This notice announces a forthcoming request for proposal for the Human Space Flight Technical Integration Contract. NASA/JSC plans to issue an RFP on or around November 1st, 2019, with proposals due December 11th, 2019. The contract is a total small business set-aside under NAICS code 541715 with a size standard of 1,250 employees. The contractor will provide technical integration services for human space flight programs. The solicitation and amendments will be available online at the listed websites. Prospective offerors must monitor the sites and are responsible for downloading documents. All technical questions must be submitted in writing.

SSP 50182

Text of this file

SSP 50182

NASA/ASI Bilateral Safety and Product Assurance Requirements V International Space Station Program

May 2, 1996 file_0.wmf file_1.doc thumbnail_0.wmf

National Aeronautics and Space Administration International Space Station Program Johnson Space Center Houston, Texas

Agenzia Spaziale Italiana (Italian Space Agency) Rome, Italy

REVISION AND HISTORY PAGE

Revision Letter Description Publication Date

Initial Release

09-13-99 ii i

PREFACE

The NASA/ASI Bilateral Safety and Product Assurance Requirements document is a joint National Aeronautics and Space Administration (NASA) and Agenzia Spaziale Italiana (ASI) document which describes all safety and product assurance requirements applicable to the ASI.

Both NASA and ASI herein mutually agree that the execution of this document is necessary for the effective and safe integration of the Mini-Pressurized Logistics Module (MPLM) in to the International Space Station.

/s/ T. W. Holloway 8/23/99____/s/ Silvana Rabbia 7/20/99
Thomas W. HollowaySilvana Rabbia
Manager, Space Station ProgramProgram Manager,
ASI MPLM Program

INTERNATIONAL SPACE STATION PROGRAM

NASA/ASI BILATERAL SAFETY AND PRODUCT ASSURANCE REQUIREMENTS DOCUMENT

CONCURRENCE

May, 1996

Prepared By:Dale Cegielski_NASA
(NASA)PRINT NAMEORGN
/s/ John K. Trainor for7/20 /99
SIGNATUREDATE

Concurred By: Gregg Baumer NASA (NASA Mgr S&MA for

International Partners)PRINT NAMEORGN
/s/ Gladys M. Henderson for7/20 /99
SIGNATUREDATE
Concurred By:Francesco P. CantelliASI PA
(ASI)PRINT NAMEORGN
/s/ Francesco P. Cantelli7/20/99
SIGNATUREDATE
DQARichard DelgadoNASA
PRINT NAMEORGN
/s/ Richard Delgado8/2/99
SIGNATUREDATE

INTERNATIONAL SPACE STATION PROGRAM

NASA/ASI BILATERAL SAFETY AND PRODUCT ASSURANCE

REQUIREMENTS DOCUMENT

LIST OF CHANGES

August 25, 1995

All changes to paragraphs, tables, and figures in this document are shown below:

SSCBD

Entry Date Change Paragraph(s)

TABLE OF CONTENTS

PARAGRAPH PAGE

1.0INTRODUCTION.1-1
1.1PURPOSE1-1
1.2SCOPE1-1
1.3MANAGEMENT APPROACH1-1
1.4RELATION TO OTHER REQUIREMENTS1-1
1.4.1PROGRAM REQUIREMENTS1-1
1.4.2GSE HARDWARE AND SOFTWARE1-2
1.5MOTIVATION.1-2
1.6INDEPENDENT EVALUATIONS FOR NASA OR THE
INTERNATIONAL PARTNERS1-2
1.7DATA REQUIREMENT DESCRIPTIONS1-2
1.8SAFETY AND PRODUCT ASSURANCE DATABASE1-2
1.9MILESTONE REVIEWS1-2
1.10CERTIFICATION1-3
1.11DELEGATION OF AUTHORITY.1-3
2.0APPLICABLE DOCUMENTS2-1
3.0RELIABILITY AND MAINTAINABILITY3-1
3.1MANAGEMENT3-1
3.1.1ORGANIZATION3-1
3.1.1.1THE PROGRAM OFFICE OVERSIGHT RESPONSIBILITY3-1
3.1.1.2PROGRAM OFFICE AVAILABILITY ASSESSMENT3-1
3.1.2RELIABILITY AND MAINTAINABILITY PLAN3-1
3.1.3AUDITS AND SURVEYS3-1
3.1.4SUPPLIER RELIABILITY AND MAINTAINABILITY CONTROL3-2
3.1.5NASA OR INTERNATIONAL PARTNER FURNISHED EQUIPMENT
(GFE/IGFE) RELIABILITY AND MAINTAINABILITY3-2
3.2RELIABILITY AND MAINTAINABILITY ENGINEERING3-2
3.2.1RELIABILITY AND MAINTAINABILITY DESIGN CRITERIA3-2
3.2.2RELIABILITY AND MAINTAINABILITY ANALYSES/TRADE STUDIES.3-2
3.2.2.1RELIABILITY ANALYSES/TRADE STUDIES3-2
3.2.2.2MAINTAINABILITY ANALYSES/TRADE STUDIES3-2
3.2.2.3PROGRAM OFFICE SUPPORTABILITY/AVAILABILITY
ANALYSES/TRADE STUDIES3-3
3.2.3HARDWARE FAILURE MODES AND EFFECTS ANALYSES3-3
3.2.3.1FLIGHT HARDWARE FMEAS3-3
3.2.3.2GROUND SUPPORT EQUIPMENT FMEAS3-3
3.2.3.3PAYLOAD FMEAS3-3
3.2.4CRITICALITY CATEGORIES3-3
3.2.5CRITICAL ITEM CONTROL3-3
3.2.5.1CRITICAL ITEMS LIST PREPARATION3-3
3.2.5.2RESERVED3-4
3.2.5.3RESERVED3-4
3.2.5.4CRITICAL ITEMS LIST PRIORITIZATION3-4
3.2.6RELIABILITY AND MAINTAINABILITY DATA3-4
3.2.6.1FLIGHT AVIONICS HARDWARE OPERATING TIME3-4
3.2.7LIMITED-LIFE ITEMS3-4
3.2.8MILESTONE REVIEWS3-4
3.2.9CONFIGURATION CONTROL BOARDS AND PANELS3-4
3.2.10PROBLEM REPORTING SYSTEM3-4
3.2.11VERIFICATION ASSURANCE3-4
3.3ELECTRICAL, ELECTRONIC, AND ELECTROMECHANICAL AND
MECHANICAL PARTS CONTROL3-5
3.3.1ELECTRICAL, ELECTRONIC, AND ELECTROMECHANICAL PARTS3-5
3.3.1.1GENERAL3-5
3.3.1.2ELECTRICAL, ELECTRONIC, AND ELECTROMECHANICAL PARTS
SELECTION3-5
3.4Materials and Processes3-5
3.5REPORTING PARTS AND MATERIALS PROBLEMS AND
ASSESSING ALERTS3-5
3.5.1NASA ALERTS3-5
3.5.2INTERNATIONAL PARTNERS ALERTS3-6
4.0QUALITY ASSURANCE4-1
4.1MANAGEMENT AND PLANNING4-1
4.1.1PLANNING4-1
4.1.2ORGANIZATION4-1
4.1.2.1THE SPACE STATION PROGRAM OVERSIGHT RESPONSIBILITY4-1
4.1.3QUALITY PROGRAM PLAN4-1
4.1.4RESERVED4-2
4.1.5MANAGEMENT ASSESSMENT DATA4-2
4.1.6TRAINING4-2
4.1.7INTERNAL QUALITY PROGRAM AUDITS AND SURVEYS4-2
4.1.8MILESTONE REVIEWS4-2
4.2DESIGN AND DEVELOPMENT CONTROLS4-3
4.2.1TECHNICAL DOCUMENTS4-3
4.2.2QUALITY SUPPORT TO DESIGN REVIEWS4-3
4.2.3CHANGE CONTROL VERIFICATION4-3
4.2.4PRODUCT/PROCESS DEVELOPMENT AND VALIDATION4-4
4.3IDENTIFICATION AND DATA RETRIEVAL4-4
4.3.1GENERAL4-4
4.3.2RETENTION OF RECORDS4-5
4.3.3RECORD RETRIEVAL4-5
4.4PROCUREMENT4-5
4.4.1PROCUREMENT CONTROLS4-5
4.4.2SELECTION OF CONTRACTOR PROCUREMENT SOURCES4-5
4.4.3PROCUREMENT DOCUMENTS4-5
4.4.3.1PRIOR TO RELEASE4-6
4.4.3.2PROCUREMENT REQUIREMENT DOCUMENTS4-6
4.4.3.3PROCUREMENT DOCUMENT CONTENTS4-6
4.4.3.3.1CHANGES4-6
4.4.3.3.2TEST RESULTS4-6
4.4.6RECEIVING INSPECTION4-6
4.4.7PROCUREMENT SOURCE DATA4-7
4.4.8AUDITS AND SURVEYS OF PROCUREMENT SOURCE OPERATIONS4-7
4.5FABRICATION CONTROLS.4-7
4.5.1FABRICATION OPERATIONS4-7
4.5.2ARTICLE AND MATERIAL CONTROLS4-8
4.5.3CLEANLINESS/CONTAMINATION CONTROL4-9
4.5.4PROCESS CONTROLS4-9
4.5.5NONDESTRUCTIVE EVALUATION4-9
4.5.6WORKMANSHIP STANDARDS4-9
4.5.7CONTROL OF TEMPORARY INSTALLATIONS AND REMOVALS4-10
4.5.8QUALITY ASSURANCE DESIGNEES4-10
4.5.9INSPECTION PROCEDURES4-10
4.6TEST CONTROLS4-10
4.6.1VERIFICATION4-10
4.6.2TEST PROCEDURES4-10
4.6.3TEST PERFORMANCE4-11
4.6.4INSPECTION AND TEST RECORDS AND DATA4-12
4.6.4.1RECORDS4-12
4.6.4.2ACCEPTANCE DATA PACKAGE4-12
4.6.4.3END-ITEM ACCEPTANCE REVIEW4-12
4.7NONCONFORMING ARTICLES AND MATERIALS4-13
4.7.1NONCONFORMANCE CONTROL SYSTEM4-13
4.7.2IDENTIFICATION OF NONCONFORMANCES4-13
4.7.3NONCONFORMANCE EVALUATION4-13
4.7.4NONCONFORMANCE DISPOSITIONS4-13
4.7.4.1RETURN TO SUPPLIER4-13
4.7.4.2RETURN FOR REWORK OR COMPLETION OF OPERATIONS4-13
4.7.4.3SCRAP4-13
4.7.4.4MATERIAL REVIEW BOARD4-13
4.7.5MATERIAL REVIEW BOARD ACTION4-14
4.7.5.1MEMBERSHIP4-14
4.7.5.2MATERIAL REVIEW BOARD DISPOSITIONS4-14
4.7.5.2.1REPAIR4-14
4.7.5.2.2USE AS IS4-14
4.7.5.2.3SCRAP4-14
4.7.5.2.4WAIVERS4-14
4.7.5.2.5ARTICLES OR MATERIALS RETURNED TO SOURCE4-15
4.7.5.3MATERIAL REVIEW BOARD HOLDING AREA4-15
4.7.5.4SUPPLIER MATERIAL REVIEW BOARD4-15
4.7.5.5RECURRENCE CONTROL4-15
4.7.6PROBLEM REPORTING4-15
4.8METROLOGY4-15
4.8.1METROLOGY CONTROLS4-15
4.8.2CALIBRATION RECORDS4-16
4.8.3MEASUREMENT ACCURACY4-16
4.8.4CALIBRATION CONTROLS4-16
4.8.4.1FACILITY4-16
4.8.4.2TRACEABILITY4-16
4.8.4.3HANDLING, STORAGE, AND TRANSPORTATION4-16
4.8.4.4IDENTIFICATION AND LABELING4-17
4.8.4.5CALIBRATION INTERVALS4-17
4.8.4.6RECALL SYSTEM4-17
4.8.4.7ENVIRONMENTAL REQUIREMENTS4-17
4.8.5REMEDIAL ACTION AND RECURRENCE CONTROL4-17
4.9STAMP CONTROLS4-17
4.9.1STAMP AND MARKING MATERIALS4-17
4.9.2STAMP TRACEABILITY4-17
4.9.3STAMP APPLICATION4-18
4.9.4ELECTRONIC DATA CONTROL4-18
4.9.5STAMPING/MARKING APPLICATION4-18
4.9.6STATUS STAMPING4-18
4.9.7STAMPING METHODS4-18
4.9.8STAMP SIGNIFICANCE4-18
4.9.9CONTRACTOR STAMP DESIGNS4-18
4.10HANDLING, STORAGE, PRESERVATION, MARKING, LABELING,
PACKAGING, PACKING, AND SHIPPING4-18
4.10.1PROCEDURES AND INSTRUCTIONS CONTROL4-18
4.10.2HANDLING4-19
4.10.3STORAGE4-19
4.10.4PRESERVATION4-19
4.10.5PACKAGING AND PACKING4-19
4.10.6MARKING AND LABELING4-19
4.10.7SHIPPING4-19
4.10.7.1CONTROL4-19
4.10.7.2UNSCHEDULED REMOVAL4-20
4.11SAMPLING PLANS, STATISTICAL PLANNING, AND ANALYSES4-20
4.11.1SAMPLING PLANS4-20
4.11.2STATISTICAL ANALYSES4-20
4.12CONTROL OF NASA AND INTERNATIONAL PARTNER PROPERTY4-20
4.12.1CONTRACTOR RESPONSIBILITY4-20
4.12.2UNSUITABLE NASA OR INTERNATIONAL PARTNER PROPERTY4-21
5.0SOFTWARE PRODUCT ASSURANCE5-1
5.1MANAGEMENT5-1
5.1.1ORGANIZATION5-1
5.1.2SOFTWARE PRODUCT ASSURANCE PLANNING5-2
5.1.3FORMAL AND INTERNAL REVIEWS5-2
5.1.4SUBTIER REQUIREMENTS5-2
5.1.5NONDEVELOPMENTAL SOFTWARE5-2
5.1.6NASA OR INTERNATIONAL PARTNER FURNISHED EQUIPMENT5-2
5.1.7PROGRESS REPORTING5-2
5.1.8CONTROL BOARDS5-3
5.1.9OPERATIONS AND MAINTENANCE5-3
5.1.10TRAINING5-3
5.1.11SOFTWARE TOOLS5-3
5.1.12SOFTWARE PRODUCT ASSURANCE RECORDS5-3
5.2SOFTWARE QUALITY ASSURANCE5-3
5.2.1AUDITS5-3
5.2.2TOOLS, TECHNIQUES, AND METHODOLOGIES5-3
5.2.3SOFTWARE DOCUMENTATION5-4
5.2.4SOFTWARE CODE INSPECTION5-4
5.2.5SOFTWARE TESTING5-4
5.3CONFIGURATION MANAGEMENT5-5
5.3.1CONFIGURATION IDENTIFICATION, STATUS ACCOUNTING AND
VERIFICATION5-5
5.3.2CONFIGURATION CHANGE CONTROL5-5
5.3.3SOFTWARE DELIVERY5-5
5.3.4SOFTWARE LIBRARIES5-5
5.3.5DEVIATIONS AND WAIVERS5-5
5.4NONCONFORMANCE REPORTING AND CORRECTIVE ACTION5-5
5.4.1NONCONFORMANCE REPORTING5-6
5.4.2PROBLEM REPORTING AND CORRECTIVE ACTION5-6
5.5RESERVED5-6
5.6SOFTWARE SAFETY5-6
5.7STANDARDS5-6
5.8TRADE STUDIES5-6
5.9INTEGRATION ASSURANCE5-6
5.10VERIFICATION AND VALIDATION5-6
5.11INDEPENDENT VERIFICATION AND VALIDATION5-7
5.12CERTIFICATION5-7
5.13SECURITY AND PRIVACY ASSURANCE5-7
6.0SAFETY6-1
6.1SAFETY MANAGEMENT6-1
6.1.1SAFETY APPROACH6-1
6.1.2ORGANIZATION6-1
6.1.3SAFETY PLAN6-1
6.1.4SAFETY REVIEW REQUIREMENTS6-1
6.1.4.1SPACE STATION REVIEW AND CERTIFICATION6-1
6.1.4.2SPACE STATION USER PAYLOAD SAFETY REVIEWS6-1
6.1.5SAFETY AUDIT TEAMS AND SURVEY6-2
6.1.6OPERATIONAL READINESS INSPECTIONS6-2
6.1.7FACILITY SAFETY REVIEWS6-2
6.1.8MISHAP REPORTING AND INVESTIGATION6-2
6.1.9SAFETY TRAINING AND CERTIFICATION6-3
6.1.10WAIVERS AND DEVIATIONS6-3
6.2SYSTEM SAFETY6-3
6.2.1SYSTEM SAFETY OBJECTIVES6-3
6.2.2SYSTEM SAFETY TECHNICAL REQUIREMENTS6-3
6.2.3SAFETY ANALYSES6-4
6.2.4HAZARD ELIMINATION AND CONTROL6-4
6.2.4.HAZARD ELIMINATION6-4
6.2.4.2DESIGN FOR MINIMUM HAZARD6-4
6.2.4.2.1SAFETY DEVICES6-4
6.2.4.2.2CAUTION AND WARNING DEVICES6-4
6.2.4.2.3SPECIAL PROCEDURES AND TRAINING6-5
6.2.5HAZARD REPORT CLOSURE CRITERIA6-5
6.2.6HUMAN ENGINEERING6-5
6.2.7SPECIFICATIONS AND PROCEDURES REVIEW6-5
6.2.8NASA OR INTERNATIONAL PARTNER FURNISHED EQUIPMENT
SAFETY6-5
6.2.9GROUND SUPPORT EQUIPMENT SAFETY6-5
6.2.10REVIEW OF CHANGES6-6
6.2.11REVIEW OF FLIGHT AND GROUND HARDWARE FAILURES6-6
6.2.12EVALUATION OF GROUND AND FLIGHT TEST RESULTS6-6
6.2.13EVALUATION OF MISSION OPERATIONAL ACTIVITY6-6
6.3INDUSTRIAL SAFETY6-6
6.3.1GROUND OPERATIONS SAFETY6-6
6.4TEST OPERATIONS SAFETY6-6
6.4.1EVALUATION OF SAFETY MARGINS6-6
6.4.2TESTING OF SAFETY CRITICAL EQUIPMENT6-6
6.4.2.1SAFETY CRITICAL SYSTEMS6-6
6.4.2.2SAFETY CRITICAL EQUIPMENT6-7
6.4.3TEST OPERATION REVIEWS6-7
6.4.4SAFETY MONITORING6-7
AABBREVIATIONS AND ACRONYMSA-1
BGLOSSARY OF TERMSB-1

