This document is an amendment to a federal solicitation for the Kofa Dome Tap Transmission Line Project. The amendment provides answers to contractor questions, adds two clauses, and clarifies the period of performance. Key details include: the project involves reconductoring 7.5 miles of transmission line with new conductor and installing one optical ground wire and one steel ground wire, removing existing structures and installing new steel structures, installing fiber optics at Kofa Substation, and installing aluminum conductor at the substation. The period of performance is from notice to proceed until May 30, 2021. Liquidated damages of $1,329.32 per day will apply for delays in completion. The bid receipt date remains January 14, 2020 at 2:00pm local time. The amendment is issued by the Department of Energy Western Area Power Administration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
89503120BWA000019
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PHOENIX AZ 85005-6457
DSW
PO BOX 6457
DESERT SOUTHWEST REGIONAL OFFICE
US DOE/WESTERN AREA POWER
WAPA (DSW)
01/02/20200001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
12/03/2019
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
See Continuation Page
FOB: Destination
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Caroline Bachelier
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
01/02/2020 Signature on File
The purpose of this Amendment is to answer contractor generated questions and add two clauses to the solicitation.
A. Answering the following questions:
1 Question: There is a discrepancy in the period of performance. In box 11 of the solicitation form 1442, the period of performance is given numerically as 180 days.
It then refers the reader to Section F, Clause 52.211-10. In words, that clause indicates a period of performance of 120 days, then immediately shows 180 days in parenthesis. Which is it?
Answer: The period of performance will be from the NTP until 5/30/2021. To avoid confusion, see the amendment for correction of this period. Outage dates remain unchanged.
2 Question: Division 1, paragraph F.1 indicates the GFE will be delivered to both Kofa and Gila substations. Why is GFE being delivered to Gila? Gila has nothing to do with the project and is seven miles south of Dome Tap, and even further south of Kofa. All GFE should be delivered to Kofa as there is plenty of room to store it, and it is far closer to the actual work than Gila. Gila should be taken completely off the points of delivery.
Answer: Only the fiber is going to Gila so WAPA can perform testing for material acceptance. The contractor shall pick up the fiber from Gila, transport it to Kofa and do their own testing as well if they desire. All items on the Table in 1F1 of the project specification will be delivered to the places designated in that table.
3 Question: Referencing item 2 above, there is no indication what GFE is to be delivered to which substation. The contractor has no idea of what goes where, and how far he will have to travel to pick up what he needs. All GFE should be delivered to Kofa; any GFE slated for delivery to Gila should be rerouted to Kofa.
Answer: See answer above.
4 There are no liquidated damages listed in the solicitation. Should there be some?
Liquidated damages are a part of this specification. Clause 52.211-12 has been added to the solicitation.
B. The following clauses have been added or corrected to the solicitation.
1. 52.211-12 Liquidated Damages - Construction. (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,329.32 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
2. 52.228-15 Performance and Payment Bonds - Construction. (OCT 2010)
3. 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK.
(APR 1984)
The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 May 2021.
The time stated for completion shall include final cleanup of the premises.
(End of clause)
C. The date and time set for receipt of bids remains unchanged, January 14, 2020 at 2:00pm local time.