LIBERTY SUBSTATION

STAGE 07 (RUDD Bay Upgrade)

Spec. No. 944 REV 01 Solicitation No. 89503118BWA000011 Amendment 0001

SECTION C

DESCRIPTION/SPECIFICATIONS

ARIZONA

SECTION C

DESCRIPTION/SPECIFICATIONS

LIBERTY SUBSTATION STAGE 07

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT

B. DESCRIPTION OF WORK

1. The Principal Components of Work

C. DESCRIPTION OF BIDDING SCHEDULE ITEM

1. Bidding Schedule item “Mobilization and preparatory work”

D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

1. Commencement, Prosecution, and Completion of the Work

2. Submittal Approval Time

3. Commencement of Control Work

4. Outage Restrictions

5. Construction Schedule Restrictions

6. Protective Ground Leads

7. Maximum Available Fault Current

8. Typical Foundations for Government-Furnished Electrical Equipment and Oil Detention

Structures

E. CONSTRUCTION SCHEDULE

1. Submittal Time

2. Format and Detail

F. MATERIAL

1. Points-of-Delivery

G. GEOLOGIC INVESTIGATIONS

H. ELECTRIC POWER FOR CONSTRUCTION PURPOSES

I. WATER FOR CONSTRUCTION PURPOSES

J. EXPLOSIVES AND BLASTING

K. BURIED UTILITIES

L. EMPLOYEE REQUIREMENTS

M. ELECTRICAL MINIMUM APPROACH DISTANCES

N. SUBMITTALS AND CORRESPONDENCE

1. General

2. Transmittal

3. Submittal Response

4. Physical Sample Submittals

5. Project Protocol

DIVISION 2 – SITEWORK

A. DESCRIPTION OF BIDDING SCHEDULE

1. Bidding Schedule item “Miscellaneous sitework”

2. Bidding Schedule item “Demolition”

3. Bidding Schedule does not contain separate items

DIVISION 3 – CONCRETE

A. GENERAL

1. Material

2. Test for Potential Reactivity of Sand and Coarse Aggregate

3. Rebar Development (LD) and Lap Length

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Concrete foundations”

2. Bidding Schedule item “Type C cable trench”

DIVISION 4 – SUBSTATION METALWORK

A. GENERAL

1. Government-Furnished Drawings

2. Measurement

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Steel structures, welded (galvanized)”

DIVISION 9 – SUBSTATION – ELECTRICAL

A. GENERAL

1. Bidding Schedule for Government-furnished items

2. Bidding Schedule for items (not furnished by the Government)

3. Associated Support Structures Provided for each Electrical Equipment Rated Above 7-kV

4. Installation and Painting of Electrical Equipment and Material

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Power circuit breaker, 230-kV, 3000 amps (Government-furnished)” ... 14

2. Bidding Schedule items “Disconnecting switch, 230-kV, 3,000 amps, and associated support structures (Government-furnished)” and “Disconnecting switch, 230-kV, 3,000 amps, with grounding blades and associated support structures (Government-furnished)”

3. Bidding Schedule items “Coupling capacitor voltage transformer, 230-kV, single-phase and associated support structures (Government-furnished)”

4. Bidding Schedule item “Outdoor bus systems”

5. Bidding Schedule item “Associated electrical equipment and material”

6. Bidding Schedule item “Existing outdoor electrical equipment and material”

7. Bidding Schedule items “Furnishing 5/c No. 10 AWG control cable” and “Furnishing 12/c

No. 10 AWG control cable”

8. Bidding Schedule items “Installing 5/c No. 10 AWG control cable” and “Installing 12/c

No. 10 AWG control cable”

9. Bidding Schedule item “Electrical testing”

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION

A. CONTRACTOR-FURNISHED DATA

1. Bidding Schedule does not contain separate items

B. SPECIAL CONDITIONS

1. BIOLOGY:

C. COMPLIANCE

SECTION 13.7--RECYCLED MATERIALS QUANTITIES

1. GENERAL

2. RECYCLED MATERIAL QUANTITY REPORT

SECTION 13.14--PREVENTION OF AIR POLLUTION

1. GENERAL

2. MACHINERY AIR EMISSIONS

3. DUST ABATEMENT

4. SULFUR HEXAFLUORIDE EMISSIONS

5. CONTRACTOR FIELD QUALITY TESTING AND SF6 HANDLING

6. CERTIFICATES OF DISPOSAL AND RECEIPTS

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT:

Construct and complete Liberty Substation (Rudd Bay) Stage 07, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; WAPA’s Construction Standards, including Standard 1 – General Requirements (September 2016), Standard 2 – Sitework (September 2016), Standard 3 – Concrete (September 2016), Standard 4 – Substation Metalwork and Transmission Line Lattice Structures (September 2016), Standard 9 – Substation – Electrical (September 2016), Standard 13 – Environmental Quality Protection (September 2016), Standard 15 – Drawings (September 2016); Standard Drawings; and these Project Specifications and Drawings.

If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.

WAPA’s Construction Standards, Standard Drawings, and Electrical Equipment Standards are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.

WAPA Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.

B. DESCRIPTION OF WORK:

1. THE PRINCIPAL COMPONENTS OF WORK include the following:

a. Installing 230-kV power circuit breaker, 230-kV disconnecting switches, and 230-kV coupling capacitor voltage transformers.

b. Providing grounding system, bus system, conduit system, insulated conductors and cables, terminal boxes, and signs.

c. Providing foundations and anchor bolts for structures, electrical equipment, and material.

Performing site work.

d. Providing galvanized steel structures.

e. Removing and disposing of electrical equipment, steel supporting structures, foundations, bus work, insulated cables, and conduits.

Paragraphs “Description of Bidding Schedule Items” in Divisions – 1, 2, 3, 4, 9, and 13 describe the work to be performed.

The work is located in Maricopa County, approximately 3-miles north of Liberty, Arizona, as shown on Drawing LIB 0015.

C. DESCRIPTION OF BIDDING SCHEDULE ITEM:

1. Bidding Schedule item “Mobilization and preparatory work” includes the following:

a. Performing mobilization and preparatory work in accordance with Section H of the contract clauses.

b. Prepare and submit a Construction Schedule for approval, no later than 15 days after receipt of NTP. Furnish a Safety and Health Program for approval, no later than 10 days prior to the start of construction.

c. Providing jobsite office trailer and the items listed below. Prior to any jobsite work, the

Contractor shall provide the office trailer for the exclusive use of WAPA.

(1) Relocation: If the Contractor changes the location of his office during the term of the contract, then the Contractor shall also move the mobile office trailer provided for WAPA, simultaneously with the transportation of his own unit.

(a) Installation: Install anchors and tie-downs for the trailer complying with local, State and Federal regulations. The office trailer shall be grounded. Entry points to the trailer shall be provided with stairways complying with OSHA (29 C.F.R. 1926.1052).

(b) Office Space Requirements:

1) Size and Arrangement: At least 250-square-feet (minimum) consisting of two (2) separate rooms (one (1) office and one (1) larger workroom).

2) Heating and Cooling: Heating and cooling unit sized to provide adequate heating and cooling.

3) Lighting and Electrical: Adequate lighting and 120 V electrical outlets.

4) Utilities: Make all arrangements and pay all costs for providing utilities, including potable drinking water, electrical power, and heating and cooling energy.

5) Toilet Facilities: Toilet facilities shall be provided in the immediate vicinity of the office and shall be maintained.

(2) Emergency Equipment: Provide and maintain the following emergency equipment:

(a) First aid kit that meets or exceeds ANSI Z308.1 (latest version) Class B, Type IV. Mount to the wall inside the workroom.

(b) Dry chemical fire extinguishers, Classified 4-A:60-B:C, one (1) to be located inside each entrance to the trailer.

(3) Window Coverings: Provide adjustable mini-blinds.

(4) Office Furniture: Provide good quality, fully functional, office furniture as follows:

QUANTITY DESCRIPTION

5 Folding Office Chairs 1 Office desk (30-inches by 60-inches minimum).

2 Office tables (30-inches by 60-inches minimum).

1 Five-drawer file cabinet.

1 Bookcase (30-inches by 13”-inches by 48-inches).

12 “Plan Hold” binders No. 1CB-24 (including one (1) plan rack).

D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:

1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF THE WORK: See FAR 52.211-10 in Section F of the solicitation/contract.

2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 30-calendar days for review of drawings or data submitted for approval.

3. COMMENCEMENT OF CONTROL WORK: Do not perform any control board or outdoor equipment wiring until receipt of Government-furnished wiring diagrams. WAPA will furnish outdoor wiring and schematic diagrams no sooner than December 01, 2018. Control board wiring and schematic diagrams will be furnished no sooner than December 01, 2018. Include these restrictions in the Construction Program.

4. OUTAGE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage restrictions shall apply:

a. One continuous outage may be taken on the Transfer Bus, Bus Tie bay, and Westwing Line bay starting on January 7, 2019 and ending on March 1, 2019.

b. One continuous outage may be taken on the Rudd Line and Shunt Capacitor bays starting on March 4, 2019 and ending on April 26, 2019.

c. Main Bus outages not exceeding 8 hours in duration may be taken to disconnect the Bus Tie/Westwing Line bays, reconnect the Bus Tie/Westwing Line bays, disconnect the Rudd Line/Shunt Capacitor bays, and reconnect the Rudd Line/Shunt Capacitor bays.

5. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply:

a. Contractor shall complete cable trench modifications before installing new control and power cables.

b. Contractor shall install new control cables, complete insulation testing (megger testing), and complete terminations of the new cables at outdoor equipment a minimum of two weeks prior to the end of each scheduled outage to allow time for WAPA personnel to complete terminations in existing control boards.

6. PROTECTIVE GROUND LEADS: See WAPA Construction Standards, Standard 1 “General

Requirements”, Section 1.4.14.3(1).

7. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the following:

a. The maximum available fault current in the 230-kV area is 35,010 amps and the X/R ratio is 11.3 prior to completing construction and 35,010 amps and the X/R ratio is 11.3 after completing construction.

b. A minimum of 1 (one) 4/0 AWG grounds shall be used in the 230-kV area.

8. TYPICAL FOUNDATIONS FOR GOVERNMENT-FURNISHED ELECTRICAL EQUIPMENT

AND OIL DETENTION STRUCTURES: Typical foundations are shown in Drawing LIB 2314.

WAPA will design these foundations after receipt of the seismic report and informational drawings and data, including the seismic report from the equipment manufacturer. WAPA will forward the revised construction drawings for these foundations no later than 45-days prior to the “NLT” delivery date listed in the, “Material” section. If the “NLT” delivery date is adjusted by WAPA, forwarding of revised foundation construction drawings will be automatically adjusted in a like manner.

E. CONSTRUCTION SCHEDULE:

1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer (CO) within 30-calendar days after date of Notice to Proceed.

2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.

F. MATERIAL: Furnish all material for completing the work, except material furnished by WAPA as listed below:

ITEM

ESTIMATED

WEIGHT

(LBS)

ESTIMATED

DELIVERY

DATE

ESTIMATED

COST

1. One (1) 3-phase, power circuit breaker, 230-kV, 3,000 amp 15,000 ea Onsite at Parker

Substation $266,000 ea

2. Disconnecting Switches:

a. Four (4) 3-phase, 230-kV, 3,000 amp and support structure

10,000 ea NST 12-1-18 NLT 12-31-18 $32,000 ea

b. One (1) 3-phase, 230-kV, 3,000 amp with ground blades and support structure

10,000 ea NST 12-1-18 NLT 12-31-18 $45,000 ea

3. Two (2) single-phase coupling capacitor voltage transformer, 230-kV with supports

1,500 ea NST 9-17-18 NLT 10-15-18 $15,000 ea

NST – No sooner than.

NLT – No later than.

1. POINTS-OF-DELIVERY (Government Furnished Material): Material item One (1) is onsite at the

Parker Substation. The Contractor shall transport item number one from Parker Substation to the Liberty Substation. Material items two (2) and three (3) will be delivered to Liberty Substation.

The Contractor shall load and unload the material to the jobsite.

Parker Dam and Parker substation are approximately eighteen (18) miles north of the town of Parker, Arizona on Highway 95. The substation is on the California side of the Colorado River.

Follow signs to the dam. Accessing the substation from the Arizona side of the Colorado River requires crossing the dam itself. Size, weight, and time restrictions may be imposed. The contractor is advised to check with Parker Dam security officials to determine if any restrictions will be in effect at the time the circuit breaker is picked up. The substation may also be accessed from the California side of the Colorado River with potentially fewer restrictions.

The Contractor shall inspect the equipment and report any damages to the COR within 10-calendar days after receipt.

G. GEOLOGIC INVESTIGATIONS:

The 8000-series geologic logs of subsurface explorations included in the “Drawings” Division constitute the information and records of geologic investigations for the work. Locations of subsurface investigations are shown on the Drawings.

Samples and cores of recovered material were not retained. Bidders shall obtain their own samples and perform tests on the material to evaluate properties, which they believe to be significant. WAPA does not guarantee that the geologic information and records show the conditions that will be encountered in performing the work, but only that the geologic information and records show conditions encountered at the particular point and time the information and records were obtained.

The geologic information may not indicate variations, such as those caused by seasonal fluctuations in rainfall and other factors, which may affect the water level. The Contractor shall determine the nature of material to be excavated, the difficulties of making and maintaining required excavations, and doing other work affected by geology and ground water elevations at the worksite.

H. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:

Limited single-phase or three-phase power at approximately 120/240 volts nominal is available without charge from receptacles or panelboards located throughout the substation. If this power is not suitable for construction purposes, the contractor shall furnish his own power. Coordinate with the Contracting Officer’s Representative (COR) for establishing such service.

I. WATER FOR CONSTRUCTION PURPOSES:

Furnish water for construction purposes. Make arrangements for obtaining the water, and provide for conveying the water to the points of use.

J. EXPLOSIVES AND BLASTING:

Explosives shall not be used.

K. BURIED UTILITIES:

Prior to excavation, the Contractor shall examine the area and determine the location of buried utilities.

Utilities shall be identified with a marker denoting the type of service.

L. EMPLOYEE REQUIREMENTS:

In addition to the requirements listed in WAPA Construction Standard 1.4.3 all employees are restricted from wearing a headset, headphone, or other listening device, other than a hearing aid or instrument for the improvement of defective human hearing, hearing protection worn as the hazard exists, or for communication purposes while on a WAPA jobsite.

M. ELECTRICAL MINIMUM APPROACH DISTANCES:

In addition to the requirements listed in WAPA Construction Standard 1.4.9 equipment other than cranes and derricks, conductive objects, or personnel, shall not be brought closer to energized facilities than the electrical minimum approach distances established by OSHA 1926.958(b), “Materials, Handling, and Storage”. The less stringent equipment clearance distances established by OSHA 1926.960, “Working On or Near Exposed Energized Parts”, Table V-5 and Table V-6, may only be used after the Contractor has completed and submitted WAPA’s Electrical Clearance Variance form and has received the signed form in return from the COR.

N. SUBMITTALS AND CORRESPONDENCE:

1. GENERAL: Submittals must be provided in accordance with the Construction Standards and Project Specifications. The Contractor shall furnish submittals electronically (i.e. e-mail), unless otherwise specified by the COR. Submittals shall be sent to DSW-G5600-CS@wapa.gov in standard PDF or electronic CAD “*.dwg” (AutoCAD 2010) formats. All submittals shall include WAPA's Contract No., Project Title, Transmittal/Submittal No., and corresponding Item No.

Refer to the Submittal Log for the list of required submittals. This list may not be all-inclusive, and it remains the Contractor's responsibility to ensure conformance to the individual Specifications for possible additional submittal requirements. All submittals must be submitted with the attached cover sheet “CM-16 Transmittal Form Appendix A” in Microsoft Excel or PDF. Submittals will be rejected if CM-16 Form is not attached.

2. TRANSMITTAL: The Contractor shall transmit submittals to the Construction Office.

In addition to required submittals, the Contractor shall submit the following information electronically to DSW-G5600-CS@wapa.gov:

mailto:DSW-G5600-CS@wapa.gov mailto:DSW-G5600-CS@wapa.gov

a) Payrolls

b) Sub-Contractor List/Forms

c) Citizenship Forms

d) Erosion Control Plan

e) Environmental Submittals

f) Request For Information (RFI)

g) Request for Equitable Adjustment (REA)

h) Any questions, comments, correspondence relevant to this project.

A submittal is required if the item is used in the performance of the contract.

Desert Southwest Region

ATTN: G5600

Email: DSW-G5600-CS@wapa.gov

3. SUBMITTAL RESPONSE: WAPA will respond to submittals electronically with an “Approved” of

“Not Approved” status, with comments as appropriate in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph to the email address where the submittals originated.

4. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e. brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a digital cover letter outlining the physical sample submittal prior to sending the sample(including tracking data when applicable), and shall deliver physical specimens to:

Western Area Power Administration

ATTN: G5600

615 S. 43rd Avenue Phoenix, AZ 85009-5313

5. PROJECT PROTOCOL:

a. Electronic Correspondence:

EMAIL SUBMITTAL FORMAT:

Subject Line in Email Submittal number, Subject, Applicable Standard Number, Project Name/Number, and Contract Number Example: Submittal 017, Steel Compression Dead Heads-Std 10, [NAME] Substation Stage

XX, DE-WA000XXXX-XXX

b. Payment Requests:

EMAIL PAYMENT REQUEST FORMAT:

Invoice number and Project Name/Number and Contract Number Example: Invoice 01, [NAME] Substation Stage XX, DE-WA000XXXX-XXX

c. Certified Payrolls-Prime and Sub-Contractors:

EMAIL CERTIFIED PAYROLL FORMAT:

Certified Payroll (CP), Contractor’s names, Week ending (WE), and Project Name/Number, and Contract Number

Example: CP-(Smith Inc., Bob’s Electrical), WE 09/12/15 & 09/19/15, [NAME] Substation Stage XX, DE-WA000XXXX-XXX

d. Request for Information:

EMAIL (REQUEST FOR INFORMATION) FORMAT:

Request for Information (RFI), Project Name/Number, and Contract Number Example: RFI-003, Labeling Info, [NAME] Substation Stage XX, DE-WA000XXXX-XXX

DIVISION 2 – SITEWORK

A. DESCRIPTION OF BIDDING SCHEDULE:

1. Bidding Schedule item “Miscellaneous sitework” includes the following:

a. Replacing and protecting existing gravel surfacing.

b. Providing a soil-applied herbicide where gravel surfacing is placed.

2. Bidding Schedule item “Demolition” includes the following:

a. Completely removing and disposing of concrete foundations designated on Existing

Installation Drawings LIB 2003, LIB 2006-1, and LIB 2006-2.

b. Removing and disposing of the following structures and platforms:

(1) One (1) 230-kV Coupling Capacitor Support (LIB 2038) located on foundation CCS1.

(2) Two (2) 230-kV Switch Supports –Type I (LIB 2031) located on foundations SS2.

(3) Two (2) 230-kV Switch Supports – Type I (LIB 2031) located on foundations SS3.

(4) One (1) 230-kV Switch Support – Type II (LIB 2031) located on foundations SS7.

(5) Associated equipment and switch operating platforms.

Existing Installation Drawings are included showing typical structure details.

3. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items.

a. Excavations for foundations, structures, and trenches.

b. Placing and compacting earth material and backfill.

c. Providing gravelfills under concrete foundations as shown on the Drawings.

d. Modifications to and disposal of existing concrete cable trench.

e. Disposing of excavated material. Material from excavations not suitable or required for earthwork shall be removed from the substation and access road right-of-way. The Contractor shall make arrangements required for disposal of waste material in an approved landfill.

f. Expansion anchors and adhesive anchors.

DIVISION 3 – CONCRETE

A. GENERAL:

1. MATERIAL:

a. Cement: Type V cement. Type IIA cement in conjunction with Class F fly ash as noted below is acceptable. Types are according to ASTM C 150.

b. Compressive Strength: 4500 psi at 28-days for concrete.

c. Water-Cement Ratio: Net water-cement ratio, exclusive of water absorbed by the aggregates, shall not exceed 0.50 by weight for NESC light loading areas.

d. Type A and D water-reducing and retarding admixtures may be used if approved by the COR.

e. Class F fly ash is required to neutralize severe alkali or ASR reaction in accordance with

ASTM C 311 (regarding test data), ASTM C 618 (regarding material), and Standard 3 – Concrete (regarding WAPA-specific requirements). Proposed concrete mix designs shall incorporate fly ash up to a maximum of 20 percent; minimum 28-day compressive strength shall be maintained in mix design.

2. TEST FOR POTENTIAL REACTIVITY OF SAND AND COARSE AGGREGATE: Perform test for each source used.

3. REBAR DEVELOPMENT (LD) AND LAP LENGTH:

a. Class B lap splices apply unless noted otherwise; refer to Table 3 on Standard Drawing 01 2004-1 General Outline and Reinforcement Notes.

b. Typical closed circular tie lap splice lengths for drilled piers and columns, 4,000 - 4,500 psi normal weight concrete, unless noted otherwise, are 18-inches for No. 3 ties, 24-inches for No. 4 ties, and 30-inches for No.5 ties.

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Concrete foundations” includes the following:

a. Earthwork, formwork, reinforcement, material used in concrete, anchor bolts, curing, finishing, joints, and other related work and material needed to complete the concrete construction.

b. Concrete foundations for steel structures.

c. Concrete foundations for electrical equipment.

d. Casing auger excavations, if required.

Measurement for quantities for concrete foundations will be made on the basis of concrete quantities shown on Drawing LIB 2075. If separate quantities of formed and auger concrete for each type of foundation are shown on the Drawing, the concrete quantity shall be the total of the formed and auger concrete quantities. Regardless of the concrete quantities actually placed, payment will be based on the quantities of concrete shown on the Drawing.

2. Bidding Schedule item “Type C cable trench” includes providing concrete Type C cable trench modifications as shown on LIB 2016, complete with sandfill, concrete covers, and other accessories.

DIVISION 4 – SUBSTATION METALWORK

A. GENERAL:

1. GOVERNMENT-FURNISHED DRAWINGS: Existing shop drawings for steel structures are not available.

2. MEASUREMENT: Measurement for quantities for Bidding Schedule items “Steel structures, welded (galvanized)” will be made on the basis of weights calculated in accordance with LRFD, “AISC Code of Standard Practice for Steel Buildings and Bridges”, except that weights for nonrectangular shapes and plates are to be based on actual detailed dimensions.

a. Steel structure weights, calculated as noted above, shall be shown on the Contractor-furnished final shop drawings, and payment will be based thereon. Steel estimated weights are shown on the specifications drawings for the structures requiring approval drawings as noted in the Bidding Schedule items “Steel structures, welded (galvanized)”.

1. Bidding Schedule item “Steel structures, welded (galvanized)” includes providing the following:

a. *Twenty-Three (23) 230-kV bus poles - Type LXI.

b. *One (1) 230-kV bus pole – Type LXII.

c. One (1) double-switch operating platforms, including grating.

d. Four (4) single-switch operating platforms, including grating.

e. Equipment cabinet platforms as follows, including gratings.

(1) One (1) – Type III for the 230-kV Circuit Breaker (JW5A).

*Denotes structures requiring approval drawings.

The above material including connection bolts, nuts, washers, and lock nuts shall be galvanized.

DIVISION 9 – SUBSTATION – ELECTRICAL

A. GENERAL: Electrical equipment and material shall be as specified in Western’s “WAPA ES”

Standard Equipment Specifications, as shown on project drawings, and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL, and Federal specifications and standards as applicable.

Applicable requirements shall be met under the following service conditions:

Ambient Temperatures:

Maximum ........................................................................................... +55°C Maximum 24-Hour Average .............................................................. +45°C Minimum ............................................................................................. -20°C

Elevation:

Above Mean Sea Level ................................................................. 950-Feet

*ASCE-7 Wind Load:

Minimum Basic Wind Speed .......................................................... 90 MPH Importance Factor ................................................................................ 1.15

Contractor furnished electrical equipment shall meet the requirements of IEEE Standard 693-2005, and the requirements of the Moderate seismic qualification level. If the equipment was qualified including its support structure, the provided structure shall exactly match the structure identified within the seismic qualification documents. Individual equipment paragraphs include requirements regarding support structures. Wind and seismic loads are nonsimultaneous.

1. Bidding Schedule for Government-furnished items (including associated supporting structures when furnished) require the Contractor to provide:

a. Unless otherwise indicated, unloading and inspecting Government-furnished items.

b. Installing Government-furnished items as shown on drawings.

c. Furnishing equipment and material not furnished by WAPA

2. Bidding Schedule for items (not furnished by the Government) shall be furnished by the

Contractor and shall include the following:

a. Providing (furnishing and installing) bidding schedule items.

b. Furnishing equipment and material not furnished by WAPA.

c. Installing bidding schedule items as shown on drawings.

3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel.

Instrument transformers that are seismically qualified shall be 96-inches in height. If tubular steel supports are furnished, they shall be galvanized internally and externally.

4. Installation and painting of electrical equipment and material shall be provided in accordance with

Standards 9 and 12 respectively.

1. Bidding Schedule item “Power circuit breaker, 230-kV, 3000 amps (Government-furnished)”:

DESIGNATION JW5A

Manufacturer Mitsubishi

Model Number 200-SFMT-63F

Type SF6 gas Nominal Voltage Rating (kV) 230

Maximum Voltage Rating (kV) 245

Continuous Current (Amps) 3,000

Short Circuit Fault Rating (KA) 63

Rated Interrupting Time (cycles) 3

Number CT’s per Bushing 3

Estimated Weight of 3-pole Breaker without SF6 Gas(LBS)

11,264

Approximate SF6 Gas Weight (LBS) 201

a. The Contractor shall transport the equipment from Parker Substation to the Liberty 230-kV yard. Contractor personnel shall inspect the power circuit breaker at Parker Substation for possible damage prior to transporting to Liberty Substation. Report any damage to Western’s COR. SF6 gas filling shall be done by the Contractor.

b. Two (2) sets of spare parts consisting of two (2) trip coils and one (1) close coil were furnished with the breakers. One (1) set of tools and appliances were also furnished. The spare parts shall be transported to Liberty substation, offloaded, and stored there.

2. Bidding Schedule items “Disconnecting switch, 230-kV, 3,000 amps, and associated support structures (Government-furnished)” and “Disconnecting switch, 230-kV, 3,000 amps, with grounding blades and associated support structures (Government-furnished)” includes furnishing all equipment and material not furnished by Western and installing the Government-furnished switches and support structures in accordance with the manufacturer’s instructions.

DESIGNATION WW4A, YW4B,

WW5A, WW5B YW4A-ZW4A

Type

3 pole, single throw, outdoor, group operated, vertical break, 3 pole, single throw, outdoor, group operated, vertical break with ground blades

DESIGNATION WW4A, YW4B,

WW5A, WW5B YW4A-ZW4A

System Nominal Voltage Rating (kV) 230 230

Rated Maximum Voltage (kV) 245 245

Basic Impulse Insulation Level (kV) 900 900

Continuous Current Rating (Amps) 3,000 3,000

Short-Time (3 seconds) Symmetrical Current Rating (kA)

63 63

Peak Withstand Current (kA @ 60Hz) 164 164

Grounding Blades None Yes

Standard Arcing Horns Yes Yes

Switch Operator Type Manual Worm-Gear Operator

Manual Worm-Gear Operator

Phase Spacing (FT) 11’-0” 11’-0”

Height of Support Structure (FT) 8’-6” 8’-6”

Mounting Position Horizontal Horizontal

Insulator Technical Reference No.

304 or 308 (as required by seismic qualifications)

304 or 308 (as required by seismic qualifications) Control Circuit Voltage Not Required Not Required

Auxiliary Switch Not Required Not Required

Key Interlock No ZW4A interlocked with YW4B

Minimum Switch Continuous Current Interrupting Rating (Amps)

N/A N/A

* Approximate mounting height.

a. The equipment supplier will unload the switches, support structures and insulators from the trucks. Contractor personnel shall inspect them for possible damage during shipment or transportation and report any damage to WAPA’s COR.

b. Spare insulators and spare parts will be furnished with switches. (A complete list will be included with the switches’ instruction books).

c. The Contractor shall deliver the spare insulators and spare parts to permanent storage locations at Liberty Substation as directed by the COR.

d. The manufacturer will provide erection engineering services. The Contractor shall make arrangements with the COR to schedule the services of the erecting engineer.

3. Bidding Schedule items “Coupling capacitor voltage transformer, 230-kV, single-phase and associated support structures (Government-furnished)” includes furnishing all equipment and material not furnished by WAPA, and installing the Government-furnished coupling capacitor voltage transformers and associated support structures.

DESIGNATION

(SINGLE-PHASE) VW4A1, VW5B1

Type

Single-phase, outdoor, 60 Hz, support structure seismically tested with CCVT qualified to

IEEE 693

Manufacturer GE/Alstom Nominal System Voltage (kV) 230

Maximum System Voltage (kV) 245

Basic Impulse Insulation Level (kV) 1050

Phase-to-Ground Withstand Voltage (kV)

Performance Reference Voltage (kV)

Primary to Secondary Ratios

1,200/2,000 : 1 1,200/2,000 : 1

ANSI Accuracy Rating 0.3% M, W, X, Y, Z

Output Rating (minimum VA) 200

Mounting Base Support Structure Height (INS) 96

The equipment supplier will unload the coupling capacitor voltage transformers. Contractor personnel shall inspect the coupling capacitor voltage transformers for possible damage during shipment or transportation and report any damage to WAPA’s COR.

4. Bidding Schedule item “Outdoor bus systems” includes providing material and services required to complete the outdoor strain buses, jumper buses, rigid buses, and overhead ground wire installations. Unless otherwise specified on the Drawings, splices, elbows, pad type terminal connectors, and other fittings used on rigid or cable buses may be 360 degree radial swaged type (DMC Power Bus & Cable Connectors and Swage System, AFL Swage system, or equal.

If swaged type fittings are used, the fittings and installation tooling shall be furnished by the same manufacturer. Bolted fittings are not permitted. Insulators shall use industry standard 5-inch (or 7-inch) base cap bolt circles in lieu of WAPA Standard 9.3.1.1.3.2 and Drawing 31 1081.

5. Bidding Schedule item “Associated electrical equipment and material” includes providing equipment, material, and services required to complete the following substation installations as shown on the Drawings:

a. Substation Grounding System: Includes providing material and services required to complete the substation grounding system. Unless otherwise specified on the Drawings, splices, crosses, tees, and other fittings used on grounding system may be compression type (DMC Power Swage system, AFL Swage system, or equal. If swaged or compression type fittings are used, the fittings and installation tooling shall be furnished by the same manufacturer. Cable trench grounding shall be two (2) 19 No. 8 copper-clad steel conductors in lieu of two (2) 2/0 AWG copper conductor as shown on Drawing 31 1061.

b. Electrical Conduit System: Includes providing material and services required to complete the substation conduit system including embedded and exposed conduit. Conduit entering the cable trench with a 90 degree bend is allowed to be Schedule 40 PVC as shown on Drawing 31 1006. All other 90 degree bends shall be fiberglass. A detectable warning tape shall be installed directly above each conduit run and located 12-inches below finished grade. All conduits shall have sealing compound installed at both ends. Rigid metal conduit in direct contact with earth shall be half-lapped with 10 mil corrosion protection tape. Rigid metal risers shall be so lapped to six (6) inches above finished grade. Informational Drawings and data are not required for this item.

c. Insulated Conductors: Includes all insulated conductors and cables except 5/c and 12/c No.

10 AWG control cables, which are covered under separate Bidding Schedule items. The Contractor shall terminate both ends of all cables.

d. Terminal Boxes: Terminal boxes’ internal components arrangements shown on

Drawings 31 1085 and 31 1086 are typical and the Contractor shall provide internal components for Type A terminal box configuration. Actual internal arrangements will be determined by the COR.

e. Substation Signs:

(1) Phase Identification Signs (31 1000): One (1) on each phase at both ends of main buses, at each high voltage circuit terminating structure, and one (1) on each phase of an instrument transformer.

(a) Phase A – 2 required.

(2) Equipment Identification Signs (31 1000): Lettering on the signs shall be as shown on Drawing LIB 1140.

6. Bidding Schedule item “Existing outdoor electrical equipment and material” includes constructing a temporary storage facility within Liberty Substation to hold existing electrical equipment containing oil. The temporary storage facility shall be in accordance with the standards in a location determined by the COR. Bidding Schedule item “Existing outdoor electrical equipment and material” also includes removal and disposal of existing electrical equipment and material.

a. Material to be removed and disposed of is as follows:

(1) Replaced equipment signs.

(2) One (1) 230-kV, three-phase power circuit breaker designated JW5A.

(3) Four (4) 230-kV three-phase disconnecting switches designated WW4A, YW4B, WW5A and WW5B.

(4) One (1) 230-kV three-phase disconnecting switch with ground blades designated

YW4A-ZW4A.

(5) Terminal boxes associated with instrument transformers VW4A1 and VW5B1.

(6) Aluminum tubing, aluminum conductors, hardware, fittings, control and power cables, conduits and grounding conductors associated with the above circuit breaker and instrument transformers. Control cables shall be completely removed from the outdoor equipment to the control boards in the service building. Power cables shall be removed from the outdoor equipment to their sources. All cables shall be removed using due care and caution to avoid damaging other cables in cable trenches.

b. Material to be placed into the temporary storage facility for disposal by others:

(1) Two (2) single-phase coupling capacitor voltage transformers designated VW4A1 and

VW5B1.

7. Bidding Schedule items “Furnishing 5/c No. 10 AWG control cable” and “Furnishing 12/c No. 10 AWG control cable” include furnishing 5/c No. 10 and 12/c No. 10 AWG control cable, respectively in accordance with Drawing LIB T600.

8. Bidding Schedule items “Installing 5/c No. 10 AWG control cable” and “Installing 12/c

No. 10 AWG control cable” include installing 5/c No. 10 and 12/c No. 10 AWG control cable, respectively in accordance with Drawings LIB T600 and LIB 4000. The Contractor shall label all control cables according to Drawing LIB T600 and Standard 9 – Substation Electrical, paragraph 9.2.3.4.(10). The Construction Contractor shall terminate control cable at the outdoor equipment and new switch board sections. WAPA will terminate control cable in the existing switch boards.

The Contractor shall coil an additional ten feet of control cable in the cable trench for each electrical device and sufficient cable in the control building to reach the furthest wall.

9. Bidding Schedule item “Electrical testing” includes providing electrical testing in accordance with Standard 9, paragraph 9.1.2 Acceptance Tests - Method B.

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION

A. CONTRACTOR-FURNISHED DATA:

1. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items:

a. Environmental Quality Protection includes the following.

(1) Environmental Requirements (see Section 13.3 of the Standards).

(2) Landscape Preservation (see Section 13.4 of the Standards).

(3) Preservation of Cultural and Paleontological Resources (see Section 13.5 of the

Standards).

(4) Noxious Weed Control (see Section 13.6 of the Standards).

(5) Recycled Material Quantities (see Section 13.7 of the Standards).

(6) Use of Recovered and Biobased Material Products (see Section 13.8 of the

(7) Disposal of Waste Material (see Section 13.9 of the Standards).

(8) Contractor’s Liability for Regulated Material Incidents (see Section 13.10 of the

(9) Pollutant Spill Prevention, Notification, and Cleanup (see Section 13.11 of the

(10) Pesticides (see Section 13.12 of the Standards).

(11) Treated Wood Utility Poles and Crossarms Recycling or Disposal (see Section 13.13 of the Standards).

(12) Material with Lead-based Paint (see Section 13.16 of the Standards).

(13) Testing, Draining, Removal, and Disposal of Oil-filled Electrical Equipment (see Section 13.18 of the Standards).

(14) Conservation of Biological Resources (see Section 13.20 of the Standards).

B. SPECIAL CONDITIONS:

1. BIOLOGY:

a. Migratory Bird Treaty Act (MBTA):

(1) If the work is completed before February 15, 2019, there are no special conditions required.

(2) If the work is not completed by February 15, 2019 (whether beginning or on-going), the Contractor shall immediately notify the COR, who will coordinate with WAPA’s Environmental Department, to perform an inspection at Liberty substation.

(3) If active nests are found, WAPA’s Environmental Department will establish a 40-feet avoidance area around the active nest. The Contractor shall suspend all work within the 40-feet avoidance area until directed to proceed by the COR.

C. COMPLIANCE:

SECTION 13.7--RECYCLED MATERIALS QUANTITIES

1. GENERAL: All materials generated from the project that can be recycled, shall be recycled.

Record quantities of material by category that is salvaged, recycled, reused, or reprocessed, including:

a. Transformers, Breakers: Weight without oil.

b. Aluminum Conductor – Steel Reinforced (ACSR): Weight in pounds or tons.

c. Steel: Weight in pounds or tons.

d. Aluminum: Weight in pounds or tons.

e. Copper: Weight in pounds or tons.

f. Other Metals: Weight in pounds or tons.

g. Oil: Gallons (separate by type - less than 2 ppm PCB, 2 to 50 ppm PCB, and 50 or greater ppm PCB).

h. Gravel, Asphalt, or Concrete: Weight in pounds or tons.

i. Batteries: Weight in pounds.

j. Treated Wood Utility Poles and Crossarms: Weight in pounds.

k. Wood construction material: Weight in pounds.

l. Cardboard: Weight in pounds.

m. Porcelain Insulators: Weight in pounds.

2. RECYCLED MATERIAL QUANTITY REPORT: Submit quantities (pounds or metric tons) of all recycled material by category to the COR within 30 days of recycling and prior to submittal of final invoice.

SECTION 13.14--PREVENTION OF AIR POLLUTION

1. GENERAL: Ensure that construction activities and the operation of equipment are undertaken to reduce the emission of air pollutants. The Contractor shall complete and submit a Dust Control Permit Application Form and a Dust Control Plan Application Form plus pay any permit fees to Maricopa Air Quality Department before construction activities begin within Maricopa County.

Submit the appropriate fee (depending on total surface area disturbed) with your Dust Control Permit and Plan Application Forms. The Contractor shall submit a copy of Permit and Plan application Forms to the COR 14-days prior to the start of work.

For additional information http://www.maricopa.gov/1919/Dust-Control-Permit-Applications- Rule-31.

2. MACHINERY AIR EMISSIONS: The Contractor and subcontractor machinery shall have, and shall use the air emissions control devices required by Federal, State or Local Regulation or ordinance.

3. DUST ABATEMENT: Dust shall be controlled as listed in the Maricopa County’s Fugitive Dust

Guidance Rule 310. The Contractor shall be familiar with Rule 310 and the Dust Control handbook. Oil shall not be used as a dust suppressant. Dust suppressants shall be approved by the COR prior to use.

4. SULFUR HEXAFLUORIDE EMISSIONS:

a. General: The Contractor shall record quantities of SF6, including:

(1) Nameplate capacity in pounds of SF6 containing equipment.

(2) Record pounds of SF6 stored in containers, before transferring into energized equipment.

(3) Record pounds of SF6 left in containers, after transferring into energized equipment.

(4) Pounds of SF6 purchased from equipment manufacturers or distributors.

(5) Pounds of SF6 returned to suppliers.

(6) Scales used to weigh cylinders must be accurate to within +/- 2 pounds and must have current calibration sticker.

5. CONTRACTOR FIELD QUALITY TESTING AND SF6 HANDLING:

a. The Contractor shall test all functions to verify correct operation and conduct a leak test. No

SF6 gas leakage shall be allowed from any equipment or storage containers.

b. Atmospheric venting of SF6 gas is not allowed.

c. The Contractor shall furnish SF6 gas in cylinders shipped under a DOT hazardous materials Bill of Lading. The cylinders shall meet all Compressed Gas Association (CGA) packaging requirements and shall be marked, labeled, and in all ways prepared for shipment in compliance with Federal, State and local transportation regulations. The cylinders and other packaging shall be reusable for returning the cylinders and excess SF6 gas to the Contractor. Gas cylinders furnished for initial filling of equipment will remain the property of the Contractor and the Contractor shall be responsible for removal of the cylinders and unused gas associated with those cylinders, from Western property. A Contractor’s representative will be onsite, the Contractor shall remove all cylinders before end of contract.

6. CERTIFICATES OF DISPOSAL AND RECEIPTS:

a. The Contractor can use Western’s Reporting Form for reporting quantities listed above.

b. The Contractor shall provide receipts of SF6 gas returned to supplier.

c. The Contractor shall submit SF6 gas reporting forms and copies of receipts to the COR prior to submittal of final invoice.

Message from the Administrator

At Western, we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our contractors who provide products or services to Western. In performing work for Western, all contractors must make the right decisions to ensure that the work environment is as safe as possible.

Our safety program is based on four points:

Safety procedures or common sense must be applied by each

Federal and contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.

Employees and contractors must believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.

Managers and supervisors must lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.

Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.

By integrating these principles into every task we take, together we can ensure Western is a safe place to work.

Mark A. Gabriel Administrator

DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
B. DESCRIPTION OF WORK:
1. THE PRINCIPAL COMPONENTS OF WORK include the following:
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work” includes the following:
1) Size and Arrangement: At least 250-square-feet (minimum) consisting of two (2) separate rooms (one (1) office and one (1) larger workroom).
2) Heating and Cooling: Heating and cooling unit sized to provide adequate heating and cooling.
3) Lighting and Electrical: Adequate lighting and 120 V electrical outlets.
4) Utilities: Make all arrangements and pay all costs for providing utilities, including potable drinking water, electrical power, and heating and cooling energy.
5) Toilet Facilities: Toilet facilities shall be provided in the immediate vicinity of the office and shall be maintained.
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF THE WORK: See FAR 52.211-10 in Section F of the solicitation/contract.
2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 30-calendar days for review of drawings or data submitted for approval.
3. COMMENCEMENT OF CONTROL WORK: Do not perform any control board or outdoor equipment wiring until receipt of Government-furnished wiring diagrams. WAPA will furnish outdoor wiring and schematic diagrams no sooner than December 01, 2018. Control b...
4. OUTAGE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage restrictions shall apply:
5. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply:
6. PROTECTIVE GROUND LEADS: See WAPA Construction Standards, Standard 1 “General Requirements”, Section 1.4.14.3(1).
7. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the f...
8. TYPICAL FOUNDATIONS FOR GOVERNMENT-FURNISHED ELECTRICAL EQUIPMENT AND OIL DETENTION STRUCTURES: Typical foundations are shown in Drawing LIB 2314. WAPA will design these foundations after receipt of the seismic report and informational drawings a...
E. CONSTRUCTION SCHEDULE:
1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer (CO) within 30-calendar days after date of Notice to Proceed.
2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.
F. MATERIAL: Furnish all material for completing the work, except material furnished by WAPA as listed below:
1. POINTS-OF-DELIVERY (Government Furnished Material): Material item One (1) is onsite at the Parker Substation. The Contractor shall transport item number one from Parker Substation to the Liberty Substation. Material items two (2) and three (3) w...
Parker Dam and Parker substation are approximately eighteen (18) miles north of the town of Parker, Arizona on Highway 95. The substation is on the California side of the Colorado River. Follow signs to the dam. Accessing the substation from the Ar...
G. GEOLOGIC INVESTIGATIONS:
H. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
I. WATER FOR CONSTRUCTION PURPOSES:
J. EXPLOSIVES AND BLASTING:
K. BURIED UTILITIES:
L. EMPLOYEE REQUIREMENTS:
M. ELECTRICAL MINIMUM APPROACH DISTANCES:
N. SUBMITTALS AND CORRESPONDENCE:
2. TRANSMITTAL: The Contractor shall transmit submittals to the Construction Office.
A submittal is required if the item is used in the performance of the contract.