Table 1 NASA/ ASI Exchange Data (S&PA) C-1

1 - 3

1.0 INTRODUCTION

1.1 PURPOSE

This document establishes programmatic hardware and software safety and product assurance (reliability, maintainability, and quality assurance) requirements and related implementation processes, agreed between NASA and Agenzia Spaziale Italiana (ASI) for the design, development, production, test, and operation of International Space Station (ISS).

1.2 SCOPE

These safety and product assurance requirements are applicable to all flight equipment, and certain Ground Support Equipment (GSE) (as specified herein) and related software supplied for ISS by ASI. The programmatic application of the requirements of this document shall be tailored, as appropriate, by ASI consistent with overall program objectives.

1.3 MANAGEMENT APPROACH

Management of safety and product assurance shall include the following:

A.Defining the major hardware and software safety and product assurance tasks and assuring that they are performed as integral parts of all phases of the program
B.Evaluating the safety, reliability, maintainability, and quality of hardware, software, and operations through analyses, tests, reviews, and assessments
C.Providing timely status reporting through periodic project reviews and as a part of overall project status reports
D.Ensuring compatible safety and product assurance requirements among manufacturing, test, launch, and ground operations sites

The ASI Safety and Product Assurance Office shall prepare, implement and maintain a Safety and Product Assurance (S&PA) Program Plan which defines the tasks and products of the Safety, Reliability, Maintainability and Quality Assurance (SRM&QA) activities and organizational responsibilities for task implementation. The plan will provide visibility of SRM&QA activities to be accomplished during the life of the ISS. Safety and product assurance management shall have direct unimpeded access to the management level having full project responsibility. The ASI S&PA Program Plan will be exchanged in accordance with SSP 50125, NASA/ASI Data Exchange Agreement, Lists and Schedules.

E. NASA Space Station Program shall assure that results of SRM&QA analyses are integrated into ISS assessment activities, so that the effects of Mini-Pressurized Logistics Module (MPLM) design options can be assessed.

1.4 RELATION TO OTHER REQUIREMENTS

1.4.1 PROGRAM REQUIREMENTS

The safety and product assurance requirements set forth in this document shall take precedence in cases of conflict with requirements contained in subtier documents. The safety and product assurance design requirements are contained in SSP 41164, Italian Mini-Pressurized Logistics Segment Specification.

1.4.2 GSE HARDWARE AND SOFTWARE

S&PA analyses for GSE hardware and software procured by ASI from existing programs need not be performed again if ASI has determined the use of the GSE is within the scope of the original analysis and meets current program requirements. All Critical Items and accepted risk hazards identified in these analyses must be baselined by the ISS.

1.5 MOTIVATION

A product-oriented motivational (awareness) activity shall be implemented by the NASA Centers (and their contractors) and, as appropriate, by ASI and its contractor as an integral part of and making maximum use of existing motivational activities. The objective of this activity shall be the prevention of human error by instilling in personnel an awareness of their personal responsibility for ISS success.

1.6 INDEPENDENT EVALUATIONS FOR NASA OR THE INTERNATIONAL PARTNERS

NASA and the International Partners reserve the right to appoint independent representatives to assist in safety and product assurance evaluation activities. These representatives will provide technical support to the applicable parent organization and determine effectiveness of and recommend improvements for safety and product assurance activities.

1.7 DATA REQUIREMENT DESCRIPTIONS

All S&PA exchange data between NASA and ASI shall be identified in this document (refer to Table 1), and details and submittal requirements of the exchange data will be specified in SSP 50125.

1.8 SAFETY AND PRODUCT ASSURANCE DATABASE

S&PA data bases shall be established. The data transfer format will be defined in SSP 50125.

1.9 MILESTONE REVIEWS

Safety and product assurance activities shall include supporting internal and supplier design reviews, and NASA and International Partner design and readiness reviews. Participation in milestone reviews shall assure that S&PA requirements are adequately considered.

ASI shall support the implementation of the ISS Safety Review Process as it is described in SSP 30599. The Safety Review Panel (SRP) assesses the MPLM element design for compliance with the safety requirements established in the SSP 50021.

Space Station Program major program milestone review safety assessment reports shall be prepared and submitted to the ISS Safety and Mission Assurance (S&MA) Program Office, within a defined period of time following the Space Station Program major program milestone reviews, as specified by the Director, International Space Station Alpha.

1.10 CERTIFICATION

S&PA shall ensure that products requiring certification meet the requirements contained in SSP 50108, Certificate of Flight Readiness Process Document.

1.11 DELEGATION OF AUTHORITY

This document is controlled, through approval signatures, by the NASA Space Station Program Manager and the ASI MPLM Program Manager. Either Program Manager can propose a change to this document by initiating a letter to the other Program Manager. Following a change proposal letter, both Program Managers will authorize the appropriate activity to discuss the proposed change. Changes to this document are approved by NASA and ASI Program Managers at either Space Station Control Boards (SSCBs) involving ASI participation or at NASA/ASI Joint Program Reviews. All changes to this document require the approval of both the NASA and ASI Program Managers. Following initial joint approval, NASA maintains this document, including the incorporation of approved changes.

2 - 2

2.0 APPLICABLE DOCUMENTS

The following documents include specifications, models, standards, guidelines, handbooks, and other special publications form a part of this document to the extent specified herein. The specific date and issue are shown in parentheses when the document is under Space Station Control Board (SSCB) control.

SSP 50102

NASA/ASI Bilateral Integration and Verification Plan

SSP 30233

Space Station Requirements for Materials and Processes

SSP 30234

Instructions for Preparation of Failure Modes and Effects Analysis (FMEA) and Critical Items List for Space Station

SSP 30309

Safety Analysis and Risk Assessment Requirements Document

SSP 30312

Electrical, Electronic, and Electromechanical (EEE) and Mechanical Parts Management and Implementation Plan for Space Station Program

SSP 30423

Space Station Approved Electrical, Electronic, and Electromechanical Parts List

SSP 30459

Space Station Interface Development Process Requirements

SSP 30599

Safety Review Process for International Space Station Alpha Program

SSP 41000

System Specification for the International Space Station Alpha

SSP 41164

Italian Mini-Pressurized Logistics Segment Specification

SSP 41170

Configuration Management Requirements

SSP 50004

Ground Support Equipment Design Requirements

SSP 50005

ISS Flight Crew Integration Standards

SSP 50021

ISS Safety Requirements

SSP 50108

Certificate of Flight Readiness Process Document

SSP 50125

July 22, 1997 NASA/ASI Data Exchange Agreement

NSTS 1700.7B

Safety Policy and Requirements for Payloads using the Space Transportation System

MIL-STD-105D

Sampling Procedures and Tables for Inspection by Attributes

SSP 50076

NASA/ASI Joint Management Plan

MIL-STD-414

Sampling Procedures and Tables for Inspection by Variables for Percent Defective

MIL-STD-975

NASA Standard Electrical, Electronic, and Electromechanical (EEE) Parts List

MSFC-HDBK-527

Materials Selection List for Space Hardware Systems, Revision D

NHB 1700.1 (V1-B)

NASA Safety Policy and Requirements Document

NSTS 13830 B

Implementation Procedure for NSTS Payloads System Safety Requirements

3 - 3 3 - 6

3.0 RELIABILITY AND MAINTAINABILITY

3.1 MANAGEMENT

Reliability and maintainability activities shall be planned and developed to be an integral part of the MPLM design, development, test and evaluation, and operational activities.

Scheduled status control will be used to provide visibility and assist in reporting, controlling and assessment of the reliability and maintainability effort. Objectives will be to plan and establish the reliability and maintainability effort; to define the major reliability and maintainability tasks and their place as an integral part of the design and development process; to assure the effective implementation of reliability and maintainability requirements; to evaluate system reliability and maintainability characteristics through a program of analysis, review, and test/demonstration; and to conduct trades between reliability, maintainability, and related disciplines to establish optimum availability.

3.1.1 ORGANIZATION

Organization of the reliability and maintainability efforts shall assure effective planning, management, implementation, and performance of reliability and maintainability activities. While the accomplishment of all reliability and maintainability tasks may not be the responsibility of the same organizational element, management of the reliability and maintainability efforts shall assure that all tasks are effectively accomplished. Reliability and maintainability management shall have direct access and shall report regularly to program/project management.

3.1.1.1 THE PROGRAM OFFICE OVERSIGHT RESPONSIBILITY

The Program Office S&MA Office shall have oversight responsibility for the reliability and maintainability efforts. This office shall monitor compliance with the reliability and maintainability requirements specified herein, and shall conduct independent assessments of the reliability process implementation, the maintainability process implementation, and reliability or maintainability analyses performed. The S&MA Office will participate in milestone and design reviews as stated in Paragraph 3.2.8.

3.1.1.2 PROGRAM OFFICE AVAILABILITY ASSESSMENT

Not Applicable.

3.1.2 RELIABILITY AND MAINTAINABILITY PLAN

The ASI Reliability and Maintainability (R&M) Program Plan will describe how its organizational activity will implement the R&M program requirements of this section and SSP 41164. The ASI R&M Program Plan will be submitted in accordance with SSP 50125.

3.1.3 AUDITS AND SURVEYS

The reliability and maintainability efforts shall include contractor internal audits and vendor/supplier surveys to evaluate the progress and effectiveness of reliability and maintainability activities and to determine the need for adjustments or changes. Audits and surveys shall be conducted, where needed, at intervals as defined by the reliability and maintainability plans.

3.1.4 SUPPLIER RELIABILITY AND MAINTAINABILITY CONTROL

The reliability and maintainability efforts shall assure that hardware/software obtained from any source, including Off-The-Shelf (OTS), meets the reliability and maintainability requirements of the overall system. Management controls shall be provided to assure the adequacy of the implementation of the requirements.

3.1.5 NASA OR INTERNATIONAL PARTNER FURNISHED EQUIPMENT (GFE/IGFE) RELIABILITY AND MAINTAINABILITY Reliability and maintainability data needed for GFE/Airborne Flight Equipment (AFE) shall be identified by the contractor or supplying agency and shall be supplied by the supplying agency. When examination of these data or testing indicates that the equipment is not consistent with the reliability and/or maintainability requirements of the MPLM, the supplying agency shall be formally and promptly notified.

3.2 RELIABILITY AND MAINTAINABILITY ENGINEERING

Reliability and maintainability engineering tasks shall be accomplished, to the extent specified, for all flight equipment, flight support equipment, orbital support equipment, ground support equipment, and NASA or ASI furnished equipment which could cause personnel injuries or damage to the facility or which interfaces with flight hardware. Maintainability engineering efforts shall support ground maintenance planning efforts as appropriate.

3.2.1 RELIABILITY AND MAINTAINABILITY DESIGN CRITERIA

The reliability and maintainability efforts shall include the establishment of reliability and maintainability design criteria and assure that the criteria are incorporated into each design. The reliability and maintainability efforts shall include a systematic approach for reviewing and concurring in design and procurement specifications and in design changes to assure that all design items reflect proper and complete reliability and maintainability design criteria and that the specifications contain applicable reliability and maintainability requirements.

3.2.2 RELIABILITY AND MAINTAINABILITY ANALYSES/TRADE STUDIES

3.2.2.1 RELIABILITY ANALYSES/TRADE STUDIES

The reliability effort shall include participation in design trades and assessments utilizing reliability modeling and numerical predictions as appropriate. Reliability criteria, such as failure modes and effects, frequency of failures, and operating life, shall be evaluated as part of engineering and operational trade studies.

3.2.2.2 MAINTAINABILITY ANALYSES/TRADE STUDIES

The maintainability effort shall include participation in design trades and assessments utilizing maintainability modeling and numerical predictions as appropriate. Maintainability criteria, such as mean-time-to-repair and restorability considerations shall be evaluated as part of engineering and operational trade studies.

3.2.2.3 PROGRAM OFFICE SUPPORTABILITY/AVAILABILITY ANALYSES/TRADE

STUDIES

Not applicable.

3.2.3 HARDWARE FAILURE MODES AND EFFECTS ANALYSES

A system for preparing, maintaining, and controlling Failure Modes and Effects Analyses (FMEAs) shall be established in accordance with SSP 50125, NASA/ASI Data Exchange Agreement.

3.2.3.1 FLIGHT HARDWARE FMEAs

Flight hardware FMEAs shall be developed for the MPLM in accordance with SSP 30234, Instructions for Preparation of FMEA and Critical Items List for Space Station. The FMEA shall be conducted for each mission phase for the MPLM. ASI will submit the MPLM FMEA/Critical Items List (CIL) report to the NASA Space Station Program in accordance with SSP 50125.

3.2.3.2 GSE FMEAs

GSE FMEAs shall be prepared in accordance with SSP 30234.

3.2.3.3 PAYLOAD FMEAs

Not applicable.

3.2.4 CRITICALITY CATEGORIES

Criticality categories for flight hardware and GSE are defined in SSP 30234.

3.2.5 CRITICAL ITEM CONTROL

3.2.5.1 CRITICAL ITEMS LIST PREPARATION

Based on results of the FMEAs, a CIL shall be prepared in accordance with SSP 30234. ASI will submit the MPLM CIL to the NASA Space Station Program as part of the FMEA/CIL Report in accordance with SSP 50125.

The CIL shall consist of Criticality 1, 1S, 1P and 2 failure points and redundant items in 1R and 1SR applications which do not meet the program failure tolerance requirements. In addition, the CIL will contain all items in which any of the following occur:

A.Item(s) which cannot be checked out during prelaunch or in orbit before being required to operate
B.Item(s) whose loss cannot be detected by the flight or ground crew during any mission phase
C.Not applicable

3.2.5.2 RESERVED

Not applicable.

3.2.5.3 RESERVED

Not applicable.

3.2.5.4 CRITICAL ITEMS LIST PRIORITIZATION

Not applicable.

3.2.6 RELIABILITY AND MAINTAINABILITY DATA

Reliability data shall be compiled for all flight hardware in accordance with SSP 50125.

3.2.6.1 FLIGHT AVIONICS HARDWARE OPERATING TIME

Reserved.

3.2.7 LIMITED-LIFE ITEMS

The life-limiting criteria and characteristics for limited-life items shall be established, and limited-life items shall be identified. Accrued data (pre-delivery) of the limited-life items shall be recorded in order to enable refurbishment and replacement of these items and projection of their remaining life after delivery. Limited life hardware identification and reporting shall be in accordance with SSP 50125.

3.2.8 MILESTONE REVIEWS

Reliability and maintainability activities shall include support to major MPLM milestone reviews. Participation in milestone reviews shall assure that reliability and maintainability requirements are adequately considered.

3.2.9 CONFIGURATION CONTROL BOARDS AND PANELS

Reliability and maintainability assurance personnel shall support configuration control boards and panels through evaluation, tracking, and followup of engineering changes. Each engineering change package shall contain a reliability and maintainability assessment of the impact of the proposed change.

3.2.10 PROBLEM REPORTING SYSTEM

Reliability and maintainability activities shall support the MPLM problem reporting system. This support shall include the establishment and verification of corrective action/recurrence control for design related problems.

3.2.11 VERIFICATION ASSURANCE

Reliability and maintainability shall assure that an effective verification program is established and implemented. Reliability and maintainability assurance activities shall include participation in such verification processes as development, certification, acceptance, check-out, and maintainability verification. The reliability and maintainability verification shall be performed as required in accordance with SSP 41164 and SSP 50125.

3.3 ELECTRICAL, ELECTRONIC, AND ELECTROMECHANICAL AND MECHANICAL

PARTS CONTROL

3.3.1 ELECTRICAL, ELECTRONIC, AND ELECTROMECHANICAL PARTS

3.3.1.1 GENERAL

A system for controlling EEE and mechanical parts shall be developed and implemented in accordance with SSP 30312, Electrical, Electronic, and Electromechanical (EEE) and Mechanical Parts Management and Implementation Plan for Space Station Program, or the appropriate International Partner documents.

3.3.1.2 ELECTRICAL, ELECTRONIC, AND ELECTROMECHANICAL PARTS SELECTION

EEE parts shall be selected in accordance with SSP 30312 or equivalent International Partner documents. The EEE parts used by NASA and the International Partners shall be listed in the SSP 30423, Space Station Approved EEE Parts List (SSAEPL), or International Partner’s Approved Parts List.

NASA and ASI shall develop and maintain their approved parts list. NASA and ASI shall develop and maintain their approved parts list respectively. NASA and ASI will exchange their approved parts list in accordance with SSP 50125.

3.4 Materials and Processes

The selection, usage and control of Materials and Processes (M&P) shall be in accordance with SSP 30233, Space Station Requirements for Materials and Processes or the equivalent International Partner document. NASA and ASI will exchange their M&P data which are Materials Usage Agreement (MUA) Summary, Spacecraft Maximum Allowance Concentration (SMAC) values, and other MAPTIS/MPLM MAPTIS data including data specified in Materials Selection List for Space Hardware Systems, Version D, (MSFC-HDBK-527). The ASI MIUL will be provided to NASA. These data elements and submittal requirements shall be in accordance with SSP 50125.

3.5 REPORTING PARTS AND MATERIALS PROBLEMS AND ASSESSING ALERTS

3.5.1 NASA ALERTS

Problems with parts, materials, equipment, or diminishing sources, which are of mutual concern to NASA and associated contractors, shall be reported through the Government-Industry Data Exchange Program (GIDEP) and NASA Acute Launch Emergency Restraint Tip (ALERT) systems. Previously published ALERTs will be reviewed to assure that generic problems and technical issues will be avoided. GIDEP and NASA distributed ALERTs shall be evaluated and responses shall be provided by a systematic closed-loop approach. NASA ALERTs with potential impact to ASI hardware and GIDEP data will be made available to ASI in accordance with SSP 50125.

3.5.2 INTERNATIONAL PARTNERS ALERTS

Problems with parts, materials, equipment, or diminishing sources, which are of mutual concern to the International Partners and their associated contractors, shall be reported through the International Partner’s ALERT system. The distributed ALERTs shall be evaluated and responses shall be provided by a systematic closed-loop approach. EEE Parts Problem Notification shall be provided to NASA Space Station Program in accordance with SSP 50125.

4 - 21

4.0 QUALITY ASSURANCE

These quality requirements are applicable to all ISS hardware and software designated as flight components, subsystems, systems and/or equipment including Flight Support Equipment (FSE) and Orbital Support Equipment (OSE). These quality requirements are also applicable to GSE that: 1) either physically or functionally interfaces with flight hardware/software; 2) could by its malfunction cause loss of life or loss/damage to flight, GSE, or facilities hardware/software; and/or 3) generated data used in determining flight worthiness/certification. These quality requirements may be tailored for other GSE as appropriate to the mission and intended useful life.

4.1 MANAGEMENT AND PLANNING

4.1.1 PLANNING

Quality Assurance activities shall be planned and developed to be an integral part of ISS design, development, test and evaluation production, and operational activities and refurbishment/ overhaul. Scheduled status reporting will be used to provide visibility and assist in controlling the quality assurance effort. Objectives will be to plan and establish the quality assurance effort; to define the major quality assurance tasks and their place as an integral part of the design and development process; and to assure the effective implementation of quality assurance requirements. Quality assurance program planning shall address all program phases and shall provide a comprehensive management approach to preventing, detecting, documenting, and resolving actual or potential nonconformances.

4.1.2 ORGANIZATION

Organizations and personnel responsible for implementing and performing quality assurance functions shall have well defined responsibilities, authority, and organizational freedom to develop and implement quality assurance disciplines and controls. One designated person shall have the responsibility and authority for directing and managing the quality assurance activity. That person shall have direct unimpeded access to the management level having full responsibility for the program/project work and shall report regularly on the status and effectiveness of quality activities.

4.1.2.1 THE SPACE STATION PROGRAM OVERSIGHT RESPONSIBILITY

The ISS S&MA/ASI S&PA Offices shall have independent assessment responsibility for the quality assurance efforts. Both offices shall monitor compliance with the quality assurance requirements specified herein. Both offices shall conduct independent assessments of the quality process implementation at their contractor/subcontractor level.

4.1.3 QUALITY PROGRAM PLAN

The quality organization shall prepare, implement, and maintain a quality plan which describes the compliance with requirements set forth herein. The plan content shall be readily identifiable with each cited requirement and shall cover all quality activities. Contractor quality procedures which define involvement by the applicable procuring agency shall be reviewed and approved by the procurement agency (i.e., NASA or ASI or their designated representatives). New or existing policies and procedures with no NASA or ASI involvement shall be available for review. The ASI Quality Assurance Program Plan shall be submitted in accordance with SSP 50125.

4.1.4 RESERVED

4.1.5 MANAGEMENT ASSESSMENT DATA

The quality organization shall provide a quality progress and status report to their respective program management office and/or applicable procurement agency as defined by the procurement documents.

4.1.6 TRAINING

Quality assurance shall determine the need for and the adequacy of training courses used in the various quality assurance disciplines for submittal to the government for inclusion in the flight crew training program.

Quality assurance shall also assure development, implementation, and maintenance of a documented training program for special processes. Personnel performing or inspecting special processes shall be trained and certified. Evidence of personnel certification shall be available in the area where duties are being performed. Personnel shall be recertified as a result of unsatisfactory performance, changes in techniques or required skills, and/or extensive interruption of work performance. Records of training, testing, and certification status of personnel shall be maintained and shall be available for review by the applicable procurement agency or its delegated representative.

4.1.7 INTERNAL QUALITY PROGRAM AUDITS AND SURVEYS

Quality assurance shall conduct audits or surveys of task performance, procedures, and operations which implement the quality program. Independent assessments shall be conducted periodically as appropriate with program maturity and shall be performed by personnel not having specific line responsibilities in those areas. Each audit or survey shall include an examination of operations and documentation, evaluation of actual operations as compared with each established requirement, documentation of discrepancies and deficiencies, and recommendations for corrective action, as appropriate. A corrective action plan which addresses measures to be taken to correct the discrepancies/deficiencies noted during the survey/audit shall be prepared and approved. Follow-up activities shall include reviews to ensure that measures required by the corrective action plan are being implemented properly.

The results of audits and surveys shall be documented in a report to management. Management action shall be taken to ensure that required corrections have been implemented. Records of the contractor's audits and surveys shall be available for review by the applicable procurement agency or its delegated representative.

4.1.8 MILESTONE REVIEWS

Quality assurance activities shall include supporting project milestones such as design, acceptance, and readiness reviews. Participation in reviews shall assure that quality requirements are adequately considered in decisions which affect hardware design, configuration controls, initiation of subsystem and integrated testing, shipment, and readiness for flight. Quality assurance data presented will contain sufficient detail to allow management to assess the acceptability to proceed with the next program phase activity.

4.2 DESIGN AND DEVELOPMENT CONTROLS

4.2.1 TECHNICAL DOCUMENTS

Quality assurance shall conduct timely reviews of technical documents and changes thereto prior to document release. Technical documents include, but are not limited to, specifications, engineering drawings, engineering change orders, program plans, implementing procedures, work instructions, deviations/waivers, and documentation. Designs produced by automated systems shall have an equivalent level of control.

4.2.1.1 Quality assurance shall verify that a documentation system that assures the inclusion of quality characteristics and design criteria in specifications, procedures, drawings, fabrication and inspection planning, and test documents is established and implemented.

4.2.1.2 Quality assurance shall assure that the drawing system and other specifications identify hardware characteristics requiring verification with particular emphasis on critical characteristics. This identification shall be used in developing quality inspection and test verification planning and procedures.

4.2.2 QUALITY SUPPORT TO DESIGN REVIEWS

Quality assurance shall participate in design reviews to ensure that designs permit and facilitate the quality considerations of producibility, repeatability, inspectability, and refurbishability/ maintainability and that other related quality considerations are defined. These reviews shall reflect the requirements and criteria as defined in the quality assurance checklist. Quality assurance shall define methods and plans for product inspection and test commensurate with the definition of design and fabrication requirements. This technical planning activity shall be integrated into the detailed fabrication and inspection planning.

Quality assurance shall review selected program documents prior to design reviews to ensure compliance with these requirements. Quality participation shall be documented to provide a historical record of quality concurrence in the design development.

4.2.3 CHANGE CONTROL VERIFICATION

Engineering changes shall be reviewed by quality assurance to determine the quality impact such as modified inspection/test requirements, identification of new or modified tooling, gaging, or test equipment needs, and identification of changes to critical inspection/test procedures. The procurement agency (NASA contractor/subcontractor or ASI) shall be notified of any proposed changes in fabrication, materials, methods, or processes which may affect the quality or intended end use of an item.

Change incorporation shall be verified in accordance with specified effectivity with special attention to changes involving interface relationships.

4.2.4 PRODUCT/PROCESS DEVELOPMENT AND VALIDATION

Quality assurance shall participate in product and process development activities to ensure that fabrication quality requirements are defined in concert with product requirements. Quality assurance shall assure criteria for material, and process controls are developed consistent with these requirements. Product and process activities include, but are not limited to, development of mockups, engineering models, qualification/protoflight units, development test units, and development of processes and fabrication methods. Commensurate with these activities, quality assurance shall develop methods and plans for verification of these requirements with particular emphasis on early identification of critical characteristics.

4.3 IDENTIFICATION AND DATA RETRIEVAL

4.3.1 GENERAL

A documented identification and data retrieval system shall be developed, implemented, and maintained. Each article and material shall be identified by a unique part or type number, and the method shall be specified on engineering drawings and specifications. All disciplines shall use identification numbers related to the engineering design. Criticality, design complexity, application, performance characteristics, manufacturing, processing or environmental conditions, and limited-life sensitivity shall be used to determine the level of control applied through identification and data retrieval requirements. An identification and data retrieval system shall be provided for parts and materials installed or consumed in ISS flight elements. This system shall provide visibility to the related manufacturer's lot or batch number and/or date code for parts and materials. An identification and retrieval system shall be developed for part and material locations as follows:

4.3.1.1 Each article and material shall be identified by a unique part or type number. One or more of the following detailed identification methods shall be used as applicable:

4.3.1.1.1 Date codes indicating date of manufacture to identify articles or materials made by a continuous and controlled process and those which are subject to variation of degradation with age.

4.3.1.1.2 Lot numbers to identify individual materials or articles produced in homogeneous groups.

4.3.1.1.3 Serial numbers to identify materials or articles for which unique data are to be maintained.

4.3.1.1.4 Standard usage hardware (e.g., non-high strength fasteners, shims, pins) which are not safety or functionally critical and fall outside the date code, lot number, and serial number screens shall require part or type number traceability only.

4.3.1.2 Other identification methods, such as paint dots, etc., must be approved by the procurement agency or a designated representative.

4.3.1.3 Methods of location of part or type numbers and detailed identification on articles shall be indicated in technical documents.

4.3.1.4 Controls shall be included to assure identification numbers are assigned in a consecutive manner.

4.3.1.5 Records shall indicate detailed identification and be organized so that records and the related article or material may be located and retrieved as necessary.

4.3.1.6 Requirements shall be established for EEE parts which will provide the capability of tracing backwards from fabricated hardware to the lot from which the part originated.

4.3.2 RETENTION OF RECORDS

Records shall be retained in a safe, accessible location for the period specified in the program requirements. Records shall not be destroyed unless authorized by the NASA contracting officer or the governing body of ASI.

4.3.3 RECORD RETRIEVAL

Record systems shall ensure that records are identified and related to the applicable articles and materials. The system shall be organized so that these records and the related articles and materials may be rapidly located and retrieved.

4.4 PROCUREMENT

4.4.1 PROCUREMENT CONTROLS

The procuring agency is responsible for assuring that purchased articles, materials, and services conform to the requirements specified in this document and other program requirements. Control of procurements shall include identification of contract quality requirements, selection of qualified suppliers, verification of product quality and compliance with contractual requirements, and provisions for reporting and correcting nonconformances.

4.4.2 SELECTION OF CONTRACTOR PROCUREMENT SOURCES

Quality personnel shall participate in the selection of procurement sources based on one of the following:

4.4.2.1 The procurement source shall have a previous and continuing record of supplying quality articles, materials, or services of the type being procured.

