This document is a Statement of Work (SOW) for the installation of a new uninterruptible power supply (UPS) system at the Utah National Guard's TASS facility located in Camp Williams, Utah. The key requirements include:

Provide a 100-amp 2-pole breaker in an existing panel on the 1st floor, install a 100-amp home run from the 1st floor electrical room to a new 16kVA UPS on the 2nd floor, demo and dispose of the existing UPS, install the new UPS in the same location as the previous one, and trim and test both new UPS units. The work is to be performed during normal business hours with a one-year standard parts and labor warranty. Exclusions include any work outside normal business hours, permit/engineering fees, troubleshooting of non-contractor supplied equipment, and additional structural/mechanical/control work.

This SOW is related to a federal contract opportunity (Solicitation #W911YP24R117A) for the procurement and installation of the APC Symmetra LX UPS system. The contract will be firm-fixed-price awarded on a lowest price technically acceptable basis, with performance to occur as stated in the attached Performance Work Statement. The response is due by 7 AM Mountain time on September 30, 2024.

View the file

Other files

File Type Posted
A-2 NLS SOW.pdf PDF
vce2579-Final.pdf PDF
A-2 JA Brand Name APC UPS LX.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW for work at UTNG TASS UPS.

Location: Building 7150, 17800 S Camp Williams Rd, Bluffdale, UT 84065

Inclusions:

** Provide 100amp 2-pole breaker in existing panel on 1st floor (space provided by UTNG).

** Install 100amp home run to new UPS in 2nd floor server room from the 1st floor electrical room below.

** Install new 16K UPS (provided by others) in footprint location provided by UTNG in server room.

** Demo and disposal existing UPS from the 1st floor server room. UTNG is to remove and maintain existing loads from existing

UPS, and reinstall when new UPS is complete.

** Install new 16K UPS (provided by others) in the same location as existing that was demoed, reuse conduit, provide new

100amp home run wire to UPS from existing panel and breaker.

** Trim and test both new UPS units.

** Any applicable state/ local taxes.

** One year standard parts and labor warranty on all Positive Power, LLC services.

** All clean-up, labeling and testing upon completion.

Exclusions:

** Any work outside normal business hours.

** Any permit or engineering fees. (If applicable)

** Any troubleshooting of equipment not supplied by Positive Power, LLC.

** Any additional structural, mechanical or control work.

** Any work, material or equipment not listed above.

** A Convenience Fee of 3.25% will be added to all Credit Card Payments

ADDER:

** Install both new 16K UPS units in 1st floor server room (footprint and space provided by UTNG).

** Provide (2) 100amp 2-pole panels (A and B power) up to 2nd floor server room.

** Install (3) L14-30 outlets from Panel A in 2nd floor server room.

** Install (3) L14-30 outlets from Panel B in 2nd floor server room.

** Providing (3) 2-pole 30 amp breakers in each A and B panels.