Section C_89503621BSW000022 w_Revision 1 071421.pdf
PDF 330 KB Posted
- Attached to
- Sikeston Fencing Project
- Solicitation number
- 89503621BSW000022
About this file
This solicitation is for the replacement of fencing at the Sikeston Substation located in Sikeston, Missouri. The scope of work involves completely removing the existing chain-link fence and installing a new electrically grounded eight-foot-tall chain-link fence. The new fence will include six barbed wires, concertina wire, one-inch wire mesh fabric, and non-motorized cantilever slide gates with security latches. The U.S. Department of Energy Southwestern Power Administration will issue an Invitation for Bid for this work. The solicitation number is 89503621BSW000022.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No.: 89503621BSW000022
UNITED STATES DEPARTMENT OF ENERGY
Southwestern Power Administration
SIKESTON SUBSTATION FENCING REPLACEMENT
Technical Specifications
June 4, 2021 Revision 1: July 13, 2021
TABLE OF CONTENTS
Division Specification Title
00 001000 Description – Specifications – Scope of Work
01 011000 Summary
014529 Testing Laboratory Services
015713 Erosion Control
02 024100 Demolition
03 033000 Cast-In-Place Concrete
26 260526 Grounding and Bonding for Electrical Systems
32 323113 Chain Link Fencing
END OF TABLE OF CONTENTS
SECTION C – DESCRIPTIONS /SPECIFICATIONS/STATEMENT OF WORK
SECTION 00 10 00 – DESCRICRIPTION/SPECIFICATIONS/SCOPE OF WORK
Table of Contents
1 GENERAL REQUIREMENTS
1.1 Requirements
1.1.1 Scope of Work
1.1.2 Location of Work
1.1.3 Submittals
1.1.4 Definitions
1.2 Materials
1.2.1 Government-Furnished Materials
1.2.2 Contractor-Furnished Materials
1.2.3 Reference Specifications and Standards
1.3 Local Conditions
1.3.1 Rights-of-Way
1.3.2 Access to the Work and Haul Routes
1.3.3 Use of Private Land for Construction Purposes
1.3.4 Protection of Existing Installations
1.3.5 Geologic Investigations
1.3.6 Electric Power for Construction Purposes
1.3.7 Water for Construction Purposes
1.3.8 Sanitation Facilities
1.3.9 Storage and Work Facilities
1.3.10 Telephone Service
1.3.11 Field Offices and Sheds
1.3.12 Cleaning During Construction
1.4 Environmental Quality Protection
1.4.1 Compliance
1.4.2 Landscape Preservation
1.4.3 Waste Removal
1.4.4 Asbestos Investigation & Remediation/Abatement Requirements
1.4.5 Lead Based Paint Investigations
1.5 Superintendent Qualifications and Responsibilities
1.5.1 Responsibilities
1.5.2 Qualifications
1.6 Employee Requirements
1.6.1 General
1.6.2 Training
1.6.3 Physical Examination
1.6.4 Operators
1.7 Inspection and Acceptance
1.8 Character of Workmen, Methods, and Equipment
SECTION 00 10 00 – DESCRIPTION/SPECIFICATIONS/SCOPE OF WORK
1 GENERAL REQUIREMENTS
1.1 Requirements
1.1.1 Scope of Work
These technical specifications are the minimum set of requirements for completing the work described below. The Contractor shall furnish all personnel, facilities, equipment, materials, supplies and services (except as may be expressly set forth in this contract as furnished by the Government) and otherwise do all things necessary for, or incident to, to performance and completion of the work described as follows or shown on the plans as described in these specifications. Any name brand specification called out for in this contract is for system compatibility and reliability purposes. “Or equal” items may be proposed, BUT must meet all functional specification of the name brand item and be approved by the COR. The scope of the work is as follows:
This Project consists of replacing the security fence and fence grounding at the Sikeston Substation.
1.1.2 Location of Work
The sites are on properties owned by the Government. Refer to the plans for location and maps.
1.1.3 Submittals
1.1.3.1 Mailing Address
The address for submittals to the COR is:
U.S. Department of Energy Southwestern Power Administration One West Third Street Tulsa, OK 74103-3502 Attn: Joseph E. González-Cruz, S2400 Email: joseph.gonzalez-cruz@swpa.gov
1.1.3.2 Submittal for Approval and Construction
The Contractor shall, prior to transmittal to Southwestern, review all submittals for compliance with the Plans and Technical Specifications as well as compatibility with all of the interrelated parts of the work. The Contractor shall apply a stamp to each submittal, signed or initialed and dated, certifying his review. The Contractor shall provide a project specific Submittal Checklist which will be used for tracking all submittals under this project to be prepared following contract award. This checklist shall contain dates whereby submittals will be provided to Southwestern for review.
The submittals are for review and approval by Southwestern. Where standard drawings which cover variations of the general class of equipment or options are furnished, each such drawing shall be individually endorsed to describe which parts of the drawing or options apply to the equipment being furnished. Each drawing shall be identified by location, name, and the contract number.
The Contractor shall coordinate all submittals of like materials, equipment, etc. such that only one submittal per item is submitted to Southwestern for processing.
Submittals shall be submitted electronically (Email). When requested by Southwestern, the Contractor shall submit hard copies of legible paper prints.
A decision on the acceptability of the drawings and data, will be given by the COR electronically within twenty-one (21) calendar days after receipt. The COR will return one (1) copy to the Contractor marked "ACCEPTABLE," "ACCEPTABLE AS MARKED," "REVISE AND RESUBMIT,” or “NOT ACCEPTABLE.”
