Spec No.

SECTION C

DESCRIPTION/SPECIFICATIONS

PROJECT SPECIFICATIONS

WATER/SEWER CONNECTION AND

BATHROOM REMODEL PROJECT

LIVERMORE SUBSTATION

CALIFORNIA

Blank Page

Table of Contents

DIVISION 1 – GENERAL REQUIREMENTS 1

A. CONTRACT REQUIREMENT 1

B. DESCRIPTION OF WORK 1

C. DESCRIPTION OF BIDDING SCHEDULE ITEM 2

D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK 2

E. CONSTRUCTION SCHEDULE 2

F. MATERIAL 2

G. SECURITY PLAN 3

H. RIGHTS-OF-WAY 3

I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES 3

J. WATER FOR CONSTRUCTION PURPOSES 3

K. EXPLOSIVES AND BLASTING 3

L. SUBMITTALS 3

DIVISION 2 – SITEWORK 5

A. GENERAL REQUIREMENTS 5

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS 13

DIVISION 11 – BUILDINGS 17

HOLLOW-METAL DOORS AND FRAMES 17

B. GENERAL 17

C. REGULATORY REQUIREMENTS 17

D. SUBMITTAL REQUIREMENTS 17

D. INTERIOR DOORS AND FRAMES 18

E. FRAME ANCHORS 18

F. MATERIALS 18

G. FABRICATION 19

H. FINISHES AND ACCESSORIES 20

I. PREPARATION AND INSTALLATION 21

TOILET ROOM ACCESSORIES 23

B. GENERAL 23

C. INSTALLATION 24

D. SURFACE-MOUNTED PAPER TOWEL DISPENSER/WASTE RECEPTACLE 24

E. CHANNEL-FRAMED MIRROR/SHELF COMBINATION 24

F. SURFACE-MOUNTED LIQUID SOAP DISPENSER 25

G. SURFACE-MOUNTED TWIN JUMBO-ROLL TOILET TISSUE DISPENSER 25

H. SURFACE-MOUNTED TOILET SEAT COVER DISPENSER 25

I. CLOTHES HOOK 25

J. GRAB BARS 25

GYPSUM BOARD 26

A. GENERAL 26

B. GYPSUM BOARD, GENERAL 26

C. INTERIOR GYPSUM BOARD 26

D. SPECIALTY GYPSUM BOARD 27

E. TRIM ACCESSORIES 27

F. JOINT TREATMENT MATERIALS 27

G. AUXILIARY MATERIALS 28

H. TEXTURE FINISHES 28

I. APPLYING AND FINISHING PANELS, GENERAL 28

J. APPLYING INTERIOR GYPSUM BOARD 29

K. INSTALLING TRIM ACCESSORIES 30

L. FINISHING GYPSUM BOARD 30

M. APPLYING TEXTURE FINISHES 30

N. PROTECTION 30

PLUMBING FIXTURES AND EQUIPMENT 32

A. GENERAL 32

B. INSTALLATION 32

PLUMBING INSULATION 34

A. GENERAL 34

B. INSULATION 34

BUILDING WATER SUPPLY SYSTEM 36

A. GENERAL 36

B. INSTALLATION OF PIPING 37

C. CONTROL VALVES 38

D. VALVES 38

E. BACKFLOW PROTECTION 39

F. TESTS 39

G. STERILIZATION 40

BUILDING SOIL AND WASTE SYSTEM 41

A. GENERAL 41

B. INSTALLATION OF PIPING 42

C. FLASHING 43

D. FLOOR DRAINS AND FLOOR SINKS 43

E. TESTS 43

VALVES AND SPECIALTIES 44

A. GENERAL 44

B. EXPANSION TANK 44

C. WATER TEMPERATURE AND PRESSURE RELIEF VALVES 45

D. INSTALLATION 45

E. TEST AND ADJUSTMENT 45

F. RELIEF VALVE DISCHARGE 45

BASIC ELECTRICAL MATERIALS AND METHODS 46

A. GENERAL 46

B. ELECTRICAL EQUIPMENT INSTALLATION 46

C. RACEWAY 47

D. WIRING 47

E. ELECTRICAL SUPPORTING DEVICE APPLICATION 48

F. SUPPORT INSTALLATION 48

G. IDENTIFICATION MATERIALS AND DEVICES 49

H. FIRESTOPPING 49

I. DEMOLITION 50

J. CUTTING AND PATCHING 50

K. FIELD QUALITY CONTROL 50

L. REFINISHING AND TOUCH-UP PAINTING 50

M. CLEANING AND PROTECTION 51

GROUNDING AND BONDING 52

A. GENERAL 52

B. EQUIPMENT GROUNDING CONDUCTORS 52

C. CONNECTIONS 52

CONDUCTORS AND CABLES 54

A. GENERAL 54

B. INSTALLATION 54

C. CONNECTIONS 55

D. FIELD QUALITY CONTROL 55

RACEWAYS AND BOXES 56

A. GENERAL 56

B. INSTALLATION 57

WIRING DEVICES 60

A. GENERAL 60

B. INSTALLATION 60

C. IDENTIFICATION 61

D. CONNECTIONS 61

E. FIELD QUALITY CONTROL 61

F. CLEANING 61

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION 62

A. GENERAL 62

B. SPECIAL REQUIREMENTS 64

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT

Construct and complete the Water/Sewer Connection and Bathroom Remodel Project in accordance with the Con-struction Contract (Standard Form 1442); the Contract Clauses; Western’s Construction Standards (September 2013), including Standard 1 – General Requirements; Standard 2 – Site work; Standard 3 – Concrete; Standard 11 – Build-ings; Standard 13 – Environmental Quality Protection; Standard 15 – Drawings; Standard Drawings; and these Project Specifications and Drawings.

If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern, except in the City of Livermore Right-of-way and the water and sewer services, where City of Livermore Details, Standards and Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Standard Specifications. Some paragraphs in the Standard Specifications will not apply to this job.

Western’s Construction Standards, and Standard Drawings are available at: https://www.wapa.gov/DoingBusi-ness/SellingToWestern/Pages/what-western-buys.aspx

Western’s Project Specifications and Standards are explained in Standard 1 – General Requirements, Section 1.1.1., “Standards and Project Specifications”.

B. DESCRIPTION OF WORK

The principal components of work include the following:

1. Water/Sewer Connection

a. Provide excavation, cutting, removal and all other preparation as necessary for installation of the utility service lines as indicated on the plans.

b. Provide installation and testing of utility service lines and components as indicated.

c. Complete cover, replacement and repair as required at prior excavation and removal of existing materials.

2. Bathroom Remodel

a. Provide moving support services to move stored contents, as necessary, to perform the work of the project and upon completion.

b. Provide disconnection and reconnection of electrical service to the existing Bathroom.

c. Demolition of existing composition tile flooring, door, door frame and existing framed wall and associated electrical and plumbing as indicated. Disposal of materials shall be in accordance with Western’s Standard 13 – Environmental Quality Protection.

d. Provide metal stud infill and room enclosure wall and install new pre-hung metal door with hardware that complies with ADA standards.

e. Remove existing toilet. Provide and install new toilet as specified that complies with ADA standards.

f. Provide plumbing rough-in for new sink locations, toilet supply and new offset vent-through-roof location.

g. Relocate existing water heater and miscellaneous electrical, as required.

h. Install, repair and finish gypsum wall board at walls and ceilings to match existing as required.

https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx

i. Re-paint new and existing inner and outer wall and ceiling finishes at the Bathroom.

j. Provide relocation of the existing service sink and provide and install additional new accessible sink, install per CBC Chapter 11b.

k. Provide new composite tile flooring to match existing.

l. Provide prefabricated stainless steel grab bars as indicated.

m. Provide Toilet Room Accessories that comply with ADA standards as follow, install per CBC Chapter 11b:

1. Surface-mounted Paper Towel Disperser/Waste Receptacle.

2. Channel-Framed Mirror/Shelf Combination.

3. Surface-mounted Liquid Soap Dispenser.

4. Surface-mounted Twin Jumbo-Roll Toilet Tissue Dispenser.

5. Surface-mounted Seat Cover Dispenser.

6. Clothes Hook.

Paragraphs “Description of Bidding Schedule Items” in Divisions 1 and 2 describe the work to be performed.

The work is located near Livermore, California.

C. DESCRIPTION OF BIDDING SCHEDULE ITEM

1. Bidding Schedule item “Mobilization and Preparatory Work” includes the following:

a. Perform mobilization and preparatory work in accordance with Section H of the contract clauses.

b. Prepare and submit a Construction Schedule and Safety and Health Program.

D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

1. COMMENCEMENT AND COMPLETION: Refer to Section F, Clause 51.211-10.

2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, Western will require 15-calendar-days for review of drawings or data submitted for approval.

3. OUTAGE RESTRICTIONS AND CONDITIONS: Follow the restrictions listed in the Standard Specifications.

E. CONSTRUCTION SCHEDULE

1. SUBMITTAL TIME: Refer to Contract Clause 52.236-15. The Schedule shall be submitted to the COR no later than 15-calendar-days after the issuance of the Notice to Proceed.

2. FORMAT AND DETAIL: The Schedule shall be provided in the Microsoft Project 2007 format, PDF, and shall clearly show a critical path base line. Do not schedule dates earlier than the estimated delivery dates shown in the “Material” paragraph.

F. MATERIAL

All material shall be furnished by the Contractor.

The Contractor shall inspect the material, report any damage to the COR, load and transport the material to the worksite(s), and unload it. All Government-furnished materials not installed, shall be transported back to Western’s Warehouse, per B.2.o., by the Contractor.

G. SECURITY PLAN

Submit a Security Plan to the COR for approval within 10-calendar-days from the date of Notice to Proceed, and prior to on-site work commencing. The Plan shall provide details of how security will be maintained while work is underway, as well as addressing the accesses through secured gates at the jobsite.

H. RIGHTS-OF-WAY

Western will furnish the right-of-way or site for the work, and the right-of-way for access to the work over routes estab-lished by Western. The Contractor shall provide all additional right-of-way or land desired for construction purposes, without expense to Western.

If additional access is needed, the Contractor shall be responsible for contacting the landowner to obtain permis-sion. The Contractor shall obtain a signed agreement from the landowner, granting permission to use their access for the duration of the project. Permission must be obtained, and the required agreements forwarded to the COR, prior to the work commencing on-site. During the contract period, Western reserves the right to use Contractor-obtained access.

I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES

Limited single-phase or three-phase power is available from receptacles or panel boards located throughout the sub-stations at approximately 120 volts nominal. Coordinate with the COR for establishing electric power service. The Contractor shall furnish power for construction purposes if greater than what is available.

J. WATER FOR CONSTRUCTION PURPOSES

Furnish water for construction purposes. Make arrangements for obtaining the water, and provide for conveying the water to the points of use.

K. EXPLOSIVES AND BLASTING

Explosives shall not be used.

L. SUBMITTALS

1. GENERAL: Submittals must be provided in accordance with the Construction Standards and Project Specifica-tions. The Contractor shall furnish submittals electronically (i.e. e-mail), unless otherwise specified by the COR.

Submittals shall be sent to DSW-G5600-CS@wapa.gov in standard PDF or electronic CAD “*.dwg” (AutoCAD 2010) formats. All submittals shall include Western's contract number, project title, trans-mittal/submittal number, and corresponding item number. Refer to the Submittal Log for the list of required sub-mittals. This list may not be all-inclusive, and it remains the Contractor's responsibility to ensure conformance to the individual Specifications for possible additional submittal requirements. The submittal cover sheet in Microsoft Word or PDF format shall be included.

a. Product Data: Manufacturer's data sheets on each product to be used, including:

1) Preparation instructions and recommendations.

2) Storage and handling requirements and recommendations.

3) Details of construction and fabrication.

4) Installation methods.

b. Shop Drawings: Include detailed plans and elevations, details of framing members, anchoring methods, clearances, hardware, and accessories.

c. Selection Samples: For each finish product specified, two complete sets of color chips representing manu-facturer's full range of available colors and patterns.

mailto:dsw-g5600-cs@wapa.gov

d. Verification Samples: For each finish product specified, two samples, minimum size six-inches- (150-mm-) long, representing actual product, color, and patterns.

e. Manufacturer's Certificates: Certify products meet or exceed specified requirements.

f. Operation and Maintenance Data: Submit lubrication requirements and frequency, and periodic adjustments required.

g. Manufacturer’s Qualifications: Company specializing in performing the work of this section, with a minimum of five-years’ experience.

h. Installer Qualifications: Company approved by manufacturer, specializing in performing work of this section with minimum three-years’ experience, with IDEA Certified Installers and service technicians on staff.

In addition to the submittals required in the attached Submittal Log, the Contractor shall submit the following information electronically to DSW-G5600-CS@wapa.gov:

a. Payrolls

b. Sub-Contractor List/Forms

c. Citizenship Forms

d. Environmental Submittals

e. Request For Information (RFI)

f. Request for Equitable Adjustment (REA)

g. Any and all correspondence, questions, etc., pertaining to this project.

A submittal is required if the item is used in the performance of the contract.

3. APPROVAL TIME: Approval time for submittals will be in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph.

h. Transmittal: The Contractor shall forward specified non-electronic submittals to one of the following ad-dresses:

Western Area Power Administration Western Area Power Administration

ATTN: G5600 ATTN: G5600

P.O. Box 6457 615 43rd Avenue

Phoenix, AZ 85005-5313 Phoenix, AZ 85009 mailto:DSW-G5600-CS@wapa.gov

DIVISION 2 – SITEWORK

A. GENERAL REQUIREMENTS

1. EXCAVATION GENERAL:

a. Schedule work to keep roads and utilities in usable condition; avoid property access incon-venience insofar as practicable.

b. Notify the City of Livermore prior to beginning work, and determine if any permits will be required. Copies of all required permits shall be submitted to the COR at least five-days prior to commencing work.

c. Contractor shall provide name, address, and telephone number of the person who has ac-cess to equipment and is authorized to make emergency repairs to Contractor's work, such as to correct trench cave-ins, moving excavated material, and correct other problems during weekends and off-work hours, so access can be maintained for firefighting equipment, and to maintain barricades for public safety.

d. Excavation shall be open cut unless otherwise specified or shown.

e. It is the intent of these Project Specifications and Drawings to result in a complete installa-tion, and in complete accordance with all applicable codes and ordinances.

f. Before submitting a bid, the Contractor shall examine the site and become familiar with all existing conditions and the requirements for performing the work. No subsequent allowance will be provided for not following this procedure.

g. Drawings are diagrammatic in character and do not necessarily indicate every required length, offset, transition, etc. Items not specifically mentioned in the Specifications or noted on the Drawings, but which are obviously necessary to make a complete working installation shall be included. Contractor shall field measure for exact requirements, and install erosion protection and appurtenances accordingly.

h. Drawings shall not be scaled for rough-in measurement, or used as shop drawings. Where drawings are required for these purposes, or have to be made from field measurements, the Contractor shall take the necessary measurements and prepare the drawings.

2. SUBMITTALS AND SHOP DRAWINGS:

a. Submittals shall conform to the requirements listed in Division 1, and the following para-graphs:

i. Submittals shall include catalog cut-sheets, manufacturer's data sheets, written de-scriptions and specification sheets detailing the associated product, item and assem-bly.

ii. Shop drawings shall include details, installation drawings, assembly drawings, fabrica-tion drawings, diagrams and other information that show adaptation or installation of Contractor-furnished shed products or materials for the project.

iii. Prior to ordering material or beginning installation work, assemble, prepare and furnish submittals and shop drawings required for the project to the COR. Contractor shall furnish submittals as required by the individual specification sections.

iv. Review of shop drawings and submittals is intended to minimize delivery to the project site and installation of materials that do not meet the intent of the Construction Docu-ments. Review by the COR does not relieve the Contractor's responsibility to comply with the requirements of the Contract Documents, governing codes and standards or requirements of the local Authority Having Jurisdiction (AHJ).

b. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician responsible for recovering refrigerant, stating that all refrigerant that was present was recovered and that recovery was performed according to EPA regulations. Include name and address of the technician, and the date refrigerant was recovered.

c. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program

d. Warranties: Documentation indicating that existing warranties are still in effect after com-pletion of selective demolition.

e. Inventory: Submit a list of items that have been removed and salvaged. Refer to Division 13.

3. FIELD CONDITIONS:

a. Prior to commencing work, a pre-job meeting will be held to discuss the following:

i. Inspect and discuss the condition of the structure to be selectively demolished.

ii. Review structural load limitations of existing structure.

iii. Review and finalize selective demolition schedule, and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.

iv. Review requirements of work performed by other trades that rely on substrates ex-posed by selective demolition operations.

v. Review areas where existing construction is to remain and requires protection.

b. Portions of the building immediately adjacent to selective demolition area will be occupied.

Conduct selective demolition so that personnel will not be disrupted.

i. Conditions existing at the time of inspection for bidding purpose will be maintained as far as practical.

ii. Notify the COR of any discrepancies between the existing conditions and the drawings before proceeding with the selective demolition.

iii. Hazardous materials present in buildings and structures to be selectively demolished.

A report on the presence of hazardous materials is on file for review and use. Examine the report to become aware of locations where hazardous materials are present.

(a) Hazardous material remediation is specified elsewhere in the contract docu-ments.

(b) Do not disturb hazardous materials, or items suspected of containing hazardous materials, except under procedures specified elsewhere in the contract docu-ments.

(c) The COR will provide Safety Data Sheets (SDS) for suspected hazardous mate-rials that are known to be present in buildings and structures to be selectively demolished because of building operations or processes performed there.

iv. Storage or sale of removed items or materials on-site is not permitted.

v. Maintain existing utilities indicated to remain in service, and protect them against dam-age during selective demolition operations.

vi. Maintain fire-protection facilities in service during selective demolition operations.

c. Temporary Protection:

i. Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

ii. Provide protection to ensure safe passage of people around selective demolition area, and to and from occupied portions of building.

iii. Provide temporary weather protection during the intervals between selective demoli-tion of the existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.

iv. Protect walls, ceilings, floors, and other existing finish work that are to remain, or that are exposed during selective demolition operations.

v. Cover and protect furniture, furnishings, and equipment that have not to be removed.

d. Design, provide, and maintain shoring, bracing, and structural supports, as required to pre-serve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

i. Strengthen or add new supports when required during progress of selective demolition.

ii. Remove temporary barricades and protections where hazards no longer exist.

e. Maintenance of Utility Services:

i. Maintain services/systems indicated to remain, and protect them against damage.

ii. Locate, identify, disconnect, and seal or cap-off utility services and mechanical/electri-cal systems serving areas to be selectively demolished.

(a) Co-ordinate with the COR to arrange to shut-off indicated services/systems.

(b) Arrange to shut-off utilities with the respective utility companies.

(c) If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that by-pass the area of selective demolition, and that maintain continuity of services/systems to other parts of the building.

(d) Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components, as indicated on the drawings.

1) Piping to be removed: Remove portion of piping indicated to be removed, and cap or plug remaining piping with same or compatible piping material

2) Piping to be abandoned-in-place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

3) Equipment to be removed: Disconnect and cap services, and remove equip-ment.

4) Equipment to be removed and reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

5) Equipment to be removed and salvaged: Disconnect and cap services, and remove equipment and deliver it per the COR’s instructions.

6) Ducts to be removed: Remove portion of ducts indicated to be removed, and plug remaining ducts with the same or compatible ductwork material.

7) Ducts to be abandoned-in-place: Cap or plug ducts with same or compatible ductwork material and leave in place.

4. EXISTING UTILITIES:

a. Contractor shall co-ordinate locating of underground utilities with both the City of Livermore and the COR. Contractor shall contact USA North (phone: 1-800-227-2600) for utility loca-tion two-days before beginning excavation.

b. If any utilities are encountered during excavation, notify the COR immediately. Maintain required separation/clearance between utilities, as required by the City of Livermore. Make arrangements with utility companies to temporarily support, brace, or remove utilities en-countered during excavation, at no cost to Western.

c. Contractor is fully responsible for repairing, at no expense to Western, permanent utilities damaged done by the Contractor. In the event of a break in the existing water main, gas main, sewer, or electric or communication cable, immediately notify the utility owner and the

COR.

5. TRAFFIC CONTROL:

Furnish, install, and maintain traffic control facilities required for the work. Remove when work is completed.

6. EXCAVATION CLASSIFICATION:

a. Earth: Materials not classified as rock; includes clay, silt, sand and gravel, hardpan, disin-tegrated shale and rock, debris, and detached rock less than one-cubic-yard in volume.

b. Rock: Materials that cannot be excavated without the use of pneumatic tools, drilling, and blasting, or line drilling and wedging, and detached pieces of such materials larger than one-cubic-yard in volume.

c. If granular material suitable for backfill is encountered in trenches: Pile in an orderly manner a sufficient distance back from edge of the excavation to avoid slides or caveins; two-foot-minimum clear distance. Place unsuitable excavated material directly on trucks and haul away; no spoil banks permitted.

7. EXCAVATION (EARTH):

a. Strip and stockpile topsoil for use in surface restoration.

b. Slope walls of trench, or provide trench shoring, as required to comply with OSHA and safety requirements.

c. Excavate to full depth by machine. Trench bottom shall be suitable for hand working of finely divided, loose, excavated material, or for placement of backfill material.

d. If soft, spongy, or otherwise unstable material is encountered which may not provide suita-ble foundation for riprap:

i. Notify COR immediately.

ii. COR will authorize remedial measures in writing, as required.

iii. Removal and replacement of questionable material will be authorized only if de-water-ing methods are unsuccessful in stabilizing trench bottom.

iv. If removal of unsuitable material is authorized, replace with suitable backfill material and compact, per these Specifications.

e. Unauthorized excavation carried below required depth will be backfilled and compacted at no expense to Western.

f. Excavate by hand:

i. Under tree roots three-inches and larger.

ii. Under and around structures and utilities.

8. DE-WATERING:

a. Provide equipment for handling water encountered.

b. Do not lay filter fabric or rip-rap on excessively wet soil.

c. Prevent surface water from flowing into excavation; promptly remove any water accumu-lated.

d. Divert stream flow and/or sewage away from areas of construction.

e. Do not discharge water pumped from excavations to existing sanitary sewers.

9. BACKFILL:

a. Limit amount of trench open at one time to 20-foot maximum.

b. Use caution when placing and compacting backfill to avoid placing construction loads on existing tower foundations which may damage or displace existing facilities.

c. Site soil may be used for backfill. Backfill material shall be selected from excavation or from a source selected by the Contractor. It shall not contain frozen lumps, stones larger than three-inches-in-diameter, chunks of clay, or other objectionable material.

d. It shall be free from an excess of soft or disintegrated pieces, alkali, adobe, vegetable mat-ter, loam, or other deleterious substances.

e. Backfill shall meet the following gradation:

% Passing Size 100 3-inches 100-90 1-inch 100-60 ¾-inches 80-35 No. 8 12-0 No. 200

10. ASPHALT PAVING:

a. QUALITY ASSURANCE:

i. Material and Producer: Supply source of asphalt paving material shall be approved by the COR before delivery.

ii. Testing Laboratory: Shall meet the qualifications of ASTM D 3666.

b. MATERIAL:

i. Aggregate for Paving Courses: ASTM D 1073 for fine aggregate, and ASTM D 692 for course aggregate; maximum nominal diameter is ¾-inch.

ii. Gravel Base: ASTM D 2940.

iii. Tack Coat: ASTM D 2397 for emulsified asphalt CSS-1H grade.

c. MIX DESIGN: The mix design shall meet the following requirements for Marshall Series ASTM D 1559, or Hveem Stabilometer ASTM D 1560:

i. Marshall Series:

Minimum Stability, lbs.: 1,200 No. of Blows: 50 Flow, .01 in.: 8 to 16 Air Voids %: 3.0 to 5.0% range, 4% target Minimum VMA %: 14 (bulk specific gravity of aggregate)

ii. Hveem Stabilometer:

Minimum Stabilometer Value: 35 Maximum Swell (inches): 0.030 Minimum Air Voids, %: 3.0 to 5.0% range, 4% target

d. BATCHING AND MIXING:

i. Comply with ASTM D 995 for material storage, control, mixing, and plant equipment and operation.

ii. Aggregates: Deliver dry aggregate to mixer at recommended temperature to suit pen-etration grade and viscosity characteristics of asphalt, ambient temperature, and mix-ture work ability.

iii. Mixing: Mix aggregates and asphalt to achieve coated particles, in accordance with

ASTM D 2489.

iv. Transporting: Provide covers over mixture when transporting during rainy or cold weather. Mix shall be delivered at no less than 300°F.

e. TESTING:

An approved testing laboratory shall be employed by the Contractor to perform asphalt pav-ing tests. Obtain test samples in accordance with ASTM D 979. Perform tests as follows:

i. Bitumen Extraction: ASTM D 2172. One test per 500-tons, or fraction thereof.

ii. Gradation Analysis: ASTM C 117 and ASTM C 136. One test per 500-tons, or fraction thereof.

iii. Marshall Series ASTM D 1559 or Hveem Stabilometer ASTM D 1560: One test per 1,000-tons, or fraction thereof.

iv. Density: ASTM D 2950.

v. Bulk Specific Gravity and Compacted Density: ASTM D 2726. Two tests per 500-tons.

Any fraction thereof will require one test.

f. PREPARATION OF SUBGRADE: Subgrade shall be compacted to a density of 95-percent of the maximum dry density, in accordance with these Specifications. Before final rolling, shape entire section and compact subgrade to provide grades, elevations, and cross section indicated on the drawings. Compact areas adjacent to structures, and other areas not accessible to rollers, with mechanical or hand tamping devices.

g. PLACING OF GRAVEL BASE:

i. Place untreated aggregate base when the air temperature is above 30°F and rising.

ii. Spread untreated aggregate base material over prepared subgrade to compacted depth and grades shown on the drawings.

iii. Compact and moisten untreated aggregate base at optimum moisture content, ±1.5-percent to achieve a minimum density of 95-percent of maximum laboratory density, in accordance with ASTM D 1557.

h. CONDITIONING OF ADJOINING SURFACES: Construct structures adjacent to proposed asphalt pavement prior to placement of pavement. Surfaces in contact with the asphalt pavement shall be painted with a uniform tack coat prior to placing asphalt pavement.

i. SPREADING AND COMPACTING ASPHALT PAVING:

i. General: Spread and compact asphalt paving in accordance with the "Spreading" and "Compaction" sections in Asphalt Institute Manual Series No. MS-8, "Asphalt Paving".

ii. Weather: Construct paving courses when air temperature is above 40°F, underlying base is dry, and weather is not rainy.

iii. Protection: Protect buildings and other facilities from asphalt splatter. Do not dis-charge unused paving material on the site.

iv. Compaction: Asphalt paving shall be compacted to a minimum of 93-percent of theo-retical maximum specific gravity, in accordance with ASTM D 2041. Do not allow ve-hicular traffic on newly paved areas until surface has cooled to air temperature. Ensure surface of completed pavement is true to lines, profiles, and elevations indicated, and is free from depressions.

j. TOLERANCES: After placement, asphalt paving shall be within the following tolerances:

i. Thickness of Asphalt Paving Courses: ±¼-inch

ii. Smoothness of Asphalt Paving Courses: Free from depressions exceeding ¼-inch when measured with a 10-foot straight-edge.

k. PAVEMENT MARKING MATERIAL: Material used shall be equal to Pro-Mar Water Borne

Traffic Paint by Sherwin Williams Company; PPG Traffic and Zone Marking Paint by PPG Industries, Inc., Coatings and Resins; or Traffic Zone Paint by ICI Americas lnc./Glidden Company. Color shall be white or yellow. Paint stripes for parking lanes shall be four-inches-wide, and sprayed or brushed at locations shown on the drawings. Provide handicap symbols in accordance with the International Symbol System. Spray or brush stripes at crosswalks and stop signs. Surface of pavement shall be thoroughly cleaned and dust free before painting.

11. ASPHALT PAVING RECYCLING:

a. GENERAL: Dispose of existing asphalt paving in accordance with Standard 13 - Environ-mental Quality Protection, Section 13.8., "Disposal of Waste Material". Recycled asphalt paving shall meet the requirements above in Section 13., "Asphalt Paving, General".

b. HOT MIX RECYCLING: In accordance with Asphalt Institute Manual Series No. MS-20.

c. COLD MIX RECYCLING: In accordance with Asphalt Institute Manual Series No. MS-21.

d. GEOTEXTILE FABRIC: Geotextile fabric shall be a woven, polypropylene fabric equal to

Propex 2002 Construction Fabric by Amoco Fabric Company, 550 Interstate North Parkway, Atlanta GA 30099. Geotextile fabric shall be black and have a fill tensile strength not less than 200-pounds, fill elongation not more than 20-percent, burst strength not less than 450-psi, and puncture strength not less than 75-pounds. Install geotextile fabric in accordance with the manufacturer's instruction.

12. REPAIR AND RESTORATION:

a. Repair, at no additional cost to Western, existing fences, culverts, utilities, and structures disturbed by construction.

b. Contractor fully responsible for liaison with utility companies and for repairing, at no expense to Western, utilities damaged by the Contractor. In the event of breaking an existing water main, gas main, sewer, or electric or communication cable, immediately notify the respon-sible official of organization operating the utility affected, and the COR.

c. Restore obstructions removed to accommodate equipment or to facilitate excavation.

d. Perform restoration work under favorable climatic conditions.

e. Maintenance of surfaces:

i. Damage due to settlement of backfill: Repair for the period of the Bond.

ii. Depressions more than six-inches-deep in rip-rap areas: Fill to grade with rip-rap for the period of the Bond.

13. SOIL AND MATERIAL TESTING:

a. Density tests:

i. Provide for laboratory tests using ASTM D1557 testing methods.

ii. In-place/field density tests shall follow AASHTO T-191 or ASTM 02922.

iii. Perform tests in areas of backfill and where compaction requirements are specified.

iv. Provide equipment necessary and perform field density tests during course of Work.

v. Perform tests for fill or backfill at following interval: One bedding test per excavation, and one additional test per excavation al fill lift in initial or final zone.

(a) Sieve analysis: ASTM C136; minimum of one test on each source of each mate-rial of specified gradation unless otherwise specified, or provide certified copy of test report from material supplier.

(b) If tests indicate inadequate placement or compaction, Contractor shall correct in-adequacies and perform additional tests in same area, at no additional cost to Western.

14. CLEAN-UP:

a. Remove brush, rubbish, spoil, excess excavated material, and material not suitable for backfill to an approved landfill.

b. Remove waste material promptly, as it is generated by construction operations; do not per-mit to accumulate. Clean-up each portion of construction as it is completed.

c. Clean-up operations in public right-of-way shall be kept within 400-feet of construction op-erations.

d. Clean-up and remove rubbish, debris, and surplus material.

e. Grade disposal areas periodically to reasonably neat surface to provide for drainage and access by others.

f. Leave site in neat condition, and re-open to traffic as soon as practicable.

15. EROSION CONTROL:

a. Take care to minimize soil erosion during and after construction.

b. Contractor shall disturb only minimum area during construction, shall pile excavated mate-rial in a manner also prevent erosion of material, shall restore surfaces to prevent erosion, and shall remove excess excavated material and debris and dispose of these materials in an acceptable manner to prevent erosion and sedimentation.

c. Contractor shall employ erosion control measures and surface restoration procedures, as appropriate, in borrow and waste disposal areas.

d. Take measures necessary, in addition to those specified herein, to prevent erosion, prevent sediment from entering surface drainage courses, and prevent sediment from being washed onto adjacent areas. Applicable steps will depend upon site characteristics (soil, slope, drainage, etc.), and construction techniques. The following are offered as possible steps which may be taken:

i. Relative to area drainage, excavated material shall be stored on upstream side of trenches.

ii. Straw or hay bales, sandbags, or silt fences placed in drainage channels or at the toe of excavation storage piles to serve as sediment dams.

iii. Route run-off around excavated areas and excavated storage piles.

iv. Mulching with straw, hay, and jute netting, or other mattings, blankets, and netting.

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item "Demolition" includes the following:

a. Proceed with selective demolition systematically, from higher to lower level. Complete se-lective demolition operations above each floor or tier before disturbing supporting members on the next lower level as shown on the drawings.

b. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping.

Temporarily cover openings to remain.

c. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring ex-isting finished surfaces.

d. Do not use cutting torches until work area is cleared of flammable materials. At con-cealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire suppression de-vices during flame-cutting operations.

e. Maintain fire watch during, and for at least two-hours after flame-cutting operations.

f. Maintain adequate ventilation when using cutting torches.

g. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of them off-site.

h. Remove structural framing members and lower to ground by method suitable to avoid free-fall, and to prevent ground impact or dust generation.

i. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing. Dispose of demolished items and materials promptly.

j. Conduct selective demolition and debris-removal operations to ensure minimum interfer-ence with roads, streets, walks, walkways, and other adjacent occupied and used facili-ties.

k. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least ¾-inch (19-mm) at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.

l. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power-driven saw, and then remove concrete be-tween saw cuts.

m. Masonry: Demolish in small sections. Cut masonry at junctures with construction to re-main, using power-driven saw, and then remove masonry between saw cuts.

n. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, and then break up and remove.

o. Resilient Floor Coverings: Remove floor coverings and adhesive according to recom-mendations in RFCl's, "Recommended Work Practices for the Removal of Resilient Floor Coverings". Do not use methods requiring solvent-based adhesive strippers.

p. Refrigerant: Before starting demolition, remove refrigerant from mechanical equipment ac-cording to 40 CFR 82 and regulations of authorities having jurisdiction.

q. Verify that utilities have been disconnected and capped before starting selective demolition operations.

r. Review project record documents of existing construction or other existing conditions and hazardous material information provided by the COR. Western does not guarantee that the existing conditions are the same as those indicated in project record documents.

s. Verify that hazardous materials have been remediated before proceeding with building dem-olition operations.

t. Comply with governing EPA notification regulations before beginning selective demolition.

Comply with hauling and disposal regulations of authorities having jurisdiction.

u. Comply with ASSE A 10.6 and NFPA 241.

v. Maintain existing building structure (including structural floor and roof decking) and envelope exterior skin and framing, excluding window assemblies and non-structural roofing material, not indicated to be demolished; do not demolish such existing construction beyond indicated limits.

w. Maintain existing interior non-structural elements (interior walls, doors, floor coverings, and ceiling systems) not indicated to be demolished; do not demolish such existing construction beyond indicated limits.

x. Maintain existing non-shell, non-structural components (walIs, flooring, and ceilings) not in-dicated to be demolished; do not demolish such existing construction beyond indicated lim-its.

y. Unless otherwise indicated, demolition waste becomes the property of the Contractor.

z. Historic items, relics, antiques, and similar objects including, but not limited to, corner-stones and their contents, commemorative plaques and tablets, and other items of inter-est or value to Western that may be uncovered during demolition remain the property of Western. Carefully salvage in a manner to prevent damage and promptly return to the

COR.

2. Bidding Schedule item “Miscellaneous Items" includes the following:

a. Remove demolition waste materials from project site and dispose of them in an EPA ap-proved construction and demolition waste landfill acceptable to authorities having jurisdic-tion, and recycle or dispose of them according to local jurisdiction.

i. Do not allow demolished materials to accumulate on-site.

ii. Remove and transport debris in a manner that will prevent spillage on adjacent sur-faces and areas.

iii. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

b. Do not burn demolished materials.

c. Removed and Salvaged Items:

i. Clean salvaged items.

ii. Pack or crate items after cleaning. Identify contents of containers.

iii. Store items in a secure area until delivery to Western’s warehouse.

iv. Transport items to Western’s warehouse, as designated by the COR.

v. Protect items from damage during transport and storage.

d. Removed and Re-installed Items:

i. Clean and repair items to functional condition adequate for intended re-use.

ii. Pack or crate items after cleaning and repairing. Identify contents of containers.

iii. Protect items from damage during transport and storage.

iv. Re-install items in locations, as indicated by the COR. Comply with installation require-ments for new materials and equipment. Provide connections, supports, and miscel-laneous materials necessary to make item functional for use, as indicated.

e. Existing Items to Remain: Protect existing items, as indicated, against damage and soiling during demolition. When permitted by the COR, items may be removed to a suitable, pro-tected storage location during selective demolition; cleaned and re-installed in their original locations after operations are complete.

5. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items.

a. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demoli-tion operations began.

b. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or dam-aged during selective demolition, by methods and with materials, and using approved con-tractors so as not to void existing warranties. Notify warrantor before proceeding.

Notify warrantor on completion of selective demolition, and obtain documentation verifying that existing system has been inspected, and warranty remains in effect.

Documentation shall be submitted prior to project close-out and final billing.

c. Temporary protection.

d. Barricades.

DIVISION 11 – BUILDINGS

HOLLOW-METAL DOORS AND FRAMES

B. GENERAL

1. MINIMUM THICKNESS: Minimum thickness of base metal without coatings according to

NAAMM-HMMA 803 or SDI A250.8.

2. MANUFACTURERS:

a. Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the work include, but are not limited to, the following:

i. Ceco Door: ASSA ABLOY

ii. Curries Company: ASSA ABLOY

iii. Steelcraft: An Allegion brand

b. Source Limitations: Obtain hollow-metal work from single source from single manufacturer.

C. REGULATORY REQUIREMENTS

1. Fire-Rated Assemblies: Complying with NFPA 80, and listed and labeled by a qualified testing agency acceptable to authorities having jurisdiction for fire-protection ratings indicated, based on testing at positive pressure according to NFPA 252 or UL 10C.

a. Smoke- and Draft-Control Assemblies: Provide an assembly with gaskets listed and labeled for smoke and draft control by a qualified testing agency acceptable to authorities having jurisdiction, based on testing according to UL 1784, and installed in compliance with NFPA 105.

2. Co-ordinate anchorage installation for hollow-metal frames. Furnish setting drawings, tem-plates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors. Deliver such items to the job site in time for installation.

D. SUBMITTAL REQUIREMENTS

1. Provide product data for each type of product. Include construction details, material descriptions, core descriptions, fire resistance ratings, temperature-rise ratings, and finishes.

2. Provide as-built drawings, including:

f. Elevations of each door type.

g. Details of doors, including vertical- and horizontal-edge details and metal thicknesses.

h. Frame details for each frame type, including dimensioned profiles and metal thicknesses.

i. Locations of reinforcement and preparations for hardware.

j. Details of each different wall opening condition.

k. Details of anchorages, joints, field splices, and connections.

l. Details of accessories.

m. Details of conduit and preparations for power, signal, and control systems.

3. Provide test reports for each type of hollow-metal door and frame assembly, for tests performed by a qualified testing agency.

D. INTERIOR DOORS AND FRAMES

1. Construct interior doors and frames to comply with the standards indicated for materials, fabrica-tion, hardware locations, hardware reinforcement, tolerances, and clearances, and as specified.

2. Heavy-Duty Doors and Frames: SDI A250.8, Level 2

f. Physical Performance: Level B according to SDI A250.4

g. Doors:

i. Type: As indicated in the Door and Frame Schedule

ii. Thickness: 1¾-inches (44.5-mm)

iii. Face: Uncoated, cold-rolled steel sheet, 18-gauge minimum thickness

iv. Edge Construction: Model 1, Full Flush

v. Core: Manufacturer's standard kraft paper honeycomb, polysty-rene, polyurethane, polyisocyanurate, mineral-board, or vertical steel-stiffener core at manufacturer's discretion.

h. Frames:

i. Materials: Uncoated steel sheet, 16-gauge minimum thickness

ii. Construction: Full profile welded

i. Exposed Finish: Prime

E. FRAME ANCHORS

1. Jamb Anchors:

a. Steel Stud-Wall Type: Designed to engage stud with screws; not less than 0.042-inches-thick (1.0-mm).

b. Floor Anchors: Formed from same material as frames, minimum thickness of 0.042-inches (1.0-mm), and as follows:

i. Monolithic Concrete Slabs: Clip-type anchors, with two holes to receive fasteners.

F. MATERIALS

1. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B; suitable for exposed applications.

2. Hot-Rolled Steel Sheet: ASTM A 1011/A 1011M, Commercial Steel (CS), Type B; free of scale, pitting, or surface defects; pickled and oiled.

3. Metallic-Coated Steel Sheet: ASTM A 653/A 653M, Commercial Steel (CS), Type B.

4. Frame Anchors: ASTM A 879/A 879M, Commercial Steel (CS), 04Z (12G) coating designation;

mill phosphatized.

a. For anchors built into exterior walls, steel sheet complying with ASTM A 1008/A 1008M or ASTM A 1011/A 1011M, hot-dip galvanized according to ASTM A 153/A 153M, Class B.

5. Inserts, Bolts, and Fasteners: Hot-dip galvanized according to ASTM A 1531A 153M.

6. Power-Actuated Fasteners in Concrete: Fastener system of type suitable for application indi-cated, fabricated from corrosion-resistant materials, with clips or other accessory devices for at-taching hollow-metal frames of type indicated.

7. Mineral-Fiber Insulation: ASTM C 665, Type I (blankets without membrane facing); consisting of fibers manufactured from slag or rock wool; with maximum flame-spread and smoke-developed indexes of 25 and 50, respectively; passing ASTM E 136 for combustion characteristics.

G. FABRICATION

1. Fabricate hollow-metal work to be rigid and free of defects, warp, or buckle. Accurately form metal to required sizes and profiles, with minimum radius for metal thickness. Where practical, fit and assemble units in manufacturer's plant. To ensure proper assembly at the jobsite, clearly identify work that cannot be permanently factory assembled before shipment.

2. Hollow-Metal Doors:

a. Steel-Stiffened Door Cores: Provide minimum thickness 0.026-inches (0.66-mm), steel ver-tical stiffeners of same material as face sheets extending full-door height, with vertical webs spaced not more than six-inches (152-mm) apart. Spot weld to face sheets no more than five-inches (127-mm) o.c. Fill spaces between stiffeners with glass- or mineral-fiber insula-tion.

b. Fire Door Cores: As required to provide fire-protection ratings indicated.

i. Vertical Edges for Single-Acting Doors: Provide beveled or square edges, at manu-facturer's discretion.

ii. Top Edge Closures: Close top edges of doors with flush closures, except provide flush closures at exterior doors of same material as face sheets.

iii. Bottom Edge Closures: Close bottom edges of doors where required for attachment of weather stripping, with end closures or channels of same material as face sheets.

iv. Exterior Doors: Provide weep-hole openings in bottoms of exterior doors to permit moisture to escape. Seal joints in top edges of doors against water penetration.

v. Astragals: Provide overlapping astragal on one leaf of pairs of doors where required by NFPA 80 for fire-performance rating, or where indicated. Extend minimum ¾-inches (19-mm) beyond the edge of the door on which astragal is mounted, or as re-quired, to comply with published listing of qualified testing agency.

3. Hollow-Metal Frames: Where frames are fabricated in sections due to shipping or handling limi-tations, provide alignment plates or angles at each joint, fabricated of same thickness metal as frames.

a. Provide countersunk, flat- or oval-head exposed screws and bolts for exposed fasteners unless otherwise indicated.

b. Provide Steel-Stud Anchors of the correct size: Locate anchors not more than 18-inches (457-mm) from top and bottom of frame.