10-B. FY26-ITB-08 McDowell Creek WRRF Primary Clarifier No. 4.pdf

PDF 404 KB Posted

Attached to
McDowell Creek WRRF Primary Clarifier No. 4. Equipment
Solicitation number
FY26-ITB-08
Issued by
Mecklenburg County, Charlotte City, North Carolina

About this file

This Invitation to Bid (ITB) is issued by Charlotte Water, a department of the City of Charlotte, North Carolina, for the procurement of equipment to support the McDowell Creek Water Resource Recovery Facility (WRRF). The scope of work involves establishing a contract for the purchase and delivery of a primary clarifier mechanism, specifically Primary Clarifier No. 4, along with associated coordination and supervision services. Bidders must submit electronic bids through the City's Bonfire e-Procurement Portal no later than April 8, 2026, at 3:00 p.m. Eastern Time. The bid opening will occur publicly on the same date at 5100 Brookshire Boulevard, Charlotte, North Carolina, with virtual attendance available by phone or Microsoft Teams. Written questions must be submitted by March 27, 2026, at 12:00 p.m. No pre-bid conference will be held. Contract award is anticipated to occur in May 2026, with an anticipated contract effective date in June 2026. The awarded company shall deliver the clarifier mechanism to McDowell Creek WRRF located at 5300 Jim Kidd Road, Huntersville, North Carolina, within forty weeks from contract execution. All products must be new, of the highest grade workmanship, and in full compliance with applicable federal, state, and local laws and regulations.

Pricing shall be submitted as a lump sum including shipping, delivery, discounts, vendor markup and profit, item costs, and storage per the provided price schedule, with no additional charges permitted. Payment will be made in three milestone installments: 10 percent upon shop drawings approval, 70 percent upon delivery, and 20 percent upon successful completion of operational acceptance testing. The company is responsible for obtaining all permits and inspections. Liquidated damages of five hundred dollars per day will be assessed for delivery delays exceeding the forty-week timeframe, and if delays extend sixty days, the City reserves the right to terminate the contract for default. All products must include a manufacturer's written warranty covering defects in materials, workmanship, and performance for a minimum of two years, with the manufacturer responsible for all warranty repair shipping and crating costs. The bid must remain binding for one hundred twenty calendar days from the opening date, and the resulting contract must receive approval from Charlotte City Council. The City reserves the right to award the contract based on the lowest responsive responsible bidder, considering vendor qualifications, experience, quality, delivery, and workmanship.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 1

INVITATION TO BID

MCDOWELL CREEK WRRF PRIMARY

CLARIFIER NO.4 EQUIPMENT

PROCUREMENT

ITB # FY26-ITB-08

CITY OF CHARLOTTE

NORTH CAROLINA

MARCH 12, 2026

ITB# FY26-ITB-08 MARCH 12, 2026 2

CITY OF CHARLOTTE – CHARLOTTE WATER

5100 BROOKSHIRE BLVD., 2ND FLOOR

CHARLOTTE, NORTH CAROLINA 28216

Date: MARCH 12, 2026 Bid Number: FY26-ITB-08

Subject: Invitation to Bid on the following apparatus, supplies, materials, equipment and/or services for:

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

This letter extends an invitation for the submission of a Bid to supply Charlotte Water, a department of the City of Charlotte, with apparatus, supplies, materials, equipment and/or services as indicated above. The City of Charlotte uses a Bonfire e-Procurement Portal (“Procurement Portal” -https://charlottenc.bonfirehub.com) for accepting and evaluating bids digitally. Bids must be submitted electronically through the Procurement Portal on or before the Bid Due Date in order to be accepted. Bids will be opened (unsealed electronically) at the time and place indicated and, unless obviously non-responsive, read aloud publicly.

As a courtesy, the public may view the bid opening virtually. Refer to Section 1.8 for additional information.

All times stated herein shall refer to the Eastern Time Zone.

No Pre-Bid Meeting will be held for this procurement.

Any changes to the terms, conditions or specifications stated in this ITB will be documented in a written addendum and will be posted on the Procurement Portal. Each Bidder is required to acknowledge receipt of all addenda. Please note that we may not consider any Bid that fails to acknowledge receipt of each issued addendum.

A response from your Company to this ITB would be appreciated. Questions should be submitted in writing through the Vendor Discussions section on the Procurement Portal.

Sincerely, Wendy Raiford Procurement Officer https://charlottenc.bonfirehub.com/

ITB# FY26-ITB-08 MARCH 12, 2026 3

Checklist for Submitting a Bid:

Step 1 Read the document fully.

Step 2 Review the solicitation timeline and upcoming events in the Procurement Portal and download copies of any documents if you plan to submit a Bid.

Step 3 Submit any questions via the Vendors Discussion Section in the Procurement Portal by the deadline(s) noted for the solicitation.

Step 4 Conduct a thorough review of the Sample Contract. No exceptions will be considered or permitted.

Step 5 Monitor the Procurement Portal for any addendums and/or responses to questions.

If you plan to submit a Bid, you must submit all required documents and respond to all questions within the Procurement Portal for the ITB

If awarded a contract, your company will be required to provide an insurance certificate(s) that meets or exceeds the requirements set forth in the Sample Contract.