4.4.2.2 A preaward survey of the procurement source facility and quality system shall be conducted in accordance with documented procedures, developed by the procuring organization, to determine if the procurement source is capable of satisfying procurement quality requirements. The results of preaward surveys shall be documented and maintained on file.

4.4.2.3 When articles or materials were fabricated specifically for contracts issued under other NASA (or associated international participants government) contracts that have current acceptable surveys, a preaward survey is not required.

4.4.3 PROCUREMENT DOCUMENTS

Procurement documents shall be written and processed in accordance with the following:

4.4.3.1 PRIOR TO RELEASE

Applicable procurement documents shall be approved by quality personnel to ensure inclusion of appropriate quality requirements and associated documentation.

4.4.3.2 PROCUREMENT REQUIREMENT DOCUMENTS

Procurement documents shall require each procurement source and its subtier sources to comply with the applicable requirements of this document. The contractor, in complying with these requirements, may use its existing procurement requirements documents subject to approval by NASA (or by ASI) prior to implementation. The quality system of suppliers of OTS hardware shall be reviewed and evaluated to establish the adequacy of their imposed quality system. Items such as historical information, previous quality performance, and compliance with standardized quality systems shall be factors during the course of the review.

4.4.3.3 PROCUREMENT DOCUMENT CONTENTS

Procurement documents shall contain the following specific requirements:

4.4.3.3.1 CHANGES

The procurement source shall be required to notify the procuring organization of any proposed changes in fabrication, materials, methods, or processes previously approved and shall obtain written approval from the procuring authority before making the change. When a proprietary item is procured, the procurement source shall be required to notify the procuring organization of changes in materials, fabrication methods, processes, or product operating characteristics prior to delivery.

4.4.3.3.2 TEST RESULTS

Records of test results shall be maintained and must be traceable to the procured articles. Purchased raw materials shall be accompanied with chemical and/or physical test results. Procedures shall provide for periodic laboratory analysis and testing to verify the validity of test reports received from suppliers of raw materials.

4.4.6 RECEIVING INSPECTION

Quality assurance shall develop, implement, and maintain a documented receiving inspection activity to ensure that procured articles comply with procurement document requirements, inspection and test data are accurate and acceptable, evidence of contractor and procurement agency source inspection (NASA or ASI) has been provided as required, specified identification and data retrieval requirements have been met, time/cycle-sensitive articles are identified, expended and remaining time/cycle information is complete, chemical analyses and physical tests are performed, and receiving inspection results and status of articles are maintained. Procedures shall provide for periodic laboratory analysis and testing to verify the validity of test reports received from suppliers.

4.4.7 PROCUREMENT SOURCE DATA

Inspections and test results commencing with receiving inspection shall be recorded to reflect, on a continuous basis, the qualitative and quantitative performance of individual sources and the quality histories of the supplied articles and materials. Quality assurance shall maintain data to aid in the selection of procurement sources, establish trends of potential problems, and initiate action to resolve any negative trends.

4.4.8 AUDITS AND SURVEYS OF PROCUREMENT SOURCE OPERATIONS

The procuring organization shall schedule and conduct audits and surveys of procurement sources to ensure contract compliance based upon the following:

4.4.8.1 Type of items being procured; e.g., criticality or complexity of article or material or special processes involved

4.4.8.2 Procurement source quality history including known problems or difficulties

4.4.8.3 Remaining period of procurement source performance. For planning purposes, a schedule shall be prepared and shall include all planned audits and surveys for at least one year in advance and shall be amended to accommodate unanticipated problem areas.

The schedule shall be maintained throughout the duration of the procurement and shall be available for review.

The audits and surveys shall be to evaluate the quality system, including implementing policies and procedures, and shall be performed in accordance with documented procedures and checklists which are based on program requirements. This shall include assurance that all manufacturing, fabrication, assembly, test, and handling operations involving ISS hardware and software are conducted using procedures approved, released, and controlled within the documentation system.

This is the start of the file's text. The full file is on GovTribe.

Other files for this federal contract opportunity

Other files attached to Human Space Flight Technical Integration Contract (HSFTIC), newest first.
File Type Posted
HSFTIC_J-4_Applicable_and_Reference_Document_List.xlsx XLSX spreadsheet
SSP_50035_Revision_C_Retired.docx DOCX document
SSP_50314-Rev_C.docx DOCX document
SSP41142P2_RD_CD_012045_2.pdf PDF
SSP-50803.doc DOC document
PPD_524_RB_FINAL_MRICB_Charter.docx DOCX document
GPO_Website_Ref.pptx PPTX presentation
SSP_50481-RevC.docx DOCX document
42124_P2_RC_.pdf PDF
SSP_50094-RevB.pdf PDF
SSP_50659_Rev_E.xlsx XLSX spreadsheet
IMPR_Package_Mar_Apr_18.pptx PPTX presentation
SSP_41167-RevJ.docx DOCX document
SSP_50835_Rev_E.doc DOC document
42097P1_RD.pdf PDF
SSP42003_P2_RevC.pdf PDF
Applicable_3.zip ZIP file
MD_101_RA_FINAL.docx DOCX document
SSP_50477-RevC.pdf PDF
SSP_50670-Rev_A-DCN001-Collated_Master.doc DOC document
SSP_50781-RevA-DCN_003.docx DOCX document
PPD_517.pdf PDF
SSP_41002-RevR.docx DOCX document
SSP_50901.docx DOCX document
SSP_54059_54060-Baseline.docx DOCX document
SSP5003.PDF PDF
SSP30559RD-Errata.pdf PDF
SSP_41000-RevCJ.pdf PDF
42137P1_RC_CD_012230.pdf PDF
SSP_41163-Rev_L.docx DOCX document
9.0.zip ZIP file
SSP_42001-RevW.docx DOCX document
SSP_50875.docx DOCX document
SSP41017p2rJ.pdf PDF
41143Pt2RD.pdf PDF
SSP_50489-Rev_G.docx DOCX document
41015P2RH.pdf PDF
SSP_42121_Part_2.pdf PDF
SSP_50309_Part_1.pdf PDF
SSP_50477-RevC_Joint_Crew_Provisioning_Catalog.pdf PDF
JSC_Form_1240.pdf PDF
SSP_41160-RevH.docx DOCX document
Increment_Utilization_Accomplishment_Report_Blank_Book_RevB(March_2019).docx DOCX document
SSP_50102.pdf PDF
SSP_50146-RevB-SSCD_15566.pdf PDF
SSP_50034_Revision_D.DOC DOC document
SSP_50227-RevC.docx DOCX document
SSP_50621-RevF-DCN001-Collated_Master.pdf PDF
SSP41004_P2_RJ.pdf PDF
DRAFT_HSFTIC_Work_Load_Indicators.xlsx XLSX spreadsheet
Show all 50

Human Space Flight Technical Integration Contract (HSFTIC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .