This statement of work outlines requirements for the renovation of the Kalvarija Fire Brigade Station in Kalvarija, Lithuania. The project includes replacing the building's heating system, installing a new vehicle exhaust extraction system in the garage, and renovating plumbing and sanitary systems. The US Army Corps of Engineers Europe District will select one contractor through a design-build solicitation to complete architectural, structural, electrical, and mechanical design and construction services. Requirements include demolishing existing systems in specified areas, installing new insulation, replacing the garage door and ceiling height, and providing designs, submittals, and construction documents in accordance with the scope of work and referenced codes.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers Europe District

APO AE 09049

Li11

Statement of Work Project Number: OHASIS 39004

Renovation of Kalvarija Fire Brigade Station Kalvarija, Lithuania

Prepared by:

Design Section

Engineering Branch 30 October 2020

01 10 10 Statement of Work Kalvarija, Lithuania

1-Dec-20 Page 2 of 52

SECTION 01 10 10

STATEMENT OF WORK

SECTION TABLE OF CONTENTS:

1 GENERAL

2 CIVIL AND GEOTECHNICAL (Not applicable)

3 ARCHITECTURAL

4 STRUCTURAL

5 ELECTRICAL & COMMUNICATIONS

6 MECHANICAL & PLUMBING

ATTACHMENTS

Attachment # 1 Location Map Attachment # 2 Conceptual Site Plan Attachment # 3 Annotated drawings Attachment # 4 Structural Calculations Guideline Attachment # 5 Dedication Plaque

1.0 GENERAL

1.1 PROJECT DESCRIPTION

The Request for Proposal (RFP) provides parameters for a design-build project for renovation of a fire station in Kalvarija, Lithuania; Latitude 54°24'16.1" N, Longitude 23°13'47.0" E W (See Attachment #1-Location Map.)

The Kalvarija Fire Brigade Station was constructed in the 1950’s and has not had significant modernization or rehabilitation of the building or components since.

The facility is inadequate compared to modern day standards and the current condition hinders the response capabilities and resiliency of the Fire and Rescue Service.

The Kalvarija Fire Brigade Station is a one story building including 2 vehicle garage bays and one equipment maintenance bay, offices, team sleeping room /rest area and break room.

The roof has been replaced more recently and the exterior has been painted, but no insulation was added. The walls and roof are not insulated. The building uses coal boilers to run hot water through radiators. The heating system is out dated and the heating pipes are narrow and insufficient. The current sanitation facility is located in the heating room and includes one shower and one toilet. The sleeping room/ rest area for firemen lack dressing room and shower area. The walls have signs of mold and visible crack lines. The entrance area corridor walls have larger cracks throughout. There is a 30 cm level difference between the ceilings height of the 2 vehicle bays. Larger vehicles cannot enter the bay with the lower ceiling height.

The facility was not constructed with occupational health and safety or environmental protection in mind. The vehicle garage does not have a code compliant vehicle exhaust extraction system installed.

The project includes the following general items of work, detailed requirements are contained elsewhere in this Statement of Work:

a. Insulate exterior walls and provide insulation in the attic;

b. Replace the heating system;

c. Modify interior layout and relocate the sanitation facility;

d. Adjust the height of the lower garage door and the ceiling height to enable taller vehicles enter the garage; and

e. Provide vehicle garage exhaust extraction system.

1-Dec-20 Page 3 of 52

1.2 GENERAL REQUIREMENTS

The Contractor must deliver fully functional, turnkey type facilities (without mobile furniture) as described in this document. The work includes - but is not limited to - design, demolition, fabrication, delivery, installation, construction, and site work. The facility and the installed equipment must be permanent construction.

The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.

These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.

1.2.1 BASE ITEMS AND OPTIONAL ITEMS

This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to Specification Section 01 22 00 PRICE AND PAYMENT PROCEDURES. The Schedule of Items identifies the breakdown between the individual base items and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base or Optional Items. Consider all items not specifically identified in the Optional Items as part of the Base Items.

1.3 FUNCTIONAL AREAS

Refer to the attached drawings for a depiction of the required functional areas and spatial adjacencies for the facility.

1.4 SUBMITTALS

Designer of Record approval is required for submittals with a “DA” designation.

Government approval is required for submittals with a “G” or “GA” designation.

Submittals having an “FIO” designation are for Contractor Quality Control approval. Submit the following to the Contracting Officer (KO) in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Demolition Plan; G

Sequencing Plan; G

SD-05 Design Data

65% Pre-Final Design; DA/GA

95% Final Design; DA/GA

100% Corrected Final Design; DA/GA

1-Dec-20 Page 4 of 52

SD-06 Test Reports

Test Results and Reports; FIO

1.4.1 DESIGN SUBMITTALS

Provide a complete design package at each milestone, as described in RFP Section 01 33 16-DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.

1.4.2 TEST REPORTS

Provide all test results and reports identified in this SOW to the Government as a submittal in accordance with RFP Section 01 33 00-SUBMITTAL PROCEDURES. Submittals will be considered for information only (FIO) submittals unless specifically identified as a submittal requiring government approval. Coordinate with the KO after award for the specific items to be included in the submittal register.

1.5 MATERIALS AND EQUIPMENT

Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.

Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the KO.

1.5.1 LIFE-SPAN

Construction must have an expected life span of 25 years.

1.5.2 MAINTAINABILITY

Provide low maintenance materials and systems appropriate for the project climate and location.

1.5.3 OPERABILITY

Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.

1.5.4 STANDARDIZATION

Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.

1.6 DESIGN DIMENSIONS

Develop the design using the metric system.

1.7 DESIGN CRITERIA

Project design, site facilities, utility systems and material standards must be in accordance with Host Nation building codes. In the absence of Host Nation building codes, use the International Building Code (IBC) and codes, technical standards, and regulations referenced in this RFP.

While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or

1-Dec-20 Page 5 of 52 other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the KO. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.

Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

1.8.1 DEMOLITION

The Contractor is responsible for all required demolition as indicated in this scope.

Submit a Demolition Plan to be tracked via the submittal register indicating all demolition, abatement, and disposal methods.

1.8.1.1 ABATEMENT AND DISPOSAL

All demolished materials, including hazardous materials identified below, must be abated and disposed of in accordance with local laws, codes and regulations. The Contractor is responsible for all required testing before, during and after demolitions as well as for all required compliance with safety standards.

1.8.1.2 LOCATION OF HAZARDOUS MATERIAL

The Contractor is responsible to survey the site and determine if hazardous materials exist. If hazardous materials are found to exist, immediately notify the KO and provide the results of the relevant sampling and testing. Provide the hazardous material report no later than 30 days after Notice to Proceed (NTP) for information and approval.

1.8.2 PROTECTION OF WORK AREA

1.8.2.1 DUST AND DEBRIS CONTAINMNET

Seal the project area with construction barriers and dust partitions in order to contain construction dust and debris and maintain a clean environment outside of the work area. In addition to protections within the work area, provide temporary protection for all finishes from the entrance of the facility to each area of work. Patch and repairing any damage caused during construction. Coordinate the locations of barriers with the Government prior to the start of work.

1.8.2.2 PROTECTION OF FURNITURE, FIXTURES, AND EQUIPMENT

Protect all existing furniture, fixtures, and equipment that remain within the work area. Coordinate with the KO for any special protection measures required for sensitive equipment. The Contractor is responsible for repairing or replacing any damage caused during construction. Either the Contractor or the KO may request to conduct a preconstruction survey of furniture, fixtures, and equipment with both the Contractor and Government representative present.

1.8.2.3 NOISE AND VIBRATION CONTROL

Employ demolition and construction methods that minimize the production of sound and vibration. Coordinate the schedule of especially loud or disruptive activities with the KO prior to the start of work.

1.8.2.4 PROTECTION OF EGRESS AND LIFE SAFETY

The Contractor must not take actions that hinder existing egress paths or disrupt operation of life safety systems without prior coordination with the KO and all applicable authorities having jurisdiction (AHJ). The Contractor is responsible for supplying signage or other protective measures as required by the KO or AHJ prior to impeding the egress path or life safety system.

1.8.3 SEQUENCING OF CONSTRUCTION WORK

1-Dec-20 Page 6 of 52

The Contractor must sequence construction to allow the facility to remain occupied during construction. Do not block access to occupied areas during construction.

Utility and communication services must remain functional in all occupied areas.

Some relocation of equipment and/or personnel may be required to comply with this requirement.

The Fire Brigade Station must remain fully operational during construction. Submit detailed sequencing Plan – including a construction schedule – to the KO for approval prior to the start of construction activities. Construction on the vehicle garage can only occur during the spring/summer when freezing temperatures and snow are not expected so that the vehicles can be operational if parked outside. The Contractor must inform the KO of any variances in the schedule during construction.

END OF SECTION

1-Dec-20 Page 7 of 52

2.0 CIVIL AND GEOTECHNICAL

Not applicable

1-Dec-20 Page 8 of 52

3.0 ARCHITECTURAL

3.1 PROJECT DESCRIPTION

Provide and perform architectural design and construction services to provide a complete, accessible, functional, and usable Fire Station in Kalvarija Lithuania.

Perform renovation of one story solid masonry building that serve as fire brigade station.

Extensive coordination is required between the architectural work and the structural, mechanical, and electrical requirements of this project.

3.1.1 DESIGN

Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this RFP. The design must incorporate all referenced codes and regulations. The Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the KO. A schematic design has been attached for reference. The schematic plans are provided for diagrammatic purposes only and do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.

3.1.2 DESIGN SUBMITTALS

Provide all architectural submittals after contract award in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and 01 33 00-SUBMITTAL PROCEDURES. Prepare and submit the documents listed below at the submittals indicated.

3.1.2.2 65% DESIGN SUBMISSION

Include the following drawings and reports as applicable to the project:

a. Code Summary – Provide a tabular code compliance summary [per UFC 3-600-01]

b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.

c. Demolition Plans – Provide existing floor plans, indicating all demolition required.

d. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.

e. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.

f. Building Elevations – Provide all building elevations indicating all exterior materials.

g. Building Section – Indicate heights of critical building elements.

h. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.

i. Interior Elevations – Provide interior elevations of all bathrooms and built-in casework and kitchenettes, indicate critical heights of surfaces and plumbing fixtures and describe all materials and finishes.

j. Pre-Final Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.

k. Pre-Final Specifications – Provide detailed explanations of requirements for all performed work or provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.

