9-J. Exhibit B - McDowell Creek WRRF Primary No. 4 Clarifier Project Manual.pdf

PDF 7 MB Posted

Attached to
McDowell Creek WRRF Primary Clarifier No. 4. Equipment
Solicitation number
FY26-ITB-08
Issued by
Mecklenburg County, Charlotte City, North Carolina

About this file

This is a Project Manual (Exhibit B) and procurement specification document issued by Charlotte Water for the McDowell Creek Water Resource Recovery Facility (WRRF) Primary Clarifier No. 4 Equipment Procurement (CW Project No. FY26-ITB-08). The procurement concerns furnishing a complete circular clarifier mechanism to replace the existing Primary Clarifier No. 4, including the clarifier mechanism, scraper arms, drive cage, hydraulic flocculating feedwell, rotating scum skimmer arm, equipment access platform and walkway, scum trough/beach, scum baffle and V-notch weir assembly, local control panel, and all associated appurtenances necessary for complete installation. The equipment tag number is PC-1801. Installation will be performed by a separate Installing Contractor under a distinct contract. The document is dated February 2026 and includes detailed specifications covering equipment design requirements, materials (predominantly 316L stainless steel), structural design criteria, control systems, lubrication specifications, spare parts requirements, and acceptance testing procedures. The basin is circular with a 70-foot inside diameter, 15-foot total sidewall depth, and 12.7-foot peak flow water depth. Design flow is 3.45 million gallons per day (mgd) average and 7 mgd peak flow. Acceptable manufacturers are Envirodyne, WesTech, Ovivo/Eimco Water Technologies, and Evoqua.

The procurement specifies comprehensive submittal requirements including detailed assembly drawings, engineering data, shop drawings sealed by a registered North Carolina engineer, and operation and maintenance manuals in electronic PDF format. The Company must field-verify all existing basin dimensions and elevations at no additional cost prior to fabrication. All equipment must comply with the Meteorological and Seismic Design Criteria section with wind speed of 118 mph ultimate design and seismic design category parameters specified. Power supply is 480 volts, 60 Hz, three-phase. The specification mandates factory quality control, factory assembly witnessing by three City representatives, field quality control with minimum two trips of four days each by the Company's authorized representative, and extensive functional acceptance testing including dry condition operation for 24 hours, non-potable water condition operation for 48 hours, and surface skimming performance testing. A two-year extended warranty commences upon successful operational acceptance testing, including an 18-month inspection. All costs for field services, training of Owner's personnel, and spare parts are included in the Procurement Contract Price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Charlotte Water 00110 - 1 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

PROJECT MANUAL

TABLE OF CONTENTS

SPECIFICATION SECTIONS PAGES

DIVISION 01 — GENERAL REQUIREMENTS

01015 – Project Requirements ................................................................................................................... 1:6

01300 - Submittal Procedures .................................................................................................................... 1:8

01610 - General Equipment Stipulations ................................................................................................... 1:5

01611 - Meteorological and Seismic Design Criteria ............................................................................... 1:4

01612 - Product Delivery Requirements .................................................................................................... 1:1

01615 - Equipment Identification .............................................................................................................. 1:2

01820 – Demonstration and Training ........................................................................................................ 1:4

DIVISION 02 — EXISTING CONDITIONS

NOT USED

DIVISION 03 — CONCRETE

NOT USED

DIVISION 04 — MASONRY

NOT USED

DIVISION 05 — METALS

05520 - Metal Railings ............................................................................................................................... 1:4

05530 - Metal Gratings .............................................................................................................................. 1:3

05590 - Structural Metals ........................................................................................................................... 1:3

DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES

NOT USED

DIVISION 07 — THERMAL AND MOISTURE PROTECTION

NOT USED

DIVISION 08 — OPENINGS

NOT USED

DIVISION 09 — FINISHES

NOT USED

DIVISION 10 — SPECIALTIES

NOT USED

DIVISION 11 — EQUIPMENT

11410 - Circular Clarifier Equipment ...................................................................................................... 1:20

DIVISION 12 — FURNISHINGS

NOT USED

DIVISION 13 — SPECIAL CONSTRUCTION

NOT USED

DIVISION 14 — CONVEYING EQUIPMENT

NOT USED

DIVISION 15 — MECHANICAL

NOT USED

Charlotte Water 00110 - 2 February 2026

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

DIVISION 16 — ELECTRICAL AND CONTROLS

16220 - Common Motor Requirements for Process Equipment ................................................................ 1:8

ATTACHMENT 1 – RELEVANT DRAWINGS

G-00-000P – COVER SHEET

G-00-001P – INDEX OF DRAWINGS, SYMBOLS AND LEGENDS

G-00-002P – CIVIL AND PROCESS MECHANICAL ABBREVIATIONS

M-21-101P - PRIMARY CLARIFIER NO. 4 - TOP PLAN

M-21-102P - PRIMARY CLARIFIER NO. 4 - SECTIONAL PLAN

M-21-301P - PRIMARY CLARIFIER NO. 4 - SECTION

M-99-501P - PRIMARY CLARIFIER NO. 4 - DETAILS

Project Requirements

Charlotte Water 01015 - 1 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

Section 01015 – PROJECT REQUIREMENTS

PART 1 - GENERAL

1.1 GENERAL DESCRIPTION OF WORK.

A. The Work to be performed under these Contract Documents is generally described as follows:

1. Purchase of the clarifier mechanism to replace existing Primary Clarifier

No. 4 mechanism including circular clarifier mechanism, scraper arms, drive cage, hydraulic flocculating feedwell, rotating scum skimmer arm, equipment access platform and walkway, scum trough/beach, scum baffle and V-notch weir assembly, local control panel, and all associated appurtenances necessary for a full and complete installation.

2. Installation of purchased equipment shall be installed by Installing

Contractor under a separate Contract.

1.2 DEFINITIONS

Bidder Refers to a person or entity that submits a Bid.

City Refers to the City of Charlotte, North Carolina.

Company During the solicitation process, refers to a company that has interest in providing the Products and

Services. After the solicitation process, refers to a company that enters into a Contract with the City for all or part of the Products and Services covered by this

Contract.

Contract Refers to the contract under which a Bidder agrees to provide all or part of the Products and Services to the

City. A Contract shall include the Terms and

Conditions set forth in the Sample Contract provided in the Public Files on the Procurement Portal.

Engineer Refers to Black and Veatch International Company.

Charlotte Water 01015 - 2 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

Installing Contractor Refers to an entity under a separate contract with the

City to provide installation services for equipment procured under this Procurement Contract.

Procurement

Contract

Refers to the contract under which a Bidder agrees to provide all or part of the Products and Services to the

City. Specifically, this refers to the contract for the procurement of the Circular Clarifier Equipment.

Installation Contract Refers to the contract under which Contractor agrees to provide all or part of the Products and Services to the City, including installation of equipment procured under the separate Procurement Contract.

1.3 OTHER CONSTRUCTION CONTRACTS

A. Work at the existing Primary Clarifier No. 4 performed by the Installing

Contractor under separate contract includes but is not limited to the following:

1. Demolish and disposal of existing Primary Clarifier No. 4 mechanism and ancillary components.

2. Installation of new circular clarifier mechanism purchased via this

Procurement Contract.

3. Replacement of plug valves (3), telescoping valve (1), and pressure relief valves (10) inside or adjacent to Primary Clarifier No. 4.

4. Replace concrete topper inside Primary Clarifier No. 4.

5. Repair structural elements (cracks and crevices) within Primary Clarifier

No. 4 and attached structures.

6. Modify the existing chemical feed dosing locations in the southeast vault.

1.4 COORDINATION.

A. The Company shall plan, schedule, and coordinate its operation for the fabrication of the necessary Products with the City and Engineer. The Company shall field verify all existing clarifier basin dimensions and elevations. The

Company shall coordinate the site visit to field verify with the City and Engineer prior to fabrication. The Company shall coordinate delivery of the clarifier mechanism with the Installing Contractor.

B. During inspection, startup, and commissioning efforts of the clarifier mechanism, the Company shall cooperate with the Installing Contractor. The

Company shall provide services as indicated in this Procurement Contract

Charlotte Water 01015 - 3 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08 including but not limited to coordination with the Installing Contractor during installation, inspection prior to startup and testing, and supervision during testing as required for Functional Acceptance Testing in accordance with the

Circular Clarifier Equipment section. Installing Contractor shall plan, schedule, and be responsible for coordination of inspection and testing with the Company to facilitate progress of the Work under the Construction Contract.

1.5 PROCUREMENT CONTRACT

A. The items of equipment and materials procured as described in the following paragraphs shall be furnished by City to Installing Contractor for installation and commissioning.

B. Shop and installation drawings pertaining to the equipment and accessories will be furnished to Installing Contractor upon completion of review by Engineer.

C. Circular Clarifier Equipment and Materials

1. Circular Clarifier Mechanism.

2. Center Pier.

3. Drive.

4. Scraper arms.

5. Drive cage.

6. Hydraulic flocculating feedwell.

7. Rotating scum skimmer arms.

8. Equipment access platform and walkway.

9. Scum trough/beach.

10. Scum baffle and V-notch weir assembly.

11. Local control panel.

12. All associated appurtenances necessary for a full and complete installation.

D. Delivery

Charlotte Water 01015 - 4 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

1. All equipment and materials provided under the Procurement Contract will be shipped and delivered at the expense of the Company and all costs relative thereto are included in the contract price of the assigned

Procurement Contract.

2. The equipment and materials will be shipped to McDowell Creek WRRF at 5300 Jim Kidd Road, Huntersville, NC 28078 by truck, subject to all applicable laws and regulations governing such shipment and delivery.

3. The equipment and materials will be delivered to Installing Contractor by the Company at the designated location between the hours of 8 a.m. and 3 p.m., Monday through Friday, or as coordinated between the Company and

Installing Contractor with approval from the City. Delivery shall be coordinated by Installing Contractor to provide adequate time for unloading during normal working hours.

4. Installing Contractor shall have the responsibility to unload the equipment and materials, and to inspect and inventory the delivered equipment and materials upon receipt at the designated location. To that end, the Company will provide the services of an authorized representative at the time of delivery to assist and advise Installing Contractor with the inventory and verification, to the mutual satisfaction of both parties. The Company will perform no direct supervision of Installing Contractor's personnel.

5. The Company will provide to Installing Contractor copies of all bills of lading and other documents necessary for the inventory. Installing

Contractor shall cooperate with the Company during the unloading and inventory activities, so that joint agreement can be reached. In the event of disagreement, Engineer shall be notified, and decisions will be made under the terms of this Contract.

6. After acceptance, Installing Contractor shall be responsible for the handling, storage, installation, and commissioning of the equipment and materials, and for administration of the installation contract, all in accordance with the Contract Documents.

1.6 PREPARATION FOR SHIPMENT.

A. All materials shall be suitably packaged to facilitate handling and protect against damage during transit and storage. Painted surfaces shall be protected against impact, abrasion, discoloration, and other damage. All painted surfaces which

Charlotte Water 01015 - 5 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08 are damaged prior to acceptance of equipment shall be repainted to the satisfaction of Engineer.

B. Each item, package, or bundle of material shall be tagged or marked as identified in the delivery schedule or on the Shop Drawings. Complete packing lists and bills of material shall be included with each shipment.

1.7 HAZARDOUS ENVIRONMENTAL CONDITIONS AT SITE

A. Abatement of Hazardous Environmental Conditions.

1. The City is not aware of Hazardous Environment Conditions at the Site and has directed that Engineer not require the Company to perform surveys of the Site.

1.8 REFERENCE STANDARDS

A. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to the laws or regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard specification, manual, code, or laws or regulations in effect at the time of opening of Bids (or on the effective date of the Contract or Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents.

B. However, no provision of any referenced standard, specification, manual, or code, or any instruction of a Company, shall be effective to change the duties or responsibilities of City, Installing Contractor, or Engineer, or any of their subcontractors, consultants, agents, or employees from those set forth in the

Contract Documents, nor shall any such provision or instruction be effective to assign to City, Engineer, or any of Engineer's Consultants, agents, or employees, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents.

Charlotte Water 01015 - 6 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

End of Section

Submittal Procedures

Charlotte Water 01300 - 1 February 2026

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

Section 01300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SHOP DRAWINGS AND ENGINEERING DATA.

A. General.

1. The Project has been designed by Engineer and Engineer will perform design-intent reviews of submittals. City, Engineer, and Company may develop a protocol for the transmittal of shop drawings, samples, and other submittals.

2. Shop Drawings and engineering data (submittals) covering all equipment and all fabricated components under this Contract shall be submitted to Engineer for review, as required. Submittals shall verify compliance with the Contract

Documents, and shall include drawings and descriptive information in sufficient detail to show the kind, size, arrangement, and the operation of component materials and devices; the external connections, anchorages, and supports required; the performance characteristics; and dimensions needed for installation and correlation with other materials and equipment.

3. Each submittal shall cover items from only one section of the specification unless the item consists of components from several sources. The Company shall submit a complete initial submittal including all components. When an item consists of components from several sources, the Company's initial submittal shall be complete including all components.

4. All submittals, regardless of origin, shall be approved by the Company and clearly identified with the name and number of this Contract, Company's name, and references to applicable specification paragraphs and Contract Drawings. Each copy of all submittals, regardless of origin, shall be stamped or affixed with an approval statement of the Company. Each submittal shall indicate the intended use of the item in the Work. When catalog pages are submitted, applicable items shall be clearly identified and inapplicable data crossed out. The current revision, issue number, and date shall be indicated on all drawings and other descriptive data.

5. The Company shall be solely responsible for the completeness of each submittal.

The Company's stamp or affixed approval statement of a submittal, per Figure 1-

01300, is a representation to the City and Engineer that Company accepts sole responsibility for determining and verifying all measurements, quantities, dimensions, and specified performance and design criteria with the Invitation to

Bid documents provided upon award of contract.

Charlotte Water 01300 - 2 February 2026

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

6. All deviations from the requirements of the Contract Documents shall be identified as deviations on each submittal and shall be tabulated in the Company's letter of transmittal using Figure 2-01300. Such submittals shall, as pertinent to the deviation, indicate essential details of all changes proposed by the Company

(including modifications to other facilities that may be a result of the deviation) and all required piping and wiring diagrams.

7. The Company shall submit shop drawings and other submittals electronically. For electronic submittals, drawings and the necessary data shall be submitted electronically to Engineer as specified below. Submittal documents shall be in color to facilitate use of red line markups.

a. All electronic files shall be in Portable Document Format (PDF) as generated by Adobe Acrobat Professional Version 7.0 or higher.

b. The PDF file(s) shall be fully indexed using the Table of Contents, searchable with thumbnails generated. PDF images must be at a readable resolution.

c. Scanned PDFs of manufacturer products are not acceptable.

d. Documents shall be generated at 300 pots per inch (dpi). Use of higher resolutions is acceptable with City and Engineer approval.

e. Optical Character Recognition (OCR) capture must be performed on images so that text can be searched, selected and copied from the PDF file.

f. The PDF documents shall have a bookmark created in the navigation frame for each major entry (“Section” or “Chapter”) in the Table of Contents.

g. Thumbnails shall be generated for each page or graphic in the PDF file.

h. The opening view for each PDF document shall be as follows:

1) Initial View: Bookmarks and Page

2) Magnification: Fit In Window

3) The file shall open to the Company’s transmittal letter, with bookmarks to the left. The first bookmark shall be linked to the Table of Contents.

i. PDF document properties shall include the submittal number for the document title and Company’s name for the author.

j. Electronic submittal file sizes shall be limited to 20 MB. When multiple files are required for a submittal the least number of files possible shall be created.

8. Submittal Naming Convention. Company shall name submittal document files per the following naming convention:

a. PRJNUM-XXXXX-YYYZ – [Description] where

1) PRJNUM is the Engineer’s Project number, Charlotte Water 01300 - 3 February 2026

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

2) XXXXX is the six-digit number corresponding to the specification section,

3) YYY is a three-digit submittal number,

4) Z is the letter signifying the initial submittal (A) and sequential resubmittals (B, C, D, etc.), and

5) [Description] is the description of what is being submitted.

b. For example:

1) Resubmittals

a) A resubmittal of the original or sequential resubmittal changes the “Z” lettering. The initial submittal of the Preliminary

Progress Schedule would be named: “193725-013216-001A –

Preliminary Progress Schedule”. If the submittal is Not

Acceptable (NA) or Returned for Correction (RFC) the resubmittal would be named: “193725-013216-001B –

Preliminary Progress Schedule”.

2) Submittals in same Section

a) For a new submittal within the same section of already existing submittals. If, for example, the “193725-013216-001A –

Preliminary Progress Schedule” has already been submitted.

Then a new submittal within the same section would change the “YYY” numbering. For example, the Progress Schedule submittal would be named: “193725-013216-002A – Progress

Schedule”.

9. The Company shall post submittals and retrieve Engineer's submittal review comments through the Project website accessible through the Internet. Instruction on procedures for posting and retrieving submittals will be provided after award of the Contract.

10. Facsimiles (fax) will not be acceptable. Submittals will not be accepted from anyone but the Company. Submittals shall be consecutively numbered in direct sequence of submittal and without division by subcontracts or trades.

B. Engineer's Review of Submittals.

1. Engineer's review of submittals covers only general conformity to the Drawings and Specifications, external connections, and dimensions that affect the layout; it does not indicate thorough review of all dimensions, quantities, and details of the material, equipment, device, or item covered. Engineer's review shall not relieve

Company of sole responsibility for errors, omissions, or deviations in the drawings

Charlotte Water 01300 - 4 February 2026

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08 and data, nor of Company's sole responsibility for compliance with the Contract

Documents.

2. Engineer's submittal review period shall be 21 consecutive calendar days and shall commence on the first calendar day following receipt of the submittal or resubmittal in Engineer's office.

3. When the drawings and data are returned with review status "NOT

ACCEPTABLE" or "RETURNED FOR CORRECTION", the corrections shall be made as instructed by Engineer.

a. The corrected drawings and data shall be resubmitted through the Project website.

b. Resubmittals by facsimile or e-mail will not be accepted. When the drawings and data are returned with review status "EXCEPTIONS

NOTED", "NO EXCEPTIONS NOTED", or "RECORD COPY", no additional copies need be furnished unless specifically requested by

Engineer.

C. Resubmittal of Shop Drawings and Data.

1. The Company shall accept full responsibility for the completeness of each resubmittal. The Company shall verify that all corrected data and additional information previously requested by Engineer are provided on the resubmittal.

Resubmittals shall be in an organized and consistent format.

2. When corrected copies are resubmitted, Company shall direct specific attention to all revisions in writing and shall list separately any revisions made other than those called for by Engineer on previous submittals. Requirements specified for initial submittals shall also apply to resubmittals. Resubmittals shall bear the number of the first submittal followed by a letter (A, B, etc.) or a unique identification that indicates the initial submittal and correct sequence of each resubmittal.

3. If more than one resubmittal is required because of failure of the Company to provide all previously requested corrected data or additional information, the

Company shall reimburse the City for the charges of Engineer for review of the additional resubmittals. This does not include initial submittal data such as shop tests and field tests that are submitted after initial submittal.

4. Resubmittals shall be made within 30 days of the date of the letter returning the material to be modified or corrected, unless within 14 days Company submits an acceptable request for an extension of the stipulated time period, listing the reasons the resubmittal cannot be completed within that time.

5. The need for more than one resubmittal, or any other delay in obtaining Engineer's review of submittals, will not entitle the Company to extension of the Contract

Times unless delay of the Work is the direct result of a change in the Work

Charlotte Water 01300 - 5 February 2026

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08 authorized by a Change Order or failure of Engineer to review and return any submittal to the Company within the specified review period.

D. Color Selection.

1. The Company shall submit samples of colors and finishes for all accepted products before Engineer will coordinate the selection of colors and finishes with the City.

Engineer will prepare a schedule of finishes that includes the colors and finishes selected for both manufactured products and for surfaces to be field painted or finished and will furnish this schedule to the Company within 60 days after the date of acceptance of the last color or finish sample.

1.2 OPERATION AND MAINTENANCE DATA AND MANUALS.

A. Adequate operation and maintenance information shall be supplied for all equipment requiring maintenance or other attention. The Company shall prepare a Project specific operation and maintenance manual for each type of equipment indicated in the individual equipment sections or the equipment schedule.

B. Unless otherwise agreed by Engineer, the operation and maintenance manual for each type of equipment shall only be submitted for review following completion of review of all shop drawings and engineering data pertaining to that equipment.

C. Parts lists and operating and maintenance instructions shall be furnished for other equipment not listed in the individual equipment sections or the equipment schedule.

D. Operation and maintenance manuals shall include the following:

1. Equipment function, normal operating characteristics, and limiting conditions.

2. Assembly, installation, alignment, adjustment, and checking instructions.

3. Operating instructions for startup, routine and normal operation, regulation and control, shutdown, and emergency conditions.

4. Lubrication and maintenance instructions.

5. Guide to troubleshooting.

6. Parts lists and predicted life of parts subject to wear.

7. Outline, cross section, and assembly drawings; engineering data; and wiring diagrams.

8. Test data and performance curves, where applicable.

Charlotte Water 01300 - 6 February 2026

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

E. The operation and maintenance manuals shall be in addition to any instructions or parts lists packed with or attached to the equipment when delivered, or which may be required by the Company.

F. Electronic Manuals

1. Manuals shall be submitted in electronic format to Engineer prior to the date of shipment of the equipment. The manuals shall be submitted and Engineer’s review comments retrieved, through the Project website accessible through the Internet.

Instruction on procedures for posting and retrieving O&M submittals and review comments will be provided after award of the Contract. When the O&M manuals are returned with the review status "RETURNED FOR CORRECTION", the corrections shall be made as instructed by Engineer, and corrected manuals resubmitted to Engineer. When review by Engineer is complete, three copies of each electronic O&M manual shall be delivered on flash drives to Engineer. Each flash drive shall contain only one copy of each manual. The completed O&M manual shall also be filed to the Project website. Delivery of the final O&M shall be made 30 days prior to placing the equipment in operation.

G. All material shall be marked with Project identification, and inapplicable information shall be marked out or deleted.

H. Shipment of equipment will not be considered complete until all required manuals and data have been received.

I. Electronic Operation and Maintenance Manual Requirements.

1. Electronic manuals shall be in Adobe Acrobat’s Portable Document Format (PDF), and shall be prepared at a resolution between 300 and 600 dots per inch (dpi), depending on document type.

2. Optical Character Recognition (OCR) capture shall be performed on these documents. OCR settings shall be performed with the “original image with hidden text” option in Adobe Acrobat Exchange.

3. File size shall be limited to 20 MB. A single PDF file greater than 20 MB may only be submitted if acceptable to the City. When multiple files are required the least number of files possible shall be created.

4. File names shall be in the format OMXXXXX-YYYZ-V.pdf, where XXXXX is the five digit number corresponding to the specification section, YYY is a three digit O&M manual number, e.g. 001, Z is the letter signifying a resubmittal, A, B, C, etc., and V is a number used only when more than one 20 MB file is required for an O&M manual.

5. Documents prepared in PDF format shall be processed as follows:

Charlotte Water 01300 - 7 February 2026

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

a. Pages shall be searchable (processed for optical character recognition) and indexed when multiple files are required.

b. Pages shall be rotated for viewing in proper orientation.

c. A bookmark shall be provided in the navigation frame for each entry in the

Table of Contents.

d. Embedded thumbnails shall be generated for each completed PDF file.

e. The opening view for PDF files shall be as follows:

1) Initial View: Bookmarks and Page

2) Page Number: Title Page (usually Page 1)

3) Magnification: Set to Fit in Window

4) Page: Single Page

f. Where the bookmark structure is longer than one page the bookmarks shall be collapsed to show the chapter headings only.

g. When multiple files are required the first file of the series (the parent file) shall list every major topic in the Table of Contents. The parent file shall also include minor headings bookmarked based on the Table of Contents.

Major headings, whose content is contained in subsequent files (children) shall be linked to be called from the parent to the specific location in the child file. The child file shall contain bookmark entries for both major and minor headings contained in the child file. The first bookmark of any child file shall link back to the parent file and shall read as follows "Return to the

Equipment Name Table of Contents", e.g. Return to the Polymer Feed

System Table of Contents.

h. Drawings shall be bookmarked individually.

i. Files shall be delivered without security settings to permit editing, insertion and deletion of material to update the manual provided by the manufacturer.

J. Labeling

1. As a minimum, the following information shall be included on all final O&M manual materials, including flash drives:

a. Equipment name and/or O&M title spelled out in complete words.

b. Project Name.

c. City Project/Contract Number.

d. Specification Section Number. Example: “Section 15500”

e. Manufacturer’s name.

f. File Name and Date.

2. Label example:

Backwash Pump Operation and Maintenance Manual

Somewhere Plant Expansion

Charlotte Water 01300 - 8 February 2026

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

Project/Contract No. FY25-ITB-05

Specification Section 15500

Manufacturer

OM11110-001.pdf, 05/05/2025

PART 2 - PRODUCTS (NOT USED)

Submittal Identification and Seller's Approval Statement

Charlotte Water Figure 1-01300 - 1 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

SUBMITTAL No. ________

SECTION ______________

Do not combine multiple sections together unless required by specifications.

(SELLER's Letterhead)

SUBMITTAL IDENTIFICATION &

SELLER'S APPROVAL STATEMENT

DATE: ____________ COPIES ____________ DRAWING SHEET NO._______

Description submittal contents:

Location:

Manufacturer:

REMARKS:

SELLER'S APPROVAL

( SELLER ) has reviewed and coordinated the submitted documentation and verifies that the equipment and material meet the requirements of the Goods and Special Services and the Contract Documents. We accept sole responsibility for determining and verifying all quantities, dimensions, field construction criteria, materials, catalog numbers, and similar data contained in the submittal as required by the Contract Documents.

Deviations: □ None □ Yes (See attached Figure 2-01300 for written description)

Approved By: ____________________ Date: ________________

This approval does not release CONSTRUCTION CONTRACTOR from the contractual responsibilities.

Submittal Identification and Contractor's Approval Statement

Charlotte Water Figure 2-01300 - 1 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

SUBMITTAL No. ________

SECTION ______________

Do not combine multiple sections together unless required by specifications.

(SELLER'S Letterhead)

SUBMITTAL IDENTIFICATION &

SELLER’S APPROVAL STATEMENT

DATE: ____________ COPIES ____________ DRAWING SHEET NO._______

Description submittal contents:

Location:

Manufacturer:

Subcontractor or Supplier (Optional)

DEVIATIONS

General Equipment Stipulations

Charlotte Water 01610 - 1 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

Section 01610 - GENERAL EQUIPMENT STIPULATIONS

PART 1 - GENERAL

1.1 SCOPE.

A. When an equipment specification section in this Contract references this section, the equipment shall conform to the general stipulations set forth in this section, except as otherwise specified in other sections.

1.2 COORDINATION.

A. Company shall coordinate all details of the equipment with other related parts of the

Work, including verification that all structures, piping, wiring, and equipment components are compatible.

1.3 MANUFACTURER'S EXPERIENCE.

A. Unless specifically named in the Specifications, a manufacturer shall have furnished equipment of the type and size specified which has been in successful operation for not less than the past 5 years.

1.4 WORKMANSHIP AND MATERIALS.

A. Company shall guarantee all equipment against faulty or inadequate design, improper assembly or erection, defective workmanship or materials, and leakage, breakage, or other failure. Materials shall be suitable for service conditions.

B. All equipment shall be designed, fabricated, and assembled in accordance with recognized and acceptable engineering and shop practice. Individual parts shall be manufactured to standard sizes and thicknesses so that repair parts, furnished at any time, can be installed in the field. Like parts of duplicate units shall be interchangeable.

Equipment shall not have been in service at any time prior to delivery, except as required by tests.

C. Except where otherwise specified, structural and miscellaneous fabricated steel used in equipment shall conform to AISC standards. All structural members shall be designed for shock or vibratory loads. Unless otherwise specified, all steel which will be submerged, all or in part, during normal operation of the equipment shall be at least

1/4 inch thick. When dissimilar metal components are used, consideration shall be given to prevention of galvanic corrosion.

Charlotte Water 01610 - 2 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

1.5 STRUCTURAL DESIGN REQUIREMENTS.

A. All equipment, including non-structural components and non-building structures as defined in ASCE 7, and their anchorage, shall be designed and detailed in accordance with the Meteorological and Seismic Design Criteria section.

1.6 LUBRICATION.

A. Equipment shall be adequately lubricated by systems which require attention no more frequently than weekly during continuous operation. Lubrication systems shall not require attention during startup or shutdown and shall not waste lubricants.

B. Lubricants of the types recommended by the equipment manufacturer shall be provided in sufficient quantities to fill all lubricant reservoirs and to replace all consumption during testing, startup, and operation prior to acceptance of equipment by City.

Lubricants for equipment where the lubricants may come in contact with water shall be suitable for use in wastewater treatment applications and shall not harm downstream biological processes. This includes lubricants for equipment not normally in contact with water, but where accidental leakage of the lubricants may contaminate the water.

C. Lubrication facilities shall be convenient and accessible. Oil drains and fill openings shall be easily accessible from the normal operating area or platform. Drains shall allow for convenient collection of waste oil in containers from the normal operating area or platform without removing the unit from its normal installed position.

1.7 ELEVATION.

A. The elevation of the site shall be as indicated in the Meteorological and Seismic Design

Criteria section. All equipment furnished shall be designed to meet stipulated conditions and to operate satisfactorily at the specified elevation.

1.8 ELECTRIC MOTORS.

A. Unless otherwise specified, motors furnished with equipment shall meet the requirements specified in Common Motor Requirements for Process Equipment section or specified in specific equipment sections.

1.9 DRIVE UNITS.

A. The nominal input horsepower rating of each gear or speed reducer shall be at least equal to the nameplate horsepower of the drive motor. Drive units shall be designed for

24 hour continuous service.

Charlotte Water 01610 - 3 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

B. Gearmotors.

1. The use of gearmotors sharing an integral housing or cutgears into the motor output shaft, or that require removal of lubricant from the gear reducer to change out the motor will not be acceptable.

C. Gear Reducers.

1. Each gear reducer shall be a totally enclosed unit with oil or grease lubricated, rolling element, antifriction bearings throughout.

D. Unless superseded by individual specification requirements each helical, spiral bevel, combination bevel-helical, and worm gear reducers shall have a service factor of at least

1.50 based on the nameplate horsepower of the drive motor. Cycloidal gear reducers shall have a service factor of at least 2.0 based on the nameplate horsepower of the drive motor. Shaft-mounted and flange-mounted gear reducers shall be rated AGMA

Class III. Helical gear reducers shall have a gear strength rating to catalog rating of 1.5.

Each gear reducer shall be designed and manufactured in compliance with applicable most current AGMA standards, except the L10 bearing life shall be 200, 000 hours.

E. The thermal horsepower rating of each unit shall equal or exceed the nameplate horsepower of the drive motor. During continuous operation, the maximum sump oil temperature shall not rise more than 100°F above the ambient air temperature in the vicinity of the unit and shall not exceed 200°F.

F. Each grease lubricated bearing shall be installed in a bearing housing designed to facilitate periodic regreasing of the bearing by means of a manually operated grease gun. Each bearing housing shall be designed to evenly distribute new grease, to properly dispose of old grease, and to prevent overgreasing of the bearing. The use of permanently sealed, grease lubricated bearings will not be acceptable in large sized reducers. In small reducers, similar to basin equipment, permanently sealed grease lubricated bearings rated L10 200,000 hour life may be provided at the manufacturer’s option. An internal or external oil pump and appurtenances shall be provided if required to properly lubricate oil lubricated bearings. A dipstick or a sight glass arranged to permit visual inspection of lubricant level shall be provided on each unit.

G. Gear reducers which require the removal of parts or the periodic disassembly of the unit for cleaning and manual regreasing of bearings will not be acceptable.

H. Certification shall be furnished by the gear reducer manufacturer indicating that the intended application of each unit has been reviewed in detail by the manufacturer and that the unit provided is fully compatible with the conditions of installation and service.

Charlotte Water 01610 - 4 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

1.10 SAFETY GUARDS.

A. All belt or chain drives, fan blades, couplings, and other moving or rotating parts shall be covered on all sides by a safety guard. Safety guards shall be fabricated from

16 USS gage thick or thicker galvanized, aluminum-clad sheet steel, or stainless sheet steel or from 1/2 inch mesh galvanized expanded metal, or pultrusion molded UV resistant materials. Each safety guard shall be reinforced or shaped to provide suitable strength to prevent vibration and deflection and shall comply with OSHA. Each guard shall be designed for easy installation and removal. All necessary supports and accessories shall be provided for each guard. Supports and accessories, including bolts, shall be galvanized. All safety guards in outdoor locations shall be designed to prevent the entrance of rain and dripping water.

1.11 ANCHOR BOLTS.

A. Company shall design and detail suitable anchor bolts for each item of equipment.

Anchor bolts shall be designed for all operating conditions of the equipment, including wind and seismic loadings when applicable. Wind and seismic loads shall be as indicated in the Meteorological and Seismic Design Criteria section.

B. Requirements for anchor bolt type, material, and minimum diameter shall be as indicated in the Anchorage in Concrete and Masonry section.

C. Unless otherwise indicated or specified, anchor bolts for items of equipment mounted on baseplates shall be long enough to permit 1-1/2 inches of grout beneath the baseplate and to provide adequate anchorage into structural concrete.

1.12 SPECIAL TOOLS AND ACCESSORIES.

A. Equipment requiring periodic repair and adjustment shall be furnished complete with all special tools, instruments, and accessories required for proper maintenance. Equipment requiring special devices for lifting or handling shall be furnished complete with those devices.

1.13 SHOP PAINTING.

A. All iron and steel surfaces of the equipment shall be protected with suitable protective coatings applied in the shop. Surfaces of the equipment that will be inaccessible after assembly shall be protected for the life of the equipment. Coatings shall be suitable for the environment where the equipment is installed. Exposed surfaces shall be finished, thoroughly cleaned, and filled as necessary to provide a smooth, uniform base for painting. Electric motors, speed reducers, starters, and other self-contained or enclosed components shall be shop primed or finished with an epoxy or polyurethane enamel or

Charlotte Water 01610 - 5 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08 universal type primer suitable for top coating in the field with a universal primer and aliphatic polyurethane system.

B. Surfaces to be coated after installation shall be prepared for painting as recommended by the paint manufacturer for the intended service, and then shop painted with one or more coats of a universal primer.

C. Machined, polished, and nonferrous surfaces which are not to be painted shall be coated with rust-preventive compound as recommended by the equipment manufacturer.

1.14 PREPARATION FOR SHIPMENT.

A. Equipment shall be prepared for shipment as specified in the Product Delivery

Requirements section.

1.15 OBSERVATION OF PERFORMANCE TESTS.

A. Where the Specifications require the presence of Engineer, initial tests shall be observed or witnessed by Engineer. City shall be reimbursed by Company for all costs of subsequent visits by Engineer to witness or observe incomplete tests, retesting, or subsequent tests.

1.16 PROGRAMMING SOFTWARE.

A. Programming software shall be provided for any equipment which includes a programmable logic controller (PLC) or other digital controller that is user-programmable.

B. The software shall be suitable for loading and running on a laptop personal computer operating with a Windows-based operating system.

C. A copy of the manufacturer's original operating logic program shall be provided for use in maintaining and troubleshooting the equipment.

D. Where multiple pieces of equipment, from the same or different vendors, use the same programming software, only one copy of the software need be provided.

PART 2 - PRODUCTS (NOT USED)

Meteorological and Seismic Design Criteria

Charlotte Water 01611 - 1 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

SECTION 01611 - METEOROLOGICAL AND SEISMIC DESIGN CRITERIA

PART 1 - GENERAL

1.1 SCOPE

A. Buildings, non-structural components and non-building structures shall be designed in accordance with this section. In the event of conflict with requirements in other sections, the more stringent criteria shall be followed.

1.2 DESIGN CRITERIA.

A. Non structural components including anchorage of such items, shall be designed in accordance with the following criteria.

1. General Design Data

Building code and references IBC 2021, ASCE 7-16 “Minimum

Design Loads and Associated

Criteria for Buildings and Other

Structures”, AISC 360

“Specification for Structural Steel

Buildings”, AISC 341 “Seismic

Provisions for Structural Steel

Buildings”

Site elevation, above mean sea level (ft) 682.17

Design flood elevation (ft) 658

Design groundwater elevation (ft)

2. Wind Design Data

Basic (Ultimate) design wind speed, V

(mph)

Allowable Stress (Nominal) design wind speed, Vasd (mph)

Exposure category C

Ground elevation factor, Ke 1.0

Risk Category III

3. Snow Design Data

Ground snow load, Pg (psf) 10

Importance factor (snow loads), I 1.1

Exposure factor (Ce) 1.0

Charlotte Water 01611 - 2 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

Thermal factor (Ct) 1.2

4. Ice Design Data

Nominal ice thickness, t (in) 1.50

Concurrent wind speed, Vc (mph) 30

Importance factor (ice loads – ice thickness), Ii

1.15

Importance factor (ice loads – concurrent wind), Iw

1.0

5. Seismic Design Data

Mapped MCE short period spectral response acceleration, SS

0.193

Mapped MCE one second period spectral response acceleration, S1

0.08

Design short period spectral response acceleration, SDS

0.206

Design one second period spectral response acceleration, SD1

0.128

Risk Category III

Non-Structural Components Importance

Factor, IP

As indicated in the Non-Structural

Components Schedule

Non-Structural Components Seismic

Design Category

Non-Building Structures Importance

Factors, I

As indicated in the Non-Building

Structure Schedule or in the applicable reference documents, whichever is greater.

1.3 WIND ANCHORAGE

A. Equipment that is to be located outdoors shall have anchor bolts designed for the effects of wind forces, as determined in accordance with ASCE 7, Chapters 26-31.

B. Design of anchorage shall be in accordance with the Anchorage in Concrete and

Masonry section.

Charlotte Water 01611 - 3 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

1.4 SEISMIC DESIGN

A. General.

1. Structural systems shall provide continuous load paths, with adequate strength and stiffness to transfer all seismic forces from the point of application to the point of final resistance.

B. Non-Structural Components.

1. Non-structural components are architectural, mechanical, and electrical items that are permanently attached to and supported by a structure but are not part of the structural system, as indicated in Chapter 13 of ASCE 7. Clarifier mechanism, by section 13.1.3 Ip=1.0 and since clarifier mechanism will be positively attached to structure, which in this case will be through the bolts, thus the mechanism is exempt from seismic requirements as indicated on section 13.1.4a of ASCE7.

2. General

a. Design of non-structural components shall be in accordance with all applicable provisions of ASCE 7, Chapter 13.

b. “Wp” shall include the total operating weight of the component or system, including, but not limited to, any insulation, fluids, and concentrated loads such as valves, condensate traps, and similar components.

PART 2 - PRODUCTS (NOT USED)

Charlotte Water 01611 - 4 February 2026

Non-Structural Components Schedule

Component Applicable

Specification

Section

Importance

Factor (Ip)

Special

Seismic

Certification

Required

Circular Clarifier Equipment 11410 1.0

Note: Some specification sections listed in the Non-Structural Components Schedule cover multiple items. Within those sections, some components may be exempt from seismic design based on their weight and/or their height above the floor. Reference ASCE 7, Paragraph 13.1.4 for specific conditions of the exemptions. Some distribution systems such as conduit, cable tray, raceways, duct systems, and piping and tubing systems may also be exempt from seismic design based on their loads and support mechanisms as indicated in their respective paragraphs in

ASCE 7, Chapter 13.

Product Delivery Requirements

Charlotte Water 01612 - 1 February 2026

Section 01612 - PRODUCT DELIVERY REQUIREMENTS

PART 1 - GENERAL

1.1 SCOPE.

A. This section covers packaging and shipping of materials and equipment.

1.2 PREPARATION FOR SHIPMENT.

A. All equipment shall be suitably packaged to facilitate handling and to protect against damage during transit and storage. All equipment shall be boxed, crated, or otherwise completely enclosed and protected during shipment, handling, and storage. All equipment shall be protected from exposure to the elements and shall be kept dry at all times.

B. Painted and coated surfaces shall be protected against impact, abrasion, discoloration, and other damage. Painted and coated surfaces which are damaged prior to acceptance of equipment shall be repainted to the satisfaction of Engineer.

C. Grease and lubricating oil shall be applied to all bearings and similar items.

1.3 SHIPPING.

A. Before shipping each item of equipment shall be tagged or marked as identified in the delivery schedule or on the Shop Drawings. Complete packing lists and bills of material shall be included with each shipment.

PART 2 - PRODUCTS (NOT USED)

Equipment Identification

Charlotte Water 01615 - 1 February 2026

McDowell Creek WRRF Issued for Procurement B&V Project No. 424706

Primary Clarifier No. 4 Equipment Procurement CW Project No. FY26-ITB-08

Section 01615 - EQUIPMENT IDENTIFICATION

PART 1 - GENERAL

1.1 SCOPE.

A. This section covers the furnishing and installation of nameplates and tags for identification of equipment, valves, panels, and instruments.

1.2 GENERAL.

A. Except as otherwise specified in equipment, valve, and instrumentation sections, nameplates and tags shall be as specified herein. Nameplates or tags shall be provided for all equipment, valves, operator interfaces, control and electrical panels, cabinets, instruments, and instrument racks that have been named and/or tagged on the Drawings.

1.3 SUBMITTALS.

A. Drawings and Data

1. Drawings and data shall be submitted in accordance with the requirements of the

Submittals Procedures section for each type of tag provided including materials, colors, sizes, letter sizes, and installation instructions.

PART 2 - PRODUCTS

2.1 EQUIPMENT INFORMATION PLATES.

A. Equipment shall be provided with…