ITB# FY26-ITB-08 MARCH 12, 2026 4

TABLE OF CONTENTS

INSTRUCTIONS TO BIDDERS

1.1. REVIEW AND COMPLY:

1.2. DEFINITIONS:

1.3. CONTRACT DOCUMENTS:

1.4. EXCEPTIONS:

1.5. MULTIPLE/ALTERNATE BIDS:

1.6. HOW TO PREPARE BID RESPONSES:

1.7. HOW TO SUBMIT BID RESPONSES:

1.8. BID OPENING PROCEDURES:

1.9. TRADE SECRETS AND PERSONAL IDENTIFICATION INFORMATION:

1.10. QUESTIONS AND PRE-BID CONFERENCE:

1.11. HOW TO SUBMIT AN OBJECTION RELATING TO THIS INVITATION TO BID:

1.12. BINDING OFFER:

1.13. ERRORS IN BIDS:

1.14. CITY’S RIGHTS AND OPTIONS:

1.15. BIDS ON ALL OR PART:

1.16. INVITATION TO BID NOT AN OFFER:

1.17. CHARLOTTE BUSINESS INCLUSION PROGRAM:

1.18. EQUAL OPPORTUNITY:

1.19. NO COLLUSION OR CONFLICT OF INTEREST:

1.20. ANTI-LOBBYING PROVISION:

1.21. CERTIFIED TEST REPORT:

1.22. BRAND NAME:

1.23. TO SUBMIT A PROPOSED ALTERNATE PRODUCT IN LIEU OF A SPECIFIED BRAND:

1.24. STATUTORY REQUIREMENTS:

1.25. GUARANTOR:

1.26. AWARD CRITERIA:

1.27. ENVIRONMENTAL PREFERABLE PURCHASING:

1.28. CONTRACT AWARD BY CHARLOTTE CITY COUNCIL:

1.29. PROCUREMENT SCHEDULE:

TERMS AND CONDITIONS

2.1. CONTRACT TYPES:

2.2. TERMS OF CONTRACT:

2.3. NOTICE TO PROCEED:

2.4. DELIVERY TIME:

2.5. PRICES ARE FIRM:

2.6. PROMPT PAYMENT DISCOUNTS:

2.7. QUALITY:

2.8. INSPECTION AT BIDDER’S SITE:

2.9. CERTIFICATION OF INDEPENDENT PRICE DETERMINATION:

2.10. INSURANCE:

2.11. SPILL PREVENTION, RESPONSE, AND REPORTING AT TREATMENT FACILITIES:

SPECIFICATIONS

ITB# FY26-ITB-08 MARCH 12, 2026 5

3.1. BACKGROUND:

3.2. SCOPE:

3.3. MANUFACTURER/MODEL:

3.4. PRODUCT SPECIFICATIONS AND STANDARDS:

3.5. WARRANTY:

3.6. INSTALLATION:

3.7. PRICING:

3.8. MILESTONE PAYMENT:

3.9. DELIVERY AND STORAGE:

3.10. DELIVERY PERSONNEL:

3.11. INVOICES:

3.12. AWARD OF CONTRACT:

3.13. CITY CONTRACTING REQUIREMENTS:

3.14. ITEMS UNDER CONTRACT:

3.15. PERMITTING RESPONSIBILITIES:

3.16. NO LIMITATIONS ON DISCLOSURE

3.17. PLACEMENT OF ORDERS:

Attachments:

Exhibit A – Price Schedule

Exhibit B – Project Manual

C. FY26-ITB-08 Sample Contract

Section One Instructions to Bidders

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 6

INSTRUCTIONS TO BIDDERS

1.1. Review and Comply:

Each reference to this Invitation to Bid (“ITB”) includes all components listed in the Table of Contents above. Please review each of them carefully. Bidders will be held accountable for having full knowledge of the contents of this ITB and for performing any due diligence that may be necessary to submit a binding Bid.

1.2. Definitions:

Addendum: Refers to any and all modifications or additions to this Invitation to Bid that are issued in writing by Charlotte Water Procurement.

Bid: Refers to a bid submitted by a company in response to this Invitation to Bid. A Bid shall be submitted on the Procurement Portal.

Bid Response Forms: Refers to the forms that a Bidder is required to complete and return as its Bid, as included in the Public Files on the Procurement Portal.

Bidder: Refers to a person or entity that submits a Bid.

CBI: Refers to the Charlotte Business INClusion office of the City of Charlotte.

Charlotte Combined Statistical Area (CSA): Refers to the area consisting of the North Carolina counties of Anson, Cabarrus, Cleveland, Gaston, Iredell, Lincoln, Mecklenburg, Rowan, Stanly, and Union, and the South Carolina counties of Chester, Lancaster, and York; a criteria used by Charlotte Business INClusion to determine eligibility to participate in the program.

City: Refers to the City of Charlotte, North Carolina.

Company: During the solicitation process, refers to a company that has interest in providing the Products and Services. After the solicitation process, refers to a company that enters into a Contract with the City for all or part of the Products and Services covered by this ITB.

Contract: A contract under which a Bidder agrees to provide all or part of the Products and Services to the City. A Contract shall include the Terms and Conditions set forth in the Sample Contract provide in the Public Files on the Procurement Portal.

Engineer: Refers to Black & Veatch International Company.

Environmentally Preferable Products: Products that have a lesser or reduced effect on human health and the environment when compared with competing products that serve the same purpose. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.

Installing Contractor: An entity under a separate contract with the City to provide installation services for equipment procured under this Contract.

Minority Business Enterprise (MBE): Refers to a business enterprise that: (i) is certified by the State of North

Carolina as a Historically Underutilized Business (HUB) within the meaning of N.C. Gen. Stat. § 143-128.4; (ii) is at least fifty-one percent (51%) owned by one or more persons who are members of one of the

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 7

following groups: African American or Black, Hispanic, Asian, Native American, or American Indian; and (iii) has a significant business presence in the Charlotte Combined Statistical Area.

MWSBE: Refers to SBEs, MBEs and WBEs, collectively.

