This attachment document outlines use cases for the Maryland Judiciary Administrative Office of the Courts (AOC) Master Contract for Electrical Services, detailing four distinct electrical service projects across multiple District Court locations in Maryland. The first use case involves installing three duplex electrical outlets at the Westminster District Court House in three specific rooms to support camera monitors, with power fed from existing circuits and no permits required. The second use case requires relocating and replacing nine existing surface-mounted electrical, data, and microphone receptacles with flush-mounted floor boxes in the Upper Marlboro District Court courtroom, including core drilling of the slab and repositioning fixtures two feet back toward the gallery rail. The third use case calls for installing two electrical disconnects for ductless mini-split HVAC units at the Harford County District Court, with specified voltage and amperage requirements, and potential assessment for core drilling needs. The fourth use case involves disconnecting power from seven existing workstations and reconnecting to seven new workstations in the Denton District Court clerk's area using existing circuits and a new whip power base feed, with no permits required and contractor availability during installation for verification.
Each use case includes detailed labor category line items for pricing purposes, specifying quantities in hours for Electrical Helper/Apprentice, Journeyman Electrician, Master Electrician, Electrical Foreman/Lead Electrician, Electrical Project Manager, and Electrical Engineer positions. The document provides specific scope details and technical requirements for each project, including equipment specifications, material requirements, and site-specific conditions such as existing infrastructure constraints and renovation considerations. These use cases serve as standardized project templates for contractors responding to the Master Contract RFP, establishing baseline expectations for the types and complexity of electrical services the AOC anticipates requiring across its service regions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1 – Use Cases
Procurement Maryland Judiciary – mdcourts.gov/procurement
Use Case No. 1 – Westminster Camera Monitor Electrical Outlets
A. SUMMARY
The AOC is seeking proposals from prospective Offerors to provide all labor, materials, supervision, and expertise to furnish and install three (3) duplex outlets in the Westminster District Court House.
B. SCOPE OF WORK
1. The Successful Offeror shall provide all materials, labor, supervision, and expertise required to complete the following:
a. One (1) duplex outlet in the main entrance behind the camera monitor (Room 100).
b. One (1) duplex outlet in the DC file room for security camera monitors on the first floor (Room
114).
c. One (1) duplex outlet inside the Judges entrance door on the ground floor (Room G49).
(1) Monitor is approximately 7’ above finished floor.
d. The new electrical outlets will be mounted behind the monitors.
(1) Power will be fed from existing circuits.
(2) No permits are required for this project.
Line Labor Category Quantity (Hours)
1 Electrical Helper/Apprentice
2 Journeyman Electrician
3 Master Electrician
4 Electrical Foreman/Lead Electrician
5 Electrical Project Manager
6 Electrical Engineer
7 Total (Lines 1-6)
Additional Comments/Clarifications:
Use Case No. 2 – Upper Marlboro Outlets
The AOC is seeking proposals from prospective Offerors to relocate and replace nine (9) existing surface-mounted electrical, data, and microphone receptacles with flush mounted floor boxes located in the floor of the
Upper Marlboro District Court courtroom #353.
1. Successful Offeror shall provide all labor, equipment, and materials to run conduit and wiring (as necessary) to relocate and replace nine (9) existing surface-mounted electrical, data, and microphone receptacles.
a. Attorney’s Table #1
(1) One (1), 20A duplex outlet
(2) One (1), triple data port receptacle
(3) One (1) single microphone jack
b. Witness Stand
(1) One (1), 20A duplex outlet
c. Attorney’s Table #2
(1) One (1), 20A duplex outlet
2. Successful Offeror shall patch all holes left from previous locations of receptacles.
3. Core drilling of slab shall be performed to house flush mounted boxes and conduit.
4. Successful Offeror shall be responsible for relocating existing cables and wiring to all electrical, data, and microphone connection boxes.
a. Existing cables and wires shall be utilized, provided there is enough slack to do so.
b. Courtsmart connections shall be disconnected and reconnected by others.
5. All flush mounted boxes shall be moved straight back towards Gallery Rail by a distance of 2’0” on center, as shown in Attachment 1- Floor Plan.
a. The Witness Stand microphone jack that is located along the side wall will need to be relocated from its existing location to underneath of the witness stand.
6. Successful Offeror may combine data ports and outlets into one (1) box at each location, in lieu of the existing two (2).
7. Successful Offeror shall pull any necessary permits prior to beginning work.
8 Electrical Helper/Apprentice
9 Journeyman Electrician
10 Master Electrician
11 Electrical Foreman/Lead Electrician
12 Electrical Project Manager
13 Electrical Engineer
14 Total (Lines 8-13)
Use Case No. 3 – Bel Air Electrical Installation
The AOC is seeking proposals from prospective Offerors to provide all labor, equipment, and materials to install two (2) electrical disconnects for two (2) Ductless Mini-Split HVAC Units to be installed in the Harford County
District Court.
1. Successful Offeror shall:
a. Install two (2) 208/230 v – 1 phase electrical disconnects to run the following HVAC systems:
(1) System 1 - 18k btu at Bailiff’s Entrance – Minimum circuit ampacity (MCA) – 11 amps, double pole breaker size 15 amps.
(2) System 2 - 24k btu at Clerk’s counter – Minimum circuit ampacity (MCA) – 19 amps, double pole breaker size 25 amps.
b. Assess if any core drilling is required and perform floor x-ray if needed.
2. See Attachment 1 for the installation area of the required disconnects.
(Continued on Next Page)
Attachment 1
15 Electrical Helper/Apprentice
16 Journeyman Electrician
17 Master Electrician
18 Electrical Foreman/Lead Electrician
19 Electrical Project Manager
20 Electrical Engineer
21 Total (Lines 15-20)
Use Case No. 4 – Denton Workstation Electric
The AOC is seeking proposals from prospective Offerors to disconnect power from existing workstations and reconnect to new workstations in the clerk’s area at Denton District Court, including all labor and materials.
1. Offeror shall provide all materials, labor, supervision, and expertise required to disconnect the current power from seven (7) workstations, reuse existing circuits, and connect one (1) new whip for power to seven (7) new workstations using power base feed.
2. Offeror will be expected to be available during the workstation installation to verify power to each workstation.
3. No permits are required for this work site.
4. Attachment 1 shows the layout of the workstations. Attachment 2 shows the workstation electric.
Attachment 3 shows the electric specs for the whip.
Attachment 1
Attachment 2
Attachment 3
22 Electrical Helper/Apprentice
23 Journeyman Electrician
24 Master Electrician
25 Electrical Foreman/Lead Electrician
26 Electrical Project Manager
27 Electrical Engineer
28 Total (Lines 22-27)