A.02 Product Description (25-R-A006).pdf
PDF 311 KB Posted
- Attached to
- CES - Replace Heaters
- Solicitation number
- W912L325RA008
About this file
This is a Purchase Description Memorandum from the 153 Air National Guard Civil Engineering Squadron (153 ANG CES) for replacing heating systems in two buildings (Buildings 35 and 40) at the Army Aviation Support Facility in Cheyenne, Wyoming. The procurement involves replacing one furnace in Building 40 (Lennox G61MPV-60C-090-07 model, Natural Gas, 80/90 BTU/hr input, 96% efficiency) and 13 infrared heaters in Building 35 (Model UA150, 150000 BTU input, Natural Gas, 115V 60Hz 1A). The vendor must conduct site assessments, safely remove existing units, install new equipment according to manufacturer specifications and local codes, perform fresh air intake installations, test systems for functionality and safety, and deliver within 30 days of order receipt to 217 Dell Range Blvd, Cheyenne, WY 82009. The technical point of contact is MSgt Michael Dooley, who will review the contractor's performance before final invoice acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B.06 RFIs Answered (25RA008).pdf | ||
| Solicitation - W912L325RA008.pdf | ||
| RFP Instructions (25RA008).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
26 August 2025
MEMORANDUM FOR USPFO WY – P&C
FROM: 153 ANG CES
SUBJECT: Purchase Description for Replace Heaters W912L3-R-A006
Background / Purpose: To improve heating performance and reliability in Building 35 & 40, the existing heating systems will be replaced. The current units are nearing the end of lifespan and have demonstrated numerous functional problems.
1.
2. Minimum Specifications: The vendor shall provide the following minimum specifications.
Building # TITLE QTY
1. 40 Furnace 1
2. 35 Infrared Heating System 13
3. Additional Description: The new equipment must include the following salient description:
• Building 40 Furnace: The new furnace shall be of an equivalent spec (e.g., Natural Gas, furnace with an 80/90 BTU/hr input and a 96% efficiency rating.
The make and model are Lennox G61MPV-60C-090-07.
o Replacement Instructions:
o Site Assessment:
- Conduct a site assessment to evaluate the existing furnace, including size, capacity, gas line configuration, ductwork, venting, and available space.
- Recommend a replacement unit based on facility needs (e.g., BTU rating, energy efficiency).
- Identify any potential challenges or modifications required for installation.
- Ensure all repairs comply with local, state, and national fire safety regulations.
o Safety Measures:
- Implement safety protocols for the repair work, including the use of personal protective equipment (PPE).
o Remove Existing Unit:
- Safely disconnect and remove the existing furnace, including all associated components (e.g., duct connections, gas line, electrical wiring, venting).
- Properly dispose of the old furnace and all associated waste materials in accordance with environmental regulations.
o Replace Components:
- Install the new furnace according to the manufacturer's specifications and all applicable codes and regulations. The new furnace shall be of an equivalent spec.
-Connect the new natural gas unit to existing gas lines, water lines, electrical (if required) and venting system, ensuring proper fittings and seals.
- Connect the furnace to the existing ductwork, gas line, electrical connections, and venting system.
- Ensure all connections are secure and leak-free.
- Inspect the existing ductwork for leaks, damage, and proper insulation.
- Clean the work area, removing any debris or leftover materials.
- Contractor responsible for disposing of old hot water heaters o Programming:
- Program new furnace controls on EMCS.
- Follow existing programming for new furnace install, with same parameters.
• Building 35 Infrared Heating System: New infrared heaters need to match Model UA150, input BTU 150000, Nat Gas, and 115V 60Hz 1A.
o Replacement Instructions:
Removal of Existing Heaters:
• Safely disconnect and remove 13 existing infrared heaters from their mounting locations.
• Dispose of old heaters in accordance with local environmental and waste disposal regulations.
Procurement and Installation of New Heaters:
- Supply 13 new infrared heaters (specifications to be approved by contracting).
- Install new heaters in optimal locations to ensure efficient heating coverage, adhering to manufacturer guidelines and local codes.
- Connect heaters to existing power/gas lines, ensuring proper electrical or fuel supply compatibility.
Installation of Fresh Air Intakes:
- Conduct a site assessment to determine optimal locations for fresh air intakes, considering hangar layout, airflow requirements, and compliance with ASHRAE or local ventilation standards.
- Install fresh air intake vents (number and size to be determined based on hangar size and ventilation needs, e.g., 2–4 intakes).
- Include ducting, dampers, and filters to ensure proper airflow and air quality.
- Integrate intakes with any existing control systems or install new controls for manual/automatic operation.
- Ensure weatherproofing and insulation of intake systems to prevent heat loss and protect against environmental elements.
- Test all heaters for functionality, safety, and performance post-installation.
• Testing:
- Turn on gas, electricity, and test the system for leaks, proper ignition, and temperature delivery.
- Adjust temperature settings to 72 degrees to meet facility requirements.
- Perform a safety inspection, including carbon monoxide detection and venting functionality.
4. Special Considerations: None.
5. Delivery: The vendor shall deliver no later than 30-days after receipt of order.
Delivery shall be made to: Army Aviation Support Facility @ 217 Dell Range Blvd, Cheyenne, WY 82009.
6. Quality Assurance: The vendor shall provide these brand new items according to acceptable standards.
7. Inspection / Acceptance: The technical point-of-contact will review the contractor’s performance, prior to the acceptance of a final invoice submitted by the vendor.
MSgt Michael Dooley
Technical Point of Contact
| 2025-08-27T09:17:36-0600 | |
| DOOLEY.MICHAEL.JOHN.1148518412 |