMS Training” heading at the top. Click on this heading and it will take you directly into the “Environmental General Awareness Training: Naval Air Station Patuxent River Complex (NASPRC)”.
o Read the training, complete the quiz, print the certificate and maintain it in your training records. You can request a roster from the EMS Manager by providing a list of names.
Air Quality and Emissions
Ensure the contractor provides a copy of each technician’s HVAC certification and the certification for each piece of equipment*. Contact the Air Quality Program Manager for assistance and additional information.
Per 40 CFR 82-97, refrigerant(s) must be recovered from each appliance prior to final disposal of the appliance. The refrigerants shall be evacuated to the levels specified in the regulation prior to opening/disposing of the appliance. Ensure the contractor provides a signed statement to the Air Quality Program Manager with the following information:
o Former location of the appliance, as it was installed/operated;
o Date the refrigerant is recovered from each appliance prior to being disposed;
o Type and quantity of refrigerant recovered from each disposed appliance; and o Name and address of the certified technician who recovered the refrigerant;
o Name and address of the person to whom the recovered refrigerant is transferred for reclamation or disposal*; and o Date that the recovered refrigerant is transferred for reclamation/disposal*.
No R-22 refrigerant shall be transferred to the Contractor. All excess/residual R-22 shall be recycled by depositing in the Navy’s portion of the ODS Reserve in accordance with
February 2024 specified procedures (www.dla.mil/Aviation/Offers/Services/AviationEngineering/OzoneDepRsrv.aspx), and as required by OPNAV-M 5090.1, Chapter 22. The collection cylinders for the recovered R-22 may be supplied by the government*. Notify the Air Quality Program Manager ASAP so that collection cylinders may be acquired for the project.
Do not procure new equipment containing an Ozone Depleting Substance (ODS) (e.g., R-22 refrigerant), per OPNAV-M 5090.1, Chapter 22. Notify the Air Quality Program Manager of the refrigerant type and charge amount used in new HVAC equipment.
Do not apply an architectural coating with a VOC content in excess of the corresponding limit specified in COMAR 26.11.39.05*. Coatings of this nature include paints and other coatings that are applied to stationary structures, portable buildings at the site of installation, pavements, and curbs. Contact the Air Quality Program Manager for assistance and additional information.
Do not apply an adhesive/sealant with a VOC content in excess of the corresponding limit specified in COMAR 26.11.35.04. These include adhesives, sealants, adhesive primers, and sealant primers. This chapter contains additional requirements for adhesives, sealants, as well as associated surface prep and cleanup solvents. Contact the Air Quality Program Manager for assistance and additional information.
Program Manager Comments:
Follow the above action items and incorporate as appropriate into all specifications (e.g., RFPs SOWs) associated with this project. Additional information is provided below:
*Technicians must be certified per EPA requirements at 40 CFR 82 [OPNAV-M 5090.1, Chapter 22]. Equipment used to recover, recycle, or reclaim refrigerant must also meet EPA standards.
*Technicians who dispose of appliances containing more than 5 lbs of refrigerant, must keep detailed records on both the recovery of refrigerant from the appliance, and the refrigerants’ ultimate transfer for disposal/reclamation (per 40 CFR 82, as amended).
*Regarding the R-22 turn in, the REQUIREMENT is for the project to collect it into dedicated cylinders and ship to DLA in Richmond. There are no-cost OPTIONS for meeting this requirement that are available during execution:
1) to have DLA (via NAVFAC EV) supply the cylinders to the contractor to fill;
2) DLA will pay for shipment of the filled cylinders (either the DLA- or contractor-owned) back to Richmond (note: contractor-owned cylinders will not be returned);
and/or
3) NAVFAC EV (via NAVSUP HazMin Center) can offer transport of the filled cylinders from the worksite to the HazMin Center warehouse, where they will be stored and shipped to Richmond.
February 2024
*Example architectural coating VOC content limits:
Flat Coatings - 0.42 pound VOC per gallon coating (lb/gal) (50 grams per liter (g/L)) Non-Flat Coatings - 0.83 lb/gal (100 g/L) Non-Flat High-Gloss Coatings - 1.2 lbs/gal (150 g/L) Primers, sealers, undercoats - 0.83 lb/gal (100 g/L) Rust preventive coatings – 2.08 lbs/gal (250 g/L)
For other coating categories and associated VOC content limitations, refer to COMAR
26.11.39.05 or contact the Air Quality Program Manager with questions.
*Example adhesive/sealant VOC content limits:
Cove Base Installation Adhesives – 1.25 pounds VOC per gallon product (lbs/gal) (150 grams per liter (g/L)) Multipurpose Construction Adhesives – 1.67 lbs/gal (200 g/L) Architectural Sealants – 2.08 lbs/gal (250 g/L) PVC adhesives – 4.25 lbs/gal (510 g/L)
For other adhesive/sealant categories and associated VOC content limitations, refer to COMAR 26.11.35.04 or contact the Air Quality Program Manager with questions.
Asbestos and Lead
Structures or buildings that were constructed prior to 1988 have the potential to contain asbestos and/or lead based paint. If the proposed project involves any type of renovation, alteration, or demolition, asbestos or lead based paint abatement may be required. Contact the Asbestos Program Manager for further guidance.
If the work area is found to contain regulated asbestos-containing material (RACM)*, the project activities must comply with the requirements of 40 CFR 61, Subpart M (National Emissions Standard for Asbestos – Demolition and Renovation) and 29 CFR 1926.1101 (OSHA Asbestos in Construction), as well as Maryland Title 26 - Department of the Environment regulations (COMAR 26). The regulations require that each owner or operator of a demolition or renovation activity involving RACM remove all such material from a facility being demolished or renovated before any activity begins that would break up, dislodge, or similarly disturb the material or preclude access to the material for subsequent removal.
If there is a release of asbestos fibers, or if there is a potential for release of lead based paint dusts, contact the Air Quality Program Manager for assistance and additional information.
If abatement is required on a project, an abatement plan is required by a State of Maryland Licensed Project Designer. All asbestos- and lead paint-containing waste shipping manifests shall be signed by a designated and qualified government representative.
Program Manager Comments:
RFPs SOWs) associated with this project. Additional information is provided below:
February 2024
*RACM includes “a) friable asbestos material; b) Category I nonfriable ACM that has become friable; c) Category I nonfriable ACM that will be or has been subjected to sanding, grinding, cutting, or abrading; or d) Category II nonfriable ACM that has a high probability of becoming or has become crumbled, pulverized, or reduced to powder by the forces expected to act on the material in the course of demolition or renovation operations…” [40 CFR 61.141]
Hazardous Materials
The Contractor will ensure proper handling, storage and proper disposal of all hazardous material (e.g., refrigerants, adhesives, sealants/caulks, coatings/paints, other products used by the project that require SDS)
The Contractor is responsible for ensuring that personnel are trained in the Hazardous Communication (HAZCOM) Standard prior to hazardous material usage.
The Contractor will maintain records throughout the course of the project of all manpower and material expenditures and will ensure accountability for material in the Contractors possession.
The use of hazardous materials in this project may be subject to the installation's regulatory reporting requirements under the Emergency Planning and Community Right-To-Know Act (EPCRA). The following information shall be submitted to the HazMat/EPCRA Program Manager as soon as possible:
o SDS and product specs for all hazardous materials to be applied/used.
o General description of the intended use for each product.
o Total amount used (preferably weight).
o Span of dates the products are used.
o Maximum amount of product that will be on site AT ONE TIME.
Ensure contractors working on new construction projects remove all unused hazardous materials and waste generated by the project.
NDWINST 5090.1 4 May 2018 (Regional CHRIMP Instruction)
Ch. 23 and Ch. 26 of OPNAV-M 5090.1
RFPs SOWs) associated with this project.
Hazardous Waste
Contractors are responsible for cost and removal of all regulated waste (Hazardous Waste, Universal Waste, Non-RCRA Regulated Waste) generated by the project in accordance with all federal, state, local, and Navy regulations.
Contact the Regulated Waste Program Manager to assist in waste stream determination.
Examples of commonly generated regulated waste include, but are not limited to:
February 2024 oil/fuel/lubricant material and contaminated debris, lead contaminated debris, lead paint, solvent/paint/thinner/stain material and contaminated debris, fuels/oils/lubricants, mercury switches, batteries, aerosol cans, and compressed gas cylinders.
Waste lamps and ballasts shall be handled as universal waste or hazardous waste dependent upon their condition. Lamps/bulbs including fluorescent, HID, neon, high-pressure sodium, CFL, metal halide, LED, or mercury vapor are considered universal waste when in undamaged condition and shall be managed accordingly. Broken lamps are hazardous waste and shall be managed accordingly.
Ensure all regulated waste is properly stored, labeled/marked, and disposed in accordance with the following local, state, and federal regulations:
o Title 40, Code of Federal Regulations, Parts 260-279 o COMAR, Title 26.13 o OPNAVINST 5090.1
All waste disposal documentation (manifests/shipping papers) require the signature of the Regulated Waste Program Manager or someone authorized by the Regulated Waste Program Manager prior to shipping off base.
Follow the above guidance throughout the project for all waste generated and contact the Regulated Waste Program Manager for further guidance as needed.
Environmental Restoration
Contact the Environmental Restoration Program Manager to discuss options.
Since the site is located on an environmental restoration site that has PFAS-contaminated soil and groundwater, any soil or groundwater excavation/removal must be handled as follows:
1) Everyone doing the excavation will need to have the HAZWOPER 40-hour class and a current annual refresher certification (if initial class was over a year). Level D PPE.
2) The contractor would need to give the government all the survey coordinates (surface excavation, bottom of the excavation).
3) The soil/groundwater will need to be tested to determine if it is hazardous waste. The contractor will need to work with the Regulated Waste Program to coordinate roll-off delivery (to hold the soil until the samples come back, disposal, and the funding requirements. The roll-offs would need to remain on site, covered (rain would add weight to the soil).
4) Sampling will be done through this contract’s, not the Environmental Restoration (ER) program. Expedited sampling is recommended if possible (48 hr or 72 hr versus the 4-week
February 2024 typical wait time). The analysis that needs to be done is EPA Method SW-846 1311 for TCLP, Ignitability, Reactivity, and Corrosivity, and EPA Method 1633 for PFBA, PFPeA, PFHxA, PFHpA, PFOA, PFNA, PFDA, PFUnA, PFDoA, PFTrDA, PFTeDA, PFBS, PFPeS, PFHxS, PFHpS, PFOS, PFNS, PFDS, PFDoS, PFOSA, MeFOSA, EtFOSA, MeFOSE, EtFOSE, MeFOSAA, EtFOSAA, 4:2FTS, 6:2FTS, 8:2FTS, HFPO-DA, ADONA, 9Cl- PF3ONS, 11Cl-PF2OUdS, PFMPA, PFMBA, NFDHA, PFEESA, 3:3FTCA, 5:3FTCA, and 7:3FTCA. Be aware that any soil samples that have detectable levels of PFAS must be disposed of properly off site.
Petroleum Systems
Must notify the Naval Air Station Fire Department and the Tanks Program Manager. The project will be located within 100 feet of an AST, UST, or fuel line. Please use extreme caution when disconnecting and replacing the fuel lines. The proposed project design shall be reviewed by the Tanks Program Manager at each design phase.
There is an AST (P-103A) located within 100 feet of B103. Please be mindful of the location of these tanks during the entirety of the project.
Spill Contingency Planning
B103 has an aboveground storage tank (AST) supplying fuel oil to the buildings dual fuel boiler (natural gas/fuel oil). Caution should be taken while working around fuel tank and associated supply/return fuel lines to the boiler.
PRESENCE OF NORMAL CIRCUMSTANCES:
This proposed action will not affect public health or safety. No wetlands or migratory bird populations will be affected by this action, and no listed threatened or endangered species are located in the vicinity. Although this project occurs on a historic building, the action is considered routine maintenance and repair and does not have an adverse effect on the building.
Therefore, consultation with the State Historic Preservation Office is not required. This project will not impact an archeology site or previously undisturbed soil. Therefore, no additional archeological surveys are required. The proposed action does not have the potential for significant environmental effects on hazardous waste sites, according to the Federal Facilities Agreement. This action will not involve effects on the human environment that are highly uncertain, involve unique or unknown risks, or that are scientifically controversial. Finally, the proposed action does not establish a precedent nor threaten a violation of Federal, State, or local environmental law.
GENERAL CONFORMITY RULE DETERMINATION:
In accordance with Section 176(c) of the Clean Air Act, the action is located in an attainment area for NAAQS levels PM10, NO2, SO2, Carbon Monoxide, Ozone, and Pb (St. Mary’s County, February 2024
MD), and is not subject to the conformity rule. This project will also meet the Northeastern Transport Region levels of 50 tons/year for Ozone.
CONCLUSION:
The subject proposed action can be categorically excluded from further National Environmental Policy Act (NEPA) processes per OPNAVINST 5090.1, Reference (c), Section 10.3.14, Table 10-6:
(8) Routine repair and maintenance of buildings, facilities, vessels, aircraft, ranges, and equipment associated with existing operations and activities (e.g., localized pest management activities, minor erosion control measures, painting, refitting, general building/structural repair, landscaping, grounds maintenance)
Action reviewed by:
NEPA Coordinator Betsy Isley
Requirements accepted by:
Project Lead Joel Rodriguez
This document does not relieve the proponent of compliance with applicable federal and state laws and regulations.
If the scope of work is modified, the Project Manager/Design Manager (or Construction Manager if Post Award) must update the Planning Checklist and have the Categorical Exclusion reviewed for accuracy.
| 2024-02-27T09:51:55-0500 | |
| ISLEY.BETSY.G.1595205634 |
| 2024-02-27T10:11:33-0500 | |
| RODRIGUEZ.JOEL.TAGAYONG.1260655007 |
File details come from the government source that posted it. Updated .