This document provides project assumptions for the Moab Remedial Action Contract final request for proposal. Key details include: the volume of remaining remedial residue material in the pile and off-pile is estimated at 4,660,000 cubic yards; containers for transportation will include 259 tall containers carrying 40 tons each and 182 short containers carrying 27 tons each; one remaining phase of cell excavation involves removing 750,000 cubic yards; and 500,000 cubic yards remain available for waste placement in the existing disposal cell. Offerors are to incorporate these assumptions into their management approach proposals. The document also lists plans and programs previously co-authored by two contractors that will be required deliverables under the new contract, including waste management, safety, and environmental plans.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOAB RAC – FINAL RFP – PROJECT COMPLETION SECTION L

SOLICITATION NO. 89303320REM000066 – AMENDMENT 0001 (AMENDED)

L-8-1

Attachment L-8

Project/Schedule Assumptions

The following assumptions shall be incorporated into all Offerors’ Management Approach Proposals, for purposes of the evaluation of competitive Closure Strategies:

Volume of RRM (including debris) remaining in the pile: 3,740,000 cubic yards

Volume of sub-pile and off-pile material: 920,000 cubic yards

Conversion factor for cubic yards to tons is 1.4 tons/cubic yard in all cases

Tall containers (qty 259) can carry 40 tons each, short containers (qty 182) can carry 27 tons each

Railcars will not be Government-Furnished

There is one phase remaining to the cell excavation activities (Phase 4) as identified in the

Remedial Action Plan. 750,000 cubic yards remain to be excavated. There remains 500,000 cubic yards available for waste placement in the existing disposal cell

No structures, trailers, roads, or above-ground utilities will remain at the end of the project

Structures, trailers, roads, above-ground utilities, rail sidings not located in the Contamination

Areas (CAs) of Moab and Crescent Junction (CJ) will be free-released if possible, or disposed in the cell at CJ

All non-RRM wastes will be disposed according to state and local regulations

Structures and above-ground utilities within the CA will be disposed in the cell at CJ

No cleanup of Vicinity Properties will be required

RRM containers will be disposed in the cell in CJ; all other equipment will be free-released or disposed in the cell at Crescent Junction or disposed according to state and local regulations

The following assumption is informational to aid all Offerors’ understanding of this RFP: Under the

Moab UMTRA Project, the following plans/programs (which are deliverables that will be required under this Contract) have previously been co-authored by two contractors and/or jointly submitted to DOE.

Copies of these documents will be available to the Contract awardee. Continuation by the awardee of this co-authoring/ joint submittal practice, however, is not required – it is optional. In meeting the Contract’s requirements, the Contractor may take on full ownership of the deliverables, or, where it determines the practice compliant with the requiring regulations/DOE Directive, may choose to submit joint deliverables.

Waste Management Plan

Worker Safety and Health Program

Health and Safety Plan

Integrated Safety Management System (ISMS) Description

Radiation Protection Program

Continuity of Operations Plan (COOP)

Contractor Assurance System Report

Quarterly Performance Analysis Report

Emergency Readiness Assurance Plan (ERAP)

Environmental Management System Manual

Site Sustainability Plan

Integrated Assessment Schedule

Annual Site Environmental Report (ASER)

MOAB RAC – FINAL RFP – PROJECT COMPLETION SECTION L

SOLICITATION NO. 89303320REM000066 – AMENDMENT 0001 (AMENDED)

L-8-2

Permits and Agreements List

Continuity Readiness Assurance Report (CRAR)

Records Management Manual