Submittals returned marked “NOT ACCEPTABLE” shall be replaced by drawings and data for alternate equipment or plans. The Contractor shall, within fourteen (14) calendar days after receipt, submit corrected prints and PDF file of data for approval.
Submittals returned marked “REVISE AND RESUBMIT", shall be corrected and resubmitted by the Contractor, within seven (7) calendar days after receipt. The Contractor shall then submit corrected prints and PDF file of data for approval.
Submittals returned marked "ACCEPTABLE" and "ACCEPTABLE AS MARKED" authorize the Contractor to proceed with the fabrication of the equipment covered by such drawings, subject to the correction, if any, indicated thereon or described in the letter of transmittal. These drawings and files will be “CONSTRUCTION DRAWINGS” and will be used by the Contractor and Southwestern for construction reference.
If revisions are needed to a “CONSTRUCTION DRAWING” or data the Contractor shall within seven
(7) calendar days furnish corrected prints of each drawing as well as PDF file of all data. Every revision made shall be shown by number, date, and subject in a revision block and a notation shall be made in the drawing margin to permit rapid location of the revision.
All of the applicable requirements for drawing submittals shall apply equally to catalog cuts, illustrations, printed specifications, weld qualifications, mill tests, factory tests, field tests, or other required data.
Any manufacturing work performed prior to the approval of drawings shall be at the Contractor's risk. The Contractor shall make any changes in the design, which are necessary to make the equipment conform to the provisions of these specifications without additional cost to the Government. Approval of the drawings or other submittals shall not be construed as a complete check but will indicate only that the general method of construction and detailing is satisfactory. Approval of the Contractor's drawings or submittals shall not be held to relieve the Contractor of any part of the Contractor's obligation to meet all of the requirements of these specifications or of the responsibility for the correctness of the information submitted by the Contractor.
1.1.3.3 Final Documentation
1.1.3.4 Submittal for Approval and Construction
The Contractor shall, prior to transmittal to Southwestern, review all submittals for compliance with the Plans and Technical Specifications as well as compatibility with all of the interrelated parts of the work. The Contractor shall apply a stamp to each submittal, signed or initialed and dated, certifying his review. The Contractor shall provide a project specific Submittal Checklist which will be used for tracking all submittals under this project to be prepared following contract award. This checklist shall contain dates whereby submittals will be provided to Southwestern for review.
The submittals are for review and approval by Southwestern. Where standard drawings which cover variations of the general class of equipment or options are furnished, each such drawing shall be individually endorsed to describe which parts of the drawing or options apply to the equipment being furnished. Each drawing shall be identified by location, name, and the contract number.
The Contractor shall coordinate all submittals of like materials, equipment, etc. such that only one submittal per item is submitted to Southwestern for processing.
Submittals shall be submitted electronically (Email). When requested by Southwestern, the Contractor shall submit hard copies of legible paper prints.
A decision on the acceptability of the drawings and data, will be given by the COR electronically within twenty-one (21) calendar days after receipt. The COR will return one (1) copy to the Contractor marked "ACCEPTABLE," "ACCEPTABLE AS MARKED," "REVISE AND RESUBMIT,” or “NOT ACCEPTABLE.”
Submittals returned marked “NOT ACCEPTABLE” shall be replaced by drawings and data for alternate equipment or plans. The Contractor shall, within fourteen (14) calendar days after receipt, submit corrected prints and PDF file of data for approval.
Submittals returned marked “REVISE AND RESUBMIT", shall be corrected and resubmitted by the Contractor, within seven (7) calendar days after receipt. The Contractor shall then submit corrected prints and PDF file of data for approval.
Submittals returned marked "ACCEPTABLE" and "ACCEPTABLE AS MARKED" authorize the Contractor to proceed with the fabrication of the equipment covered by such drawings, subject to the correction, if any, indicated thereon or described in the letter of transmittal. These drawings and files will be “CONSTRUCTION DRAWINGS” and will be used by the Contractor and Southwestern for construction reference.
If revisions are needed to a “CONSTRUCTION DRAWING” or data the Contractor shall within seven
(7) calendar days furnish corrected prints of each drawing as well as PDF file of all data. Every revision made shall be shown by number, date, and subject in a revision block and a notation shall be made in the drawing margin to permit rapid location of the revision.
All of the applicable requirements for drawing submittals shall apply equally to catalog cuts, illustrations, printed specifications, weld qualifications, mill tests, factory tests, field tests, or other required data.
Any manufacturing work performed prior to the approval of drawings shall be at the Contractor's risk. The Contractor shall make any changes in the design, which are necessary to make the equipment conform to the provisions of these specifications without additional cost to the Government. Approval of the drawings or other submittals shall not be construed as a complete check but will indicate only that the general method of construction and detailing is satisfactory. Approval of the Contractor's drawings or submittals shall not be held to relieve the Contractor of any part of the Contractor's obligation to meet all of the requirements of these specifications or of the responsibility for the correctness of the information submitted by the Contractor.
The Contractor shall track all changes through the course of the work and upon completion shall revise all drawings to show the final, “as-built” facilities. The Contractor shall also provide all installation, operation, parts, and service instructions as well as warranty validation information and forms (including purchase receipts) for all equipment provided. All drawings and data shall be of standard size (8-1/2 x 11 inches, 11 x 17 inches or 24 x 36 inches). Drawings shall be rolled or backed appropriately to protect from damage during shipment.
Final drawings and documentation shall be provided within twenty-one (21) calendar days after Southwestern’s acceptance of the work at that location.
