9-05-Bid Package - Bid Form Independence Plaza Water Damage Repairs at 703 and 711 Atlantic Ave Fillable.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Document Digitation Services
- Solicitation number
- RFP-RFP 26-2971-DP-0-2027/DP
- Issued by
- San Diego County, California
About this file
This is a bid form for water damage repairs at Independence Plaza, specifically at buildings located at 703 and 711 Atlantic Avenue. The project encompasses restoration work across multiple residential units and common areas following water damage. Building 703 requires flooring and baseboard installation along with cove base installation in three units (105, 106, and 108). Building 711 contains the majority of the work, spanning eleven units (156 through 161, and 256 through 261) plus three common areas (1st Floor Corridor, 2nd Floor Corridor, and Stairwell). Each residential unit requires comprehensive restoration including insulation, drywall finishing, painting, walk-in shower installation, cabinet and countertop work, plumbing fixtures, new flooring and baseboards, electrical finishing, and appliances. Common areas require insulation, drywall, tape, texture, painting, and new flooring with baseboard installation.
The bid form requires contractors to submit itemized costs for all work categories, general conditions, contractor fees, insurance, local taxes, and bond fees, with a mandatory 15 percent owner's discretionary contingency for unforeseen conditions added to unit and labor costs. Contractors must also provide unit pricing for potential additional work including drywall finishing, painting, and various flooring installations by square footage or linear footage, as well as hourly rates for applicable trades including insulators, drywall installers, painters, plumbers, carpenters, flooring installers, and general condition personnel. The bid form requires completion with contractor firm name, signatory information, title, and date of submission.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| BID FORM - WATER DAMAGE REPAIRS AT 703 AND 711 ATLANTIC AVE. | ||
| ITEM # | DESCRIPTION OF WORK | COST |
| BUILDING 703 | ||
| Corridor | Supply and Install flooring and baseboard | |
| Unit # 105 | Supply and Install new cove base | |
| Unit # 106 | Supply and Install new cove base | |
| Unit # 108 | Supply and Install new cove base |
| BUILDING 711 | |
| Unit # 156 | |
| Unit #156 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 157 | |
| Unit #157 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 158 | |
| Unit #158 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 159 | |
| Unit #159 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 160 | |
| Unit #160 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 161 | |
| Unit #161 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 256 | |
| Unit #256 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 257 | |
| Unit #257 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 258 | |
| Unit #258 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 259 | |
| Unit #259 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 260 | |
| Unit #260 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| Unit # 261 | |
| Unit #261 | Insulation |
| Drywall, tape, and texture | |
| Paint | |
| Walk in shower | |
| Cabinets and Countertops | |
| Sinks, faucets, and toilets | |
| New flooring and base | |
| Finish electrical | |
| Appliances | |
| 1st Floor Corridor | |
| 1st Floor Corridor | Insulation, drywall, tape, and texture |
| Paint | |
| New flooring and base | |
| 2nd Floor Corridor | |
| 2nd Floor Corridor | Insulation, drywall, tape, and texture |
| Paint | |
| New flooring and base | |
| Stairwell | |
| Stairwell | Insulation, drywall, tape, and texture |
| Paint | |
| New flooring and base | |
| Total- |
| General Conditions | ||
| Contractor Fees | ||
| Insurance | ||
| Local Tax | ||
| Bond Fees | ||
| Total Construction- | ||
| REQUIRED: Owner's Discretionary Contingency for unforeseen conditions at 15% (unit and labor costs below) | (Add 15%) | |
| TOTAL BID |
| Please provide additional unit costs for the following line items in the event that additional work would be required. | SF/LF Cost |
| Drywall, tape, and texture (SF) | |
| Paint (SF) | |
| Bedroom Carpet (SF) | |
| Bathroom Flooring (SF) | |
| Unit Flooring (SF) |
| Hourly rate for each applicable trade | ||
| Trade | Hourly Rate | Overtime Rate |
| Insulation Installer | ||
| Drywall Installer | ||
| Drywall Finisher | ||
| Painter | ||
| Plumber | ||
| Rough Carpenter | ||
| Finish Carpenter | ||
| Flooring-Carpet Installer | ||
| Flooring-LVP Installer | ||
| GC Foreman | ||
| GC Superintendant | ||
| GC Project Manager | ||
| FIRM: | ||
| NAME: | ||
| TITLE: | ||
| DATE: |
SIGNATURE: