21 - Atch B - Specifications.pdf
PDF 916 KB Posted
- Attached to
- Kofa Dome Tap Transmission Line Project
- Solicitation number
- 89503120BWA000019
About this file
This federal contract opportunity solicitation seeks a contractor to perform work on the Kofa Dome Tap Transmission Line Project. The solicitation requires removing existing infrastructure and reconductoring over seven miles of transmission line, including removing two existing overhead ground wires and installing one government-furnished optical ground wire and one steel overhead ground wire. Additional work includes removing eight wood pole structures and one light-duty steel pole structure and installing nine new light-duty and one heavy-duty steel pole structure. The solicitation also requires furnishing, installing, and terminating fiber optics at Kofa Substation, as well as furnishing and installing aluminum conductor and associated fittings. All work must comply strictly with the specifications and drawings. The Department of Energy Western Area Power Administration is the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KOFA – DOME TAP 161-KV TRANSMISSION
LINE PROJECT
Spec. No. 969
SECTION C
DESCRIPTION/SPECIFICATIONS
ARIZONA
SECTION C
DESCRIPTION/SECIFICATIONS
KOFA – DOME TAP 161-KV TRANSMISSION LINE PROJECT
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT
B. DESCRIPTION OF WORK
1. The Principal Components of Work
C. DESCRIPTION OF BIDDING SCHEDULE ITEM
1. Bidding Schedule item “Mobilization and preparatory work”
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
1. Commencement, Prosecution and Completion of the Work
2. Submittal Approval Time
3. Outage Restrictions
4. Construction Schedule Restrictions
5. Protective Ground Leads
6. Maximum Available Fault Current
E. CONSTRUCTION SCHEDULE
1. Submittal Time
2. Format and Detail
F. MATERIAL
1. POINTS-OF-DELIVERY
G. RIGHTS-OF-WAY
1. General
2. Work on the Right-of-Way
H. GEOLOGIC INVESTIGATIONS
I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES
J. WATER FOR CONSTRUCTION PURPOSES
K. SAFETY PROFESSIONAL
1. Safety
L. EXPLOSIVES AND BLASTING
M. BURIED UTILITIES
N. CONTRACTOR COMMUNICATIONS FOR WAPA USE
O. EMPLOYEE REQUIREMENTS
P. ELECTRICAL MINIMUM APPROACH DISTANCES
Q. SUBMITTALS AND CORRESPONDENCE
1. General
2. Approval Time
3. Submittal Response
4. Physical Sample Submittals
6. Project Protocol
DIVISION 2 – SITEWORK
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item “Miscellaneous Sitework”
2. Bidding Schedule item “Remove existing transmission line”
3. Bidding Schedule does not contain separate items
DIVISION 3 – CONCRETE
A. GENERAL
1. Material
2. Test for Potential Alkali Silica Reactivity of Sand and Coarse Aggregate
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item “Concrete foundation for Government-furnished base-plated (BP) transmission line steel pole structure”
DIVISION 5 – TRANSMISSION LINE STEEL POLE STRUCTURES
A. GENERAL
1. Government-furnished, weathering steel pole structure Type 157N (BP)
2. Structure Components
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item for installing base-plated (BP) Government-furnished transmission line steel pole structure on concrete foundation
DIVISION 6 – LIGHT DUTY TRANSMISSION LINE STEEL POLE STRUCTURES
A. GENERAL
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item for installing direct-embedded (DE) Government-furnished light duty transmission line steel pole structures with polyurethane foam backfill
C. GUYS AND ANCHORS
DIVISION 9 – SUBSTATION – ELECTRICAL
A. GENERAL
1. Bidding Schedule for Government-furnished items
2. Bidding Schedule for items (not furnished by the Government)
3. Associated Support Structures Provided for each Electrical Equipment rated above 7-kV
4. Installation and Painting of Electrical Equipment and Material
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule item “Bus system at Kofa Substation”
2. Bidding Schedule item “Existing outdoor electrical equipment and material”
DIVISION 10 – TRANSMISSION LINE ELECTRICAL
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS
1. Bidding Schedule items for furnishing and installing conductor insulator assemblies
2. Bidding Schedule items for furnishing and installing overhead ground wire assemblies
3. Bidding Schedule items for furnishing and installing optical overhead ground wire assemblies
4. Bidding Schedule item “Furnish and install three (3) 336.4 kcmil, ACSS/MA3, 30/7, ORIOLE conductor”
5. Bidding Schedule item “Furnish and install one (1) 3/8-inch-diameter, galvanized, high-strength steel, 7-strand overhead ground wires”
6. Bidding Schedule item “Install one (1) Government-furnished 0.465-inch-diameter, 48-fiber optical overhead ground wire”
7. Bidding Schedule item “Vibration dampers for conductors, overhead ground wires, and optical overhead ground wires”
8. Bidding Schedule item “Hold-down weights”
9. Bidding Schedule item “Line markers”
DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION
A. GENERAL REQUIREMENTS
1. Bidding Schedule does not contain separate items
B. SPECIAL REQUIREMENTS
1. Project Area
2. Coordination
3. Special Cultural Resources Requirements
4. Special Biological Requirements
5. Special Compliance Requirements
DIVISION 14 – COMMUNICATIONS FACILITIES
A. COMMUNICATION FACILITIES
1. Bidding Schedule item “Furnish and install fiber optics (FO) and associated equipment”
DIVISION 15 – DRAWINGS
A. GENERAL
1. Construction Drawings
B. AS-BUILT DRAWINGS
1. General
2. Recording Information
3. Marking of Drawings
4. Drawing Review
5. As-Built Information to be Recorded
6. Submittals
LIST OF APPENDICIES
Appendix A – Laydown Yard
Appendix B – Geotechnical Engineering Report
Appendix C – Geotechnical Engineering Report
Appendix D – KOF-DME Oriole ACSS Stringing Charts
Appendix E – KOF-DME 3/8 inch 7-Strand HS Steel OGW Stringing Charts
Appendix F – KOF-DME 0.465 inch OPGW (CC-57/465, 48-fiber) Stringing Charts
Appendix G – CM 16
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
Construct and complete Kofa – Dome Tap 161-kV Transmission Line Reconductor Project, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; WAPA’s Construction Standards, including Standard 1 – General Requirements (September 2016), Standard 2 – Sitework (September 2016), Standard 3 – Concrete (September 2016), Standard 4 – Substation Metalwork and Transmission Line Lattice Structures (September 2016), Standard 5 – Transmission Line Steel Pole Structures (September 2016), Standard 6 – Light Duty Transmission Line Steel Pole Structures (September 2016), Standard 9 – Substation – Electrical (September 2016), Standard 10 – Transmission Line – Electrical (September 2016), Standard 13 – Environmental Quality Protection (September 2016), Standard 14 – Communication Facilities (September 2016), Standard 15 – Drawings (September 2016); Standard Drawings; and these Project Specifications and Drawings.
If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.
WAPA’s Construction Standards, Standard Drawings, and Electrical Equipment Standards are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.
WAPA Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.
“WAPA”, “Western”, or “Western Area Power Administration” as used herein means the Government.
B. DESCRIPTION OF WORK:
1. THE PRINCIPAL COMPONENTS OF WORK include the following:
a. Removing existing copper conductor and reconductoring 7.5-miles of transmission line with ACSS conductor.
b. Removing two (2) existing steel overhead ground wires and installing one (1) Government-furnished optical ground wire and furnishing and installing one (1) steel overhead ground wire on 7.5-miles of transmission line.
c. Removing eight (8) transmission line wood pole structures and one (1) transmission line light-duty steel pole structures. Installing eight (8) new transmission line light-duty steel structures and one (1) new transmission line heavy-duty steel pole structure.
d. Furnishing, installing and terminating fiber optics at Kofa Substation (KOF).
e. Furnishing and installing aluminum conductor and associated fittings at Kofa Substation.
Paragraphs “Description of Bidding Schedule Items” in Divisions – 1, 2, 3, 5, 6, 9, 10 and 14 describe the work to be performed.
The work is located between WAPA’s facilities at Kofa Substation (KOF) and Dome Tap (DME) near Yuma, Arizona, as shown on Drawings KOF 0019 and DME 0015.
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work” includes the following:
a. Performing mobilization and preparatory work in accordance with Section H of the contract clauses.
b. Prepare and submit a Construction Schedule and furnish a Safety and Health Program.
c. Providing jobsite office trailer and the items listed below. Prior to any jobsite work, the
Contractor shall provide the office trailer for the exclusive use of WAPA.
(1) Relocation: If the Contractor changes the location of his office during the term of the contract, then the Contractor shall also move the mobile office trailer provided for WAPA, simultaneously with the transportation of his own unit.
(a) Installation: Install anchors and tie-downs for the trailer complying with local, State and Federal regulations. The office trailer shall be grounded. Entry points to the trailer shall be provided with stairways complying with OSHA (29 C.F.R. 1926.1052).
(b) Office Space Requirements:
1) Size and Arrangement: At least 250-square-feet (minimum) consisting of two (2) separate rooms (one (1) office and one (1) larger workroom).
2) Heating and Cooling: Heating and cooling unit sized to provide adequate heating and cooling.
3) Lighting and Electrical: Adequate lighting and 110 V electrical outlets.
4) Utilities: Make all arrangements and pay all costs for providing utilities, including potable drinking water, electrical power and heating and cooling energy.
5) Toilet Facilities: Toilet facilities shall be provided in the immediate vicinity of the office and shall be maintained.
(2) Emergency Equipment: Provide and maintain the following emergency equipment:
(a) First aid kit that meets or exceeds ANSI Z308.1 (latest version) Class B, Type IV. Mount to the wall inside the workroom.
(b) Dry chemical fire extinguishers, Classified 4-A:60-B:C, one (1) to be located inside each entrance to the trailer.
(3) Window Coverings: Provide adjustable mini-blinds.
(4) Office Furniture: Provide good quality, fully functional, office furniture as follows:
QUANTITY DESCRIPTION
Five (5) Folding Office Chairs One (1) Office desk (30-inches by 60-inches minimum).
Two (2) Office tables (30-inches by 60-inches minimum).
One (1) Five-drawer file cabinet.
One (1) Bookcase (30-inches by 13-inches by 48-inches).
QUANTITY DESCRIPTION
Twelve (12) “Plan Hold” binders No. 1CB-24 (including one (1) plan rack).
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
1. COMMENCEMENT, PROSECUTION AND COMPLETION OF THE WORK: See FAR 52.211-10 in Section F of the solicitation/contract.
2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 30-calendar days for review of drawings or data submitted for approval.
3. OUTAGE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage restrictions shall apply:
a. One continuous outage may be taken October 7, 2020 to April 30, 2021.
4. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply:
a. Work shall be performed during daylight hours unless otherwise approved by the Contracting Officer’s Representative (COR).
b. The electrical operation of the transmission lines are under the jurisdiction of WAPA’s
Operations Office. Approval or denial of an individual outage request will be based on transmission system electrical loads, system operating configurations and weather conditions at the time the outage is scheduled to begin. At any time because of transmission system electrical loads, transmission system operation or reliability, WAPA may deny an outage request or direct the Contractor to return facilities to operating conditions and release the applicable Special Work Permit. Make all outage requests in wiring to the COR a minimum of 30-days in advance. Meeting the minimum advance notice requirement of 30-days does not guarantee an outage will be approved. To improve the chances of an outage being approved, all outages should be submitted with as much advance notice as practicable. Weather conditions and other system conditions such as other scheduled and nonscheduled (forced) outages must be evaluated against an outage request before approval can be granted.