1.1.3.5 Right to Use Contractor's Drawings
Southwestern reserves the right to use, reproduce in whole or in part, distribute, and reuse any and all such drawings, whether copyrighted or not, in connection with the following:
1. Installation, maintenance, replacement, and repair of the articles to be furnished under these specifications.
2. Making any and all such drawings and reproductions thereof available to subsequent Contractors, where necessary for fabricating and furnishing articles connected with or dependent upon, information shown on the drawings and duplicating the drawings to be furnished hereunder.
The depositing of all such drawings and/or PDF files with Southwestern shall constitute a license to Southwestern to use said drawings in the manner hereinabove stated and as Southwestern sees fit.
1.1.3.6 Test Reports and Certifications
The contractor shall furnish the COR such certifications or test reports required on all materials (except materials to be furnished by the Government) supplied under this contract. The contractor shall receive no direct payment for these certifications or reports; the cost shall be considered as having been included in the prices stipulated for the appropriate items.
1.1.3.7 Construction Program
1.1.3.6.1 Project Management
The Contractor shall establish a Project Management program that encompasses all phases of the work identified under this contract. The project management program shall include, but not be limited to, the following items.
1. Project Schedule. Contractor shall develop an overall project schedule detailing the activities and sequence of events associated with this project. The project schedule shall be software-generated in a Gantt chart format with critical project milestones identified.
2. Project Manager: Contractor shall assign an experienced Project Manager that provides overall management of the construction program and ensures that the project schedule is kept current.
3. Communication. Contractor shall designate critical personnel to participate in regularly scheduled conference calls or face-to-face meetings to review the project schedule and discuss scheduled activities.
1.1.3.6.2 Construction Schedule
The construction schedule shall be submitted within fifteen (15) calendar days from contract award date. The construction schedule shall provide for orderly performance of the work and shall show in detail the Contractor’s schedule of operations, including the following:
1. Sequence of operations.
2. Dates for commencing and completing work on the controlling features.
3. Order issue and delivery dates for Contractor-furnished materials.
After the start of construction, by 8:00 a.m. Friday of each week, the Contractor shall email the COR an updated detailed estimate of the proposed daily work that is planned for the next three weeks.
1.1.3.6.3 Order of Work
Whenever a definite order of doing the work and a general sequence of operations is set forth in the contract and specifications, and conditions arise that require such order and sequence of operations to be changed, the Contractor shall comply with any direction from the COR requiring such changes and shall revise his schedule of operations to comply therewith. The COR further reserves the right to re-order the sequence of operations regardless of previously approved schedule(s).
1.1.3.6.4 Interference with Traffic
The Contractor shall conduct the work so as to interfere with traffic as little as possible. Contractor shall not close any road until obtaining the permission of the proper authorities to do so. When a road is not closed, the Contractor shall provide a safe and substitute route for any portion obstructed by operations and shall erect and maintain all necessary barricades, directions to travelers, suitable and sufficient red lights, danger signals, and signs, and shall take all necessary precautions for the protection of the work and the safety of Contractor or Subcontractor employees and of the public. The Contractor shall follow all state and local procedures for performing work along or on state, county, and city roads.
1.1.3.6.5 Variations from Requirements and Specifications
No change, variation, or deviation from the drawings or specifications shall be made, except by prior written order of the COR, except that any change that would result in a change in contract price is contingent on advance approval by the CO. During the progress of the work, should the Contractor at any time find that existing conditions demand, make desirable, or are beneficial for a modification in requirements covering any particular item or items, a written or verbal report shall be made to the CO for consideration. The Contractor shall promptly report any conflicts between the drawings and specifications, ambiguities, or other apparent discrepancy in the drawings or specifications that they become aware of, to the Southwestern COR for resolution.
1.1.4 Definitions
The terms and definitions listed below apply.
• "Approved" or "approval" as used herein shall mean approved by the COR except where another specific authority is designated.
• "CLIN" as used herein shall refer to the contract line items.
• "CO" as used herein shall mean the Contracting Officer.
• "COSR" as used herein means the Government Inspector or Southwestern’s designated representative appointed as the Contracting Officer’s Site Representative and given authority to review the work for quality and compliance with the plans and specifications, under direction of the COR.
• "COR" as used herein means the person duly appointed as the Contracting Officer's Technical Representative by the Contracting Officer. Also may be referred to as “COTR”.
• "Material" or "materials" as used herein to denote items furnished by the Contractor or by Southwestern means machinery, equipment, components, products, or any other item incorporated in the work.
• "NMT" as used herein means “not more than” or “not greater than.”
• "NLT" as used herein means “not less than” or “not smaller than.”
• "Or equal" or “or approved equal” as used herein means that a Contractor may furnish a Southwestern COR approved "equal" item.
• Plans, as used herein, shall mean the construction and work description drawings and the Materials List.
• "Provide or providing" as used herein shall mean furnish and install or furnishing and installing, including all labor and materials to construct or install an item complete and ready for use.
• Where "provide", "install", "furnish", "repair", or words of similar import are used, it shall be understood that reference to the Contractor is intended unless clearly indicated otherwise.
• "Section" as used herein means all written text designated by a section number (e.g. 1.1.6) and includes all subsections under the referenced designation.
• "Southwestern" or "Southwestern Power Administration" or “SWPA” as used herein and on related documents means the Government.
• "SOW" as used herein means the Statement of Work provided for each station.
• “WD” or Work Description as used herein and on the plans means drawings depicting the existing arrangement and denoting work to be done. Generally, if applicable, companion drawings will be included showing the final arrangement.
1.2 Materials
1.2.1 Government-Furnished Materials
No materials will be furnished by the Government.
1.2.2 Contractor-Furnished Materials
1.2.2.1 General
All materials for completing the work shall be furnished by the Contractor, except materials that are identified in the technical specifications or plans to be furnished by Southwestern. All Contractor furnished materials shall be new, of current manufacture, and be in accordance with all contract provisions. No substitutions of any material shall be made without prior approval from the COR.
1.2.2.2 Materials List
The Materials List, when furnished with the contract documents, is provided as a convenience to assist in the specification of approved materials, but is not intended to be a listing of all materials needed to complete the work. The Contractor shall submit for approval any additional and alternate materials.
1.2.2.3 Specifications and Data Sheets
The Contractor shall submit manufacturer specifications and/or data sheets that describe the materials to be furnished to Southwestern for approval in accordance with Section 1.1.3 /Submittals. The submittal shall clearly identify the specific part numbers of the materials proposed to be furnished.
1.2.3 Reference Specifications and Standards
1.2.3.1 General
Reference to Federal Specifications, Federal Standards, American National Standards Institute (ANSI) standards, American Society for Testing and Materials (ASTM) standards, and other standard specifications and codes shall be to the latest editions or revisions in effect on the contract award date, including any amendments or supplements. If requirements in a referenced specification, standard, or code conflict with these specifications, these specifications shall govern. If materials are not specified by Federal, ANSI, ASTM, or other standards or codes, then materials furnished shall be of standard commercial quality.
1.2.3.2 Obtaining Federal Specifications
The Contractor may obtain copies of Federal Specifications at Business Service Centers of Regional Offices of the General Services Administration.
1.2.3.3 Obtaining Other Specifications
Specifications, standards, and codes published by associations or other standardizing agencies may be obtained directly from those agencies.
1.2.3.4 Addresses
Addresses and abbreviations for associations and standardizing agencies are listed below.
Federal Specifications and Standards General Services Administration Federal Supply Service FSS Product Acquisition Center Supply Standards Division (FLAS) Arlington, VA 22202 WEB: http://apps.fss.gsa.gov/pub/fedspecs/
Military Specifications and Standards Document Automation and Production Service Building 4/D, 700 Robbins Avenue Philadelphia, PA 19111-5094 WEB: http://assist.daps.dla.mil/quicksearch/
AA-Aluminum Association 1525 Wilson Blvd., Suite 600 Arlington, VA 22209 WEB: http://www.aluminum.org
AAMA-Architectural Aluminum Manufactures Association 35 East Wacker Drive Chicago, IL 60601
AASHTO-American Association of State Highway Transportation Officials 444 North Capitol Street, N.W., Suite 249 Washington, DC 20001 WEB: http://www.transportatiomn.org
ACI-American Concrete Institute 38800 Country Club Drive Farmington Hills, MI 48331 WEB: http://www.aci-int.org
AISC-American Institute of Steel Construction, Inc.
One East Wacker Drive Chicago, IL 60601 WEB: http://www.aisc.org
AISI-American Iron and Steel Institute 1000 16th Street, N.W. Washington, DC 20001 WEB: http://www.steel.org/
ANSI-American National Standards Institute 25 West 43rd Street (4th Floor) New York, NY 10036 WEB: http://www.ansi.org
The Engineered Wood Association 7011 South 19th Street Tacoma, WA 98466 WEB: http://www.engineeredwood.org
ASHRAE-American Society of Heating, Refrigeration & Air-Conditioning Engineers, Inc.
1791 Tullie Circle, N.E. Atlanta, GA 30329 WEB: http://www.ashrae.org.
ASME-American Society of Mechanical Engineers 3 Park Avenue New York, NY 10016 WEB: http://www.asme.org
ASTM-American Society for Testing and Materials 100 Barr Harbor Drive P.O. Box C700 West Conshohocken, PA 19438-2959 WEB: http://www.astm.org
AWI-Architectural Woodwork Institute 46179 Westlake Drive, Suite 120 Potomac Falls, VA 20165 WEB: http://www.awinet.org
AWPA-American Wood Preservers’ Association P.O. Box 361784 Birmingham, AL 35236-1784 WEB: http://email@awpaa.com
AWS-American Welding Society, Inc.
550 N.W. LeJeune Road Miami, FL 33126 WEB: http://www.aws.org
AWWA-American Water Works Association, Inc.
6666 West Quincy Avenue Denver, CO 80235 WEB: http://www.awwa.org
BIA-Brick Institute of America 1850 Centennial Park Drive, Suite 301
Reston, VA 20191 WEB: http://www.bia.org or www.gobricck.com
BuRec-Bureau of Reclamation, Engineering and Research Center Denver Federal Center, Bldg. 67 Denver, CO 80225 WEB: http://www.firstgov.gov
CPSC-Consumer Product Safety Commission 4330 E. West Highway Bethesda, MD 20814 WEB: http://www.cpse.gov
EPA-Environmental Protection Agency 401 M Street Southwest Washington, DC 20024 WEB: http://www.epa.gov
FCC- Federal Communications Commission 445 12th Street Southwest Washington, DC 20554
WEB: http:://www.fcc.gov
FHWA- Federal Highway Administration Federal Highway Administration Report Center 9701 Philadelphia Court, Unit Q Lanham, MD 20706 http://www.fhwa.dot.gov
FM-Factory Mutual System 1151 Boston-Providence Turnpike Norwood, MA 02062
GSA-General Services Administration 1500 East Banister Road Kansas City, MO 64108
IEEE-Institute of Electrical and Electronic Engineers 3 Park Avenue New York, NY 10016 WEB: http://www.ieee.org
IES-Illuminating Engineering Society 1201 Wall Street New York, NY 10005 WEB: http://www.iesna.org
ICEA-Insulated Cable Engineers Association P.O. Box 1568 Carrollton, GA 30112 WEB: http://www.icea.net
NACE-National Association of Corrosion Engineers 1440 South Creek Drive Houston, TX 77084 WEB: http://www.nace.org
NEC-National Electrical Code National Fire Protection Association One Battery March Park Quincy, MA 02169-7471 WEB:http://www.nfpa.org
NEMA-National Electrical Manufacturers Association 1300 North 17th Street, Suite Rosslyn, VA 22209 WEB: http://www.nema.org
NESC-National Electrical Safety Code Institute of Electrical and Electronic Engineers 345 East 47th Street New York, NY 10017 WEB: http://www.standards.ieee.org/nesc
NFPA-National Fire Protection Association One Battery March Park Quincy, MA 02169 WEB: http://www.nfpa.org
NFOPA-National Forest Products Association 1111 19th Street Northwest Washington, DC 20036 WEB: http://www.afandpa.org
NSF-International /National Sanitation Foundation 789 N. Dixboro Road (P.O. Box 130140) Ann Arbor, MI 48113-0140 WEB: http://www.nsf.org
NTIS-National Technical Information Service 5285 Port Royal Road Springfield, VA 22161 http://www.ntis.gov/
NTIA-National Telecommunications and Information Administration U.S. Department of Commerce 14th & Constitution Avenue Washington, DC 20001 WEB: http://www.ntia.doc.gov
OSHA-Occupational Safety and Health Administration 200 Constitution Avenue Washington, DC 20001 WEB: http://www.osha.gov
PCA-Portland Cement Association 5420 Old Orchard Road Skokie, IL 60077 WEB: http://www.cement.org
PS-Product Standards U.S. Department of Commerce NIST Standards Coordination and Conformity Group Standards Services Division 100 Bureau Drive, MS 2150 Gaithersburg, MD 20899-2150 http://ts.nist.gov/Standards/Conformity/vps.cfm
RIS-Redwood Inspection Service One Lombard Street San Francisco, CA 94111
SAE-Society of Automotive Engineers 400 Commonwealth Drive Warrendale, PA 15086 WEB: http://www.sae.org
SDI-Steel Deck Institute P.O. Box 25 Fox River Grove, IL 60021 WEB: http://www.si.org
SJI-Steel Joist Institute 3127 Mr. Joe White Avenue Myrtle Beach, SC 29577-6760 WEB:
http://www.steeljoist.org
SMACNA-Sheet Metal and Air-Conditioning Contractors National Association, Inc.
4201 Lafayette Center Drive Chantilly, VA 20151-1209 WEB:
http://www.smacna.org
SSPC-Steel Structures Painting Council 21414 68th Avenue Kent, WA 98032
SSPC-Steel Structures Painting Council 2663 N.W. St. Helens Road Portland, OR 97210
TCA-Tile Council of America, Inc.
100 Clemson Research Boulevard Anderson, SC 29625
TIA/EIA- Telecommunications Industry Associations/Electronic Industry Association 2500 Wilson Boulevard Arlington, VA 22201 WEB: http://www.tiaonline.com
TPI-Truss Plate Institute 218 N. Lee Street, Suite 312 Alexandria, VA 22314
IBC-International Building Code International Code Council 500 New Jersey Avenue, NW 6th Floor Washington, DC 20001 http://www.iccsafe.org
UL-Underwriters’ Laboratories, Inc.
Customer Service 333 Pfingsten Road Northbrook, IL 60062-2096 USA http://www.ul.com
IPC-International Plumbing Code International Code Council 500 New Jersey Avenue, NW 6th Floor Washington, DC 20001 http://www.iccsafe.org
WWPA-Western Wood Products Association 1500 Yeon Building Portland, OR 97201 WEB: http://www.wwpa.org
1.3 Local Conditions
1.3.1 Rights-of-Way
Southwestern will furnish the site for the work. Southwestern shall grant the Contractor access to Federal lands and rights-of-way for performance of the work.
1.3.2 Access to the Work and Haul Routes
Access includes ingress and egress to the work over approved routes established by Southwestern. The Contractor shall conduct operations in a manner that minimizes damages (including crop damage) on Federal lands or within the Federal rights-of-way and on adjoining lands during performance. The Contractor shall not lay fences down to gain access to Southwestern’s rights-of-way but may install gates, gateposts, etc., approved by the COR at their own expense. The Contractor shall install silt fences or other runoff controls to minimize silt runoff from disturbed access roads and shall suitably clear and clean highways and roads adjacent to the access if excess mud droppings are discharged thereon.
1.3.2.1 Contractor's Investigations
Delivery of the materials to the site shall be the Contractor’s responsibility. This includes any investigations of the condition and availability of public and private roads and clearances, restrictions, bridge load limits, bond requirements, and other limitations that may affect transportation and ingress and egress at the jobsite that the Contractor deems prudent and/or necessary to assure delivery. No claim for damages or extension of time shall be made based on unavailability of transportation facilities or limitations thereon.
1.3.2.2 Haul Routes
Intra-job hauling over public highways, roads, and bridges shall be performed in accordance with applicable local regulations and shall minimize interference with local traffic. Where haul routes cross public highways or roads, the Contractor shall provide barricades, flag persons, and other necessary precautions.
