9-AM27-112 Bid Results(UNOFFICIAL).xlsx

XLSX spreadsheet 10 KB Posted

Attached to
AM27-112 Ibapah Bullhog (Pre-Qualified Contractors)
Solicitation number
AM27-112
Issued by
Tooele County, Utah

About this file

This is an unofficial bid results document for a state and local contract opportunity issued by the State of Utah Division of Purchasing on behalf of the Division of Wildlife Resources. The solicitation (AM27-112) seeks Bullhog/Mastication services for up to 2,270 acres in Tooele County. The project performance period runs from September 24, 2026, through March 15, 2027. Participation was limited to pre-qualified contractors only. The procurement was structured as an Invitation for Bid (IFB) anticipated to result in a single contract award to the lowest cost responsive and responsible vendor, with award determination based on the lowest cost per acre methodology.

Five contractors submitted bids for the project: England Construction at $394.00 per acre ($894,380.00 total), Hall's HammerTime Construction LLC at $298.05 per acre ($676,573.50 total), Kolob Mountain Construction LLC at $414.00 per acre ($939,780.00 total), Retroscape LLC at $323.00 per acre ($733,210.00 total), and Wilkinson Construction Company at $327.00 per acre ($742,290.00 total). Hall's HammerTime Construction LLC was selected as the lowest responsive bid at $676,573.50. The vendor is required to guarantee its pricing through completion of the project.

View the file

Other files

File Type Posted
20260825_Ibapah_i_BH.dbf DBF file
3-Ibapah i BH 8x11 vicinity.pdf PDF
5-Attachment A-PO Terms and Conditions.docx DOCX document
1-Contract Performance Evaluation FOR REFERENCE USE ONLY.pdf PDF
20260825_Ibapah_i_BH.shp —
20260825_Ibapah_i_BH.sbx —
20260825_Ibapah_i_BH.prj —
4-Ibapah i BH 8x11 imagery.pdf PDF
20260825_Ibapah_i_BH.kmz KMZ file
20260825_Ibapah_i_BH.shx —
20260825_Ibapah_i_BH.CPG —
2-Vendor Prerequisites - IFB Agency.pdf PDF
8-Attachment B-Scope of Work.docx DOCX document
7-Ibapah i BH 8x11 ownership.pdf PDF
20260825_Ibapah_i_BH.shp.xml XML file
20260825_Ibapah_i_BH.sbn —
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AM27-112

AM27-112England ConstructionHall's HammerTime Construction LLCKolob Mountain Construction LLCRetroscape LLCWilkinson Construction Company
Total Cost$ 894,380.0$ 676,573.5$ 939,780.0$ 733,210.0$ 742,290.0
Selected #01000
Selected ($)$ 0$ 676,573.5$ 0$ 0$ 0
ItemsLowestQuantity
RequiredUnit

of

MeasurementUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal

Cost

Mastication/ Bullhog of 2,270 Acres in Tooele County, according to Attachment B-Scope of Work$ 676,573.52270Acres$ 394$ 894,380.0$ 298.05$ 676,573.5$ 414$ 939,780.0$ 323$ 733,210.0$ 327$ 742,290.0
LOWEST

File details come from the government source that posted it. Updated .