3.1.2.3 95% DESIGN SUBMISSION

The 95% Submittal provides a complete and final set of contract documents essentially

1-Dec-20 Page 9 of 52 ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include the following drawings and reports as applicable to the project:

a. All documents from the 65% submittal updated to incorporate 65% review comments.

b. Floor Plans – Provide all floor plans, indicating room names, areas, and dimensions, scale 1:50.

c. Building Elevations – Provide all building elevations indicating all exterior materials.

d. Building Section – Indicate heights.

e. Wall Sections – Provide sufficient wall section(s) to indicate all materials and different conditions.

f. Section and Plan Details – Provide details of critical building intersections.

g. Window and Door Schedule – Provide a schedule of all windows and doors, indicating sizes, hardware, and operation.

h. Finish Schedule – Indicate all proposed finishes.

i. Final Design Analysis – Provide a finalized narrative describing all work to be performed on the project and how it meets the functional and code requirements of the project. Provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.

j. Final Specifications – Provide line items and detailed descriptions of all work to be performed.

3.1.2.4 100% DESIGN SUBMISSION

The 100% Submittal provides a complete and final set of contract documents ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include all drawings, specifications and calculations from the 95% Submittal updated to incorporate all previous review comments.

3.2 TECHNICAL CRITERIA AND STANDARDS

Design and construct the project in accordance with the requirements outlined in Section 1.7 DESIGN CRITERIA.

3.2.1 LIFE SAFETY REQUIREMENTS

The Design must meet all Host Nation and local Fire Suppression System codes and requirements.

In the absence of Host Nation codes and standards, for individual concerns of Life Safety the Contractor must follow appropriate US codes and standards, including the International Building Code (IBC) and NFPA 101 Life Safety Code.

3.3 GENERAL SCOPE OF WORK

Design the architectural elements of this facility to withstand all site-specific environmental conditions such as wide seasonal temperature swings, local wind, rain, snow and earthquake conditions. All architectural features must be appropriately braced for anticipated seismic activity. The Contractor may propose alternate building materials to meet the facility’s requirements, but final selection of materials is subject to the approval of the KO. Consider economics not only in the initial acquisition, but also in the future maintenance of the materials, when selecting materials and building systems to be incorporated into the project. When requested, the Contractor must provide documentation demonstrating that a chosen alternative material is life cycle cost effective.

3.4 DETAILED SCOPE OF WORK

The Contractor is responsible for the following specific tasks required for the construction of this facility.

1-Dec-20 Page 10 of 52

3.4.1 DEMOLITION

Demolition work includes, but is not limited to, the following items:

a. Demolish and remove existing exterior steps to the existing break room;

b. Demolish and remove existing exterior doors and garage doors on the vehicle garage;

c. Demolish and remove existing downspouts, gutters and metal window sills;

d. Demolish interior walls as indicated on drawings;

e. Demolish and remove existing interior doors;

f. Demolish and remove existing floor, wall, and ceiling finishes; and

g. Demolish and remove existing electrical and lighting systems.

3.4.2 BUILDING SYSTEM AND MATERIALS

The intent of this RFP is to allow the Contractor the maximum flexibility to design and construct this facility in an economical manner without sacrificing good engineering practices, quality materials and systems. The Government requires low or no maintenance finish materials to the greatest extent possible. Building materials as described herein are minimum requirements and may require revision based on code compliance and criteria.

3.4.2.1 FIRE PROTECTION RATINGS OF INTERIOR FINISHES

All interior finishes must conform to Host Nation fire protection standards/requirements or equivalent US standards/requirements.

3.4.2.2 ACOUSTICAL DESIGN

Doors, walls, floors, and ceilings must meet the minimum sound protection per Host Nation requirements.

3.4.2.3 THERMAL INSULATION

Provide thermal insulation in accordance with Host Nation and local requirements.

At a minimum, provide thermal insulation in accordance with the International Energy Conservation Code (IECC). Minimum R-values and maximum U-factors required by this SOW are minimally acceptable levels of thermal insulation.

3.4.2.4 CORROSION PREVENTION

All exterior materials and finishes must be appropriate for continuous exterior exposure. All materials susceptible to UV degradation must contain UV inhibitors.

Provide corrosion resistant coatings on all materials susceptible to corrosion.

Coatings must be applied in the factory prior to delivery to the maximum extent practicable. Physically separate dissimilar metals with non-conductive hardware.

Do not install aluminum in direct contact with concrete. Treat all wood with preservatives where it is contact with concrete or exposed to the exterior. Cover all exterior wood with metal flashing or exterior grade paint. Do not install wood in contact with soil.

3.4.3 EXTERIOR CONSTRUCTION WORK

Provide the following exterior architectural systems.

3.4.3.1 EXTERIOR WALLS

Design and construct new exterior walls in accordance with (IAW) the requirements of this SOW. Refer to Section 4.0 STRUCTURAL. Exterior walls must have smoke/fire resistance ratings as required by Host Nation, and local fire and life safety codes. Provide exterior wall finishes appropriate for the wall structure as required below.

