21_-_Atch_G__Submittal_Log_-_GLA07.pdf
PDF 94 KB Posted
- Attached to
- Gila Substation Stage 07
- Solicitation number
- 89503118BWA000005
About this file
Attachment G - Submittal Log
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Title: GILA SUBSTATION, STAGE 07 Award Date:
Contract No.: NTP:
Contractor: Completion Date:
Contractor's Western's Location Date Submittal Item In Date Date Approved /
# # Submittal Item Standards Due Submitted Rejected COMMENTS
STANDARD 1
1 Construction Schedule 1.1.4.1. (see project spec)
2 Survey Plan 1.1.5.2.(1) Prior to survey work
3 Survey Notes 1.1.5.5. & 1.1.5.7. Immed. upon completing
4 Survey Data Collector Dump & Computer Printout 1.1.5.6. Immed. upon completing
5 Survey Field Book 1.1.5.7. Immed. upon completing
6 Breakdown of Contract Prices 1.1.6.1. NLT 30 days after NTP
7 Electrical Equipment & Steel Purchase Orders 1.2.3.1.
NLT 10 working days after PO award
8 Cable Location Plan w/Print of Locations 1.3.4.2 & 1.4.5.2 Prior to starting excavation
9 Acknowledgement When Stringing Over Energized Lines 1.3.5.3. Prior to starting stringing
10 Safety and Health Program 1.4.1.5.
NLT 10 days prior to start of construction
11 Copies of Certifications, Test Records & Technical Data 1.4.1.10. Prior to use
12 - Load Performance Tests 1.4.1.10.(1) Prior to use
13 - Crane & Aerial Lift Equipment Annual Inspection Records 1.4.1.10.(2) Prior to use
14 - Brake Performance Test 1.4.1.10.(3) Prior to use
15 - Test Results of Protective Ground Leads 1.4.1.10.(4) Prior to use
16 - Material Safety Data Sheets 1.4.1.10.(5) Prior to use
17 - Manufacturer's Load Rating For Hoists and Grips 1.4.1.10.(6) Prior to use
18 - Certification of Fabricated Lifting and Rigging Devices 1.4.1.10.(7) & 1.4.11 Prior to use
19 - Medical Examiner's Certificate 1.4.1.10.(8) & 1.4.3.3 Prior to use
20 - Data For Excavation Protective System 1.4.1.10.(9) & 1.4.5.5 Prior to use
21 Assurance of Competency in Equipment Operation 1.4.3.4. Prior to use
22 Respiratory Protection Program 1.4.4.8 Prior to work requiring resp.
protection
23 Blasting Plan 1.4.6.2. Prior to blasting
24 Structure Erection Plan 1.4.8.1. Prior to structure erection
SUBMITTAL TRACKING SHEET
Contractor's Western's Location Date Submittal Item In Date Date Approved /
# # Submittal Item Standards Due Submitted Rejected COMMENTS 25 Suspended Work Cart Work Procedure 1.4.12 Prior to use
26 Helicopter Operations and Safety Program 1.4.13 NLT 15 days prior to helicopter operations
27 Protective Ground Lead Test Results & Certification 1.4.14.3. Prior to use
28 Clearance, Hot Line Order & Special Work Permit Requests 1.4.15.3.
NLT 10 working days prior to starting work
29 Stringing Plan 1.4.17.3. Prior to stringing
30 HLO/Clearance Approval or Denial From Other Utilities 1.4.17.4.(3) 1) Prior to stringing
31 Transmission Line Removal Plan 1.4.18 Prior to removal
STANDARD 2
32 Earth Material Testing Laboratory 2.1.1.2.(1) & 2.7.1.2.(1) 20 days prior to compacting
33 Earth Material Compaction Test Reports 2.1.1.2.(2)& 2.7.1. Immed. after test complete
34 Approval Drawings For Cattle Guards 2.1.1.3. Prior to providing
35 Gravel Surfacing Material Gradation 2.1.1.4 Prior to placing
36 Gravel Surfacing Density & Compaction Test Results 2.1.1.4 NLT 7 days after test complete
37 Herbicide Applicator's References 2.1.1.5.(1) & 2.11.3.2.
NLT 30 calendar days prior to application
38 Herbicide Applicator's Certification/License 2.1.1.5.(2) NLT 30 calendar days prior to application
39 Herbicide Application Plan 2.1.1.5.(3) NLT 30 calendar days prior to application
40 Herbicide Application Final Report 2.1.1.5.(4) NLT 7 days after application
41 Seed Certification 2.1.1.6.(1) prior to seeding
42 Fertilizer Certification 2.1.1.6.(2) prior to seeding
43 Asphalt Paving Testing Laboratory 2.1.1.7.(1) NLT 20 days prior to paving
44 Asphalt Mix Design 2.1.1.7.(2) NLT 20 days prior to paving
45 Asphalt Cement 2.1.1.7.(3) NLT 20 days prior to paving
46 Aggregate for Paving Courses 2.1.1.7.(4) NLT 20 days prior to paving
47 Gravel Base Certification 2.1.1.7.(5) NLT 20 days prior to paving
48 Batch Certification 2.1.1.7.(6) NLT 20 days prior to paving
49 Earth Backfill Material 2.3.1.3. & 2.8.1.2.(1) Prior to refill
50 Tree Trimmer Qualifications 2.4.4. Prior to trimming
# # Submittal Item Standards Due Submitted Rejected COMMENTS
STANDARD 3
51 Concrete Testing Laboratory 3.1.1.2.(1) & 3.1.1.3.
NLT 20 days prior to concrete placement
52 Concrete Mix Design 3.1.1.2.(2) & 3.1.1.5. NLT 10 days prior to use
53 Fly Ash For Concrete 3.1.1.2.(5) & 3.1.1.4. NLT 20 days prior to use
54 Admixtures and Curing Compound 3.1.1.2.(6) & 3.1.1.4. NLT 10 days prior to use
55 Batch Certificates 3.1.1.2.(7) Provide at delivery
56 Test Reports 3.1.1.2.(8) Immed. upon completing
57 Void Forming Material 3.1.1.2.(9) & 3.1.1.4. &
3.1.4.2. Prior to use
58 Nonshrink Grout 3.1.1.2.(10) Prior to use
59 Drawings & Data For Electrical Equip. Foundation Design 3.2.1.2. Prior to installation
60 Approval Drawings For Precast Cable Trench 3.2.1.3. Prior to precasting
61 Approval Drawings For Precast Concrete Pull Boxes 3.2.1.4. Prior to precasting
62 Final Drawings For Precast Cable Trench & Pull Boxes 3.2.1.5. Prior to material shipment
STANDARD 4
63 Approval Drawings For Steel Structures & Steel Modifications 4.1.1.2. Prior to fabrication
64 Approval Drawings & Data For Oil Storage Tanks 4.1.1.3. Prior to fabrication
65 Final Drawings For Steel Structures & Oil Storage Tanks 4.1.1.4. Prior to material shipment
66 Weld Procedures 4.1.1.5.(1) & 4.1.7.4. Prior to fabrication
67 Partial Penetration Weld - Test & Evaluation Procedure 4.1.1.5.(2) & 4.1.7.4. Prior to fabrication
68 Nondestructive & Metallographic Test Reports 4.1.1.5.(3) & 4.1.7.4. NLT 20 days after test
69 Connection Bolts 4.1.1.6. Prior to fabrication
70 Mill Test Reports 4.1.1.7. Prior to fabrication
71 Dulling Surface Treatment For Galvanizing 4.1.1.8. Prior to use
72 Tower Test Procedures 4.1.1.9.(1) Prior to testing
73 Calibration of Load Testing Devices 4.1.1.9.(2) NLT 5 days prior to testing
74 Tower Test Report 4.1.1.9.(3) NLT 4 weeks after testing
75 Certified Mill Test Reports 4.1.5.3. Prior to shipping material
76 Magnetic Particle and Dye Penetrant Weld Test (if required by COR) 4.1.7.5. Upon test completion
# # Submittal Item Standards Due Submitted Rejected COMMENTS
77 Master List of Bundles - Steel Structure & Tower Material 4.1.13 Upon completion of material bundling
STANDARD 5
78 Steel Pole Design Data 5.1.1.2. & 5.1.1.9. Prior to fabrication
79 Mill Test Reports 5.1.1.3. & 5.1.1.9. Prior to material shipment
80 Weld Procedures 5.1.1.4.(1) & 5.1.1.9. Prior to fabrication
81 Test & Evaluation Procedure For Partial Penetration Welds 5.1.1.4.(2) & 5.1.1.9. Prior to fabrication
82 Nondestructive and Metallographic Test Reports 5.1.1.4.(3) & 5.1.1.9. NLT 20 days after test
83 Chemical Composition of Dulling Treatment 5.1.1.5.(1) & 5.1.1.9. Prior to use
84 Dulling Treatment Application Procedure 5.1.1.5.(2) & 5.1.1.9. Prior to use
85 3 Samples Representing Reflectance 5.1.1.5.(3) & 5.1.1.9. Prior to use
86 Paints 5.1.1.6.(1) & 5.1.1.9. &
5.1.4.9. Prior to use
87 Material Safety Data Sheets 5.1.1.6.(2) & 5.1.1.9. Prior to use
88 Approval Erection Drawings 5.1.1.7.(1) & 5.1.1.9. Prior to fabrication
89 Approval Shop Detail Drawings 5.1.1.7.(2) & 5.1.1.9. Prior to fabrication
90 Final As-builts & Bill of Materials 5.1.1.8. & 5.1.1.9. Prior to final payment
STANDARD 6
91 Design Data 6.1.1.2. & 6.1.1.9. Prior to fabrication
92 Mill Test Reports 6.1.1.3. & 6.1.1.9. Prior to material shipment
93 Weld Procedures 6.1.1.4.(1) & 6.1.1.9. Prior to fabrication
94 Test & Evaluation Procedure For Partial Penetration Welds 6.1.1.4.(2) & 6.1.1.9. Prior to fabrication
95 Nondestructive and Metallographic Test Reports 6.1.1.4.(3) & 6.1.1.9. NLT 20 days after test
96 Chemical Composition of Dulling Treatment 6.1.1.5.(1) & 6.1.1.9. Prior to use
97 Dulling Treatment Application Procedure 6.1.1.5.(2) & 6.1.1.9. Prior to use
98 3 Samples Representing Reflectance 6.1.1.5.(3) & 6.1.1.9. Prior to use
99 Paints 6.1.1.6.(1) & 6.1.1.9. &
6.1.4.8. Prior to use
100 Material Safety Data Sheets 6.1.1.6.(2) & 6.1.1.9. Prior to use
101 Approval Drawings 6.1.1.7. & 6.1.1.9. Prior to fabrication
102 Final Drawings 6.1.1.8. & 6.1.1.9. Prior to fabrication
STANDARD 7
# # Submittal Item Standards Due Submitted Rejected COMMENTS 103 Data Sheets 7.1.1.(3) & 7.1.2.1. Prior to material installation
104 Certifications 7.1.1.(3) & 7.1.2.2. Prior to material installation
105 Purchase Orders 7.1.1.(3) & 1.2.3.1.
NLT 10 working days after PO award
106 Reports of Chemical Analysies & Physical Tests of Structural Steel/Bolts & Chemical Analyses & Coating Tests of Galvanizing 7.1.4.3.(2) Prior to material shipment
STANDARD 8
107 Design Data 8.1.2.1. & 8.1.2.2. & 8.1.2.5.(2)
Prior to fabrication
108 Approval Drawings 8.1.2.3. & 8.1.2.5.(3) Prior to fabrication
109 Final Original Drawings 8.1.2.4. & 8.1.2.5.(5) Prior to material shipment
110 Final Reproductions 8.1.2.4 & 8.1.2.5.(4) Prior to material shipment
111 Data Sheets 8.1.4.1. & 7.1.1.(3) & 7.1.2.1.
Prior to material installation
112 Certifications 8.1.4.1. & 7.1.1.(3) & 7.1.2.2.
Prior to material installation
113 Purchase Orders 8.1.4.1. & 7.1.1.(3) & 1.2.3.1.
NLT 10 working days after PO award
114 Reports of Chemical Analysies & Physical Tests of Structural Steel/Bolts & Chemical Analyses & Coating Tests of Galvanizing 8.1.4.1. & 7.1.4.3.(2) Prior to material shipment
STANDARD 9
115 Contractor On-site Test Personnel 9.1.2.2.(2) Prior to working on-site
116 Electrical Test Reports & Documents 9.1.2.2.(3) NLT 7 days after testing
117 Continuity & Megohmmeter Testing Personnel 9.1.2.2.(7) Prior to testing
118 Infrared Inspection Tape 9.1.2.2.(15) NLT 48 hours after testing
119 Equipment Installation Drawings Including Seismic Qualification Report Table 9-1 & 9.1.3.2. NLT 60 days after NTP
120 Equipment Informational Drawings & Data Table 9-1 & 9.1.3.3. NLT 60 days after NTP
121 Equipment Final Drawings Table 9-1 & 9.1.3.4.(1) NLT 21 days prior to equip.
installation
122 Equipment Parts Identification Lists & Bills of Materials Table 9-1 & 9.1.3.4.(2) NLT 21 days prior to equip.
installation
123 Manufacturer's Operation & Maintenance Instructions Table 9-1 & 9.1.3.4.(3) NLT 21 days prior to equip.
installation
124 Equipment & Oil Test Reports Table 9-1 & 9.1.3.5. Prior to shipping equipment
125 Equipment Insulating Liquid PCB Certification Table 9-1 & 9.1.3.6. Prior to delivery of oil or equip.
# # Submittal Item Standards Due Submitted Rejected COMMENTS 126 Insulated Conductor Data Table 9-1 & 9.1.3.7. NLT 60 days after NTP
127 Revised Wiring Diagrams Table 9-1 & 9.1.3.9.
NLT 60 days after receipt of drawings
128 Contractor's As-Built Equipment Drawings Table 9-1 & 9.1.3.10.(1) NLT 60 days after equip.
checkout
129 As-built Western Drawings Table 9-1 & 9.1.3.10.(2) NLT 60 days after equip.
checkout
130 Test Reports For Ground Tests 9.2.1.3.
NLT 15 days after completion of testing
STANDARD 10
131 Catalog Data Sheets of Accessories & Hardware Used In Conductor & Overhead Ground Wire Installation 10.2.2.
NLT 40 days prior to material installation
132 Drawings of Insulator & Overhead Groundwire Assemblies and Details 10.2.2.
NLT 40 days prior to material installation
133 Complete Material List 10.2.2.
NLT 40 days prior to material installation
134 Conductor Insulator Assembly Test Reports 10.2.3.1. & 10.3.3. ASAP
135 Conductor Test Reports 10.2.3.2. & 10.6.1.2. ASAP
136 Overhead Groundwire Test Reports 10.2.3.3. & 10.6.2.2. ASAP
137 Overhead Groundwire Assemblies Test Reports 10.2.3.4. & 10.4.3. ASAP
138 Ground Resistance Measurements 10.2.3.5. & 10.5.3. ASAP
139 Vibration Damper Test Reports 10.2.3.6. & 10.6.4.3. ASAP
140 Conductor Spacer Damper Test Reports 10.2.3.7. & 10.6.6.2. ASAP
141 Optical Overhead Groundwire Test Reports 10.2.3.8. & 10.6.3.2. ASAP
142 Assembly & Installation Instructions For Conductor Insulator Assemblies 10.3.4
NLT 2 weeks prior to installation
143 Optical Overhead Groundwire Suspension Clamp Attachment Assemblies 10.4.2.3. Prior to use
STANDARD 11
144 Wood Truss Shop Drawings 11.1.2.4. & 11.6.2.3.(1)
145 Steel Doors and Frames Shop Drawings 11.1.2.4. & 11.8.1.2.(1)
146 Access Flooring Shop Drawings 11.1.2.4. & 11.10.1.3.(1)
147 Termite Control Product Data 11.1.2.5. & 11.2.3.3.(1)
148 Masonry Veneer Product Data 11.1.2.5. & 11.4.2.2.(1)
149 Miscellaneous Metals Product Data 11.1.2.5. & 11.5.1.2.
150 Preformed Roof Panels Product Data 11.1.2.5. & 11.7.2.2.(1)
151 Prefinished Plywood Soffit Product Data 11.1.2.5. & 11.7.3.2.(1)
# # Submittal Item Standards Due Submitted Rejected COMMENTS 152 Caulking and Sealants Product Data 11.1.2.5. & 11.7.4.2.(1)
153 Finish Hardware Product Data 11.1.2.5. & 11.8.2.2.(1)
154 Access Flooring Product Data 11.1.2.5. & 11.10.1.3.(2)
155 Emergency Spray Product Data 11.1.2.5. & 11.11.1.2.(1)
156 Mechanical, General Product Data 11.1.2.5. & 11.12.1.2.
157 Service Building Electrical, General Product Data 11.1.2.5. & 11.13.1.4.
158 Termite Control Installation Data 11.1.2.6. & 11.2.3.(2)
159 Masonry Veneer-Water Repellent Coating Installation Data 11.1.2.6. & 11.4.2.2.(3)
160 Masonry Veneer Samples 11.1.2.7. & 11.4.2.2.(2)
161 Preformed Roof Panel Samples 11.1.2.7. & 11.7.2.2.(3)
162 Prefinished Plywood Soffit Samples 11.1.2.7. & 11.7.3.2.(2)
163 Rubber Cove Base Samples 11.1.2.7. & 11.9.2.2.(1)
164 Access Flooring Samples 11.1.2.7. & 11.10.1.3.(3)
165 Finish Hardware Maintenance Material 11.1.2.8. & 11.8.2.2.(2)
166 Access Flooring Maintenance Material 11.1.2.8. & 11.10.1.3.(4)
167 Mechanical, General Maintenance Material 11.1.2.8. & 11.12.1.2.
168 Termite Control Test Reports 11.1.2.9. & 11.2.3.(4)
169 Mechanical, General Test Reports 11.1.2.9. & 11.12.1.2.
170 Project Record Documents 11.1.2.10.
171 Draft Operation and Maintenance Data For Emergency Spray 11.1.3.2.(1) & 11.11.1.2.(2)
172 Draft Operation and Maintenance Data For Mechanical, General 11.1.3.2.(1) & 11.12.1
173 Completed Operation and Maintenance Data For Emergency Spray 11.1.3.2.(1)
174 Completed Operation & Maintenance Data For Mechanical, General 11.1.3.2.(2)
175 Termiticide Applicator's Certificate/License 11.2.3.3.(3)
176 Preformed Roof Panel Shop Drawings 11.7.2.2.(2)
177 System Operational Manual 11.12.3.5.
STANDARD 12
178 Manufacturer's Data 12.1.1.2.
STANDARD 13
179 Recycled Materials Quantity Report 13.2.1. & 13.7.2.
180 Products Containing Recovered Materials Report 13.2.2. & 13.8.3.
181 Reclaimed Refrigerant Receipt & Technician Certification 13.2.3. & 13.9.
182 Spill Prevention Notification & Cleanup Plan 13.2.5. & 13.11.2.
183 Tanker Oil Spill Prevention & Response Plan 13.2.6. & 13.11.3.
184 Pesticide Use Plan 13.2.7 & 13.12.3.
185 Treated Wood Pole & Members Recycling Consumer Info. Receipt 13.2.8. & 13.13.
# # Submittal Item Standards Due Submitted Rejected COMMENTS 186 Asbestos Licenses or Certificates 13.2.10. & 13.15.
187 Lead Paint Notices 13.2.11. & 13.16.
188 Water Pollution Permits 13.2.12. & 13.17.2.
189 PCB Test Reports 13.2.13 & 13.18.2
190 Oil & Oil-Filled Electrical Equipment Receipt 13.2.14. & 13.18.5.
191 Cleanup Work Management Plan 13.2.16. & 13.19.2.
192 Post Cleanup Report 13.2.17. & 13.19.7.
STANDARD 15
193 As-Built Drawings 15.2.6.
"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable
Sheet1
File details come from the government source that posted it.