1.3.2.3 Equipment and Material Removal
All Contractor-owned equipment and materials shall be removed from Government-owned land within two (2) weeks after completion of the project. Access for removal shall be coordinated with the COR. Any excess charges for returning to the site shall be at the Contractor’s expense.
1.3.3 Use of Private Land for Construction Purposes
All necessary arrangements shall be made with the owner If private land is used. All rentals or other costs shall be paid by the Contractor. The Contractor shall provide a copy of the written agreement to the COR, signed by the landowner, describing the arrangements.
1.3.3.1 Damage to Existing Property and Crops
The Contractor shall be financially responsible for any damage to existing structures, work, materials, or equipment because of the Contractor’s operations and shall repair or replace any damaged structures, work, materials, or equipment to the satisfaction of, and at no additional cost to, Southwestern. The Contractor shall protect all existing structures and property from damage and shall provide shielding, bracing, shoring, and other work necessary for such protection. The Contractor shall be responsible for all damage to streets, roads, curbs, sidewalks, highways, shoulders, ditches, embankments, culverts, bridges, or other public or private property (including crop damage inside and outside Southwestern’s rights-or-way and property owner fences and gates inside and outside the right-of-way), which may be caused by transporting equipment, materials, or personnel to or from work site. The Contractor shall make satisfactory and acceptable arrangements with Southwestern and with the agency having jurisdiction over the damaged property concerning its repair or replacement.
1.3.4 Protection of Existing Installations
1.3.4.1 General
The location of buried conduit, pipe, cable, ground mat, and other buried items shall be determined by the Contractor prior to performing any excavation at existing installations. Proper methods shall be used for protecting existing installations during excavation and backfilling operations and when installing equipment and materials.
1.3.4.2 Protective Installations
Protective installations shall permit operation of existing equipment and facilities while construction work is in progress. Trenches shall be filled or protected (barricaded) at the end of each workday to provide safe nighttime access for emergency maintenance. All protective installations shall be removed after they have served their purpose. Materials furnished by the Contractor to provide protection shall remain the Contractor’s property.
All holes made in or under a fence and/or barricade (permanent and temporary) shall be secured by the Contractor and approved by the COSR prior to the end of each workday or termination of work at the site.
No materials or vehicles are allowed within 3.05 m (10 feet) of security construction fences. This includes temporary fences at the job site and lay-down area.
Temporary Fence shall meet the following minimum requirements:
The temporary fence shall meet the following minimum requirements:
• Be at least 8’ tall
• Barbed wire is not required for temporary fence
• Standard 11-1/2" gauge galvanized fence fabric with 2-1/4" mesh
• If self-supported fence panels are used, the panels shall be interlocked
• Include bottom rails to prevent something from pushing under the fence
• Fence frame shall be strong to withstand strong winds (sandbags can be used)
1.3.4.3 Method of Cable Location
Prior to starting excavation, a plan shall be submitted to the COR for review, giving proposed methods of locating existing buried cable and excavation procedure to minimize risk of damage to the cable(s). The plan shall include methods of identifying subsurface cable installations within the work area and methods of surface marking of cable locations and line of excavation. When locating cable, wires shall not be loosened or removed from the terminals and signals shall not be induced into the control circuit. The site shall remain operational at all times and the methods used for cable location shall not interfere with operation of the station. Excavation will not be allowed until cable location(s) has been marked on the ground and the COR has received a marked print showing the cable location(s) and given approval to begin.
1.3.5 Geologic Investigations
The Contractor shall be responsible for determining the nature of materials to be excavated, the difficulties of making and maintaining required excavations, and performing other work affected by geology and ground water elevations at the work site.
1.3.6 Electric Power for Construction Purposes
Where available, electric power for construction purposes will be provided, at no cost to the Contractor, by Southwestern. This power will typically be one circuit of single phase, 60 Hz, at approximately 120 volts, with 20 Amps capacity. The Contractor shall provide any needed plug, cordage and GFI protection. Contractor’s use, however, shall not interrupt or interfere with service to existing equipment. The Contractor shall immediately notify the COR if the circuit trips due to the Contractors use. The Contractor shall not reset the circuit breaker or replace any fuse without express permission of the COR or designated representative. Repeated circuit trips shall be cause for Southwestern to discontinue service to the Contractor.
Where Southwestern electric power is not available, the Contractor shall furnish power for construction needs by other means and at contractor’s sole cost.
1.3.7 Water for Construction Purposes
Water for construction purposes shall be furnished by the Contractor. Arrangements shall be made for obtaining the water and providing for conveyance of the water to the points of use.
1.3.8 Sanitation Facilities
Chemical toilet facilities, to be set at locations approved by the COR, shall be provided by the Contractor. Contractor personnel shall not use the permanent facilities in the Southwestern stations. The Contractor provided facilities shall also be available for use by Southwestern personnel or representatives.
1.3.9 Storage and Work Facilities
Any required dry storage and work facilities shall be provided by the Contractor.
Southwestern buildings or facilities shall not be used for storage of materials or as a workshop or lunchroom.
1.3.10 Telephone Service
Contractor shall arrange for his own telephone service. Contractor personnel shall not use the telephone in the Southwestern stations.
1.3.11 Field Offices and Sheds Reserved
For each construction site, the Contractor shall supply a water-tight construction field office with lighting, electrical outlets, heating, cooling and ventilating equipment. The office shall contain all drawings, submittals, construction plans, etc. necessary for completing the work as specified.
The Contractor shall also provide storage sheds for tools, materials and maintenance. The storage shed shall be water-tight, with heat and ventilation for products requiring controlled conditions with adequate space for storage, and lighting for inspection of stored materials.
1.3.12 Cleaning During Construction
The Contractor shall execute periodic cleaning to keep the work, the site, and adjacent properties free from accumulations of waste materials, rubbish, and windblown debris resulting from construction operations.
The Contractor shall also provide on-site containers for the collection of waste materials, debris, and rubbish, periodically removing the waste materials, debris, and rubbish from the site to legal disposal areas away from the site.
1.3.13 Signage: Existing signage shall be removed prior to demolition of existing fence and re-installed once new fence has been installed. Any signage in disrepair prior to removal shall be addressed with the site Government personnel. Any signage damaged by the contractor shall be replace at no cost to the Government.
1.4 Environmental Quality Protection
1.4.1 Compliance
The Contractor shall comply with applicable Federal, state, and local environmental laws, orders, and regulations. The Contract clauses prescribe environmental requirements and the sections in this subsection specify further measures to be followed.
The Contractor, in accordance with FAR 52.236-7 “Permits and Responsibilities” and Section H.01 “SWPA-Contractor Environmental, Safety, and Health Requirements”, is responsible for developing and submitting plans, obtaining necessary permits, and implementing the required local, state, and federal laws, codes, and regulations for protecting the environment.
The Contractor shall submit copies of all documents to the COR for review and approval.
1.4.2 Landscape Preservation
The Contractor shall take all necessary measures to preserve the landscape on or adjacent to the work site in accordance with FAR 52.236-9/Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.
1.4.2.1 Construction Roads
Location, alignment, and grade of construction roads shall be subject to COR approval. When no longer required, construction roads shall be restored to their original condition. Surfaces of construction roads shall be scarified to facilitate natural re-vegetation, provide for proper drainage, and prevent erosion.
1.4.2.2 Construction Facilities
Shop, office, and yard areas shall be located and arranged in a manner to preserve trees and vegetation to the maximum practicable extent. On abandonment, storage and construction buildings, including concrete foundations and slabs, shall be removed from the site. The area shall be re-graded as required so that all surfaces drain and are left in a condition that will facilitate natural re-vegetation, provide for proper drainage, and prevent erosion.
1.4.3 Waste Removal
In addition to the requirements of FAR 52.236-12/Cleanup, all waste materials shall be removed from the construction site specifically as specified in the sections to follow.
1.4.3.1 Waste Material
Waste materials include refuse, garbage, sanitary waste, industrial wastes, petroleum products, cleared materials, lumber, pipe, electrical cable, and all other excess materials resulting from demolition and construction operations.
1.4.3.2 Artifacts
If, during excavation, the Contractor encounters artifact(s) suspected of being cultural, historic, or archaeological resources, the Contractor shall stop excavation immediately and notify the COR. The CO may direct the Contractor to cease excavation activities indefinitely until the suspected artifact(s) can be evaluated by the Government. Under no circumstances shall the Contractor disturb or remove suspect artifact(s) without written consent from the CO.
1.4.3.3 Disposal of Waste Material
The Contractor shall haul waste material to an approved facility. All metal materials shall be disposed of at a metal recycling facility. The Contractor shall make all arrangements with private properties and local officials to dispose of waste materials.
The Contractor shall provide completed shipping documents, hereinafter referred to as “Bills of Lading”, to the COR for all materials removed from the site. A Bill of Lading must accompany each waste shipment and must include information regarding the quantity and type of waste being removed, the destination and recycling/disposal firm accepting the waste, the waste transporter name, and the date of removal from Southwestern’s site.
1.4.3.4 Disposal of Controlled and Regulated Materials
The Contractor shall dispose of controlled and regulated materials and their containers in accordance with the manufacturer's label instructions and applicable laws and regulations. The Contractor shall provide proof of disposal in the form satisfactory to the COR.
1.4.3.5 Exposure to Hazardous Materials
If, during the progress of work, the Contractor encounters materials suspected of being in contact with or exposed to hazardous wastes, the Contractor shall immediately stop work in the affected area and notify the COR. Also, if anything, including off-color or suspicious appearing soils, suspected of being in contact with or exposed to hazardous wastes is discovered, the Contractor shall immediately cease all operations in the area and notify the COR. Under no circumstances shall the Contractor disturb or remove suspect materials without written consent from the CO.
1.4.4 Asbestos Investigation & Remediation/Abatement Requirements
The sites have been surveyed for the presence of asbestos containing materials (ACM) and have been found not to contain ACM.
1.4.5 Lead Based Paint Investigations
The sites have been investigated and found to be free of lead-based paint materials.
If handling of lead-based paint materials is required, then the contractor shall comply with all pertinent OSHA precautions and procedures, including:
• Requirement that the Contractor use engineering controls and work practices, where feasible, to reduce worker exposure to a permissible exposure limit (PEL) of NMT 50 micrograms of lead per cubic meter of air, as averaged over an 8-hour period.
• Requirement that employees observe good personal hygiene practices, such as washing hands before eating.
• Requirements that employees be provided with protective clothing and, where necessary, with respiratory protection accordance with 29 CFR 1910.134.
1.5 Superintendent Qualifications and Responsibilities
1.5.1 Responsibilities
The Contractor shall have a superintendent on the work site continuously during hours of work, prior to the arrival of any materials at the job site, and throughout the progress of the work. The superintendent shall be thoroughly familiar with the requirements of the project. The superintendent shall supervise and direct the work efficiently using skill and attention. Superintendents shall be in a non-work status during work requiring a Hot Line Order, Clearance, or other critical phases of work as determined by the COR. The superintendent shall be in contact with the crews at all times. The superintendent shall not also serve as the Quality Control Manager (QCM) but shall work hand in hand with the QCM to ensure the work performed is as required in the contract.
1.5.2 Qualifications
The superintendent shall have a minimum of 3 years experience as a superintendent or foreman in the type of construction contained in these specifications and shall have demonstrated knowledge of applicable OSHA construction safety standards. The superintendent’s resume shall be submitted to the COR for review and approval including the following minimum information:
1. Work history relating to above requirements
2. Three job-related references
3. Current first aid and CPR certificates
4. Listing of safety and health training
1.6 Employee Requirements
1.6.1 General
Employees shall be qualified to perform their assigned duties. Employees shall not work while their ability or alertness is impaired because of fatigue, illness, medications, drugs, alcohol, or any other reason that may expose them or others to injury.
1.6.2 Training
Ensure that each employee entering the work site has experience, training, and, where required, the certification, skills, and knowledge necessary to safely perform their assigned tasks. In addition, ensure each employee receives initial work site safety orientation and continued safety and health training addressing the hazards associated with the work and the measures necessary to control or eliminate the hazards.
1.6.3 Physical Examination
Each employee who operates the following listed equipment shall be given and pass a Department of Transportation (DOT 49 CFR 391.43) physical examination once every 24 months:
• Cranes.
• Aerial lift equipment.
• Other vehicles as required by Federal and State laws and regulations.
A copy of the Medical Examiner's certificate shall be furnished to the COR prior to the employee operating the listed equipment. The certificate shall state that the physical examination met the requirements of DOT 49 CFR 391.43.
1.6.4 Operators
Employees operating motor vehicles and other equipment shall be licensed in accordance with applicable Federal and State laws and regulations.
Upon request, provide the COR with assurance of competency of employees operating cranes, aerial lift equipment, heavy equipment, and other motor vehicles by documentation of their experience, training, and licensing.
1.7 Inspection and Acceptance
1.8 Character of Workmen, Methods, and Equipment
1.8.1 The Contractor shall employ at all times sufficient labor and equipment for prosecuting the work to full completion in the manner and time required by these specifications. All workers shall have sufficient skill and experience to perform the work assigned them. As soon as practicable after award of the contract and before work is started, the Contractor and subcontractors shall submit to the COR a list of each employee with his skill to be employed under this contract.
1.8.2 The Contractor shall furnish equipment of sufficient size and quantity and in such mechanical condition as to meet the requirements of the work and to produce a satisfactory quality of work. Equipment used on any project shall be such that no injury to the substation, radio site, or adjacent property will result. As soon as practicable after award of the contract and before work is started, the Contractor and subcontractors shall submit to the COR, for approval, a schedule in duplicate, listing each major item of equipment to be used under this contract. This list shall show the name, manufacturer, equipment description (including picture), and rated size of each item of equipment to be used. The Contractor and subcontractors shall make available for inspection by the COR each item of equipment listed to be used under this contract.
1.8.3 When the methods and equipment to be used by the Contractor in accomplishing the construction are not prescribed in the contract, the Contractor is free to use any method or equipment that he demonstrates to the satisfaction of the COR and will accomplish the contract work in conformity with the requirements of the contract.
1.8.4 The Contracting Officer or COR has authority to suspend work wholly or in part for such period or periods as he may deem necessary due to the failure to the Contractor or subcontractor to correct conditions unsafe for the workers; for failure to carry out orders; or for failure on the part of the Contractor or subcontractor to comply with any of the provisions of the contract. Should it become necessary to stop work for an indefinite period, the Contractor shall store all materials in a manner that will protect them from damage and shall take every precaution to prevent damage to or deterioration of the work performed.
SECTION 01 10 00 - SUMMARY
PART 1 GENERAL
1.1 PROJECT
A. Project Name: Sikeston Substation Fencing Replacement B. Project Location: i. Latitude: 36 degrees 52 minutes 33.2076 seconds North
ii. Longitude: 89 degrees 37 minutes 29.9784 seconds West C. Owner's Name: Southwestern Power Administration.
D. This Project consists of replacing the security fence and fence grounding at the Sikeston Substation.
1.2 OWNER OCCUPANCY
A. Southwestern Power Administration intends to continue to occupy adjacent portions of the existing complex during the entire construction period.
B. Southwestern Power Administration intends to occupy the Project upon Substantial Completion.
C. Cooperate with Southwestern Power Administration to minimize conflict and to facilitate Southwestern Power Administration's operations.
D. Schedule the Work to accommodate Southwestern Power Administration occupancy.
1.3 CONTRACTOR USE OF SITE AND PREMISES
A. Construction Operations: Limited to areas noted on Drawings.
B. Arrange use of site and premises to allow:
1. Southwestern Power Administration occupancy.
C. Provide access to and from site as required by law and by Southwestern Power Administration:
1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.
2. Do not obstruct roadways, sidewalks, or other public ways without permit.
D. Time Restrictions:
1. Provide Southwestern COR with a proposed work schedule for approval prior to the beginning of the Work. Any deviation from the original schedule MUST be approved by COR prior to execution of the Work.
2. The Contractor's work hours shall be as outlined in Section F of this contract.
E. Utility Outages and Shutdown:
1. Any required shutdown of utility services shall be…