3.4.3.1.2 EXTERIOR WALL INSULATION FINISH SYSTEM (EIFS)

1-Dec-20 Page 11 of 52

Install new exterior insulation finish system (EIFS) with new polystyrene thermal insulation, stucco and paint over existing building facade. Install exterior insulation system consisting of insulation boards, to include mineral lightweight plaster and fiberglass reinforcing net. Install EIFS system on the building base.

Dowel all boards. Provide all necessary expansion joints, base and corner rails, diagonal fiberglass-reinforcing fabric at the window and door corners, and end flashing at eaves.

Demolish existing metal window sills. Remove and set aside existing, downspouts, light fixtures, switches, receptacles, signage, utility connection boxes, loudspeakers, satellite dish and other miscellaneous accessories on the exterior of the building for reinstallation after the project is complete.

Clean the wall surface facades to prepare for installation of new EIFS. Repair any existing structural damage. Protruding bricks of existing façade must be modified to create a flat surface for EIFS application. All exteriors must be cleaned of any sand, dust, dirt, sealers, efflorescence, environmental contaminants and bond breakers that could have negative effects on adhesion. Adhesion tests must be completed to insure that EIFS system will properly adhere to existing brick façade. Install exterior insulation system must consist of insulation boards, to include mineral lightweight plaster, fiberglass reinforcing net and secondary air/weather barrier layer. Additionally dowel/anchor the boards. Thermal insulation boards must be as dense as practicable to provide the greatest resistance to thermal conductivity with the least material thickness. Thermal insulation must meet the requirements of HN building code (STR 2.01.02:2016 “Design and Certification of Energy Performance of Buildings”). Thermal insulation must wrap the corner of all window and door openings and provide the greatest thickness of insulation possible without obscuring frames, hinges, or weep holes.

The work must include all necessary expansion joints, base - and corner rails, diagonal fiberglass-reinforcing fabric at the window and door corners and end flashing at eave. Use products from a single system, by a single manufacturer, which are certified by the manufacturer to be suitable for the purpose. This also applies to the paint. Apply products in accordance with the manufacturer's instructions. The work must include all necessary sealing e.g. at window sills.

Submit a sample of the insulation system along with the manufacturer's catalog data including installation instructions, typical details and product data for KO acceptance.

3.4.3.2 EXTERIOR DOORS

Provide new exterior doors as indicated on attached drawings.

3.4.3.2.1 EXTERIOR PERSONNEL DOORS

Provide new factory finished, insulated aluminum or steel exterior doors and frames to include new exit / escape doors. New door shall have steel-reinforced, insulated, non-conductive frame and panel (PVC, fiberglass, or vinyl). Provide all necessary hardware for all doors including panic hardware locking mechanisms. All hardware must be heavy-duty metal and have a brushed chrome finish. Mount all door frames flush with surrounding walls and seal all seams. Exterior doors must include a commercially manufactured threshold with a vinyl or silicone rubber weather stripping insert in the face of the stop. Weather stripping must be held in an extruded non-ferrous metal housing. All doors must have heavy-duty closers.

Size closers in accordance with the specific door application and size, and with manufacturer's recommendations. Coordinate key system with the KO and end user.

3.4.3.2.2 EXTERIOR OVERHEAD COILING DOORS

Provide heavy-duty, industrial type roll-up door. Size overhead coiling doors for the function of the facility, but with a minimum clear opening as required to fit

1-Dec-20 Page 12 of 52 the Vehicle. Thermal resistance shall meet the requirements of HN building code.

Roll-up doors must be electrically power operated, powder coated aluminum panels, thermally insulated with safety glass panels to provide natural light and view to the outside. Roll-up doors must have manual means of operation in the event of a power failure. Roll-up doors must be equipped with bottom bar and guide rail weather stripping and/or brushes. Roll-up doors must be provided with emergency stop function operated by push button and integrated sensor at the lower edge of the lowest panel.

3.4.3.3 EXTERIOR WINDOWS

3.4.3.3.1 EXTERIOR WINDOW SILLS

Install new exterior factory-coated galvanized steel window sills at all windows.

The window sills must match the color of window frames. Caulk all joints between window frames and building with sealant to provide a watertight installation and proper finish.

3.4.3.4 ATTIC THERMAL INSULATION

Provide new vapor barrier and thermal insulation on the top of the attic floor structure. Attic insulation must meet the thermal insulation requirements of HN building code (STR 2.01.02:2016 “Design and Certification of Energy Performance of Buildings” and STR 2.05.02:2008 “Building Structures – Roofs”). Attic and wall insulation must be continuous to eliminate thermal breaks. Insulated attics must be vented.

3.4.3.5 EXTERIOR METAL

All new exterior metal must be finished with an architectural coating. Provide exterior metal elements with a factory applied finish to the greatest extent practicable. For all new metal elements that have not been provided with a factory applied finish, clean and paint the metal in the field. All existing metal elements showing evidence of corrosion or having failing coatings must be cleaned and painted in the field. Scrape and clean all surfaces to remove rust and dirt before painting. Paint system must be one coat of rust inhibitive primer and two coats of an alkyd-base finish paint. Submit paint samples and colors for review and approval.

