Exhibit F of RFP 2026-12 outlines the Job Order Procedures for a contract involving the Town of Fairfield, Connecticut, and a qualified contractor for infrastructure services. Work shall be performed exclusively under executed Job Orders or Amended Job Orders (Change Orders) issued jointly by both parties. The Town initiates requests through Draft Job Orders that specify the project scope of work, site location, schedule, and priority, with the Town responsible for assessing permitting needs prior to issuance. The performance schedule must be negotiated and mutually agreed upon by both parties, with the contractor required to commence work within ten calendar days of execution unless a specific alternative timeframe is mutually agreed upon. Construction documents typically consist of sketch plans, site maps, or approved site plan drawings with appropriate specifications and details attached to the Job Order. The executed Job Order must remain at the job site at all times, and failure to do so may result in a stop work order at no additional cost to the Town. Upon project completion, the contractor must submit Record Drawings and a Statutory Affidavit certifying that all subcontractors and material suppliers have been fully compensated.
The contractor must notify the Town immediately upon recognizing the need for an Amended Job Order (Change Order) due to additional materials, equipment, labor, time, or scope changes, with no work outside the Job Order scope permitted without prior Town authorization and executed Change Order documentation. The Town recognizes that the Pricing Breakdown is not all-inclusive and additional services may be necessary; such services shall be negotiated for each Job Order with rates subject to Town review and approval, with the Town reserving the right to solicit cost information from other contractors and award work accordingly. Any additional services performed without prior written Town authorization will not be reimbursable. All subcontractors must be pre-approved in writing by the Town and must maintain a Town Business License along with all insurance and licenses required by the work and contract. Where time is of the essence, the Town may impose liquidated damages as clearly indicated in the Job Order, assessed daily until substantial completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT F
RFP 2026-12
JOB ORDER PROCEDURES
1. Job Order Procedure Overview
• Work under this Contract shall only be performed under the basis of a Job Order or Amended Job Order (Change Order) that has been executed by both parties.
• The Town will request work from a Contractor by means of a Draft Job Order and will establish a project scope of work, site location, schedule, and priority. The project scope of work will be a general description of the desired work, provided with the goal of assisting the Contractor with the allocation of labor, equipment, and materials.
Generally, the project site will consist of a single location; however, the project site may consist of multiple locations, whenever necessary to reduce the number of mobilizations for multiple project locations within close proximity of each other. Generally, the Draft Job Order will specify the scope of work, an estimate of quantities, and a desired performance schedule.
• The Town will be responsible for assessing permitting needs and will address these prior to the issuance of any Job Order.
• The Town will review the Contractor’s comments and may revise the Job Order. The scope of work, estimate of quantities, performance schedule, and not to exceed fee shall be negotiated and agreed upon for each Job Order by both the Town and the Contractor prior to beginning work. Once the Job Order is signed by both the Town and the Contractor, the document is considered executed, and the Contractor shall begin work according to the schedule in the Job Order.
• Where time is of the essence, the Town may impose liquidated damages. This shall be clearly indicated in the Job Order. Liquidated damages in the amount specified on the executed Job Order will be assessed for each day beyond the Job Order deadline until the work is substantially complete.
• Once the Town and Contractor have signed the Job Order, the Job Order is executed.
2. Timing and Schedules
• The performance schedule for each Job Order shall be negotiated and mutually agreed to by the Town and
Contractor.
• Once the Job Order is executed by both parties, the Contractor shall have ten (10) calendar days to commence work, unless there is a specific timeframe stated on the Job Order and mutually agreed to by the Contractor and the Town.
• Time extensions must be requested in writing by the Contractor, with proper justification.
3. Construction Documents
Most of the projects will be based on a sketch plan, Site Map or approved site plan drawings, with the appropriate lines, labels, grades, information, and dimensions necessary to execute the work. The applicable specifications and details will be specified or attached to the Job Order. The executed Job Order must be located at the job site at all times.
If the Job Order is not onsite, the Town may issue a stop work order until the issue is corrected, at no additional cost to the Town. The Contractor shall provide all submittals in accordance with the Contract. The Contractor shall maintain Record Drawings of the work onsite and provide these to the Town at the completion of the project. Once all work is complete and accepted by the Town, the Contractor shall submit to the Town a Statutory Affidavit certifying that all Subcontractors and material suppliers have been fully compensated.
4. Amended Job Orders (Change Orders) The Contractor shall notify the Town immediately if they recognize that a Amended Job Order is required (i.e.
additional material, equipment, labor, or time is needed, or there is a change in scope of work). The Contractor shall not perform any work outside of the Job Order Scope of Work without first notifying the Town and executing a Change Order. Any additional service, material, equipment, or labor that is utilized/performed without the Town’s prior authorization will not be reimbursable.
5. New Items The Town understands that the Pricing Breakdown is not all-inclusive of labor, material, and other resources necessary for the completion of the services performed under this Contract, and that additional services may occasionally be necessary. Any such additional services will be negotiated as needed for each particular Job Order, and the negotiated rate will remain in effect for the duration of the Job Order. Rates/charges for additional services may be changed from one Job Order to another but are subject to the Town’s review and approval. The Town reserves the right to solicit cost information for such additional services from other Contractors and may award the work to another Contractor at its convenience. Any additional services that are performed without the Town’s prior written authorization will not be reimbursable. The Contract shall be amended to include new items as deemed necessary by the Town.
6. Subcontractors All Subcontractors must be pre-approved in writing by the Town. All Subcontractors used on this Contract must have a Town Business License, as well as the insurance and licenses required by the work and the Contract.