This is a Statement of Work (SOW) for the White Sands Complex (WSC) Second TDRSS Ground Terminal in Las Cruces, New Mexico, a NASA-supporting facility requiring procurement of materials for water fountain replacement and modernization.
The SOW requires the provision of four new water fountains with integrated bottle filling stations to replace existing units, comprising one Elkay ezH2O® Retrofit Bottle Filling Station for SwirlFlo® Fountain Filtered Refrigerated Stainless (Model LZWS-ERPB8-RF) and three Elkay ezH2O® Bottle Filling Station & SwirlFlo® Single Fountain High Efficiency Filtered Refrigerated Stainless units (Model LZWS-SFGRN8K). The contractor must provide all installation materials including four Fernco PVC couplings (1-1/2-in and 1-1/4-in Schedule 40), four SharkBite angle valves with stop function, one SharkBite removal tool, flexible faucet supply lines, P-traps, brass cap fittings, reducing couplings, two 50-foot spools of SharkBite PEX-B pipe (1/4-in and 3/8-in), and four Dial Manufacturing brass insert tubes. Additionally, the contractor must supply two years' worth of replacement filters for each fountain based on manufacturer recommendations and ensure material compatibility with existing building infrastructure to minimize installation labor. Installation will be conducted separately under task order SENSE TO-137.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SATPC0041255 Tab 10 Open Market RFQ.pdf | ||
| SATPC0041255 Tab 04 4 SOW.pdf | ||
| SATPC0041255 Tab 10 Open Market RFQ.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW Background The White Sands Complex (WSC) Second TDRSS Ground Terminal (STGT) is a facility in Las Cruces, New Mexico dedicated to supporting NASA by providing essential communications infrastructure and services. This SOW involves procuring materials necessary for the replacement of four existing water fountains with modern filtered water bottle filling stations, ensuring improved access to clean drinking water for personnel and visitors. Installation of these stations will be conducted under a separate task order, with the goal of enhancing the facility’s amenities and supporting ongoing mission readiness.
Technical Task Requirements
• Provide four new water fountains with integrated bottle filling stations to replace the existing units at WSC STGT.
• Installation is not included in this Statement of Work and will be addressed separately under
SENSE TO-137.
• Basis of design:
o 1 qty: Elkay ezH2O® Retrofit Bottle Filling Station for SwirlFlo® Fountain Filtered Refrigerated Stainless (Model LZWS-ERPB8-RF) o 3 qty: Elkay ezH2O® Bottle Filling Station & SwirlFlo® Single Fountain High Efficiency Filtered Refrigerated Stainless (Model: LZWS-SFGRN8K)
• Provide materials needed for installation as provided in below list as basis of design. Provide item below or equivalent:
o 4 qty: Fernco - 1-1/2-in Schedule 40 PVC Coupling (Model #P1056-150) o 4 qty: SharkBite 1/2-in Push-to-connect x 3/8-in Compression Brass Quarter turn Stop
Angle valve (Model #UR23036ZC) o 1 qty: SharkBite - 1/2 In Removal tool (Model #U710Z) o 4 qty: Fernco - 1-1/4-in Schedule 40 PVC Coupling (Model #P1056-150/125) o 4 qty: RELIABILT 3/8-in compression x 3/8-in Compression x 20-in Braided stainless steel
Flexible Faucet Supply Line (Model #7223-20-38-6-RB) o 4 qty: Dearborn - 1-1/2-in PVC P-trap (Model #1000000665) o 4 qty: ProLine Series - 2 -Pack Brass 3/8-in Female Cap Fitting (Model #CP-107NLB) o 4 qty: SharkBite - 3/8-in OD x 1/4-in OD Pushto-Connect Reducing Coupling (Model
#25424Z) o 1 qty: SharkBite - 1/4-in (3/8-in O.D.) x 50-ft White PEX-B Pipe (Model #U850W50) o 1 qty: SharkBite - 3/8-in (1/2-in O.D) x 50-ft White PEX-B Pipe (Model #U855W50) o 4 qty: Dial Manufacturing 9512 DelrIn Sleeve and Poly Tube Brass Insert Tube ¼ (Model
#9512-0D36)
• Ensure material compatibility with existing building infrastructure thus minimizing labor needed for installation.
• Include two years’ worth of replacement filters for each fountain, based on manufacturer’s recommended replacement intervals.