3.4.4 INTERIOR CONSTRUCTION WORK

Provide the following interior architectural systems.

3.4.4.1 INTERIOR WALLS

Provide new interior partition walls IAW functional requirements. Provide penetration openings (for example for ventilation, piping and cables) as required by other sections and drawings of this RFP. All interior walls must be full height between floor and roof/ceiling structure.

3.4.4.1.1 INTERIOR CONCRETE/MASONRY WALLS

Provide new masonry in fill walls as required and indicated on the attached floor plan. Unless specified otherwise, provide two-layers of interior plaster and new paint on all masonry walls in normally occupied areas. Install plaster IAW manufacturer's guidelines. Refer to Section 4.0 STRUCTURAL for additional requirements for masonry and concrete construction.

3.4.4.1.2 METAL FRAMED PARTITION WALLS

Provide new light gauge metal framed partition walls as required. Provide slotted deflection tracks at the top of all metal framed partition walls. Unless specified otherwise, provide new gypsum wall board and paint on all metal framed partition walls. Provide cavity insulation and/or multiple layers of gypsum wall board as necessary to meet required acoustic and/or fire resistance ratings IAW

1-Dec-20 Page 13 of 52 manufacturer's guidelines. Provide gypsum board with a minimum thickness of 12,5

mm. Install gypsum board to provide a flat, smooth, and seamless finished surface suitable to receive paint or tile, as appropriate. Provide all necessary trim and edge beads. Provide moisture resistant gypsum board in all areas to receive tile and in all toilet rooms, janitor closets, and kitchens. Provide fire resistance rated gypsum board where required. All fire resistance rated gypsum wall board must be labeled by an approved independent testing laboratory and installed per testing laboratory instructions.

3.4.4.2 INTERIOR WALL FINISHES

Provide new interior wall finishes as described below. Submit data sheets, color, and pattern of all wall finishes for review and approval.

3.4.4.2.1 INTERIOR PAINT

Paint all interior walls with a minimum of two coats of latex enamel paint over compatible primer. Paint must be lead free, water resistive and open to vapor diffusion. All paint must be low VOC and washable after drying.

3.4.4.2.2 CERAMIC WALL TILE

Provide glazed ceramic wall tiles from floor to ceiling in all toilet and bathrooms. Protect all walls in toilet and bathrooms with elastomeric waterproofing membrane half meter high above floors. Provide ceramic wall tiles on window sills in all rooms / areas to receive ceramic wall tiles. Provide a glazed ceramic wall tile backsplash (from top of counter to underside of upper cabinetry) at all kitchens. Install tiles according to manufacturer’s instructions with appropriate grout-filled joints.

3.4.4.3 CEILINGS

Provide new ceilings as described below. Install ceilings to provide a clear room height in accordance with US, HN, and local building codes, but not less than 2.5 m above finished floor surface in any room. Do not use combustible materials for ceiling construction. Submit data sheets, color, and pattern of all ceiling finishes for review and approval.

3.4.4.3.1 SUSPENDED ACOUSTIC CEILINGS

Provide new suspended acoustic ceilings offices and team restroom, changing room and bathroom area. Acoustic tile ceilings must be level and flat. Provide and install all required components for a suspended acoustic tile ceiling system including mounting and supports of light fixtures. Integrate all light fixtures and mechanical grilles in the ceiling grid. Provide moisture resistant ceilings for toilets, bathrooms and kitchen. Do not repair plaster on the ceiling if new suspended ceilings are provided.

3.4.4.3.2 GYPSUM BOARD CEILINGS

Provide suspended gypsum board ceilings with primer and paint. Gypsum board ceilings must be level and flat and appear seamless once finished. Provide all necessary trim and edge beads. Coordinate location of light fixtures and mechanical grilles. Provide moisture resistant gypsum board in all toilet rooms, janitor closets, and kitchens.

Provide multiple layers of gypsum board as necessary to meet required acoustic and/or fire resistance ratings IAW manufacturer's guidelines. Provide fire resistance rated gypsum board where required. All fire resistance rated gypsum board must be labeled by an approved independent testing laboratory and installed per testing laboratory instructions.

3.4.4.3.3 EXPOSED CONCRETE CEILINGS

Paint all exposed concrete ceilings. Provide a minimum of two coats of latex enamel paint over compatible primer. Refer to Section 3.4.4.2.1 INTERIOR PAINT for additional requirements.

1-Dec-20 Page 14 of 52

3.4.4.4 FLOOR SLABS

Provide floor slabs in accordance with the requirements of Section 4.0 STRUCTURAL and the following.

3.4.4.4.1 HORIZONTAL WATERPROOFING AGAINST MOISTURE FROM OUTSIDE

Apply waterproofing on all ground floor slabs in the building. Apply liquid proof coating with fabric reinforcement corner strips in accordance with manufacturer guidelines. Apply on floors before installing new screed. Provide photographic documentation to the KO showing the application of the waterproofing material.

3.4.4.4.2 SCREED AND FLOOR SLABS

Provide thermal insulation and floating cement screed in all rooms / areas.

3.4.4.5 FLOOR FINISHES

Provide new interior floor finishes as described below Submit data sheets, color, and pattern of all floor finishes for review and approval.

3.4.4.5.1 CERAMIC TILE FLOORING

Provide new non-slip ceramic tile flooring and baseboards. Provide ceramic tile flooring for toilet, shower and janitor room. Protect ceramic tile flooring in wet rooms/areas with elastomeric waterproofing membrane on the concrete slabs and turn up half meter high above floor. Tiles must be size 30x30 cm with joints of 3mm width. Fill joints with water resistive grout. Do NOT fill joints between wall and floor with grout, but with permanent elastic silicone. Color of grout and silicone must match. Install proofing layer suited for the application. Install ceramic tile baseboards in all rooms that receive ceramic tile flooring but not ceramic wall tile.

3.4.4.5.2 NON-SLIP RESILIENT FLOORING

Provide new non-slip PVC flooring and baseboards. Welded sheets at seems. Flooring must be heavy duty suitable for office use. Provide PVC flooring in all offices, living and team restroom. Color and pattern must be consistent through the entire thickness of the flooring sheet.

3.4.4.5.4 CONCRETE FLOOR SEALER

Provide low VOC, clear epoxy concrete sealer on all exposed concrete floors.

Concrete sealer must be appropriate for high-traffic areas and have high oil and chemical resistance. Apply epoxy concrete sealer in accordance with manufacturer instructions. Test concrete for appropriate moisture content prior to application.

Provide low VOC, clear oil/fuel resistive high-traffic epoxy concrete sealer on vehicle garage floor slab. Grind the existing vehicle garage slab to remove all existing finishes and to produce a level and even slab finish. Repair all existing cracks and holes with an epoxy-based filling compound formulated for the function of the vehicle garage.

3.4.4.6 INTERIOR DOORS

Provide new single wooden doors and steel frames. All hardware must meet the fire rating assemblies for the doors and frames. Provide standard door 45mm thickness.

Provide moisture resistant doors and door frames for all bathrooms and kitchens.

Paint all interior doors and frames using one coat primer and two coats of a finish paint. Submit color for review and approval.

3.4.4.6.1 DOOR HARDWARE

1-Dec-20 Page 15 of 52

All hardware must be heavy-duty and have a brushed chrome finish. Install all hardware in accordance with the manufacturer’s instructions. All doors into toilet and bathrooms must have solid kick-plates on both sides.

Each door must have the following additional hardware as a minimum:

a. Three hinges on each leaf;

b. One floor or wall mounted doorstopper, as appropriate;

c. Lever latch handles;

d. Fully mortised lockset compatible with existing keying system;

e. Fully adjustable hydraulic door closer;

f. Door coordinator on all door pairs;

g. Panic push bar in compliance with Host Nation criteria on each leaf, as required;

h. Acoustic gasketing, as required; and

i. Host Nation compliant door threshold.

All doors must have a mortise lockset. All locksets must be keyed to one master key system. Provide panic hardware and smoke tight fire rated doors in egress routes as required by the Life Safety Code.

3.4.4.7 INTERIOR WINDOW ACCESSORIES

Provide the following accessories on all windows.

3.4.4.7.1 INTERIOR WINDOW SILLS

Provide laminated interior window sills at all windows except walls with ceramic tiles.

3.4.4.7.2 WINDOW COVERINGS

Provide a surface mounted curtain rod over all windows. Curtain rod must be steel or aluminum and be adequately sized to span the window without sagging once curtains have been installed.

3.4.4.8 BATHROOM AND TOILET ACCESSORIES

Provide bathroom and toilet accessories as described below. All bathroom and toilet accessories must be made from corrosion resistant materials and have corrosion resistant, concealed fasteners. All bathroom and toilet accessories made from the same material must be finished to match. For toilet and plumbing fixtures, see Section 6.0 MECHANICAL. Submit data sheets and color/finish for all bathroom and toilet accessories for review and approval.

3.4.4.8.1 TOILET ROOM MIRRORS

Provide mirrors of 6 mm minimum thickness over each sink. Size must be approximately 450 x 800 mm (width x height). Securely fasten mirrors to the wall using mechanical fasteners through a steel frame. Do not hang or hook mirrors.

3.4.4.8.2 TOILET ROOM SHELVES

Provide one commercial grade, heavy duty stainless steel shelf below each toilet room mirror and in each shower. Toilet room shelves must be wall mounted with mechanical fasteners.

3.4.4.8.3 SOAP HOLDER

Provide one metal soap holder for each sink and shower. Soap holder must be surface mounted with mechanical fasteners.

3.4.4.8.4 TOILET TISSUE DISPENSER

Provide one, two-roll metal toilet tissue dispenser at each toilet. Toilet tissue dispenser must be surface mounted with horizontal dispensing.

1-Dec-20 Page 16 of 52

3.4.4.8.5 TOWEL BAR

Provide one surface mounted metal towel bar. Towel bar must be sized to fit two hand towels.

3.4.4.8.6 GARMENT HOOKS

Provide heavy duty, commercial grade, stainless steel double-hooks. Unless indicated otherwise, mount garment hooks on the inside of each toilet cubicle door at a minimum.