5. PROTECTIVE GROUND LEADS: See WAPA Construction Standards, Standard 1 “General
Requirements”, Section 1.4.14.3(1).
6. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the following:
a. The maximum available fault current in the 161-kV area at Kofa Substation is 4,238 amps.
b. X/R ratio is 5.4.
c. A minimum of one (1) 1/0 copper ground shall be used.
E. CONSTRUCTION SCHEDULE:
1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer (CO) within 45-calendar days after date of Notice to Proceed.
2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.
F. MATERIAL: Furnish all material for completing the work, except material furnished by WAPA as listed below:
ITEM
ESTIMATED
WEIGHT
(LBS)
ESTIMATED
DELIVERY
DATE
(LOCATION)
ESTIMATED
COST
1. One (1) Type 157N-50 (BP) steel pole structure with maintenance provisions and anchor bolt cage
28,500
NST 3/1/20
NLT 3/31/20
(Kofa Substation) $53,300
2. One (1) 161-kV Type 40A-60-60- 60 (DE) light-duty steel pole structure with maintenance provisions and fall protection
NST 3/1/20
NLT 3/31/20
(Kofa Substation) $11,400
3. One (1) 161-kV Type 40H-60 (DE) light-duty steel pole structure with maintenance provisions and fall protection
NST 3/1/20
NLT 3/31/20
(Kofa Substation) $9700
4. One (1) 161-kV Type 40H-65 (DE) light-duty steel pole structure with maintenance provisions and fall protection
NST 3/1/20
NLT 3/31/20
(Kofa Substation) $10,700
5. Two (2) 161-kV Type 40H-70 (DE) light-duty steel pole structure with maintenance provisions and fall protection
4750 EA
NST 3/1/20
NLT 3/31/20
(Kofa Substation)
$11,900 EA
6. One (1) 161-kV Type 40H-75 (DE) light-duty steel pole structure with maintenance provisions and fall protection
NST 3/1/20
NLT 3/31/20
(Kofa Substation) $13,200
7. One (1) 161-kV Type 40T-70-55- 70 (DE) light-duty steel pole structure with maintenance provisions and fall protection
NST 3/1/20
NLT 3/31/20
(Kofa Substation) $14,400
8. One (1) 161-kV Type 40T-85-70- 85 (DE) light-duty steel pole structure with maintenance provisions and fall protection
NST 3/1/20
NLT 3/31/20
(Kofa Substation) $16,800
9. Twenty-two (22) Left Anchor Plates galvanized – Mark 1FP-5L for Type 157N structure
1.3 EA
NST 3/1/20
NLT 3/31/20
(Kofa Substation)
$6.12 EA
10. Twenty-two (22) Right Anchor Plates galvanized – Mark 1FP-5R for Type 157N structure
1.3 EA
NST 3/1/20
NLT 3/31/20
(Kofa Substation)
$6.12 EA
11. One (1) 13,000 ft reel of optical ground wire – CC-57/465 (48 Fiber)
NST 3/1/20
NLT 3/31/20
(Gila Substation) $23,920
12. One (1) 15,000 ft reel of optical ground wire – CC-57/465 (48 Fiber)
NST 3/1/20
NLT 3/31/20
(Gila Substation) $27,600
13. One (1) 16,000 ft reel of optical ground wire – CC-57/465 (48 Fiber)
NST 3/1/20
NLT 3/31/20
(Gila Substation) $29,440
14. Fiber Optic Patch Panel, 48 position 24
NST 3/1/20
NLT 3/31/20
(Kofa Substation) $1118
NST – No sooner than.
NLT – No later than.
1. POINTS-OF-DELIVERY: Material furnished by WAPA will be delivered to a storage yard located at the Kofa Substation, as shown on Appendix A and on Drawing KOF 0019 and to Gila Substation, as shown on Drawing GLA 0015. The Contractor shall load, transport, and unload the material to the jobsite. The Contractor shall inspect the equipment and report any damages to the COR.
G. RIGHTS-OF-WAY:
1. GENERAL: Transmission line right-of-way is 100-feet-wide. WAPA does not represent that the Contractor can gain access to every structure site or travel continuously along the transmission line.
Orient construction methods and equipment to utilize Government-furnished rights-of-way, or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired by the Contractor shall have prior COR approval, since several areas of the transmission line have travel restricted areas. During the contract period, WAPA reserves the right to use Contractor-obtained access.
Make necessary provisions to perform work to avoid interference with the operation or maintenance of railroads, highways and overhead/underground utility lines, including pipelines, transmission, telegraph and telephone lines, in a manner satisfactory to the owners or operators thereof and to WAPA. If required, furnish liability insurance, indemnity and other bonds, obtain all required permits and safety certifications.
2. WORK ON THE RIGHT-OF-WAY:
a. General: Perform work on the rights-of-way necessary for access to or along the transmission line. Only that excavation, dozing, or blading absolutely necessary will be allowed. Excavation, dozing and blading for ease of travel may only be performed after field review and approval by the COR. Unauthorized excavation, dozing, blading shall immediately be repaired, or WAPA will have the damage repaired and backcharge the Contractor for all costs involved.
b. Work within the Yuma Proving Grounds (YPG) will require personnel receive a one hour briefing on recognizing unexploded ordinance. This training will be provided onsite by YPG personnel at a time following mobilization. Contractor assumes all responsibility and risk associated with working in hazardous areas. All costs for time or training are at the Contractor’s expense.
c. Ease of Travel and Crane Landings: Excavation, dozing, or blading done for ease of travel on any easement or for crane landings shall be restored to the original contour of the land, and shall be compacted to a dry density not less than the natural in-place dry density of the surrounding earth. The use of water may be required to obtain the required density. Topsoil shall be stockpiled and spread on cuts prior to completion of work.
