21 - Atch D - Submittal Log.pdf

PDF 52 KB Posted

Attached to
Kofa Dome Tap Transmission Line Project
Solicitation number
89503120BWA000019
Issued by

About this file

This submittal log outlines the requirements and due dates for 41 submittals required from the contractor awarded the Kofa Dome Tap Transmission Line Project solicitation. Key submittals include a construction schedule due 30 days after NTP, safety and health program due 10 days prior to construction, structure erection plans prior to erection, stringing plans prior to stringing, and as-built drawings. Other notable submittals include load ratings, test results, certifications, recycling and environmental plans, drawings, and reports. Submittal items range from technical specifications and test data due prior to construction, to post-completion as-built drawings and reports. Adherence to the submittal requirements and deadlines provided in the log is necessary for the contractor to meet the requirements of the solicitation issued by the Department of Energy Western Area Power Administration for the Kofa Dome Tap Transmission Line Project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Included Contract Title: DOME TAP – GILA 161-KV TRANSMISSION LINE PROJECT Award Date: Not included Contract No.: NTP:

Contractor: Completion Date:

Western Location Submittal In

# Standards

STANDARD 1

1 Construction Schedule 1.1.4.1. (see project spec)

6 Breakdown of Contract Prices 1.1.6.1. NLT 30 days after NTP

7 Electrical Equipment & Steel Purchase Orders 1.2.3.1.

NLT 10 working days after PO award

8 Cable Location Plan w/Print of Locations 1.3.4.2 & 1.4.5.2 Prior to starting excavation

9 Acknowledgement When Stringing Over Energized Lines 1.3.5.3. Prior to starting stringing

10 Safety and Health Program 1.4.1.5.

NLT 10 days prior to start of construction

11 Copies of Certifications, Test Records & Technical Data 1.4.1.10. Prior to use

12 Load Performance Tests 1.4.1.10.(1) Prior to use

13 Crane & Aerial Lift Equipment Annual Inspection Records 1.4.1.10.(2) Prior to use

14 Brake Performance Test 1.4.1.10.(3) Prior to use

15 Test Results of Protective Ground Leads 1.4.1.10.(4) Prior to use

16 Material Safety Data Sheets 1.4.1.10.(5) Prior to use

17 Manufacturer's Load Rating For Hoists and Grips 1.4.1.10.(6) Prior to use

18 Certification of Fabricated Lifting and Rigging Devices 1.4.1.10.(7) & 1.4.11 Prior to use

19 Medical Examiner's Certificate 1.4.1.10.(8) & 1.4.3.3 Prior to use

21 Assurance of Competency in Equipment Operation 1.4.3.4. Prior to use

24 Structure Erection Plan 1.4.8.1. Prior to structure erection

27 Protective Ground Lead Test Results & Certification 1.4.14.3. Prior to use

28 Clearance, Hot Line Order & Special Work Permit Requests 1.4.15.3.

NLT 10 working days prior to starting work

29 Stringing Plan 1.4.17.3. Prior to stringing

30 HLO and Clearance Approval or Denial From Other Utilities 1.4.17.4.(3) 1) Prior to stringing

31 Transmission Line Removal Plan 1.4.18 Prior to removal

STANDARD 10

131.0 Catalog Data Sheets of Accessories & Hardware Used In Conductor & Overhead Ground Wire Installation 10.2.2.

NLT 40 days prior to material installation

132.0 Drawings of Insulator & Overhead Groundwire Assemblies and Details 10.2.2.

NLT 40 days prior to material installation

133.0 Complete Material List 10.2.2.

NLT 40 days prior to material installation

134.0 Conductor Insulator Assembly Test Reports 10.2.3.1. & 10.3.3. ASAP

135.0 Conductor Test Reports 10.2.3.2. & 10.6.1.2. ASAP

136.0 Overhead Ground Wire Test Reports 10.2.3.3. & 10.6.2.2. ASAP

137.0 Overhead Ground Wire Assemblies Test Reports 10.2.3.4. & 10.4.3. ASAP

138.0 Ground Resistance Measurements 10.2.3.5. & 10.5.3. ASAP

139.0 Vibration Damper Test Reports 10.2.3.6. & 10.6.4.3. ASAP

141.0 Optical Overhead Ground Wire Test Reports 10.2.3.8. & 10.6.3.2. ASAP

142.0 Assembly & Installation Instructions For Conductor Insulator Assemblies 10.3.4 NLT 2 weeks prior to installation

143.0 Optical Overhead Ground Wire Suspension Clamp Attachment Assemblies 10.4.2.3. Prior to use

STANDARD 13

179.0 Recycled Materials Quantity Report 13.2.1. & 13.7.2.

180.0 Products Containing Recovered Materials Report 13.2.2. & 13.8.3.

181.0 Reclaimed Refrigerant Receipt & Technician Certification 13.2.3. & 13.9.

182.0 Spill Prevention Notification & Cleanup Plan 13.2.5. & 13.11.2.

183.0 Tanker Oil Spill Prevention & Response Plan 13.2.6. & 13.11.3.

184.0 Pesticide Use Plan 13.2.7 & 13.12.3.

185.0 Treated Wood Pole & Members Recycling Consumer Info. Receipt 13.2.8. & 13.13.

186.0 Asbestos Licenses or Certificates 13.2.10. & 13.15.

187.0 Lead Paint Notices 13.2.11. & 13.16.

188.0 Water Pollution Permits 13.2.12. & 13.17.2.

189.0 PCB Test Reports 13.2.13 & 13.18.2

190.0 Oil & Oil-Filled Electrical Equipment Receipt 13.2.14. & 13.18.5.

191.0 Cleanup Work Management Plan 13.2.16. & 13.19.2.

192.0 Post Cleanup Report 13.2.17. & 13.19.7.

STANDARD 15

193.0 As-Built Drawings 15.2.6.

194.0 195.0

SUBMITTAL LOG

*Submittal required if item is used in the performance of the contract.

"T"= Submit transmittal sheet only.

"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable

Submittal Item Date Due

CUSTOM ENTRIES BELOW

TRANSMISSION LINE – ELECTRICAL

ENVIRONMENTAL QUALITY PROTECTION

DRAWINGS

GENERAL REQUIREMENTS

Submittal List