3.4.4.8.7 WASTE RECEPTACLE

Provide steel waste receptacles in each toilet and bathroom. Receptacles must be designed for surface mounting or free standing, painted, with reusable liner.

Capacity must be not less than 20 Liters.

3.4.4.8.8 SHOWER CURTAIN RODS

Provide stainless steel shower curtain rods at shower. Shower curtain rod must be wall mounted with concealed mechanical fasteners. Mount shower curtain rod 2.0 m above shower floor.

3.4.4.8.9 MOP RACKS

Provide stainless steel mop and broom racks in Janitor Closet with a minimum of four (4) spring loaded cam holders each. Mop racks must be wall mounted with concealed mechanical fasteners.

3.4.4.10 CASEWORK

Provide the following casework. Provide samples of all materials and colors for approval.

3.4.4.10.1 BUILT-IN KITCHEN

Provide built-in kitchens as indicated on attached drawings. Coordinate with other engineering disciplines to provide utilities for all required equipment. At a minimum, kitchen must include the following:

a. Built-in base cabinets with drawers and adjustable shelves;

b. Countertops;

c. Built-in upper cabinets with adjustable shelves;

d. Self-rimming stainless steel sink with drain board, 86cm;

e. One (1) microwave oven, 1000s watt (30 liter capacity);

f. One (1) oven (60 liter capacity);

g. One (1) cooktop, electric, 4 burner;

h. One (1) dishwasher (600 mm wide);

i. One (1) refrigerator (230 liter refrigerator capacity + 70 liter freezer capacity)and

j. Kitchen hood, 650 CFM.

3.4.4.10.2 BASE CABINETS

Provide base cabinets constructed from laminate-clad medium density fiberboard (MDF). All built-in cabinet materials must be formaldehyde-free and resistant to chemicals (no negative change of color). Configure base cabinets with one drawer over each door. Base cabinets must be a minimum of 600 mm deep. Except in base cabinets under sinks, provide two shelves in all base cabinets. Install false fronts in lieu of drawers at base cabinets under sinks. Construct all base cabinets with a toe base. Attach drawers to telescoping rails with ball bearing slides and silent stops that allow full drawer depth to be pulled from base cabinets. Provide doors with concealed hinges. Provide drawer and door pulls constructed form a corrosion resistant metal. All pulls must be a minimum of 300 mm long. Provide filler panels as required. Anchor base cabinets to floor and wall.

1-Dec-20 Page 17 of 52

3.4.4.10.3 COUNTERTOPS

Provide countertops constructed from laminate-clad medium density fiberboard (MDF). Countertops must be minimum 40mm thick. Provide minimum 100 mm x 15 mm back and side splashes on all countertops adjacent to walls. Countertops must have a 20 mm overhang. Coordinate openings in countertops for sinks, refer to Section 6.0 MECHANICAL. Coordinate height of base cabinetry with thickness of countertops to provide 900 mm finished height at countertop.

3.4.4.10.4 UPPER CABINETS

Provide upper cabinets to match base cabinets. Provide double-door upper cabinets with opposing doors. Upper cabinets must be as wide as base cabinets. Upper cabinets must be minimum 800 mm tall and mounted to provide a minimum 455 mm clearance above counter. All hardware on upper cabinets must match base cabinets.

Provide each upper cabinet with two adjustable shelves. Anchor upper cabinets to walls.

3.4.5 SIGNAGE

Provide all signage in accordance with Host Nation standards.

3.4.5.2 EXTERIOR SIGNAGE

Provide exterior signage as described below. Construct all exterior signs from corrosion resistant materials appropriate for continuous exposure to the elements.

3.4.5.2.1 EXTERIOR DEDICATION PLAQUE

Provide a dedication plaque approximately 600 mm wide x 450 mm high fabricated from powder coated aluminum with permanent printed 18 mm high, “Arial“ font letters as indicated below. Adhesive applied images or text are not acceptable.

Provide the emblem of the United States European Command between two flag emblems, one flag of the United States of America and one of the Lithuania. Plaque location and mounting height to be directed by the KO.

The exterior dedication plaque must have text similar to the following in both English and the Host Nation language: “The Construction of Kalvarija Fire Brigade Station was accomplished as a partnership between the people of the United States of America and the people of Lithuania, with support from the United States European Command and the Office of Defense Cooperation, U.S. Embassy Lithuania.”

Provide the year of project completion below the text. Coordinate the final dedication plaque verbiage and graphics with the KO prior to procuring the sign.

See attached dedication plaque template for reference.

3.4.6 FINAL CLEAN-UP

Clean all areas impacted by the work under this project. This includes all rooms where renovation work was completed and all circulation paths (corridors, vestibules, etc.) leading to work areas from building entrances. Follow the cleaning instructions provided by the manufacturers for all building material and equipment. Follow the application instructions provided by all cleaning agent manufacturers. Provide all devices and tools required for the performance of the work to include all necessary additional scaffolding and ladders. Remove all temporary protective coatings left in place during construction. Liquid cleaners must not contain any volatile organic content (VOC).

1-Dec-20 Page 18 of 52

4.0 STRUCTURAL

4.1 GENERAL

The Contractor must provide and perform structural engineering design and construction services as required to provide a complete, accessible, functional and usable project.

The primary structural effort of this project includes

a. Investigation, assessment, and renovation design work of the existing Kalvarija Fire Brigade Station. The renovation work to include but not limited to; placement of new dead loads such as insulation, structural work resulted due reconfiguration of the architectural layout, and repairs of existing structural damages.

b. The Contractor is required conduct a visual structural investigation of the existing building and document all structural system information in the report such as; the size and locations of load bearing walls, openings, columns, beams, slab, etc., existing structural damages, and deteriorations.

If required, the Contractor may perform destructive testing in order to determine certain structural characteristic of the existing building which cannot be obtained by non-destructive means. Destructive testing must be approved by the KO prior to commencement of this work. The Contractor is responsible for conducting and documenting all existing material investigations and testing as required for a code complaint design.

c. The Contractor is responsible to verify, test, and evaluate the structural capacity of the existing materials and structural elements of the structural system to accommodate the new loads and planned renovation work. Where the existing structure is damaged, deteriorated, or lacks sufficient structural strength to resist new loads, the Contractor must; identify, repair, and strengthen theses areas of the existing structural system.

d. The Contractor is required to design and construct any structural modification necessary to adjust the height of the garage door and the lower ceiling to enable taller vehicles enter the garage. Provide new structural ceiling slab and reinforcement at 30 cm higher than the existing slab to match the height of the adjacent bay. All structural elements supporting the new slab must be evaluated and reinforced as required to support the new ceiling slab. Design and construct new lintels and jambs as required for the new larger garage door.

e. The Contractor is required to design and construct any structural modification necessary to support the vehicle garage exhaust extraction system.

f. The Contractor is required to design and construct new headers, lintels, or other structural reinforcement as required to complete the proposed interior reconfiguration described in the Architectural Section. This involves gravity load and lateral load reinforcement as required for the removal of interior walls and creating new interior wall openings.

g. Repairs of existing walls are expected to be 5% of wall facade area and consist of repairing freeze/thaw, expansion/contraction or settlement damage to existing masonry walls. Repair work consists of sealing cracks, replacing masonry, replacing mortar, and repointing mortar as necessary to return the damaged areas of wall to original condition.

h. The Contractor is responsible for shoring the existing structure to maintain its local and global stability during any demolition, rehabilitation, and curing phase, as required.

i. Other elements must include but are not limited to foundations, superstructure (i.e. walls, columns and beams), roof framing, lateral load stability and diaphragm design, framing and connection of any architectural features, and support of mechanical and electrical equipment, and civil/site features.

1-Dec-20 Page 19 of 52

The contractor must have as part of his design team a licensed structural engineer per Host Nations standards. If work is being performed in a country that does not have licensed structural engineers, then engineering degrees along with extension structural design experience can be submitted to the KO for qualification verification and approval. The structural engineer’s licensure or qualifications must be submitted to the KO in the design quality control plan prior to the start of design. The Contractor’s structural engineer must be responsible for the design of any part of the building structural systems.

The structural design of the renovation work, assessment of existing structural systems, foundation, superstructure and any other structural aspects must be in accordance with the design criteria listed in this document. The superstructure of the project building and the foundation must be constructed from locally available materials.

4.2 APPLICABLE DESIGN CRITERIA

All Design, Safety in Construction, Materials, and Performance of Construction Services must be in accordance with current local or national Host Nation codes and standards. In absence of Host Nation codes, use 2018 International Existing Building Code and ASCE 7-16 for structural calculations. In case of conflicting requirements between the various elements, the more stringent criteria must govern.

Any material or construction installed by the Contractor as part of this contract that does not meet the requirements of this RFP or does not meet the applicable codes and standards must be removed and replaced at the Contractor’s expense.

Structural design methods and allowable stresses or load factors for the various structural materials must be in accordance with paragraph 1.7 of this document and the following codes/criteria:

International Existing Building Code (IEBC) 2018

4.3 SUBMITTALS

4.3.1 DESIGN SUBMITTALS

The contractor must provide the structural submittals after contract award in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. In addition to General Section 1.7.1 Design Submittals of this document the following documents must be submitted.

4.3.1.1 DRAWINGS, SPECIFICATIONS, AND DESIGN ANALYSIS

The following structural detail drawings must be provided by the Contractor as required, but must conform to the requirements of this SOW and are subject to the approval of the Contracting Officer (KO). Construction drawings must include:

65% Design Submittal

a. Provide a structural investigation report that documents that the existing facility have been thoroughly verified, evaluated, and tested. This report must document existing conditions of the facility and identify any damages and deterioration. This report must document all existing damage and deteriorations. This report must provide all information (analysis and calculations) required for the design of these existing repairs/ rehabilitations work.

b. Preliminary plan that shows where structural repairs and rehabilitations work to the existing facility will be required. The documentation must have a plan and procedures for executing these repair work.

1-Dec-20 Page 20 of 52

c. Documentation of all design criteria, codes, and standards used. Provide Host Nation Annex of wind and seismic criteria used for the design analysis.

d. Document all design loads used including dead loads, floor live loads, roof loads, wind loads, seismic loads,…