80JSC022R0009 SST III RFP - A0002 - Change Matrix.pdf
PDF 63 KB Posted
- Attached to
- Simulation and Software Technology (SST) III Federal contract opportunity
- Solicitation number
- 80JSC022R0009
About this file
This document outlines changes made to the Simulation and Software Technology (SST) III Request for Proposal (RFP) 80JSC022R0009 issued by the National Aeronautics and Space Administration Johnson Space Center.
The RFP seeks proposals for software engineering and related services in support of NASA's Johnson Space Center. Changes include removing language from a contract value clause, updating references to attachments, adding experience requirements to key personnel descriptions, and increasing page limits for proposal volumes. The proposal due date is March 28, 2022. A pre-proposal pricing conference will be held virtually on March 7, 2022. Interested parties must register by March 4.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
80JSC022R0009 A0002 Change Matrix
Change # RFP Reference RFP Section Page No. Change Description
1 B.8(a) Section B 10 The language "shall not be included in contract value” was removed from this clause.
2 G.3(c) Section G 29 Attachment J-16, Government Furnished Property reference was removed from paragraph (c).
3 DRD-05, B.1 Section J Attachments 79 Paragraph f added under the Program and Performance Management section.
4 DRD-12, A Section J Attachments 104 DRD referenced in Section A has been updated to reflect "J-14, Abbreviated Compensation Plan."
5 DRD-13, A Section J Attachments 107 DRD referenced in Section A has been updated to reflect J-15, Small Business Subcontracting Plan and Reports.
6 DRD-13, B.2.ii Section J Attachments 108
"DRD-TEST3-CM-04" referenced in Section B, was replaced with "H.5, JPI 52.219-90 SMALL BUSINESS
SUBCONTRACTING GOALS (OCT 2006) (JOHNSON
PROCUREMENT INSTRUCTION)."
7 Attachment J-4 Section J Attachments 141-142
Attachment J-4 language was updated to include "Degree in Engineering or Science" to the following SLC descriptions: Engr 1, Engr 2, Sr. Engr 1, Principal Engr 1, Principal Engr 2 and Principal Engr 3.
8 Attachment J-4 Section J Attachments 141-142 Years of Experience Required and Job Description Guidelines updated for Graphic Spc.
9 Attachment, J-14 Section J Attachments 153 J-14 title is changed to reflect "Abbreviated Compensation Plan."
10 L.8 Section L 178 Paragraph b was amended to reflect "L.22, JPI 52.215- 113 Proposal Formatting Instructions."
11 L.12 Section L 181 Clause has been removed. L.12 is now reserved.
12 L.20 Section L 185 Updated first table to reflect correct paragraph references.
13 L.21(b), Table L.2 Section L 187
MA2 has been updated to reflect "Abbreviated Compensation Plan." Page limitations have been increased by 5 pages for Mission Suitability and Past Performance Volumes. Basis of Estimate for Sample Task Orders has been excluded from the Volume I page limit and Small Business Partcipation Statements and Export Control have been excluded from the Volume II page limit.
14 L.22(b)(2) Section L 189 Paragraph (b)(2) was updated to require offerors to submit electronic proposals in Microsoft Office 2016 or higher.
15 L.23.1, MA2 Section L 191 "Abbreviated" added to reference of Total Compensation Plan.
16 L.23.1, MA4 Section L 190 MA4 - Key Personnel Approach modified.
17 L.23.2(c)(3) Section L 194 Paragraph (c)(3) revised to include this statement, "Offerors may consolidate their mappings and present this content only once in Volume I."
18 L.23.2(c)(4), Table L.4 Section L 195 The GRE for STO2 has been changed from 23 to 13 WYEs.
19 L.23.4(h) Section L 199 Paragraph (h) has been revised.
20 Attachment L-4 Section L 240
6.c modified to reflect "References, including points of contact (contracting officer, contracting officer's representative, technical representative, etc.) and contract numbers, for experience referenced in item b above." Also, 6.f has been deleted.
21 Attachment L-6, EPM Section L 243 Several Changes have been made to the EPM based on RFP questions received.
22 M.5 Section M 250 "Abbreviated" added to reference of Total Compensation Plan.
23 M.10(b)(1) Section M 258 Paragraph (b)(1) has been revised to reflect 9.5 versus 9.504.
File details come from the government source that posted it. Updated .