MWSBE Goal: If an ITB or Contract has separate Subcontracting Goals for MBEs, WBEs, and/or SBEs, the term MWSBE is a shorthand way to refer collectively to all MBE, WBE, and SBE Goals set for the ITB. In some instances, the City may set one combined goal for MBEs, WBEs, and/or SBEs, in which event the term MWSBE Goal refers to that one, combined goal. In the latter instance, calculated as a percentage, the MWSBE Goal represents the total dollars spent with MBEs, WBEs, and SBEs as a portion of the total Bid amount, including any contingency.

Post-Consumer Recycled Material: Refers to material and by-products which have served their intended end-use by a consumer and have been recovered or diverted from solid waste.

It does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

Procurement: Refers to Charlotte Water Procurement.

Products: Refers to all products that the Bidder agrees to provide to the City as part of its Bid.

Recyclability: Products or materials that can be collected, separated or otherwise recovered from the solid waste stream for reuse, or used in the manufacture or assembly of another package or product, through an established recycling program. For products that are made of both recyclable and non-recyclable components, the recyclable claim should be adequately qualified to avoid consumer deception about which portions or components are recyclable.

Recycled Material: Refers to material and by-products which have been recovered or diverted from solid waste for the purpose of recycling. It does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

Services: Refers to all services that the Bidder agrees to provide to the City as part of its Bid, including but not limited to training, warranty, and maintenance.

Small Business Enterprise (SBE): Refers to a business enterprise that is certified by the City of Charlotte under Part E of the CBI Policy as meeting all of the requirements for SBE certification.

Specifications: Refers to the written description of the functions or features of the Products and Services for which the City seeks bids, as shown in Section 3.

Terms and Conditions: Refers to the City’s standard contractual terms and conditions as set forth in the Sample Contract.

Women Business Enterprise (WBE): Refers to a business enterprise that: (i) is certified by the State of North

Carolina as a Historically Underutilized Business (HUB) within the

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 8

meaning of N.C. Gen. Stat. § 143-128.4; (ii) is at least fifty-one percent (51%) owned by one or more persons who are female; and (iii) has a significant business presence in the Charlotte Combined Statistical Area.

1.3. Contract Documents:

Each Bid constitutes an offer to become legally bound to a Contract with the City incorporating the ITB and the Bidder’s Bid. Upon Contract award by City Council or City Manager (as applicable), the City will send the successful Bidder the Contract, which shall consist of the Terms and Conditions contained in the Sample Contract, together with all attachments referenced therein.

1.4. Exceptions:

Each Bid submitted in response to this ITB constitutes a binding offer to comply with all terms, conditions, special conditions, specifications, and requirements stated in this ITB (including but not limited to the Terms and Conditions). The City will not consider any exceptions to the terms and conditions deemed important by the Bidder.

Bidders are also reminded that a material variance from the terms of this ITB may result in the Bid being rejected by the City.

1.5. Multiple/Alternate Bids:

No Bidder shall submit more than one (1) Bid unless multiple or alternate Bids are requested in the Special Conditions. Unless specifically stated in the Special Conditions, any multiple or alternate Bids must be brought to the City's attention either during the Pre-Bid Conference or submitted in writing at least five (5) days prior to the opening of the Bid.

1.6. How to Prepare Bid Responses:

All bids shall be prepared as follows:

• Refer to the Bonfire Procurement Portal Instructions document in the Procurement Portal for submission instructions.

• Complete the Bid Response Forms provided in the Procurement Portal under the “Requested Information.” Bid responses must be submitted only on these forms.

• Bid responses must be typewritten or completed in ink, signed by the Bidder or the bidding firm's authorized representative. All erasures or corrections must be initialed and dated by the person who signs the Bid Response Form on behalf of the Bidder.

• Bids must be accompanied by accurate descriptions of the exact materials, supplies, vehicles, and/or equipment offered for purchase. The Specifications may require that copies of detailed factory specifications, ratings, technical data, etc. be submitted along with the Bidder's response package.

1.7. How to Submit Bid Responses:

All Bidders shall:

• Submit their electronic Bid via the Procurement Portal at https://charlottenc.bonfirehub.com no later than APRIL 8, 2026 at 3:00 p.m. The original Bid shall be complete and shall not refer to any other copy of the Bid for any references, clarifications, or additional information. When received, all Bids and supporting materials, as well as correspondence relating to this ITB, shall become the property of the City.

Bids not received by the time and date specified in this section will not be considered, unless the delay is a result of the negligence of the City, its agents, or assigns.

The City reserves the right to change the Bid opening date, or any other dates relevant to this procurement process, at any time in its sole discretion.

https://charlottenc.bonfirehub.com/

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 9

1.8. Bid Opening Procedures:

1.8.1 Bids will be opened publicly via the Procurement Portal at the time and place indicated in

Section 1.30 and, unless obviously non-responsive, read aloud publicly.

1.8.2 As a courtesy, the public may also view the bid opening virtually by calling 1-872-256- 4172 (access code: 221 321 02#) or by visiting https://teams.microsoft.com/meet/23249650080724?p=FDIVmW7PGZaaobU34A

1.8.3 Charlotte Water is not responsible for technical difficulties experienced by those attending virtually and will proceed with opening bids in accordance with Section 1.8.1.

1.9. Trade Secrets and Personal Identification Information:

Definition Upon receipt by Procurement, all materials submitted by a Bidder (including the Bid) are considered public records except for: (1) material that qualifies as “trade secret” information under N.C. Gen. Stat. § 66-152 et seq. (“Trade Secrets”), or (2) “personal identification information” protected by state or federal law, to include, but not be limited to, Social Security numbers, bank account numbers, and driver’s license numbers (“Personally Identifiable Information” or “PII”).

Instructions for Marking and Identifying Trade Secrets If any Bid contains Trade Secrets or PII, such Trade Secrets and PII must specifically and clearly be identified in accordance with this Section by clearly separating them from the rest of the Bid and marked either “Personally Identifiable Information – Confidential” or “Trade Secret— Confidential and Proprietary Information.” This confidentiality caption must appear on each page of the Trade Secret or PII materials, and the document(s) must be submitted separately in the Procurement Portal.

Availability of Bids to City Staff and Contractors By submitting a Bid, each Bidder agrees that the City may reveal any Trade Secret materials and PII contained therein to all City staff and City officials involved in the selection process, and to any outside consultant or other third parties who assist in the selection process or who are hired or appointed by the City to assist in the selection process.

Availability of Bids via Public Records Requests Any person or entity (including competitors) may request Bids submitted in response to an ITB.

Only those portions of ITBs properly designated as Trade Secret or PII are not subject to disclosure.

The public disclosure of the contents of a Bid or other materials submitted by a Bidder is governed by N.C. Gen. Stat. §§ 132 and 66-152, et seq.

When determining whether to mark materials as Trade Secret, please note the following:

• Entire Bids may not be marked as Trade Secret; and

• Pricing may not be marked as Trade Secret.

The City may disqualify any Bidder that designates its entire Bid as a Trade Secret or PII, or any portion thereof that clearly does not qualify under applicable law as a Trade Secret or PII. Each Bidder agrees to indemnify, defend, and hold harmless the City and each of its officers, employees, and agents from all costs, damages, and expenses incurred in connection with refusing to disclose any material that the Bidder has designated as a Trade Secret or PII. This includes an obligation on the part of the Bidder to defend any litigation brought by a party that has requested Bids or other information that the Bidder has marked Trade Secret or PII.

1.10. Questions and Pre-Bid Conference:

Submit a question in writing under the Vendor Discussion section on the Procurement Portal.

Other than these permitted questions, Bidders should refrain from contacting City staff prior to the https://teams.microsoft.com/meet/23249650080724?p=FDIVmW7PGZaaobU34A

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 10

Bid opening date. The City is not bound by any statements, representations or clarifications regarding this ITB other than those provided in writing by the Procurement Officer.

Questions should reference the ITB page and topic number. Questions must be submitted by 12:00 p.m. on MARCH 27, 2026.

The City will post answers to questions posed by prospective Bidders and/or general information concerning this ITB in the form of an addendum to the ITB on the Procurement Portal. It is the responsibility of the prospective Bidder to check the Procurement Portal for any addenda issued for this ITB.

A Pre-bid Conference will not be held for this solicitation.

1.11. How to Submit an Objection Relating to This Invitation to Bid:

When a Pre-Bid Conference is scheduled, Bidders should either present their objection at that time (either verbally or in writing), or submit a written objection through the Procurement Portal prior to the scheduled Pre-Bid Conference.

When a Pre-Bid Conference is not scheduled, Bidders must submit objections through the Procurement Portal in writing at least ten (10) days prior to the opening of the Bid.

Except for objections raised at the Pre-Bid Conference, all objections must be in writing directed to the Procurement Officer designated in the preceding section.

Failure to object in the manner specified above shall constitute a waiver of any objections the Bidder may have to the terms of this ITB, or anything that occurred in the Bid process through the end of the Pre-Bid Conference.

1.12. Binding Offer:

Each Bid shall constitute a firm offer that is binding for one hundred twenty (120) calendar days from the date of the Bid opening.

1.13. Errors in Bids:

Withdrawal of inadvertently erroneous Bids may be permitted where appropriate, if the request is submitted to the City within seventy-two (72) hours after Bid opening, not including Saturdays, Sundays, and other days the City of Charlotte is not open to the public for business. A request for withdrawal must be made in writing to the Procurement Officer using their email address provided in the Procurement Portal. Consideration of a request to withdraw a bid will be made in accordance with N.C. Gen. Stat. § 143-129.1.

In case of Bidder errors calculating “extended” prices stated in a Bid, the unit prices shall govern.

1.14. City’s Rights and Options:

The City reserves the following rights, which may be exercised at the sole discretion of the City of Charlotte:

• to supplement, amend, substitute or otherwise modify this ITB at any time;

• to cancel this ITB with or without the substitution of another ITB;

• to take any action affecting this ITB, this ITB process or the Products or Services subject to this ITB that would be in the best interests of the City;

• to issue additional requests for information;

• to require one or more Bidders to supplement, clarify or provide additional information in order for the City to evaluate the Bids submitted;

• to conduct investigations with respect to the qualifications and experience of each Bidder;

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 11

• to change the Bid opening date or any other dates relevant to this ITB;

• to waive any defect or irregularity in any Bid received;

• to reject any or all Bids;

• to award all, none, or any part of the items that is in the best interest of the City, with one or more of the Bidders responding, which may be done with or without re-solicitation; and

• to enter into any agreement deemed by the City to be in the best interest of the City, with one or more of the Bidders responding.

1.15. Bids on All or Part:

Unless otherwise specified by the City or by the Bidder, the City reserves the right to make award on all or part of the items to be purchased. Bidders may restrict their bids to consideration in the aggregate by so stating in the Bid. However, Bids restricted to consideration in the aggregate must also include a unit price on each item Bid.

1.16. Invitation to Bid Not an Offer:

This ITB does not constitute an offer by the City. No recommendations or conclusions from this ITB process shall constitute a right (property or otherwise) under the Constitution of the United States or under the Constitution, case law, or statutory law of North Carolina.

1.17. Charlotte Business INClusion Program:

Pursuant to Charlotte City Council’s adoption of the Charlotte Business INClusion (CBI) Policy, the CBI program promotes diversity, inclusion, and local business opportunities in the City’s contracting and procurement process for Minority, Women, and Small Business Enterprises (MWSBEs) with a significant business presence in the Charlotte Combined Statistical Area (CSA).

The CBI Policy is posted at www.charlottebusinessinclusion.com.

The City is committed to promoting opportunities for maximum participation of certified MWSBEs on City-funded contracts at both the Prime and Subcontract level. For MWSBE participation to count towards a Goal, MWSBEs must meet both the certification and geographic requirements as detailed throughout this solicitation and in the CBI Policy.

1.18. Equal Opportunity:

The City has an equal opportunity purchasing policy. The City seeks to ensure that all segments of the business community have access to supplying the products and services needed by City programs. The City provides equal opportunity for all businesses and does not discriminate against any Bidders regardless of race, color, religion, age, sex, and national origin or disability.

1.19. No Collusion or Conflict of Interest:

By responding to this ITB, the Bidder shall be deemed to have represented and warranted that the Bid is not made in connection with any competing Bidder submitting a separate response to this ITB, and is in all respects fair and without collusion or fraud.

Bidder shall also be deemed to have represented and warranted that none of Bidder’s or its subcontractors’ owners, employees, directors, or contractors will be in violation of the City’s Conflict of Interest Policy for City, Secondary and Other Employment Relationships (HR 13) if a Contract is awarded to the Bidder.

1.20. Anti-lobbying Provision:

Maintaining the integrity of its ITB process is of paramount importance for the City. To this end, we ask each Bidder’s cooperation in voluntarily refraining from contacting any members of the Charlotte City Council until the award of this Contract.

http://www.charlottebusinessinclusion.com/

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 12

1.21. Certified Test Report:

If the Specifications or Special Conditions require a certified test report, Bidders shall provide such report at their expense, prior to or with their sealed Bids. The certified test report shall be from a recognized independent testing laboratory or manufacturer’s quality control laboratory and shall show all test results and full compliance with the applicable Specifications.

1.22. Brand Name:

If and whenever brand names, makes, names of manufacturers, trade names, Bidder catalogs or model numbers are stated in this ITB, they are for the purpose of establishing a grade or quality of material. The City will evaluate any approved alternates to specified brand names as provided in Section 1.22-1.23 of this ITB, except for items identified in Section 3 as Products for which no substitute is acceptable.

1.23. To Submit a Proposed Alternate Product In Lieu of a Specified Brand:

No alternate products will be considered for this contract.

1.24. Statutory Requirements:

Any Bid submitted in response to this ITB shall be deemed to include full conformance with all statutory requirements of North Carolina and all statutory requirements of the Federal Government, to the extent applicable. It is the responsibility of each Bidder to conduct its own due diligence as to what statutory requirements may apply.

1.25. Guarantor:

If the Bidder is a subsidiary of another entity, the City requires that the Bidder’s parent entity provide a guarantee of payment of all of the Bidder’s obligations under the Contract. The City may also require that the Bidder obtain a guaranty from an entity other than the parent if the City concludes that such guaranty would be beneficial to protect the City’s interest. If the Bidder is not a subsidiary, the City may require that the Bidder obtain a guaranty of payment from another entity if the City concludes that such guaranty would be beneficial to protect the City’s interest. If a guarantor is required, the Bidder must: (1) identify a guarantor that is acceptable to the City, (2) provide the City with the same financial information about the guarantor that the Bidder is required to provide about itself under this ITB; and (3) provide the City with a signed, legally binding guaranty agreement from the approved guarantor that is acceptable to the City in the City’s sole discretion. Failure to comply with the foregoing shall be grounds for rejection of the Bidder’s Bid.

1.26. Award Criteria:

The City reserves the right to award a Contract to the lowest responsive responsible Bidder taking into consideration vendor qualifications and experience, quality, delivery, workmanship, and services. The City reserves the right to reject any Bid on the basis of function, compatibility with user requirements of utility, as well as cost.

1.27. Environmental Preferable Purchasing:

The City promotes the practice of Environmentally Preferable Purchasing (EPP) in acquiring Products or Services. Applicable EPP attributes that may be taken into consideration as environmental criterion include the following:

Recycled content Renewable resources

Recyclability Reduced Packaging

Biodegradability Reduced toxicity

Compostability Low Volatile Organic Compounds (LVOCs)

Energy and Water Efficiency Pollution Prevention

Life Cycle Management End of Life Management

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 13

Bidders able to supply Products or Services containing any of the applicable environmentally preferable attributes that meet performance requirements are encouraged to offer them in their Bids.

Bidders must provide certification of environmental standards and other environmental claims, such as recycled content and emissions data, or a formal statement signed by a senior company official.

1.28. Contract Award by Charlotte City Council:

The Contract to be awarded under this ITB must be approved by the Charlotte City Council. If such approval is granted, Procurement will provide the Contract to the Bidder for the Bidder to sign and return. In the event such approval is not received within one hundred twenty (120) calendar days after opening of the Bids, the Bidder may request that it be released from the Bid.

1.29. Procurement Schedule:

The following chart shows the schedule of events for the conduct of this ITB. The key events and deadlines for this process are as follows, some of which are set forth in more detail in the Sections that follow:

DATE EVENT

March 12, 2026 Issuance of ITB. The City issues this ITB.

March 27, 2026 Submission of Written Questions. Prospective Bidders are permitted to submit written questions, for purposes of clarifying this ITB. All submissions must be pursuant to the instructions in Section 1.10 by 12:00 p.m.

April 8, 2026 Bid Submission and Bid Opening. Bids are due by 3:00 p.m. Please arrange for electronic bid delivery per instructions in Section 1.7.

All Bids will be opened and publicly read aloud at 5100 Brookshire Blvd., Charlotte, NC 28216 in the 2nd Floor Conference Room.

April 2026 Bid Evaluation.

May 2026 Contract Award by City Council.

June 2026 Anticipated Contract Effective Date. Company begins providing the Products and/Services.

Section Two Terms and Conditions

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 14

TERMS AND CONDITIONS

Each Bid submitted in response to this ITB constitutes an offer to become legally bound to a Contract incorporating terms and conditions set forth in this Section 2 as well as the Terms and Conditions in the Sample Contract. For purposes of this Section, a Bidder that enters into a Contract with the City may be referred to as the “successful Bidder” or the “Company.”

2.

2.1. Contract Types:

The Contract resulting from this Invitation to Bid will be of the type indicated below:

Definite Quantity: The Contract will be a fixed-price contract that provides for delivery of a specified quantity of Products and Services either at specified times or when ordered.

2.2. Terms of Contract:

One Time Purchase: Contract awarded is for a specific quantity purchased at one time.

2.3. Notice to Proceed:

The successful Bidder shall not commence work or make shipment under this ITB until duly notified by receipt of an executed Contract from the City and/or through a Purchase Order (PO). If the successful Bidder commences work or makes shipment prior to that time, such action is taken at the Bidder's risk, without any obligation of reimbursement by the City.

2.4. Delivery Time:

When delivery time is requested in this ITB (whether in the form of a specific delivery date or maximum number of days for delivery), time is of the essence. Each Bid shall be deemed a binding commitment of the Bidder to meet the delivery time stated herein. If such delivery time is not met, the City shall be entitled to terminate the Contract immediately for default and/or exercise any other remedies available by law or in equity. Unless otherwise specified, delivery shall be FOB Destination.

2.5. Prices Are Firm:

Each Bidder warrants the Bid price(s), terms and conditions quoted in its Bid shall be firm for acceptance by the City for a period of one hundred twenty (120) calendar days from the date of the Bid opening. Once award is made and a Contract is in place, prices shall remain firm and fixed for the entire Contract period, unless otherwise allowed in accordance with Section 17 of Purchase Terms of the Sample Contract.

2.6. Prompt Payment Discounts:

Bidders are urged to compute all discounts into the price offered. If a prompt payment discount is offered, it will not be considered in the award of the Contract except as a factor to aid in resolving cases of identical prices.

2.7. Quality:

Unless this ITB specifically states otherwise for a particular item, all components used to manufacture or construct any supplies, materials or equipment or Products provided under this Invitation to Bid shall be: (a) new; (b) the latest model; (c) of the best quality and highest grade workmanship; and (d) in compliance with all applicable federal, state and local laws, regulations and requirements. By “new”, the City means that the item has been recently produced and has not been previously sold or used.

Whenever this Invitation to Bid or any other part of the Contract states that a Product or Service shall be in accordance with laws, ordinances, building codes, underwriter’s codes, applicable A.S.T.M. regulations or similar expressions, the requirements of such laws, ordinances, etc., shall be construed to be minimum requirements that are in addition to any other requirements that may be stated in this Invitation to Bid or the Contract.

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 15

2.8. Inspection at Bidder’s Site:

The City reserves the right to inspect the equipment, plant, store or other facilities of a Bidder prior to Contract award, and during the Contract term from time to time as the City deems necessary to confirm that such equipment, plant, store or other facilities conform with the Specifications and are adequate and suitable for proper and effective performance of the Contract. Such inspections shall be conducted during normal business hours and upon at least three (3) days’ notice to the Bidder (except that a store may be inspected at any time during regular store hours without notice).

2.9. Certification of Independent Price Determination:

By submission of a Bid, the Bidder certifies, and in the case of a joint Bid each party thereto certifies as to its own organization, that in connection with this procurement:

The prices in the Bid have been arrived at independently, without consultation, communication, or agreement, for the purpose of restricting competition, as to any matter relating to such prices with any other Bidder or with any competitor;

Unless otherwise required by law, the Bidder has not knowingly disclosed the prices that have been quoted in this bid directly or indirectly to any other Bidder or to any competition prior to the opening of the bid; and

No attempt has been made or will be made by the Bidder to induce any other person or firm to submit or not to submit a Bid for the purpose of restricting competition.

2.10. Insurance:

All Bidders must indicate compliance with the Insurance requirements stated in the Sample Contract.

2.11. Spill Prevention, Response, and Reporting at Treatment Facilities:

2.11.1 International Standards Organization (ISO) 14001:2015 Environmental Management

Systems Standard. The Environmental Management Division of Charlotte Water holds a corporate certification for the biosolids program, Mallard Creek Water Reclamation Facility (WRF), Sugar Creek Wastewater Treatment Plant (WWTP), and McDowell Creek WWTP and is certified to the ISO 14001:2015 Environmental Management Systems standard. The ISO is an international standard-setting body composed of representatives from various national organizations throughout the world, such as American National Standards Institute (ANSI) in the United States. The ISO14000 Environmental Management System standards exist to help organizations minimize how their operations can negatively affect the environment while continually improving in all areas. The Companies, subcontractors, and suppliers shall take measures as needed to prevent pollution to help the City conform to the ISO14001:2015 standard.

2.11.2 Each wastewater treatment facility has a Spill Prevention, Control, and Countermeasure (SPCC) Plan in accordance with the SPCC regulation (40 Code of Federal Regulations (CFR) 112) and a Stormwater Pollution Prevention Plan in accordance with the Federal Water Pollution Control Act’s National Pollutant Discharge Elimination System (NPDES) Program. The Company shall pay any costs incurred for spill response including clean-up and disposal fees and fines levied against the City for any spills or leaks caused by the Company or any of their subcontractors or vendors. The Company is responsible for training their staff, subcontractors, and suppliers on spill prevention, response, and reporting procedures. The Company shall maintain equipment necessary for the clean-up of spills, drips or leaks near the equipment or material that is being used or stored at all times. Suggested equipment includes absorbent, industrial wipers, barrier systems, and clean-up containers. Company must notify City immediately if a spill of any quantity or type occurs on the property.

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 16

2.11.2.1 Oil Pollution Prevention: Company shall be responsible for spill prevention and response for all storage tanks, pumps, and equipment holding any quantity of oil that the Company or his subcontractor or suppliers are using to execute the Work or have on-site in preparation for executing the Work. The Company shall provide prior notification to the City of all oil and petroleum deliveries, and the City must be present at the time of connect to and disconnect from storage containers or equipment. The following delivery requirements shall be followed for all petroleum and oil deliveries:

2.11.2.1.1 Give the City notice that delivery is going to be made.

2.11.2.1.2 The Company shall follow standard operating procedures and good safety practices in accordance with the regulations including but not limited to those defined by the Department of Transportation and to confirm proper connection and disconnection of tank trucks from oil transfer lines during oil deliveries.

2.11.2.1.3 Have delivery personnel sign in at the Administration Building or other City-designated facility immediately upon entering the facility.

2.11.2.1.4 Use the City-designated truck route from the Administration Building or City-designated facility to the delivery point.

2.11.2.1.5 Be escorted to the delivery point by Company staff. A competent member of the Company’s staff shall be present during all connections and disconnections.

2.11.2.1.6 Remain with the vehicle at all times, and continually monitor the fuel transfer process.

2.11.2.1.7 Use physical barriers systems such as wheel chocks shall be used to reduce the potential for unintentional disconnections.

2.11.2.1.8 Drain the loading/unloading lines to the storage tank and close the drain valves before disconnecting loading/unloading lines.

2.11.2.1.9 Place a drain pan or other appropriate containment device under all connections.

2.11.2.1.10 Inspect the vehicle before departure to confirm all loading/unloading lines have been disconnected and all drain and vent valves are closed and there are no leaks.

2.11.2.1.11 Companies shall not conduct filling operations during precipitation events.

2.11.2.2 Stormwater Pollution Prevention:

2.11.2.2.12 Outdoor Washing Activities: Discharges from outdoor washing activities shall not be allowed to enter the stormwater system (stormwater pipes, catch basins, drainage ditches, rain gardens, and similar conveyances). The Company must have adequate equipment and implement management practices to properly treat, contain, collect, and dispose of wash water runoff generated during washing activities. Proper disposal of collected wash water must be arranged prior to beginning work.

2.11.2.2.13 Painting: Company shall not discharge into the stormwater system any wastes resulting from the cleaning of painting equipment or the removal of paint from structures. If solvents or other potentially hazardous products are used to clean

MCDOWELL CREEK WRRF PRIMARY CLARIFIER NO. 4 EQUIPMENT PROCUREMENT

ITB# FY26-ITB-08 MARCH 12, 2026 17

painting equipment, the resulting wastewater may be hazardous and must be properly disposed of or recycled.

2.11.2.2.14 Concrete: Company shall not discharge concrete or any residue from rinsing equipment or trucks onto the ground or into the stormwater system. The City shall designate a concrete chute and tool wash area at each facility. All concrete remaining in delivery trucks after completion of the Work shall not be discharged or rinsed from truck at the facility.

2.11.2.2.15 Waste Management: Companies shall use waste

bins/dumpsters that are leak proof (no holes or damage). All bins/dumpsters shall be covered and have drain plugs.

2.11.2.2.16 Chemicals and Fuels: Companies shall provide containment and any other spill prevention necessary for all chemicals and fuels stored or used on-site.

2.11.2.2.17 Seeding: Companies must follow proper pesticide and fertilizer application methods as prescribed by industry standards and on product labels during seeding. If such products are spilled, the Company must respond promptly to collect and properly dispose of the spilled product and clean up the impacted area.

2.11.2.2.18 Erosion: All land disturbing activities, including those that disturb less than an acre, shall provide adequate erosion control measures, structures, or devices in accordance with local, state and federal regulations. Company shall refer to other specification sections for requirements related to Sedimentation Control Plans and National Pollutant Discharge Elimination System (NPDES) Stormwater General Permit NCG10000 for Construction Activities coverage.

2.11.3 The Company shall visually check any temporary pipelines, pumping equipment, and associated connections conveying wastewaters, sludges, chemicals, or similar potential pollutants on the schedule outlined in the scope of work to detect and stop any leaks and spills. The Company shall maintain a log(s) of inspections and shall make the log(s) available to the City upon request.

Section Three Specifications

ITB# FY26-ITB-08 MARCH 12, 2026 18

SPECIFICATIONS

3.

3.1. Background:

McDowell Creek Water Resource Recovery Facility (WRRF) is one of five WRRFs for Charlotte Water, a department of the City of Charlotte. Charlotte Water, in conjunction with Black & Veatch International Company as the Engineer, is assisting Charlotte Water with this project.

3.2. Scope:

The scope of this Invitation to Bid (ITB) is to establish a contract for the purchase, delivery and other inherently related activities of the Products and Services and in compliance with the specifications and terms and conditions set forth in this ITB.

All Products and component parts furnished under the Contract shall be new, shall comply with the specifications and terms and conditions set forth in this ITB, and shall operate in full compliance with these Specifications.

3.3. Manufacturer/Model:

This section supersedes 1.22. For all items in Exhibit B – Project Manual where specific brand names, makes, names of manufacturers, trade names, Bidder catalogs or model numbers are listed, only those manufacturers are acceptable. No substitutions or exceptions will be permitted.

3.4. Product Specifications and Standards:

The Company shall comply fully with all Project Specifications, Standards, and Relevant Drawings identified in Exhibit B – Project Manual.

3.5. Warranty:

All Products supplied under the Contract shall be covered by a manufacturer’s written guarantee and/or warranty that such Products will be free from defects in materials, workmanship and performance for a minimum of two years; merchantable and in full conformity with the Specifications set forth in this ITB, industry standards, dimension charts and Bidder's descriptions, representations and samples. The Company shall administer the warranty on the City’s behalf, and shall ensure that the manufacturer repairs or replaces at no charge to the City all Products that violate either the above warranty or the applicable manufacturer’s warranty.

3.5.1 The Company shall provide the City with two copies of the manufacturer’s written warranty for each item of equipment.

3.5.2 It shall be the responsibility of the manufacturer to pay all shipping and crating costs associated with warranty repairs.

3.6. Installation:

The awarded Company shall provide coordination with the Installing Contractor during installation, inspection prior to startup and testing, and supervision during functional acceptance testing by the Installing Contractor in accordance with Exhibit B – Project Manual, in its entirety. A representative from the awarded Company must be on site at McDowell Creek WRRF as described in Exhibit B-Project Manual. All work must be performed according to the standards established by the terms, specifications, and drawings.

3.7. Pricing:

Bids shall be submitted as a lump sum that includes shipping and delivery, any discounts, vendor markup/profit, item cost and storage per the Exhibit A-Price Schedule. No other charges are allowed.

ITB# FY26-ITB-08 MARCH 12, 2026 19

3.8. Milestone Payment:

The City shall pay the awarded Company for the Products and Services delivered in compliance with the specifications at prices set forth. The awarded Company shall be compensated according to the following schedule:

• 10% Shop Drawings approval

• 70% Upon Delivery

• 20% Upon Successful Completion of Operation Acceptance Testing

3.8.1 The Company shall provide the City with two copies of the manufacturer’s written warranty for each item of equipment.

3.8.2 It shall be the responsibility of the manufacturer to pay all shipping and crating costs associated with warranty repairs.

3.9. Delivery and Storage:

Assembled clarifying mechanism shall be delivered to McDowell Creek Water Resource Facility (WRRF) located at 5300 Jim Kidd Road Huntersville, NC 28078. Company shall coordinate with City for exact delivery location at McDowell Creek WRRF. Delivery shall be FOB Destination.

Each Bid shall be deemed a binding commitment of the Bidder to meet the delivery time stated herein. All Products shall be delivered to the site within forty (40) weeks from Contract Execution. The City and Company recognize that time is of the essence (as indicated in Section 2.4) and that the City will suffer financial and other losses if the delivery date is not met. The parties also recognize the delays, expense, and difficulties involved in proving in legal or arbitration proceedings the actual loss suffered by the City if the delivery date is not met. Accordingly, instead of requiring any such proof, the City and Company agree that as liquidated damages for delay, Company shall pay five hundred dollars ($500) for each day that expires after the time specified for the delivery of the clarifier specified. If such delivery time is not met, the City has assessed liquidated damages for sixty (60) days, then, the City shall be entitled to terminate the Contract immediately for default and/or exercise any other remedies available by law or in equity.

3.10. Delivery Personnel:

All delivery personnel of the successful Bidder may be subject to background checks at the discretion of the City. Bids shall include company policies regarding selection of personnel who will be frequenting City facilities.

3.11. Invoices:

The Company must submit invoices after each milestone is met (but not more than once a month) to the City’s Finance department. Invoices must include the item number, description, unit cost, quantity and extended price, and contract and purchase order number of each item purchased. Every invoice must also include the City department that placed the order and be submitted to City of Charlotte Accounts Payable per the billing instructions of the subsequent Contract.

3.11.1 It is acknowledged and agreed that having correctly priced invoices is a material element of the proposal to the City. Failure by the Company to submit correct invoices may be grounds for termination of the contract. Without limiting the City’s right to terminate the contract for incorrect pricing on invoices, the Company agrees to pay the City a service fee for correcting invoices equal to twenty-five dollars ($25) for each item incorrectly priced on an invoice. Payment must be in the form of a deduction from other amounts owed to the Company.

3.11.2 Invoices must include only Products and Services that have been delivered and completed.

ITB# FY26-ITB-08 MARCH 12, 2026 20

3.11.3 As a condition of payment, the Company must invoice the City for Products and Services within 60 days after such Products and Services are delivered. The Company waives the right to charge the City for any products or services that have not been invoiced to the City within 60 days after such products or services were delivered.

3.12. Award of Contract:

The City reserves the right to award this contract based on the lowest responsive responsible bidder taking into consideration vendor qualifications and experience, quality, delivery, workmanship.

The City also reserves the right to award contract(s) by item, combination of items or grand total, whichever is in the best interest of the City.

Multiple awards may be made as a result of this ITB if doing so will ensure that any ensuing contract(s) will allow the City to fulfill current and future requirements or in the best interest of the City.

The City reserves the right to add items excluded under this Invitation to Bid, or to delete items, which are included under this Invitation to Bid.

3.13. City Contracting Requirements:

The City will enter into an Agreement written by the City with the successful Bidder that contains the terms and conditions set forth in this ITB and Sample Contract. Each Bidder must state specifically in its bid response its compliance with City contracting requirements and that no exceptions, deviations, substitutions or modifications have been included in this ITB, or the Sample Contract.

The terms and conditions set forth in this ITB are not all inclusive. The City may propose additional terms and conditions based on the responses to this ITB and the City’s analysis of the successful bid.

The term “Contract” shall…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .