This document outlines a progress payment schedule for audit assistance services for the Government National Mortgage Association. It specifies twelve partial payments totaling 100% of the contract value to be made upon acceptance of specified deliverables. The deliverables include strategic audit plans, internal control assessments, interim and final legal representation letters, testing of controls, IT systems, and year-end balances, draft and final audit and management letters. Acceptance will generally occur within seven days of receipt except for some early deliverables which allow 30 days. Payments are tied to completion dates ranging from 30 to 360 days from contract award and equate to percentages of the total contract value ranging from 5% to 15%.

View the file

Other files

File Type Posted
Sol_86612720R00001_Amd_0002.pdf PDF
Questions and Answers 2 FINAL 12102019.docx DOCX document
ATTACHMENT #4 - DEGM - Final.docx DOCX document
Sol_86612720R00001_Amd_001.pdf PDF
QA 1.docx DOCX document
P14 - Instructions to Offerors and Evaluation Criteria FINAL FINAL.docx DOCX document
ATTACHMENT A - NFR FORM - 10-2-2019.docx DOCX document
ATTACHMENT 1 FINAL FINAL.docx DOCX document
P02 - PWS - 11-15-19 FINAL FINAL.docx DOCX document
ATTACHMENT D - NDA - 10-10-2019 POST OLC POST CAPD.docx DOCX document
ATTACHMENT 2 FINAL FINAL.docx DOCX document
ATTACHMENT B - NFR GUIDANCE - 10-2-2019.docx DOCX document
ATTACHMENT 3 FINAL FINAL.docx DOCX document
ATTACHMENT C NFR LOGISTICS - 10-2-2019.docx DOCX document
ATTACHMENT #5 - Past Performance Chart - 10-03-2019.docx DOCX document
ATTACHMENT #6 - Past Performance Survey - 10-03-2019.docx DOCX document
ATTACHMENT E - LEVEL PROJECTIONS.docx DOCX document
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT #7

PROGRESS PAYMENT SCHEDULE

Partial Payment #

Base or Option Base

Deliverable*
Dollars
Percent
1
Strategic Audit Plan, Part 1 – billable upon receipt and acceptance of deliverable numbers 1, 2, 3, 5a through 5d, 5i, 6, and

No earlier than 30 days of contract award date

10%

2
Strategic Audit Plan, Part II – billable upon receipt and acceptance of deliverable numbers 4a, 5e through 5h and

No earlier than 60 days of contract award date

10%

3
Internal Control Phase Completion – billable upon receipt and acceptance of deliverable number 8 and

No earlier than 90 days of contract award date

5%

4
Revised Strategic Audit Plan – billable upon receipt and acceptance of deliverable number 9 and

No earlier than 120 days of contract award date

10%

5
Interim Legal Representation Letter – billable upon receipt and acceptance of deliverable number 7a and

No earlier than 150 days of contract award date

5%

6
Control Testing – billable upon receipt and acceptance of deliverable number 11a, 12a and

No earlier than 180 days of contract award date

10%

7
IT Testing – billable upon receipt and acceptance of deliverable 10a and 10b, 14a and

No earlier than 210 days of contract award date

5%

8
Year-end Testing – billable upon receipt and acceptance of deliverable numbers 11b and 12b, 14b, 14c, 14d and

No earlier than 240 days of contract award date

10%

9
Final Audit Reports – billable upon receipt and acceptance of deliverable numbers 7b, 13, 15, 16, and 17; and

No earlier than 270 days of contract award date

15%

10
Draft Management Letter – billable upon receipt and acceptance of deliverable number 18 and

No earlier than 300 days of contract award date

5%

11
Final Management Letter – billable upon receipt and acceptance of deliverable number 19 and

No earlier than 330 days of contract award date

5%

12
Audit Wrap-up – billable upon receipt and acceptance of deliverable numbers 20, 21 22, and 4b; and

No earlier 360 days of contract award date

10%

Totals
$
100.00%

*In general, HUDOIG’s acceptance of the deliverable will be provided within seven calendar days from the receipt of a deliverable. However, due to the nature and volume of the documents for other deliverables HUDOIG’s acceptance will be provided within 30 calendar days from receipt of the deliverable for partial payment numbers 1,2,3,and 4 (see section 6.2) .