QA4.docx

DOCX document 12 KB Posted

Attached to
Heat Exchanger Demolition Federal contract opportunity
Solicitation number
80NSSC19Q0416
Issued by
National Aeronautics and Space Administration Shared Services Center

About this file

Please see attached question and answer.

View the file

Other files for this federal contract opportunity

Other files attached to Heat Exchanger Demolition, newest first.
File Type Posted
QA_5.docx DOCX document
Q&A_3.pdf PDF
Q&A.docx DOCX document
RFQ_80NSSC19Q0416.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The Q and A posted yesterday states that a pump is to become the property of the Government? There is no reference to removing pump, piping, and HX enclosure in the SOW. There is no electrical or control wiring demolition mentioned in the SOW. A photo shows piping, pump, electrical, controls, HX housing etc but does not stat the demolition of these items.

Please provide clarification?

NCCIPS expects all items removed from the heat exchanger pad including the pump, piping, pipe stands, and HX enclosure. The items listed as (items to keep) are to be placed by the contractor on a NCCIPS component provided trailer as stated in the SOW (Section F Contract Requirements) and will remain property of the Government. It is NCCIPS responsibility to remove electrical wiring, control wiring and associated conduit.