About this file
This document contains a price schedule for the renovation of the Kalvarija Fire Brigade Station in Kalvarija, Lithuania. The U.S. Army Corps of Engineers Europe District intends to select one contractor through a design-build project to complete exterior wall and attic insulation work, replace an existing heating system, modify interior layouts and relocate sanitation facilities. There are also two optional items that may be awarded for renovating an existing garage door/ceiling and installing a new garage exhaust extraction system. Contractors must commence work within 7 days of receiving the notice to proceed and complete all work within 450 calendar days to avoid liquidated damages of $583 per day. Pricing is solicited for the base items and options on both a lump sum and unit price basis.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
POP and LD Clauses
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
06/19
PART 1 GENERAL
PHASING REQUIREMENTS
PAYMENT TYPES
SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved.
The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
If there is any work required of this contract that is not associated with a base bid item description or bid option description, then the costs for that work shall be included in the first base bid item.
SCHEDULE OF ITEMS: BASE ITEMS
Base Item 0001: Exterior Walls and Attic Insulation
Unit of Measure: Job.
Payment will be made for costs associated with the design and construction for the exterior walls and attic insulation as indicated in the SECTION 01 10 10 and shown on the conceptual layout, with the exceptions of the bid options listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.
Base Item 0002: Replacement of Existing Heating System
Unit of Measure: Job.
Payment will be made for costs associated with the design and construction/replacement of the existing heating system as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.
Base Item 0003: Modify Interior Layout and Relocate Sanitation Facility
Payment will be made for costs associated with the design and renovation/modification of the interior layout and relocate the sanitation facility as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.
SCHEDULE OF ITEMS: OPTION ITEMS
Option 1: Item 0004: Renovation of Existing Garage Door and Ceiling Height
Payment will be made for costs associated with the design and renovation of the existing garage door and ceiling height as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below.
Option 2: Item 0005: Garage Exhaust Extraction System
Payment will be made for costs associated with the design and construction/installation of a new garage exhaust extraction system as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section -- V3.0 Jun 2019
SECTION 01 22 00 Page 1
The following items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation/Request for Proposal. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, and safety requirements. All work shall be performed in accordance with these documents. Refer to Specification Section 01 22 00 Price and Payment Procedures for additional description of the work associated with each of the items.
Period of Performance: Refer to clause COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10) in the Solicitation/Request for Proposal for the period of performance for all base and option items.
Liquidated Damages: Refer to clause LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12) in the Solicitation/Request for Proposal for the liquidated damages for all base and option items.
Option Items: The Government reserves the right to award the options up to 90 calendar days from contact award. Refer to Section 01 22 00 Price and Payment Procedures for the period of performance and liquidated damages associated with option items.
| Item No. |
| Description |
| Quantity |
| Unit |
| Unit Price |
| Amount |
BASE ITEMS
| 0001 |
| Exterior Walls and Attic Insulation |
| 1 |
| Job |
| $ |
| $ |
| 0002 |
| Replacement of Existing Heating System |
| 1 |
| Job |
| $ |
| $ |
| 0003 |
| Modify Interior Layout and Relocate Sanitation Facility |
| 1 |
| Job |
| $ |
| $ |
| Total of Base Items 0001 thru 0003 |
| $ |
OPTION ITEMS
| 0004 |
| Renovation of Existing Garage Door and Ceiling Height |
| 1 |
| Job |
| $ |
| $ |
| 0005 |
| Garage Exhaust Extraction System |
| 1 |
| Job |
| $ |
| $ |
| Total of Option Items 0004-0005 |
| $ |
| Total of all Base and Option Items |
| $ |
EVALUATION OF OFFERS.
EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.
-- END OF PROPOSAL SCHEDULE --
ATTACHMENT 1
PRICE SCHEDULE
Renovation of Kalvarija Fire Brigade Station Kalvarija, Lithuania
04 November 2020
Renovation of Kalvarija Fire Brigade Station Kalvarija, Lithuania
COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10)
The Contractor shall be required to (a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use no later than 450 calendar days after the contractor receives the Notice to Proceed. Any options, if awarded, shall be completed concurrently with all other work.
The time stated for completion shall include final cleanup of the premises. The Government intends to issue a single Notice to Proceed for all work.
LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12)
If the Contractor fails to complete the work within the time specified in clause 52.211-10 COMMENCEMENT PROSECUTION AND EXECUTION OF WORK, the Contractor shall pay liquidated damages to the Government in the amount of $583.00 for each calendar day of delay until the work is completed or accepted.
If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.