2. Events Schedule with Critical Milestones

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WAPA–DSW Solicitation No. 89503119QWA000071 Page 1 of 1

Western Area Power Administration (WAPA) – Desert Southwest Region (DSW)

EVENTS SCHEDULE WITH CRITICAL MILESTONES

Solicitation No. 89503119QWA000071 Self-Loading Pole Truck, Minimum 3–Axle 6x6 Semi Tractor

The contractor shall propose an event schedule to include, at a minimum, the following:

1. Post-Award Kick-Off Meeting within 7 days after award.

2. Pre-build Design / Drawing Submittal within 30 days after award.

3. Final design / Drawing Approval within 45 days after award. Commence Build.

4. Build Progress Monthly Updates. Provide customer with periodic updates of build progression and critical milestones via email correspondence, to include pictures.

5. Identify Inspection Points of Major Components Completed, and if applicable, at Vendor Facility.

6. Pre-Delivery Inspection of Equipment Completed at Vendor Facility.

7. Delivery to Customer.

8. On-Site Training.