H. GEOLOGIC INVESTIGATIONS:
The Geotechnical Engineering Report for Kofa Substation prepared by Desert Earth Engineering, dated August 1, 1992 and the Geotechnical Engineering Report for Dome Tap prepared by Terracon Consultants, Inc., Project No. 65185154, dated October 25, 2018 are incorporated into these Project Specifications as a requirement for design and construction of this project. The reports are included as Appendix B and C respectively.
Samples and cores of recovered material were not retained. Bidders shall obtain their own samples and perform tests on the material to evaluate properties, which they believe to be significant. WAPA does not guarantee that the geologic information and records show the conditions that will be encountered in performing the work, but only that the geologic information and records show conditions encountered at the particular point and time the information and records were obtained.
The geologic information may not indicate variations, such as those caused by seasonal fluctuations in rainfall and other factors, which may affect the water level. The Contractor shall determine the nature of material to be excavated, the difficulties of making and maintaining required excavations, and doing other work affected by geology and ground water elevations at the worksite.
Due to the presence of groundwater and loose subsurface soils, caving potential of uncased foundations is high. Temporary casing for drilled shaft foundations is required. Refer to Geotechnical Engineering Report, Appendix B, for more information on drilled shaft construction considerations.
I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
The Contractor shall make arrangements and provide all electric power for construction purposes.
Provide necessary transmission lines, distribution circuits, transformers and other electrical equipment for distributing the power to the places of use. At contract completion, remove temporary electrical equipment and distribution lines.
J. WATER FOR CONSTRUCTION PURPOSES:
The Contractor shall furnish water for construction purposes. Make arrangements for obtaining the water, and provide for conveying the water to the points of use.
K. SAFETY PROFESSIONAL:
1. SAFETY:
a. Contractor’s Safety and Health Program: The Contractor shall submit a Safety and health program that includes all sixteen (16) requirements specified under Section 1.4 of the construction standards no less than twenty-days prior to start of field construction operations at the jobsite.
b. In performing the work required by this contract, the Contractor shall comply with all applicable Federal, State and local safety, health, or industrial safety codes, including the latest effective standards promulgated by the Secretary of Labor for the Department of Labor and Health Administration, Safety and Health Standards (29 CFR 1910), and the Construction Safety and Health regulations promulgated under Section 107 of the Contract Work Hours and Safety Standards Act (29 CFR 1926). If there is a conflict between the requirements of the applicable Federal, State and local safety, health, or industrial safety codes, the more stringent requirements shall prevail. The United States is liable only for negligence on the part of its employees in accordance with the Federal Government Claims Act, as amended.
c. Prior to commencing work, an onsite safety meeting shall be held with WAPA’s representatives to address and discuss safety procedures related to the work required and to discuss potential hazards and their mitigation. WAPA has the right to remove any Contractor employee that does not adhere to the safety requirements.
L. EXPLOSIVES AND BLASTING:
Explosives shall not be used.
M. BURIED UTILITIES:
Prior to excavation, examine the area and determine the location of buried utilities. Utilities shall be identified with a marker denoting the type of service.
N. CONTRACTOR COMMUNICATIONS FOR WAPA USE:
Furnish, install, maintain and remove up to three (3) Contractor mobile radio units in WAPA’s inspector’s vehicles. The radio units shall be provided for WAPA’s use for the duration of the field work and shall be installed ready for use at the beginning of the Contractor’s field work. The radios shall operate on the Contractor’s normal radio frequencies; be complete with appropriate accessories and antenna, be installed, adjusted and maintained in good working condition; provide reliable 2-way communication with the Contractor’s office and field crews. When the Contractor’s field work is completed, the radios shall be removed from the inspector’s vehicles and all mounting or antenna holes shall be plugged with appropriate rubber plugs.
O. EMPLOYEE REQUIREMENTS:
In addition to the requirements listed in WAPA Construction Standard 1.4.3 all employees are restricted from wearing a headset, headphone, or other listening device, other than a hearing aid or instrument for the improvement of defective human hearing, hearing protection worn as the hazard exists, or for communication purposes while on a WAPA jobsite.
P. ELECTRICAL MINIMUM APPROACH DISTANCES:
In addition to the requirements listed in WAPA Construction Standard 1.4.9 equipment other than cranes and derricks, conductive objects, or personnel, shall not be brought closer to energized facilities than the electrical minimum approach distances established by OSHA 1926.958(b), “Materials, Handling, and Storage”. The less stringent equipment clearance distances established by OSHA 1926.960, “Working On or Near Exposed Energized Parts”, Table V-5 and Table V-6, may only be used after the Contractor has completed and submitted WAPA’s Electrical Clearance Variance form and has received the signed form in return from the COR.
Q. SUBMITTALS AND CORRESPONDENCE:
1. GENERAL: Submittals must be provided in accordance with the Construction Standards and Project Specifications. The Contractor shall furnish submittals electronically to the project SharePoint site unless otherwise specified by the COR. Submittals shall be sent to DSW Construction SharePoint Site in standard PDF or electronic CAD “*.dwg” (AutoCAD 2016) formats. All submittals shall include WAPA’s Contract No., Project Title, Transmittal/Submittal No. and corresponding Item No. Refer to the Submittal Log for the list of required submittals.
This list may not be all-inclusive, and it remains the Contractor’s responsibility to ensure conformance to the individual Specifications for possible additional submittal requirements. All submittals must be submitted with the attached cover sheet “CM-16 Transmittal Form Appendix D” in Microsoft Excel or PDF. Submittals will be rejected if the DSW Transmittal Form (Appendix G) is not attached.
In addition to the submittals required in the attached Submittal Log, the Contractor shall submit the following to DSW Construction SharePoint site:
a. Payrolls.
b. Sub-Contractor List/Forms.
c. Citizenship Forms.
d. Erosion Control Plan.
e. Environmental Submittals.
f. Request For Information (RFI.)
g. Request for Equitable Adjustment (REA).
h. Any questions comments, correspondence relevant to this project.
A submittal is required if the item is used in the performance of this contract.
2. APPROVAL TIME: Approval time for submittals shall be in accordance Section 1.D.2 with the “Commencement, Prosecution and Completion of Work” paragraph.
3. SUBMITTAL RESPONSE: WAPA will respond to submittals electronically with an “Approved”
“Received,” or “Not Approved” status, with comments as appropriate in accordance with the “Commencement, Prosecution and Completion of Work” paragraph to the email address where the submittals originated.
4. PHYSICAL SAMPLE SUBMITTALS: The Contractor shall transmit specified non electronic submittals to the following address:
Western Area Power Administration
ATTN: G5600
P.O. Box 6457 Phoenix, AZ 85005-5313
6. PROJECT PROTOCOL:
a. Electronic Correspondence:
SUBMITTAL FORMAT:
Subject Line Transmittal number, Submittal number, Subject, Applicable Standard Number, and Project Name/Number Example: Transmittal 001, Submittal 017, Steel Compression Dead Heads-Std 10, Substation
Stage 06-DE-WA000xxxx
b. Payment Requests:
PAYMENT REQUEST FORMAT:
Invoice number and Project Name/Number Example: Invoice 01, Substation Stage 06 DE-WA000xxxx
c. Certified Payrolls-Prime and Sub-Contractors:
CERTIFIED PAYROLL FORMAT:
Certified Payroll (CP), Contractor’s names, Week ending (WE), and Project Name/Number Example: CP-(Smith Inc., Bob’s Electrical), WE 09/12/15 & 09/19/15, Substation Stage 06-DE-
WA000xxx
d. Request for Information:
(REQUEST FOR INFORMATION) FORMAT:
Request for Information (RFI), Project Name/Number Example: RFI-003, Labeling Info, Substation Stage 06-DE-WA000xxxx
DIVISION 2 – SITEWORK
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Miscellaneous Sitework” includes the following:
a. Clearing and grubbing.
b. Replace and protecting existing gravel surfacing.
c. Provide a soil-applied herbicide where gravel surfacing is placed.
2. Bidding Schedule item “Remove existing transmission line” includes the following:
a. Removing electrical items, wood pole structures, and light-duty steel pole structure.
Locations described by structure number are on the existing Kofa – Dome Tap 161-kV transmission line. Items removed from the existing line may not be reused in constructing the new line.
b. Recycled materials shall be reported in accordance with Division 13 – Environmental Quality
Protection.
c. Approximate quantities are listed in Tables 2-1 and 2-2. The Contractor shall determine the actual quantities to be removed and, regardless of the quantities removed, payment will only be made for the lump sum price bid in the Bidding Schedule.
d. Remove and dispose of the conductors and overhead ground wires, complete with accessories, listed in Table 2-1.
TABLE 2-1 – ELECTRICAL ITEMS TO BE REMOVED
MATERIAL UNIT QUANTITY
Three (3) hollow core copper conductors “CU 300 178R2” from Kofa Take-Off Structure (T.KOF.DME) to Dome Tap Take-Off Structure (T.DME.KOF), complete with insulator assemblies
MI 7.5
Two (2) 3/8-inch-diameter, galvanized, high-strength steel, 7-strand overhead ground wires from Kofa Take-Off Structure (T.KOF.DME) to Dome Tap Take-Off Structure (T.DME.KOF), complete with insulator assemblies
MI 7.5
e. Remove and dispose of the wood pole structures and light-duty steel pole structures, complete with guys and anchors, listed in Table 2-2.
TABLE 2-2 – STRUCTURES TO BE REMOVED
STRUCTURE NO. STRUCTURE TYPE
101/5 60-65-60-3A-1
101/7 60-HS
102/3 60-HS
103/5 70-HTR
103/6 70-HTR
106/3 65-55-65-3A
106/7 65-HS
107/9 60-50-60-3A
STRUCTURE NO. STRUCTURE TYPE
108/8 144H-50
3. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items.
a. Excavations for foundations.
b. Disposing of excavated material.
c. Access Road Repair: Only existing access roads may be improved. Limit access road improvement and width to what is required to complete the work. The widening of any access road within a wash is not authorized. Access road improvement within Environmentally Sensitive Areas is not authorized as described in Division 13.
DIVISION 3 – CONCRETE
A. GENERAL:
1. MATERIAL:
a. Cement: Type V cement. As an alternative to Type V cement, Type IIA cement in conjunction with Class F fly ash as noted below may be used. Types are according to
ASTM C 150.
b. Compressive Strength:
(1) Transmission Line: 4000 psi minimum at 28-days for concrete foundations.
c. Water-Cement Ratio: Net water-cement ratio, exclusive of water absorbed by the aggregates, shall not exceed 0.52 by weight for NESC light loading areas.
d. Type A and D water-reducing and retarding admixtures may be used if approved by the COR.
e. Class F fly ash is required to neutralize severe alkali or ASR reaction in accordance with
ASTM C 311 (regarding test data), ASTM C 618 (regarding material), and Standard 3 – Concrete (regarding WAPA-specific requirements). Proposed concrete mix designs shall incorporate fly ash up to a maximum of 20 percent; minimum 28-day compressive strength shall be maintained in mix design.
2. TEST FOR POTENTIAL ALKALI SILICA REACTIVITY OF SAND AND COARSE AGGREGATE:
Perform tests for potential alkali silica reactivity for the sand and coarse aggregate for each source to be used. If the tests determine the aggregate(s) to be unsuitable as a concrete aggregate, a suitable source shall be obtained by the Contractor.
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule item “Concrete foundation for Government-furnished base-plated (BP) transmission line steel pole structure” include providing the following:
a. Constructing concrete foundation for one (1) steel pole structures listed in Table 3-1 and as shown on Drawing KOF-GLA 2101 with Government-furnished anchor bolt cage.
TABLE 3-1 – CONCRETE FOUNDATION
STRUCTURE NUMBER STRUCTURE TYPE & HEIGHT “H” 1 (FT)
101/5 157N-50 (BP)
1 “H” refers to the height portion of the structure’s designation, which is the distance from the top of base plate to bottom insulator attachments.
b. Concrete construction includes earthwork, formwork, reinforcement, anchor bolts, material used in concrete, curing, finishing, joints and other related work and material needed to complete the required concrete construction, in accordance with Standard 3.
c. Unwatering foundation excavations, if required.
d. Casing auger excavations, if required.
e. Measurement for quantities will be made on the basis of concrete quantities shown on Drawing KOF-GLA 2101 for the transmission line structure. Regardless of concrete quantities actually placed, payment will be based on the quantities shown on the Drawing.
DIVISION 5 – TRANSMISSION LINE STEEL POLE STRUCTURES
1. One (1) Government-furnished, weathering steel pole structure Type 157N (BP) shall be installed for this project.
2. Structure components include pole shaft sections, anchor bolt cage, nuts, washers, fixed climbing rung sections and rungs, connection bolts, nuts and locknuts. Also included (loose) are forty-four
(44) fall protection anchorage plates for every other step bolt. Steel pole shop and erection drawings will be furnished when they become available.
1. Bidding Schedule item for installing base-plated (BP) Government-furnished transmission line steel pole structure on concrete foundation includes assembling and installing the one (1) steel pole structure listed in Table 5-1 complete with the following:
a. Connection bolts, nuts and locknuts.
b. All pole shaft sections shall be jacked together in accordance with the Manufacturer’s recommendations, as shown on the steel pole shop drawings.
c. Attach rungs, fall protection anchorage plates, and install fixed climbing rung sections on the structure with bolts, nuts, and locknuts. Attach fall protection anchorage plates every two-feet on fixed climbing rung sections, alternating left and right, in accordance with Standard Drawing 41 2701.
d. Furnish and install structure number signs on both the ahead and back span side of the structure in accordance with Standard Drawing 41 9027-2. Structure numbers shall be as shown on the Plan and Profile Drawings. Two (2) structure number signs are required. The Contractor shall furnish all mounting hardware consisting of 5/8-inch-diameter bolts, nuts, and locknuts.
Structure number signs and mounting provisions for the structure shall be in accordance with the 3-digit-mile number detail on Standard Drawing 41 9027-2.
e. Install the structure listed in Table 5-1 on the concrete foundation. Refer to Division 3.
TABLE 5-1 – STRUCTURE TO BE INSTALLED ON CONCRETE FOUNDATION
STRUCTURE
NUMBER
STRUCTURE
TYPE &
HEIGHT “H” 1
(FT)
ESTIMATED
NUMBER OF
POLE SHAFT
SECTIONS
ESTIMATED
POLE BASE
DIAM. 2 (IN)
ESTIMATED
BOLT CIRCLE
DIAM. (IN)
101/5 157N-50 (BP) 2 60 78
1 “H” refers to the height portion of the structure’s designation, which is the distance from the top of base plate to bottom insulator attachments.
2 Structure pole base diameter is largest flat-to-flat dimension at the base of the pole.
DIVISION 6 – LIGHT DUTY TRANSMISSION LINE STEEL POLE STRUCTURES
1. A total of eight (8) dulled galvanized light duty, Class 2 wood equivalent, steel pole structures shall be installed for this project as follows: One (1) 3-Pole Type 40A (DE); two (2) 3-Pole Type 40T (DE) and five (5) H-Frame Type 40H (DE).
2. Structure components include pole shaft sections, cross arms, cross-bracing, connection bolts, nuts, locknuts, removable step bolts and fall protection anchorage plates for each removable step bolt. Steel pole shop drawings will be furnished when they become available.
1. Bidding Schedule item for installing direct-embedded (DE) Government-furnished light duty transmission line steel pole structures with polyurethane foam backfill include assembling and installing the eight (8) light duty, class 2 wood equivalent, steel pole structures listed in Table 6-1 complete with the following:
a. Connection bolts, nuts and locknuts.
b. All pole shaft sections shall be jacked together in accordance with the Manufacturer’s recommendations, as shown on the steel pole shop drawings.
c. All structure pole spacing shall be the 161-kV spacing dimension in accordance with Drawings 43 40A 2200, 43 40H 2200 and 43 40T 2200-1.
d. Install removable step bolts and fall protection anchorage plates from the top of each pole to 10-feet above ground line on the structures with bolts, nuts and locknuts. Install fall protection anchorage plates at each removable step bolts location in accordance with Standard Drawings 43 2217-1 and 43 2217-2.
e. Excavation and polyurethane foam backfill for direct-embedded structures: Polyurethane foam backfill construction includes earthwork, curing, finishing and other work and material needed to complete the required polyurethane foam backfill construction. Casing auger excavations and dewatering, if required. Polyurethane foam backfill shall not be placed in standing water. Polyurethane foam backfill shall be Poly-Ground and Poly-Set by Utility Structural Systems, www.utilitystructural.com or approved equal. Polyurethane foam backfill shall be installed in accordance with Manufacturer’s installation procedures with the Poly-Ground, or approved equal, being the initial polyurethane foam backfill placed at the bottom 2-feet of each structure base. The remainder of the excavation will be filled with the Poly-Set, or approved equal, polyurethane foam backfill.
(1) Grounding of the structures will be a result of the structure base encased in the
Poly-Ground, or approved equal, electrically conductive polyurethane foam backfill at the bottom 2-feet of each structure base.
f. Guys, guy hardware, fiberglass guy insulators, and guy anchors for the Type 40A (DE) and
Type 40T (DE) structures. Fiberglass guy insulators shall be used with all Type 40A (DE) and Type 40T (DE) structure guy assemblies.
g. Furnish and install structure number signs on both the ahead and back span side of all structures in accordance with Standard Drawings 41 9027-2 and 41 9030. Structure numbers shall be as shown on the Plan and Profile drawings. Ten (10) structure number signs are required for Type 40H (DE) structures, two (2) per structure. Twelve (12) structure number signs are required for Type 40A (DE) and 40T (DE) structures, four (4) per structure.
For the H-Frame Type 40H (DE) structures, the structure number signs shall be located and mounted as shown on Standard Drawing 41 9030. For the 3-Pole Type 40A (DE) and 40T (DE) structures, the structure number signs shall be located and mounted on the left and right (outside) poles as shown on Standard Drawing 41 9027-2. The Contractor shall furnish all mounting hardware consisting of 3/8-inch-diameter bolts, nuts, washers and locknuts for the Type 40H (DE) structures and 5/8-inch-diameter bolts, nuts and locknuts for the Type 40A (DE) and 40T (DE) structures.
Structure number signs and mounting provisions for Type 40H (DE) structures shall be in accordance with the 3- and 4-digit sign detail on Standard Drawing 41 9030. Structure number signs and mounting provisions for Type 40A (DE) and 40T (DE) structures shall be in accordance with the 3-digit-mile number detail on Standard Drawing 41 9027-2.
h. The Contractor shall field drill all holes in the Type 40A (DE) and 40T (DE) structures required for mounting the hardware needed for pole-to-pole ties, overhead ground wire assemblies, guy assemblies, suspension insulator assemblies, line post insulators and tension insulator assemblies in accordance with Standard Drawings 43 40A 2200, 43 40T 2200-1, and 43 40T 2200-2. Any field drilled holes shall have the galvanizing repaired in accordance with Standard 6.
i. Structure Embedment Depths for direct-embedded (DE) light duty transmission line steel pole structures shall be as listed in Table 6-1.
TABLE 6-1 – STRUCTURE EMBEDMENT DEPTHS
STRUCTURE
NUMBER
STRUCTURE
TYPE & LENGTH
“L” 1 (FT)
ESTIMATED
NUMBER OF
POLE SHAFT
SECTIONS 2
ESTIMATED
POLE SHAFT
BASE DIAM. 3
(IN)
EMBEDMENT
DEPTH 4 (FT)
101/7 40H-70 (DE) 4 18 9
102/3 40H-70 (DE) 4 18 9
103/5 40H-65 (DE) 4 17 8.5
103/6 40T-70-55-70 (DE) 6 18-16-18 9-7.5-9
106/3 40T-85-70-85 (DE) 6 20-18-20 10.5-9-10.5
106/7 40H-75 (DE) 4 18 9.5
107/9 40A-60-60-60 (DE) 6 16-16-16 8-8-8
108/8 40H-60 (DE) 4 16 8
1 “L” refers to the total length of the pole from top to base.
2 Estimated number of pole shaft sections is total per structure type.
3 Structure pole base diameter is the outside dimension at the base of the pole. Minimum foundation auger diameter shall be the manufactured pole base outside diameter plus 1-foot.
4 Embedment depth equals “L”/10 plus 2-feet”.
C. GUYS AND ANCHORS:
1. Determine number, size, and location of guys and anchors required for the Type 40A (DE) and 40T (DE) structures. Determination shall be based on criteria on Standard Drawings 41 6047, 41 6053, 41 6125 and the Plan and Profile drawings.
2. Guys, guy hardware, fiberglass insulators, guy anchors, and guy arrangement for the Type 40A
(DE) structures shall match that of the Type 3A and 3AB structure types as shown on Standard
Drawings 41 6047 and 41 6053. Guys, guy hardware, fiberglass insulators, guy anchors and guy arrangement for the Type 40T (DE) structures shall match that of the Type 3TA-1 structure type as shown on Standard Drawings 41 6047 and 41 6125.
3. Guy anchors shall be steel screw anchors, steel disc anchors, concrete anchors, or other anchor types subject to WAPA approval.
4. Structures shall not be raked.
DIVISION 9 – SUBSTATION – ELECTRICAL
A. GENERAL: Electrical equipment and material shall be as specified in Western’s “WAPA ES”
Standard Equipment Specifications, as shown on project drawings and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL, and Federal specifications and standards as applicable.
Applicable requirements shall be met under the following service conditions:
Ambient Temperatures:
Maximum ........................................................................................... +55°C Maximum 24-Hour Average .............................................................. +45°C Minimum ............................................................................................. -10°C
Elevation:
Above Mean Sea Level ................................................................. 400 Feet
*ASCE-7 Wind Load:
Minimum Basic Wind Speed .......................................................... 90 MPH Importance Factor ................................................................................ 1.15
*IEEE 693 Seismic Qualification ............................................................. Moderate
*May include support structure in accordance with STANDARD 9.1.1.2. Wind and seismic loads are nonsimultaneous.
1. Bidding Schedule for Government-furnished items (including associated supporting structures when furnished) require the Contractor to provide:
a. Unless otherwise indicated, unloading and inspecting Government-furnished items.
b. Installing Government-furnished items as shown on drawings.
c. Furnishing equipment and material not furnished by WAPA.
2. Bidding Schedule for items (not furnished by the Government) shall be furnished by the
Contractor and shall include the following:
a. Providing (furnishing and installing) bidding schedule items.
b. Furnishing equipment and material not furnished by WAPA.
c. Installing bidding schedule items as shown on drawings.
3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel.
Instrument transformers that are seismically qualified shall be 96-inches in height. If tubular steel supports are furnished, they shall be galvanized internally and externally.
4. Installation and painting of electrical equipment and material shall be provided in accordance with
Standards 9 and 12 respectively.
1. Bidding Schedule item “Bus system at Kofa Substation” includes providing equipment, material, and services required to complete the following substation installations as shown on the Drawings:
a. Outdoor strain and jumper buses. Unless otherwise specified on the Drawings, pad type terminal connectors and other fittings used on cable buses may be 360 degree radial swaged type (DMC Power, AFL Swage, or equal). If swaged type fittings are used, the fittings and installation tooling shall be furnished by the same manufacturer. Bolted fittings are not permitted.
2. Bidding Schedule item “Existing outdoor electrical equipment and material” includes removing and disposing of existing electrical equipment and material at Kofa Substation.
a. Material to be removed and disposed of is as follows:
(1) Conductor jumpers, fittings and hardware.
DIVISION 10 – TRANSMISSION LINE ELECTRICAL
A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule items for furnishing and installing conductor insulator assemblies include furnishing material and performing work and tests to furnish and install insulator assemblies shown on Drawings 41 1020, 41 1022 and 41 1024. Assembly characteristics and an estimate of material quantities for each type of structure is shown on Drawing KOF-GLA 1004.
Suspension clamps and compression dead ends for ACSS conductor shall be suitable for operation up to 250 degrees Celsius (482 degrees Fahrenheit).
2. Bidding Schedule items for furnishing and installing overhead ground wire assemblies include furnishing material and performing work and tests to provide overhead ground wire assemblies shown on Drawings 41 1018 and 41 1019. Assembly characteristics and an estimate of material quantities for each type of structure is shown on Drawing KOF-GLA 1004.
3. Bidding Schedule items for furnishing and installing optical overhead ground wire assemblies include furnishing material and performing work and tests to provide optical overhead ground wire assemblies shown on Drawing 41 1031. Assembly characteristics and an estimate of material quantities for each type of structure is shown on Drawing KOF-GLA 1004.
4. Bidding Schedule item “Furnish and install three (3) 336.4 kcmil, ACSS/MA3, 30/7, ORIOLE conductor” includes furnishing, stringing, splicing, repairing, sagging and clipping in the conductors; installing jumper loops; and furnishing and installing material to complete the conductor installations, except for material furnished and installed as a part of insulator assemblies and accessories. Furnish and install material including conductor, conductor joints, conductor repair sleeves and joint inhibitor compound required to complete conductor installation.
Measurement for furnishing and stringing conductors will be made horizontally along the centerline of the transmission line.
TABLE 10-1 – 161-KV CONDUCTOR SPECIAL CHARACTERISTICS
SPECIAL CHARACTERISTICS
Completed conductor size (circular mil) 336,400
Ultimate strength, as computed for the strength of the individual strands, not less than (LBS) 16,300
Aluminum strands Number 30
Diameter (IN) 0.1059
Steel strands Number 7
Diameter (IN) 0.1059
5. Bidding Schedule item “Furnish and install one (1) 3/8-inch-diameter, galvanized, high-strength steel, 7-strand overhead ground wires” includes furnishing, stringing, splicing, sagging and clipping in the overhead ground wires, as described; and furnishing and installing material to complete the overhead ground wire installations, except for material furnished and installed as a part of suspension and tension assemblies for overhead ground wires and accessories.
6. Bidding Schedule item “Install one (1) Government-furnished 0.465-inch-diameter, 48-fiber optical overhead ground wire” includes furnishing material and stringing, splicing, sagging and clipping in the optical overhead ground wire, to complete the Government-furnished optical overhead ground wire installations, except for material furnished and installed as a part of suspension and tension assemblies for optical overhead ground wires.
a. Install one optical overhead ground wire, as shown on Plan and Profile Drawings, between the Kofa Take-off Structure (T.KOF.DME) and Dome Tap Take-off Structure (T.DME.KOF).
The OPGW will be Government-furnished AFL 48-fiber type CC-57/465 (AFL Specification
DNO-3826).
b. Stringing shall strictly adhere to procedures recommended by the manufacturer. Ensure that the allowable bending radius limitation of the fiber optic cable is not violated at any time.
c. OPGW wires shall be routed down and attached to structures using guide clamps, as shown on Standard Drawing 41 1028. Coil approximately 75-feet of extra length, per OPGW wire, at each splice location and temporarily secure coil to coil bracket. Coiling and splicing operations are described in Division 14 – Communication Facilities.
d. Fiber optic testing is described in Division 14 – Communication Facilities.
7. Bidding Schedule item “Vibration dampers for conductors, overhead ground wires, and optical overhead ground wires” includes determining the number of vibration dampers needed, furnishing material, and performing all work, including testing, required to furnish and install vibration dampers for ACSS conductors, steel-strand overhead ground wires and optical overhead ground wires.
a. Vibration Damper Drawing KOF-GLA 1005 contains all the wire, span and tension data necessary for a damper manufacturer to provide recommendations for quantities and spacing for dampers. The Contractor should provide this specification paragraph and the damper drawing to the manufacturer for application recommendations and final spacings for attachments.
b. The Contractor’s bid shall be for either, but not both, of the stockbridge or spiral types of dampers for the overhead ground wires and optical overhead ground wires.
8. Bidding Schedule item “Hold-down weights” includes furnishing and installing hold-down weights as shown on the plan and profile drawings.
9. Bidding Schedule item “Line markers” includes furnishing and installing aerial marker balls as shown on the plan and profile drawings.
DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION
A. GENERAL REQUIREMENTS:
1. Bidding Schedule does not contain separate items for the following. Include the following items in the applicable Bidding Schedule items. Construction Standards are referenced in Division 1 – General Requirements.
a. Contractor-furnished Data (Standard 13.2). Submit quantities, reports, receipts, permits, and plans, as stated, to the COR prior to submittal of the final invoice.
b. Environmental Requirements (Standard 13.3). Comply with all appropriate Federal, State and local environmental laws and regulations.
c. Landscape Preservation (Standard 13.4).
d. Preservation of Cultural and Paleontological Resources (Standard 13.5). Do not remove or alter cultural artifacts or paleontological resources (fossils). Cultural artifacts may be of scientific or cultural importance and includes, but is not limited to, bones, pottery, glass, projectile points (arrowheads), other stone or metal tools, historic buildings and features.
Paleontological resources can be of scientific importance and include mineralized animals and plants or trace fossils, such as footprints. Both cultural and paleontological resources are protected by Federal Regulations during Federal construction projects.