Project Overview and Bidding Requirements
This project manual and bidding document package pertains to the Smokestack Demolition project at Transfer Station #3 for the Delaware County Solid Waste Authority (DCSWA) in Broomall, Pennsylvania. The work includes complete demolition of a smokestack and management of resulting debris through either hauling to the DCSWA's Rolling Hills Landfill for disposal or crushing and stockpiling material on-site. A mandatory pre-bid conference is scheduled for November 12, 2026, at 10:00 a.m. at DCSWA Transfer Station #3 (895 Sussex Blvd, Broomall, PA 19008), with attendance required for bid eligibility. Online bids via PennBid must be submitted by December 3, 2026, at 1:00 p.m. local time. The contract term is approximately three months, with substantial completion required by March 12, 2027, and final completion by March 29, 2027. Bid items include mobilization, erosion control, temporary security fence installation, demolition, landfill disposal (3,500 tons), restoration, and demobilization, with an alternate bid item for crushing and stockpiling smokestack brick (2,000 cubic yards). Bidders must demonstrate minimum qualifications including completion of at least three demolition projects involving smokestacks or tall structures within the past five years and must not have been held in default on any DCSWA contract within 36 months prior to bid opening.
Bid Security, Pricing, and Award Criteria
Bidders must submit bid security equal to 10 percent of their maximum bid price in the form of a performance bond. Contract pricing is on a unit price basis, with discrepancies resolved in favor of unit prices. The successful bidder will be the lowest, responsible, responsive bidder as determined by the Owner. Progress payments during performance will be made at 90 percent of completed work value with 10 percent retainage; once 50 percent of work is completed and progress is satisfactory, no additional retainage will be imposed. Upon substantial completion, payment increases to 100 percent of work completed less the estimated value of punch list items. Liquidated damages are assessed at $1,000 per day for failure to achieve substantial completion or final completion dates. Contractors must comply with Pennsylvania Prevailing Wage Act requirements, maintain required performance and payment bonds, provide proof of state contractor licensure, and demonstrate authority to do business in Pennsylvania. The Owner is exempt from sales and use taxes on materials and equipment incorporated into the work.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
22 Denver Road, Suite E | Denver, PA 17517 610-382-3050 | scsengineers.com
Project No. 02222834.01| October 27, 2026
Project Manual Smokestack Demolition Transfer Station #3
DELAWARE COUNTY SOLID WASTE AUTHORITY
610 E. Baltimore Avenue, Media, PA 19063
SECTION 00 00 10
Table of Contents
BIDDING REQUIREMENTS
C-111 Advertisement C-200 Instructions to Bidders C-410 Bid Form NA-1 Non-Collusion Affidavit Iran Free Procurement Certification Form C-435 Bid Bond C-451 Contractor Qualifications W-9 IRS Request for Taxpayer Identification Number and Certification (to be provided by Contractor)
CONTRACT FORMS
C-510 Notice of Award C-520 Agreement C-550 Notice to Proceed C-610 Performance Bond C-615(A) Construction Payment Bond Certificate of Insurance (to be provided by Contractor) C-620 Contractorʼs Application for Payment C-625 Certificate of Substantial Completion C-940 Work Change Directive C-941 Change Order C-942 Field Order
CONDITIONS OF THE CONTRACT
C-700 General Conditions C-800 Supplementary Conditions Attachment A: Prevailing Wage Rates Attachment B: Public Works Employment Verification Form
TECHNICAL SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 22 13 Measurement and Payment 01 31 13 Project Coordination and Meetings
01 32 19 Contractorʼs Drawings and Submittals 01 32 23 Survey and Layout Data 01 35 29 Health and Safety 01 35 43 Environmental Protection 01 50 00 Temporary Facilities and Controls 01 77 00 Closeout Procedures
DIVISION 31 – EARTHWORK
31 22 30 Site Preparation and Demolition 31 25 00 Erosion and Sediment Control
DRAWINGS
1. Existing Conditions
2. Demolition Plan
ATTACHMENTS
A B
GPRS Utility Locating Asbestos Sampling Report
END OF SECTION
BIDDING REQUIREMENTS
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ADVERTISEMENT FOR BIDS
DELAWARE COUNTY SOLID WASTE AUTHORITY
BROOMALL, PENNSYLVANIA
SMOKESTACK DEMOLITION
General Notice
Delaware County Solid Waste Authority (Owner) is requesting Bids for the following Project:
Smokestack Demolition
Bids for the Project will be received online via PennBid until December 3, 2026 at 1:00 p.m. local time.
Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com) by the date and time indicated in the Instruction to Bidders along with the Bid security and the other documents required to be submitted as identified herein. It is advised that bidders contact the Owner to make sure the bid has been received. Bidding documents will only be distributed online at PennBid.
The work includes the furnishing of all labor, materials and equipment necessary to complete the work as shown on the Drawings and as described in the Specifications. The project includes demolition of a smokestack, and managing debris either by hauling it to the DCSWA’s Rolling Hills Landfill for disposal, or crushing and stockpiling the material on-site.
Mandatory Pre-bid Conference
A pre-bid conference for the Project will be held on November 12, 2026 at 10 a.m. at DCSWA Transfer Station #3 located at 895 Sussex Blvd, Broomall, Pennsylvania, 19008. Attendance at the pre-bid conference is mandatory.
Instructions to Bidders.
For all further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.
This Advertisement is issued by:
Owner: Delaware County Solid Waste Authority By: Ben Patti Title: DCSWA Accounting Manager Date: October 27, 2026
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
TOC Page1 of 1
INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
Article 1— Defined Terms
Article 2— Bidding Documents
Article 3— Qualifications of Bidders
Article 4— Pre-Bid Conference
Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site
Article 6— Bidder’s Representations and Certifications
Article 7— Interpretations and Addenda
Article 8— Bid Security
Article 9— Contract Times
Article 10— Substitute and “Or Equal” Items
Article 11— Subcontractors, Suppliers, and Others
Article 12— Preparation of Bid
Article 13— Basis of Bid
Article 14— Submittal of Bid
Article 15— Modification and Withdrawal of Bid
Article 16— Opening of Bids
Article 17— Bids to Remain Subject to Acceptance
Article 18— Evaluation of Bids and Award of Contract
Article 19— Bonds and Insurance
Article 20— Signing of Agreement
Article 21— Sales and Use Taxes
Article 22— Employment Guidelines
Article 23— Prevailing Wage
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ARTICLE 1—DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.
B. Bidder means one who submits a Bid directly to Owner, as distinct from a sub-Bidder, who submits a bid to a Bidder.
C. Successful Bidder means the lowest, responsible Bidder to whom Owner (on the basis of Owner's evaluation as hereinafter provided) makes an award.
D. Bidding Documents includes the Advertisement and Invitation to Bid, Instructions to Bidders, Bid Form and the Contract Documents (including all Addenda issued prior to receipt of Bids).
1.02 Other terms used in the Bidding Documents and not defined elsewhere have the following meanings, which are applicable to both the singular and plural thereof:
A. Day means a calendar day of twenty-four (24) hours measured from midnight to the next midnight shall constitute a day, unless otherwise specified.
B. Contract Drawings means "Drawings" as defined in the General Conditions of the Contract Documents.
ARTICLE 2—BIDDING DOCUMENTS
2.01 Bidding documents are available at no cost via the PennBid Program (https://pennbid.bonfirehub.com).
2.02 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.
2.03 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.
ARTICLE 3—QUALIFICATIONS OF BIDDERS
3.01 Bidder is to submit the following information with its Bid to demonstrate Bidder’s qualifications to perform the Work:
A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.
C. Bidder’s state or other contractor license number, if applicable.
D. Subcontractor and Supplier qualification information.
E. Other required information regarding qualifications.
3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
3.04 The Bidder, including any individual, corporation, or partnership affiliated in any way with the Bidder, including any of Bidder’s subcontractors, shall not appear on the current Pennsylvania Department of Labor and Industry Debarment List.
3.05 A bid may be rejected at Owner’s sole discretion if the Bidder does not submit evidence that it meets or exceeds the above minimum qualifications.
3.06 At a minimum, the Bidder shall provide demonstrative evidence that it meets or exceeds the following qualifications:
A. Within the last five (5) years, the Bidder has completed at least three (3) demolition projects that have involved demolition of smokestacks or tall structures.
B. The Bidder, including any individual, corporation, or partnership affiliated in any way with the Bidder, shall not have been held in default by Owner on any contract of Owner within 36 months prior to the day of the Bid Opening.
ARTICLE 4—PRE-BID CONFERENCE
4.01 A mandatory pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project. Proposals will not be accepted from Bidders who do not attend the conference. It is each Bidder’s responsibility to sign in at the pre-bid conference to verify its participation. Bidders must sign in using the name of the organization that will be submitting a Bid. A list of qualified Bidders that attended the pre-bid conference and are eligible to submit a Bid for this Project will be issued in an Addendum.
4.02 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.
ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S
SAFETY PROGRAM; OTHER WORK AT THE SITE
5.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
5.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:
a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.
b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.
c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.
B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.
C. No other Site-related documents are available.
5.03 Site Visit and Testing by Bidders
A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.
B. A Site visit is scheduled following the pre-bid conference. Maps to the Site will be available at the pre-Bid conference.
C. Bidders visiting the Site are required to arrange their own transportation to the Site.
D. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the following Owner or Engineer contact for visiting the Site: Ben Patti, DCSWA
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Accounting Manager, 610-892,9620, bpatti@dcswa.net. Bidder must conduct the required Site visit during normal working hours.
E. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.
F. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.
G. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
H. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
5.04 Owner’s Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.
5.05 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Express Representations and Certifications in Bid Form, Agreement
A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.
B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.
ARTICLE 7—INTERPRETATIONS AND ADDENDA
7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents via the “Messages/Vendor Discussions” feature in PennBid no later than seven (7) days prior to the date for receipt of bids.
7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.
7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.
ARTICLE 8—BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.
ARTICLE 9—CONTRACT TIMES
9.01 The date by which, the Work and identified portions thereof (Milestones) are to be substantially complete and available for Owner’s use, and also completed and ready for final payment (the Contract Time), are set forth in the Agreement. Such Contract Times are of the essence..
9.02 The phrase “available for Owner’s Use” does not mean physically capable of being utilized by Owner. The phrase “available for Owner’s Use” means that the Owner is able to commence and carry out its operations in accordance with the design intent of the Plans and Specifications and not alter its normal operating procedure as a result of any failure by Contractor to complete any aspect of that portion of the Work.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
9.03 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.
ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS
10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.
10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.
ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS
11.01 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed within five days after Bid opening.
11.02 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, without an increase in Bid price.
11.03 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.
Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder.
ARTICLE 12—PREPARATION OF BID
12.01 The Bid Form is included with the Bidding Documents for reference. Bidders shall complete the electronic bid form within PennBid (“Prepare Your Submission” tab).
12.02 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.
12.03 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.
12.04 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
12.05 A Bid by an individual must show the Bidder’s name and official address.
12.06 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.
12.07 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.
12.08 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.
12.09 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.
ARTICLE 13—BASIS OF BID
13.01 Unit Price
A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
ARTICLE 14—SUBMITTAL OF BID
14.01 A Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com) by the date and time indicated in the Invitation for Bids along with the Bid security and the other documents required to be submitted as identified herein.
14.02 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted.
The following documents are submitted with and made a condition of this Bid:
A. Required Bid security;
B. Bid Form (with completed Bid Schedule)
C. List of Proposed Subcontractors;
D. Evidence of authority to do business in the state of the Project;
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
E. Evidence of Bidder’s State Contractor’s License;
F. Required Bidder Qualification Statement with Project Information (Schedule A & B);
G. Non-Collusion Affidavit;
H. Consent of Surety;
I. Owner Disclosure Form;
J. Bid Document and Submission Checklist;
K. Bidder’s Affidavit;
L. Acknowledgement of Addenda;
M. Disclosure of Investment Activities in Iran;
N. Affirmative Action Affidavit; and
O. Affirmative Action Requirements.
ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID
15.01 A Bid may be withdrawn or modified at any time within PennBid prior to the due date and time identified in the Invitation for Bids.
15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.
15.03 No Bid may be withdrawn after the opening of Bids, except in accordance with Pennsylvania law relating to the withdrawal of bids, Act 4, approved January 23, 1974, P.L. 9, Section 1 et. seq., as amended.
ARTICLE 16—OPENING OF BIDS
16.01 A summary of bids received will be issued via a Public Notice on PennBid shortly after bid opening, the time of which is listed in the Invitation to Bid. It should be noted that bid results are subject to further review and should not be construed as issuance of an award.
ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE
17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT
18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.
18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.
18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.
18.05 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
18.06 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 19—BONDS AND INSURANCE
19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.
19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.
ARTICLE 20—SIGNING OF AGREEMENT
20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.
ARTICLE 21—SALES AND USE TAXES
21.01 Owner is exempt from Pennsylvania state sales and use taxes on materials and equipment to be incorporated in the Work. Said taxes must not be included in the Bid. Refer to Paragraph SC-7.10 of the Supplementary Conditions for additional information.
ARTICLE 22—EMPLOYMENT GUIDELINES
22.01 Attention of Bidders is particularly called to the requirement for ensuring that employees and applicants for employment are not discriminated against because of their race, color, religion, sex, age, ancestry, national origin, or handicap. Responsibility under the Immigration Reform and Control Act of 1986, for verifications of identity and employment eligibility in connection with Bidder’s own agents/servants, workers, and employees, is assumed and continues to be assumed and complied with by the Bidder. The Bidder/Contractor expressly agrees to comply with the
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Americans with Disabilities Act of 1990 (the “ADA”), and all other applicable Federal, State, and/or Local laws, ordinances, rules regulations and orders prohibiting discrimination in hiring or employment opportunities. Compliance is not delegable to any union, training program, or other source of recruitment, which prevents the Successful Bidder from meeting his/her obligations hereunder. The Successful Bidder has the responsibility and obligation to become aware of and comply with all applicable statutes, rules, regulations, etc. which affect this transaction in any regard.
ARTICLE 23—PREVAILING WAGE
23.01 The Successful Bidder will be required to comply with the Pennsylvania Prevailing Wage Act.
EJCDC® C-410, Bid Form for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BID FORM FOR CONSTRUCTION CONTRACT
The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
ARTICLE 1—OWNER AND BIDDER
1.01 This Bid is submitted to: Delaware County Solid Waste Authority.
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2—ATTACHMENTS TO THIS BID
2.01 The following documents are submitted with and made a condition of this Bid:
A. Required Bid security;
B. List of Proposed Subcontractors;
C. List of Proposed Suppliers;
D. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids;
E. Contractor’s license number as evidence of Bidder’s State Contractor’s License or a covenant by Bidder to obtain said license within the time for acceptance of Bids; and, F. Bidder Qualification Statement with supporting data.
ARTICLE 3—BASIS OF BID—UNIT PRICES
3.01 Unit Price Bids
A. Bidder will perform the following Work at the indicated unit prices:
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Description Approx.
Quantity Unit Unit Price Total Price
1. Mobilization 1 LS __________/LS $___________________________.______
2. Erosion Control 1 LS __________/LS $___________________________.______
3. Temporary Security Fence Installation
1 LS __________/LS $___________________________.______
4. Demolition 1 LS __________/LS $___________________________.______
5. Landfill Disposal 3,500 Ton _________/Ton $___________________________.______
6. Restoration 1 LS __________/LS $___________________________.______
7. Demobilization 1 LS __________/LS $___________________________.______
Total Bid (in words) for Bid Items 1 through 7: ______________________________________________
Alternate Bid Item
#1: Crush to 3” Minus and Stockpile
Smokestack Brick
2,000 CY _______/CY $_____________________________.____
Contractor’s Proposed Method of Demolition: ________________________________________________
B. Bidder acknowledges that:
1. each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and
2. estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.
ARTICLE 4—TIME OF COMPLETION
4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
4.02 Bidder accepts the provisions of the Agreement as to liquidated damages.
ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF
ADDENDA
5.01 Bid Acceptance Period
A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
5.02 Instructions to Bidders
A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.
5.03 Receipt of Addenda
A. Bidder hereby acknowledges receipt of the following Addenda:
Addendum Number Addendum Date
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Bidder’s Representations
A. In submitting this Bid, Bidder represents the following:
1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.
2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.
4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.
5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.
6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and
(c) Bidder’s (Contractor’s) safety precautions and programs.
7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.
8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.
10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
6.02 Bidder’s Certifications
A. The Bidder certifies the following:
1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.
2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.
3. Bidder has not solicited or induced any individual or entity to refrain from bidding.
4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 8.02.A:
a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.
b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.
c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.
d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BIDDER hereby submits this Bid as set forth above:
Bidder:
(typed or printed name of organization)
By:
(individual’s signature) Name:
(typed or printed) Title:
(typed or printed)
Date:
(typed or printed)
If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.
Attest:
(individual’s signature)
Name:
(typed or printed)
Title:
(typed or printed)
Date:
Address for giving notices:
Bidder’s Contact:
Name:
(typed or printed)
Title:
(typed or printed)
Phone:
Email:
Address:
Bidder’s Contractor License No.: (if applicable)
BOP-1701
Published: 1/26/2017
IRAN FREE PROCUREMENT CERTIFICATION FORM
(Pennsylvania’s Procurement Code Sections 3501-3506, 62 Pa.C.S. §§ 3501-3506)
To be eligible for an award of a contract with a Commonwealth entity for goods or services worth at least $1,000,000 or more, a vendor must either: a) certify it is not on the current list of persons engaged in investment activities in Iran created by the Pennsylvania Department of General Services (“DGS”) pursuant to Section 3503 of the Procurement Code and is eligible to contract with the Commonwealth under Sections 3501-3506 of the Procurement Code; or b) demonstrate it has received an exception from the certification requirement for that solicitation or contract pursuant to Section 3503(e).
To comply with this requirement, please insert your vendor or financial institution name and complete one of the options below. Please note: Pennsylvania law establishes penalties for providing false certifications, including civil penalties equal to the greater of $250,000 or twice the amount of the contract for which the false certification was made; contract termination; and three-year ineligibility to bid on contracts. (Section 3503 of the Procurement Code.)
OPTION #1 - CERTIFICATION
I, the official named below, certify I am duly authorized to execute this certification on behalf of the vendor/financial institution identified below, and the vendor/financial institution identified below is not on the current list of persons engaged in investment activities in Iran created by DGS and is eligible to contract with the Commonwealth of Pennsylvania Sections 3501-3506 of the Procurement Code.
Vendor Name/Financial Institution (Printed)
By (Authorized Signature)
Printed Name and Title of Person Signing Date Executed
OPTION #2 – EXEMPTION
Pursuant to Procurement Code Section 3503(e), DGS may permit a vendor/financial institution engaged in investment activities in Iran, on a case-by-case basis, to enter into a contract for goods and services.
If you have obtained a written exemption from the certification requirement, please fill out the information below, and attach the written documentation demonstrating the exemption approval.
Vendor Name/Financial Institution (Printed)
By (Authorized Signature)
Printed Name and Title of Person Signing Date Executed
EJCDC® C-435, Bid Bond (Damages Form).
Copyright© 2018 National Society of Professional Engineer, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BID BOND (DAMAGES FORM)
Bidder Surety Name: [Full formal name of Bidder] Name: [Full formal name of Surety]
Address (principal place of business): Address (principal place of business):
[Address of Bidder’s principal place of business] [Address of Surety’s principal place of business]
Owner Bid
Name: Delaware County Solid Waste Authority Project (name and location):
Address (principal place of business): Smokestack Demolition, Transfer Station #3, 895 Sussex Blvd, Broomall, Pennsylvania, 19008 610 E. Baltimore Avenue, Media, PA 19063
Bid Due Date: November 25, 2026
Bond
Bond Amount: [Amount]
Date of Bond: [Date] Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth in this Bid Bond, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.
Bidder Surety
(Full formal name of Bidder) (Full formal name of Surety) (corporate seal)
By: By:
(Signature) (Signature) (Attach Power of Attorney)
Name: Name:
(Printed or typed) (Printed or typed)
Title: Title:
Attest: Attest:
(Signature) (Signature)
Name: Name:
(Printed or typed) (Printed or typed)
Title: Title:
Notes: (1) Note: Addresses are to be used for giving any required notice. (2) Provide execution by any additional parties, such as joint venturers, if necessary.
EJCDC® C-435, Bid Bond (Damages Form).
Copyright© 2018 National Society of Professional Engineer, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder any difference between the total amount of Bidder’s Bid and the total amount of the Bid of the next lowest, responsible Bidder that submitted a responsive Bid, as determined by Owner, for the work required by the Contract Documents, provided that:
1.1. If there is no such next Bidder, and Owner does not abandon the Project, then Bidder and Surety shall pay to Owner the bond amount set forth on the face of this Bond, and
1.2. In no event will Bidder’s and Surety’s obligation hereunder exceed the bond amount set forth on the face of this Bond.
1.3. Recovery under the terms of this Bond will be Owner’s sole and exclusive remedy upon default of Bidder.
2. Default of Bidder occurs upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.
3. This obligation will be null and void if:
3.1. Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or
3.2. All Bids are rejected by Owner, or
3.3. Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).
4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.
5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions will not in the aggregate exceed 120 days from Bid due date without Surety’s written consent.
6. No suit or action will be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety, and in no case later than one year after the Bid due date.
7. Any suit or action under this Bond must be commenced only in a court of competent jurisdiction located in the state in which the Project is located.
8. Notices required hereunder must be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Postal Service registered or certified mail, return receipt requested, postage pre-paid, and will be deemed to be effective upon receipt by the party concerned.
9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .