About this file
This document is the October 2017 Hillsborough County Public Works Standard Specifications for Construction, which establishes the technical and administrative requirements for construction projects undertaken by or on behalf of Hillsborough County, Florida. The specifications provide comprehensive guidance covering project management, quality control, materials, equipment, traffic management, environmental controls, and construction methodologies. The document addresses work across multiple infrastructure categories including roadways, bridges, utilities, drainage systems, and traffic control devices. Key administrative requirements include the appointment of a Project Manager and Project Representative to oversee contract execution, mandatory preconstruction conferences, weekly progress meetings, and submittal requirements for schedules, shop drawings, quality control plans, erosion control plans, and record drawings. The contractor is responsible for mobilization within ten days of Notice to Proceed, including establishment of field offices, temporary utilities, and site security. Contractors must maintain traffic flow, protect existing utilities and facilities, control dust and erosion, and comply with all environmental regulations throughout the construction period.
The specifications establish that all work must conform to the most current FDOT Standard Specifications for Road and Bridge Construction and applicable OSHA regulations, with the County retaining quality assurance and verification testing authority independent of contractor quality control efforts. Payment is made on a unit price or lump sum basis as specified in individual bid items, with mobilization costs spread across contract items unless separately itemized. The contractor bears all costs for materials, labor, equipment, temporary facilities, traffic control, utility protection, environmental compliance, and site restoration. Record drawings must be submitted in both hard copy and digital format, signed and sealed by a licensed professional surveyor or engineer, prior to final payment approval. The specifications require contractors to provide comprehensive documentation including daily force reports, progress reports, quality control test results, and updated schedules on a monthly basis. Demobilization and final site cleanup must be completed within ten working days of the Notice of Completion, with the County's field office remaining operational for an additional thirty days at contractor expense.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
October 2017 Table of Contents | 1
TABLE OF CONTENTS
Hillsborough County utilizes the latest FDOT Standard Specifications for Road and Bridge Construction with the following additions and/or exceptions.
Hillsborough County Division I Standard Specifications 01010 Summary of Work 01015 Project Representative 01020 Mobilization 01030 Construction Equipment 01035 Prosecution and Progress 01040 Control of the Work 01070 Abbreviations and Definitions 01091 Reference Specifications 01200 Meetings and Conferences 01300 Contractor Submittals 01310 Bar Chart Schedule 01311 CPM Construction Schedule 01312 Measurement and Payment 01385 Color Audio Video Construction Record 01400 Quality Control / Assurance 01500 Maintenance of Traffic 01510 Temporary Construction Utilities 01530 Protection of Existing Facilities 01550 Access and Temporary Access Provisions 01560 Temporary Environmental Controls 01590 Field Offices, Equipment and Services 01600 Materials and Material Storage 01700 Completion, Start-up and Closeout
Hillsborough County Standard Specifications to be used in lieu of latest FDOT Standard Specifications for Road and Bridge Construction:
204 Graded Aggregate Base 283 Reclaimed Asphalt Pavement Base 320 Hot Bituminous Mixtures; Plant, Methods and Equipment 327 Milling of Existing Asphalt Pavement 330 Hot Bituminous Mixtures General Construction Requirements 334 Superpave Asphalt Concrete 336 Asphalt Rubber Binder 337 Asphalt Concrete Friction Courses 341 Asphalt Rubber Membrane Interlayer 430 Pipe Culverts
October 2017 Table of Contents | 2
901 Coarse Aggregate 902 Fine Aggregate 916 Bituminous Materials 919 Ground Rubber Tire 931 Metal Accessory Materials for Concrete Pavement and Concrete Structures
Hillsborough County Standard Specifications for Traffic Signals to be added or supplemented to the latest FDOT Standard Specifications for Road and Bridge Construction:
600 Traffic Signal Overview 603 General Requirements for Traffic Control Signals and Devices 611 Acceptance Procedures for Traffic Control Signals and Devices 620 Grounding and Lighting Protection 630 Conduit 632 Signal Cable 634 Span Wire Assembly 635 Pull, Splice, and Junction Boxes 639 Electrical Power Service Assemblies 650 Vehicular Traffic Signal Assemblies 652 24/7 Solar Flashing Beacon Assembly 653 Pedestrian Signal Assemblies 654 Midblock Crosswalk Enhancement Assemblies 660 Vehicle Detection System 663 Signal Priority and Preemption Systems 665 Pedestrian Detection System 671 Traffic Controllers 676 Controller Cabinet Assemblies 700 Highway Signing
- End of Section -
October 2017 Section 01010: Summary of Work | 1
01010-1 General Descriptions of Portions of The Work
01010-1.01 Sequencing and Scheduling Constraints: Schedule and perform the WORK in such a manner as to result in the least possible disruption to the public's use of roadways, driveways, and utilities. Deliver notice to adjacent property occupants (private and public) and to the PROJECT MANAGER of all planned disruptions to roadways, driveways, and utilities ten days in advance of the disruption.
01010-1.02 Labor Employed: All labor employed by the CONTRACTOR and his
Subcontractors for work on the project shall work in harmony with and be compatible with all other labor being used by CONTRACTORs now or hereafter on the site of the WORK covered by this Contract.
01010-1.03 Sanitary Provisions: Provide and maintain, in a neat and sanitary condition, such accommodations for the use of employees as are necessary to comply with the requirements and regulations of the State and Federal Government. Commit no public nuisance.
0101-1.04 Plant Quarantine Regulations: The U.S. Department of Agriculture and the
Florida Department of Agriculture and Consumer Services have issued quarantine regulations pertaining to control of the nematodes of citrus and other plant pests.
Contact the Animal and Plant Health Inspection Service of the U.S. Department of Agriculture, and the Division of Plant Industry of the Florida Department of Agriculture and Consumer Services to ascertain any current restrictions regarding plant pests which may be imposed by these agencies. Keep advised of current quarantine boundary lines throughout the construction period.
These restrictions may affect operations in connection with such items as clearing, grubbing, earthwork, grassing and mulching, sodding, landscaping, and other items which might involve the movement of materials containing plant pests across quarantine lines.
Quarantine regulations and related information can be obtained from the following:
Animal and Plant Health Inspection Service U.S. Department of Agriculture 3031 Lake Alfred Road Winter Haven, Florida 33881
Director, Division of Plant Industry Florida Department of Agriculture and Consumer Services Post Office Box 147100 Gainesville, Florida 32614-7100
October 2017 Section 01010: Summary of Work | 2
01010-1.05 Introduction or Release of Prohibited Aquatic Plants, Plant Pests or Noxious
Weeds: Do not introduce or release prohibited aquatic plants, plant pests or noxious weeds into the project limits as a result of clearing, grubbing, earthwork, grassing and mulching, sodding, landscaping, or other such activities.
Immediately notify the COUNTY upon discovery of any prohibited aquatic plants, plant pests or noxious weeds within the project limits. Do not move prohibited aquatic plants, plant pests or noxious weeds within the project limits or to locations outside of the project limits without permission of the COUNTY. All borrow material brought onto the project site shall be free of prohibited aquatic plants, plant pests or noxious weeds and their reproductive parts. Attention is directed to the Florida Administrative Code for the definition of prohibited aquatic plants, plant pests and noxious weeds.
01010-1.06 Compliance with Federal Endangered Species Act: The Federal Endangered
Species Act requires that the potential of any activity performed in conjunction with a highway construction project to impact an endangered Species be investigated prior to initiating such activity. If there is a potential impact on an endangered species, a biological assessment will be necessary to determine what measures are necessary to mitigate such impact. In the event that a biological assessment indicates that mitigation measures are necessary, the CONTRACTOR shall cooperate as necessary to comply with such measures.
01010-1.07 Air Pollution: Comply with the provisions of Chapter 403, Florida Statutes, regarding control of air pollution. There will be no open burning operations allowed.
01010-1.08 Underground Pollutant Storage Tanks: CONTRACTORs removing underground pollutant storage tanks must be certified by the Construction Industry Licensing Board as required by the Florida Statutes, regardless of exemptions allowed by the State. Disposition of the tanks and pollutants will be made in accordance with the requirements and regulations of any Local, State or Federal Agency having jurisdiction.
01010-1.09 Discovery of an Unmarked Human Burial: If an unmarked human burial is discovered, all activity that may disturb the unmarked human burial shall cease immediately, and the PROJECT MANAGER shall be notified by the CONTRACTOR. Activity shall not resume until specifically authorized by the
PROJECT MANAGER.
01010-1.10 Work or Structures in Navigable Waters of the U.S., Waters of the U.S., and
Waters of the State: In carrying out the WORK in the Contract, when under the jurisdiction of any environmental regulatory agency, comply with all regulations issued by such agencies and with all general, special, and particular conditions
October 2017 Section 01010: Summary of Work | 3 relating to construction activities of any and all permits issued to the COUNTY as though such conditions were issued to the CONTRACTOR. The CONTRACTOR is responsible for posting any permit placards in a protected location at the WORK site.
In case of any discrepancy between any permit condition and a requirement of the plans or a special provision; or a developmental, supplemental, or standard specification; the permit condition shall prevail. If the permit conditions require WORK or the furnishing of materials not specifically provided for in the basis of payment clause for a pay item contained in the proposal, such WORK or the furnishing of materials shall be considered to be included in the other items of WORK and is to be completed as part of the WORK. Special sequencing or scheduling of operations that may be required by permit conditions shall also be considered as part of the WORK.
Do not obstruct navigation channels without permission from the proper authority. Provide and maintain navigation lights and signals in accordance with the Federal requirements for the protection of the structure, of false work, and of navigation. In the event of accidental blocking of the navigation channel, the U.S.
Coast Guard must immediately be notified by the CONTRACTOR of the blockage and upon removal of the blockage.
Where the WORK includes the excavation of a channel or other underwater areas to a required section, maintain the section against shoaling or other encroachment until final acceptance of the project.
01010-1.11 Dredging and Filling: The Florida Statutes require that all persons who engage in certain dredge or fill activities in the State of Florida shall obtain a certificate of registration and shall keep accurate logs and records of all such activities so that natural resources may be protected and conserved. Details as to the application of this law should be obtained from the State.
01010-1.12 Control of the Contractor's Equipment Traffic Interference: Equipment, while it is on or traversing a road or street, is not to unreasonably interfere with traffic. If traffic is unreasonably obstructed or accidents do occur, it may result in the COUNTY issuing a stop work order.
01010-1.13 Preservation of Property:
General: Preserve from damage all property along the line of work (or which is in the vicinity of or is in any way affected by the work) the removal or destruction of which is not called for by the plans.
October 2017 Section 01010: Summary of Work | 4
Special attention is directed to the protection of any geodetic monument, horizontal or vertical, located within the limits of construction.
Failure to Restore Damaged Property: In case of failure on the part of the CONTRACTOR to restore such property, bridge, road or street, or to make good such damage or injury, the COUNTY may, upon 48 hours notice, proceed to repair, rebuild or otherwise restore such property, road or street as may be deemed necessary, and the cost thereof will be deducted from any monies due or which may become due the CONTRACTOR under the contract. Nothing in this clause shall prevent the CONTRACTOR from receiving proper compensation for the removal, damage or replacement of any public or private property, not shown on the plans, which is made necessary by alteration of grade or alignment and such WORK is authorized by the PROJECT MANAGER; provided that such property has not been damaged through fault of the CONTRACTOR, his employees or agents.
Guardrail: All existing guardrail shall be protected against damage or displacement. Whenever such guardrail lies within the limits of construction, or wherever so directed by the PROJECT MANAGER due to exigencies of construction operations, the existing roadside guardrail shall be taken up by the CONTRACTOR, properly stored, and subsequently reset at the original location or, in the case of widened pavement or roadbed, at locations designated by the
01010-1.14 Operations Within Railroad Right of Way:
Notification to the Railroad Company: The CONTRACTOR shall give notification to the Division Engineer or the Superintendent of the railroad company and to the COUNTY appropriately in advance of (minimum of 72 hours) his beginning of any operations within the limits of the railroad right of way, any operations requiring movement of employees, trucks or other equipment across the tracks of the railroad company at other than an established public crossing and any other WORK which may affect railroad operations or property.
Contractor's Responsibilities: Comply with whatever requirements an authorized representative of the railroad company deems necessary in order to safeguard the railroad's property and operations. Any damage, delay or injury and any suits, actions or claims brought on account of damages or injuries resulting from the operations within or adjacent to railroad company right of way shall be the CONTRACTOR's responsibility.
Watchman or Flagging Services: Any protective services to insure the safety of railroad operations (watchman or flagman service) needed during the project are
October 2017 Section 01010: Summary of Work | 5 the CONTRACTOR's responsibility and should be incorporated into the bid price.
01010-1.15 CONTRACTOR's Responsibility for Work: Until acceptance of the WORK by the COUNTY it shall be under the charge and custody of the CONTRACTOR and he shall take every necessary precaution against injury or damage to the WORK by the action of the elements or from any other cause whatsoever, arising either from the execution or from the nonexecution of the work. The CONTRACTOR shall protect, rebuild, repair, restore and make good, without additional compensation, all injury or damage to any portion of the WORK occasioned by any cause before its completion and acceptance. As an example of protection as indicated above, the CONTRACTOR shall provide manpower on the site during the cure period of concrete, such as sidewalks, to ensure that the surface is not marred by passersby.
The CONTRACTOR will not be held responsible for damage to any landscape items caused by an officially declared hurricane which occurs after the final acceptance of the entire work, but during any remaining portion of the 90-day establishment period.
01010-1.16 Special Traffic Measures: Provide all measures to ensure the safe passage of pedestrian and vehicular traffic, including flagmen, lights, barricades, signs and off-duty policemen. One or two lanes of traffic shall be maintained during such work. Provide all necessary measures to ensure the safety of workmen and the general public. Temporary or permanent patches shall be in place by the end of the time period allowed for street cuts and two-way traffic shall be resumed.
01010-1.17 Normal Working Hours and Noise Control: Eliminate noise within the project area to the extent possible. "Residential" type mufflers shall be installed on all gasoline and diesel engines. All local ordinances and regulations covering noise control shall be observed. Only emergency WORK shall be performed between the hours of 5 p.m. and 8 a.m., or on Saturdays, Sundays or COUNTY Holidays.
Written permission shall be obtained from the PROJECT MANAGER prior to performing any WORK during these periods.
The normal work week shall be Monday through Friday, exclusive of COUNTY holidays. The normal day shall be between the hours of 8:00 a.m. to 5:00 p.m.
Schedule all WORK around these parameters. Any variation must be requested, in writing, 48 hours in advance with written approval from the PROJECT
MANAGER.
01010-1.18 Salvage: All items encountered or produced during the execution of the WORK which are not able to be incorporated into the WORK and as determined by the COUNTY's PROJECT MANAGER, are to be disposed of by the
October 2017 Section 01010: Summary of Work | 6
CONTRACTOR, with the exception of those items identified in the SPECIAL CONDITIONS. No materials shall be removed from the project site unless approved by the COUNTY's PROJECT MANAGER.
01010-1.19 Storage: Storage conditions shall be acceptable to COUNTY for all materials and equipment not incorporated into the WORK but included in Applications for Payment. Such storage arrangements and conditions shall be presented in writing for COUNTY's review and approval and shall afford adequate and satisfactory security and protection. Off-site storage facilities shall be accessible to PROJECT MANAGER. The stored materials shall be insured for full value.
Certificates of liability insurance coverage must be submitted to the PROJECT MANAGER with the request for payment. All arrangements and costs for storage facilities shall be paid by the CONTRACTOR, unless specifically designated in the Contract Documents to be furnished by the COUNTY.
01010-1.20 Lines and Grades:
A. All WORK shall be done to the lines, grades, and elevations shown on the Drawings.
B. Basic horizontal and vertical control points will be established or designated by the COUNTY as provided in the General Conditions.
These points shall be used as datum for the WORK. The CONTRACTOR, through a licensed professional surveyor, shall verify all horizontal and vertical control points. All additional survey, layout, and measurement WORK shall be performed by CONTRACTOR as part of the WORK.
C. All field books, notes, and other data developed by CONTRACTOR in performing the surveys required by the WORK shall be available to PROJECT MANAGER for examination throughout the construction period. All such data shall be submitted to PROJECT MANAGER with documentation required for final acceptance of the WORK.
D. CONTRACTOR shall keep PROJECT MANAGER informed, a reasonable time in advance, of the times and places at which it wishes to do WORK, so that horizontal and vertical control points may be established and any checking deemed necessary by PROJECT MANAGER may be done with minimum delay to CONTRACTOR.
E. CONTRACTOR shall remove and reconstruct WORK which is improperly located.
October 2017 Section 01010: Summary of Work | 7
01010-1.21 Staging Area:
A. CONTRACTOR shall employ an area outside the limits of the site for location of office facilities, storage of materials and equipment, and staging area. The specific location shall be subject to approval of the PROJECT MANAGER and shall be coordinated to minimize interference with the operation of the existing facilities located therein and any other construction contracts containing WORK to be performed at this site. Submit a sketch of the proposed staging area showing such facilities to the PROJECT MANAGER at the preconstruction conference for consideration and approval. Any changes to same are to be resubmitted for approval.
B. The Site shall be returned to the original condition or better upon completion of the WORK.
C. Nothing in this AGREEMENT shall imply that the CONTRACTOR has exclusive use of roadways or public and/or private land employed to perform the WORK.
01010 - 1.22 Prior to Digging: Contact the Hillsborough County Traffic Control Services
Section prior to digging where a traffic signal exists.
01010 - 1.23 Provide 24-hour notice to Planning and Growth Management Department, Natural
Resources Team, Hillsborough County before working within 25 feet of existing trees.
01010 - 2.00 Basis of Payment: The cost of performing all WORK as described above shall be included in the contract unit prices for the various items of WORK to which it is incidental.
October 2017 Section 01015: Project Representative | 1
01015-1.01 The PROJECT MANAGER may assign a PROJECT REPRESENTATIVE to assist the PROJECT MANAGER and Or ENGINEER in the discharge of his/her duties. This PROJECT REPRESENTATIVE may be a Resident Engineer or a Construction Manager or other similar named person designated by the PROJECT MANAGER. PROJECT REPRESENTATIVE shall act as directed by and under the supervision of PROJECT MANAGER, and shall confer with PROJECT MANAGER regarding the actions to be taken.
PROJECT REPRESENTATIVE's dealings in matters pertaining to the on-site WORK shall, in general, be only with PROFESSIONAL and CONTRACTOR.
Dealings with Subcontractors, except in the event of an emergency, shall only be through or with the full knowledge of CONTRACTOR.
01015-2.01 Duties and Responsibilities:
Project Representative shall:
A. Schedules.
1. Review the CONTRACTOR's initial schedule submittal which once approved by the PROJECT MANAGER will become the baseline schedule. Ensure the baseline schedule incorporates the original construction phasing plan and utility relocation schedules as per the CONTRACT and has a project completion date which matches the CONTRACT completion date. Modifications of the construction phasing plan by the CONTRACTOR must be approved by the PROJECT MANAGER and agreed to by all agencies and utilities impacted by the change.
2. Review and recommend to the PROJECT MANAGER action on the progress schedule, schedule of submittals, and schedule of values prepared by CONTRACTOR.
B. Conferences. Attend preconstruction conference. Arrange a schedule of progress meetings and other job conferences as required. Attend meetings; prepare, maintain, and circulate copies of minutes. Prepare and maintain action item logs from meetings.
C. Liaison.
1. Serve as PROJECT MANAGER's liaison with CONTRACTOR, working principally through CONTRACTOR's PROJECT MANAGER and
October 2017 Section 01015: Project Representative | 2
Superintendent(s) and assist CONTRACTOR in understanding the intent of the Contract Documents.
2. As requested by PROJECT MANAGER, assist in obtaining from
COUNTY additional details or information when required at the job site for proper execution of the WORK.
3. Conduct periodic pre-construction phase meetings with
CONTRACTOR's personnel to review the upcoming phase of work to ensure the CONTRACTOR's personnel understand the scope of work as outlined in the plans and specifications, COUNTY's testing requirements, standards of construction, and can describe their internal quality control procedures for approval by the COUNTY.
D. Submittals.
1. Receive and record date of receipt of Submittals and samples, receive samples which are furnished at the site by CONTRACTOR, and notify PROFESSIONAL of their availability for examination or transmit to PROFESSIONAL as appropriate.
2. Advise PROFESSIONAL and CONTRACTOR immediately of the commencement of any WORK requiring Submittal if the submission has not been approved by PROFESSIONAL.
3. Advise PROJECT MANAGER of adequacy and timeliness of the review of submittals by the PROFESSIONAL.
E. Review of WORK, Rejection of Defective WORK, Inspections, and Tests.
1. Conduct and record on-site observations of the WORK in progress to determine if the WORK is proceeding in accordance with the Contract Documents and that completed WORK will conform to the Contract Documents.
2. Report to PROJECT MANAGER whenever any WORK is unsatisfactory, faulty, does not conform to the Contract Documents, is otherwise defective, does not meet the requirements of any inspections, tests or approvals required to be made, or has been damaged prior to final payment; and advise PROJECT MANAGER when WORK should be corrected or rejected or
October 2017 Section 01015: Project Representative | 3 should be uncovered for observation, or requires special testing, inspection, or approval.
3. Verify that tests, equipment, and systems start-ups and operating and maintenance instructions are conducted as required by the Contract Documents and in the presence of the required personnel, and that CONTRACTOR maintains adequate records thereof;
observe, record, and report to PROJECT MANAGER appropriate details relative to the test procedures and start-ups.
4. Accompany visiting inspectors representing public or other agencies having jurisdiction over the Project, record the outcome of these inspections, and report to PROJECT MANAGER.
F. Interpretation of Contract Documents.
1. Prepare and maintain a Request for Information log. Record all requests from the CONTRACTOR and note date of resolution.
2. Transmit PROFESSIONAL's clarifications and interpretation of the Contract Documents to CONTRACTOR.
G. Change Orders.
1. Prepare a Proposed Change Request for approval by PROJECT MANAGER, PROFESSIONAL and others as required to document the need and reasons for a change.
2. Prepare and maintain a Request for Proposal log. Record receipt of each change proposal and monitor its disposition.
3. Evaluate CONTRACTOR's proposals for changes to the WORK and report them with recommendations to PROJECT
4. Prepare negotiating plan and when requested, assist PROJECT
MANAGER in negotiating Change Orders with
CONTRACTOR.
5. Prepare Change Order documentation, obtain necessary signatures and certifications from CONTRACTOR and PROFESSIONAL, and forward package to PROJECT MANAGER.
October 2017 Section 01015: Project Representative | 4
H. Records.
1. Maintain at the job site orderly files for correspondence, reports of job conferences, Submittals, samples, reproductions of original Contract Documents including all Addenda, Change Orders, Field Orders, additional Drawings issued subsequent to the execution of the Agreement, and PROFESSIONAL's clarifications and interpretations of the Contract Documents, progress reports, and other Project related documents.
2. Prepare a daily report recording hours on the job site, weather conditions, data relative to WORK activities, list of visiting officials and representatives of manufacturers, fabricators, suppliers, and distributors, inspections and tests performed, decisions, observations in general and specific observations in more detail as in the case of observing test procedures.
I. Reports.
1. Furnish PROJECT MANAGER periodic reports of progress of the WORK and CONTRACTOR's compliance with the approved progress schedule and schedule of Shop Drawing submissions.
2. Consult with CONTRACTOR in advance of scheduled major tests, inspections, or start of important phases of the WORK.
Advise PROJECT MANAGER and PROFESSIONAL of schedules for and changes to the schedule for testing.
3. Report immediately to PROJECT MANAGER upon the occurrence of any accident.
J. Payment Applications. Review Applications for Payment with
CONTRACTOR for compliance with the established procedure for their submission. Make recommendations to PROJECT MANAGER in relation to the schedule of values of WORK completed and materials and equipment delivered at the Site but not incorporated in the WORK.
K. Certificates, Maintenance, and Operation Manuals. During the course of the WORK, verify that certificates, maintenance, and operation manuals and other data required to be assembled and furnished by CONTRACTOR are applicable to the items actually installed; and deliver this material to PROFESSIONAL for its review and forwarding the COUNTY prior to final acceptance of the WORK.
October 2017 Section 01015: Project Representative | 5
L. Record Drawings. Review the CONTRACTOR's Record Drawings monthly to ensure CONTRACTOR is keeping adequate records as required.
M. Completion
1. Prior to PROJECT MANAGER's issuance of a Certificate of Substantial Completion, assist PROJECT MANAGER in evaluating CONTRACTOR's punch list and developing an official punch list for Substantial Completion.
2. Conduct final inspection of the WORK in the company of
PROFESSIONAL, COUNTY, and CONTRACTOR and prepare a final list of items to be completed or corrected.
3. Verify that all items on final list have been completed or corrected and make recommendations to PROJECT MANAGER concerning acceptance.
4. Prepare Transfer Document for execution and signature. Forward complete document and attachments to the PROJECT
01015-2.02 Limitations of Authority: Except upon written instructions of PROJECT
MANAGER, PROJECT REPRESENTATIVE shall not:
A. Authorize any deviation from the Contract Documents or approve any substitute materials or equipment.
B. Exceed limitations on PROJECT REPRESENTATIVE's authority as set forth in the Contract Documents.
C. Undertake any of the responsibilities of CONTRACTOR, Subcontractors, or CONTRACTOR's superintendent, or expedite the
WORK.
D. Advise on or issue directions relative to any aspect of the means, methods, techniques, sequences, or procedures of construction unless such is specifically called for in the Contract Documents.
E. Advise on or issue directions as to safety precautions and program in connection with the WORK.
F. Authorize COUNTY to occupy the Project in whole or in part.
October 2017 Section 01015: Project Representative | 6
G. Take any action not specifically authorized either herein above or in any separate contract between the COUNTY and the PROJECT
REPRESENTATIVE.
October 2017 Section 01020: Mobilization | 1
01020 - 1.01 Definition and Scope:
A. Mobilization shall include the obtaining of all permits, insurance, and bonds; moving onto the site of all plant and equipment; furnishing and erecting plants, temporary buildings, and other construction facilities; all as required for the proper performance and completion of the WORK.
Mobilization shall normally include, but not be limited to, the following principal items:
1. Move onto the site all plant and equipment required for first month operations.
2. Install temporary construction power, wiring, and lighting facilities.
3. Establish fire protection plan and safety program.
4. Secure construction water supply.
5. Provide field office trailers for CONTRACTOR and PROJECT
MANAGER complete with all specified furnishings and utility services, including telephones.
6. Provide on-site sanitary facilities and potable water facilities as specified.
7. Arrange for and erect CONTRACTOR's work and storage yard and employees' parking facilities.
8. All required insurance certificates and bonds.
9. Obtain all required permits.
10. Post all OSHA, EPA, Department of Labor, and all other required notices.
11. Have CONTRACTOR's superintendent at the job site full time.
12. Erect project construction sign(s) as specified.
13. Construct, maintain, and restore temporary access and haul roads.
October 2017 Section 01020: Mobilization | 2
01020 - 1.02 Payment for Mobilization:
A. No payment for mobilization, or any part thereof, will be approved until all mobilization items listed above have been completed or updated as specified. On Lump Sum contracts, the CONTRACTOR shall spread the mobilization cost over the items included in the schedule of values. In Unit Price contracts where the COUNTY has not included a specific unit price item for mobilization in the Bid Proposal, the mobilization cost shall be spread over the items in the schedule of values.
B. Any identified lump sum Price for mobilization shall include the obtaining of all items as noted in these Specifications and as required for the proper performance and completion of the WORK.
01020-2.01 Basis of Payment: Payment for mobilization will be made on an incremental basis in accordance with the following:
1. No payment will be made until all required submittals are in and the field office (if any) is operational.
2.
The WORK and incidental costs specified as being covered under this Section will be paid for at the contract lump sum price for the item of Mobilization.
When such item is included in the proposal, payment shall be made under:
Item No. 201020-001- Mobilization - lump sum.
The standard retainage will be applied to mobilization.
If a separate pay item is not in the contract for Mobilization then the costs for the items specified in this section shall be included in the individual pay items.
When more than one project or job (separate job number) is included in the contract, the above percentages shall apply separately to each job which has a separate pay item for Mobilization.
Percent of Original Contract Amount Earned
Allowable Percent of the Lump Sum Price for mobilization
5 25 10 50 25 75 50 100
October 2017 Section 01020: Mobilization | 3
Where the Special Conditions have indicated that the CONTRACTOR will be reimbursed separately for the cost of obtaining performance and payment bonds, the CONTRACTOR will be paid the invoice price of the bonds(s) when the PROJECT MANAGER has been furnished with a certified copy of the invoice from the bonding company and the CONTRACTOR requests payment for such.
October 2017 Section 01030: Construction Equipment | 1
01030 - 1.01 Equipment: Unless shown on the plans or specifications, perform the WORK using equipment, tools, machinery, etc., of own choosing. Facilities to be constructed are adequate to support only their design loads in their completed construction stage. Any part of the facility which is damaged by the CONTRACTOR's equipment or procedures during construction shall be replaced or repaired as directed by the PROJECT MANAGER at the CONTRACTOR's expense.
01030 - 1.02 Equipment Condition and Approval:
A. Approval: All equipment to be used in construction of the project shall be on the site in due time prior to its need, in working condition, and shall be subject to approval or disapproval by the PROJECT MANAGER. Only factory recommended exhaust mufflers on internal combustion engines shall be used. Equipment which is disapproved shall be removed from the job, or altered or repaired, as required by the PROJECT MANAGER.
The number of units, the sizes, etc., of the equipment on hand shall be adequate to insure completion of the WORK within the contract time.
B. Maintenance: Consistent with public interest, safety, and good practice, all equipment, tools, and machinery used shall be maintained in a satisfactory working condition throughout the period they are on the job site. This will include adequate equipment maintenance procedures to insure the elimination of unnecessary noise caused by loose body parts on all construction equipment.
C. Tailgate Noise: Excessive tailgate banging by haul trucks will be prohibited.
D. Stationary Equipment: All stationary equipment such as pumps, compressors, generators, etc., shall be screened if that equipment is to operate beyond normal working hours. If it is feasible, this equipment shall be screened during normal working hours to reduce noise impacts.
01030 - 1.03 Experimental Equipment:
A. General: To encourage the development and use of new or improved equipment the PROJECT MANAGER may grant permission to use equipment other than that normally used and currently accepted, by approval of a written request for permission to use such equipment in place of the normally used equipment. The PROJECT MANAGER, before considering or granting such request, may require that the CONTRACTOR establish, at his own expense, satisfactory evidence that the proposed equipment will produce WORK equal in quality to that
October 2017 Section 01030: Construction Equipment | 2 produced by the specified equipment.
B. Conditions of Approval: When permission is granted for the use of new or improved equipment it shall be understood that such permission is given for the purpose of testing the quality of WORK actually produced by this equipment. The PROJECT MANAGER shall have the right to retract permission for use of the equipment, at any time that, in his opinion, results are not at least equal to the results obtainable with currently accepted equipment. Upon such withdrawal of permission for the use of the equipment the CONTRACTOR will be required to use the equipment currently accepted and normal for the WORK and shall remove and dispose of, or otherwise remedy, at his expense, any WORK which is considered defective or unsatisfactory as a result of the use of such experimental equipment. The approval for use of particular equipment on a particular project shall in no way be considered as approval for use of such equipment on any other project and shall not relieve the CONTRACTOR of any responsibility for producing finished WORK of the quality required by the plans and specifications.
01030 - 2.00 Basis of Payment: The cost of performing all WORK as described above shall be
October 2017 Section 01035: Prosecution and Progress | 1
01035 - 1.01 Drainage: Conduct operations and maintain the WORK in such condition that adequate drainage will be in effect at all times. Do not obstruct existing functioning storm sewers, gutters, ditches, and other run-off facilities.
01035 - 1.02 Protection of Structures: Heavy equipment shall not be operated close enough to pipe headwalls or other structures to cause their displacement.
01035 - 1.03 Fencing: Erect a permanent fence as a first order of business where necessary for maintaining the security of livestock, adjacent property, or for protection of pedestrians who are likely to gain access to the project.
01035 - 1.04 Hazardous or Toxic Waste: When the CONTRACTOR's operations encounter or expose any abnormal condition which may indicate the presence of a hazardous or toxic waste, such operations shall be discontinued in the vicinity of the abnormal condition and the PROFESSIONAL shall be notified immediately. The presence of tanks or barrels; discolored earth, metal, wood, ground water, etc.;
visible fumes; abnormal odors; excessively hot earth; smoke; or other conditions which appear abnormal may be indicators of hazardous or toxic wastes and shall be treated with extraordinary caution.
Every effort shall be made by the CONTRACTOR to minimize the spread of any hazardous or toxic waste into uncontaminated areas.
The CONTRACTOR's operations shall not resume until so directed by the
PROJECT MANAGER.
Disposition of the hazardous or toxic waste will be made in accordance with the requirements and regulations of any Local, State, or Federal Agency having jurisdiction. Where the CONTRACTOR performs WORK necessary to dispose of hazardous or toxic waste, and the contract does not include pay items for disposal, payment will be made with a change order.
01035 - 1.05 Milling: Provide positive drainage of the remaining pavement after milling. This operation shall be done during the same day as milling.
Restrict milling operations such that any lane milled will be repaved no later than the day after the initial milling operation.
01035 - 1.06 Qualifications of Contractor's Personnel
The CONTRACTOR shall assure the COUNTY that all superintendents, foremen and workmen employed by him are competent, careful and reliable.
PROJECT MANAGER shall have authority to approve the use of CONTRACTOR personnel and call for their removal if determined necessary based on ability or performance. All workmen must have sufficient skill and
October 2017 Section 01035: Prosecution and Progress | 2 experience to properly perform the WORK assigned them. All workmen engaged on special work, or skilled WORK such as bituminous courses or mixtures, concrete bases, pavements, or structures, or in any trade, shall have had sufficient training and experience in such WORK to perform it properly and satisfactorily and to operate the equipment involved, and shall make due and proper effort to execute the WORK in the manner prescribed in the specifications.
01035 - 2.00 Basis of Payment: The cost of performing all WORK as described above shall be
October 2017 Section 01040: Control of the Work | 1
01040 - 1.01 Description: This Section describes handling of the Contract Documents, to include the plans and specifications.
01040 - 2.01 Plans and Contract Documents: The CONTRACTOR will be furnished an appropriate number of copies of the plans and special conditions as required for the particular project. Copies of the Standard Specifications may be provided electronically or purchased from the COUNTY. CONTRACTOR is responsible for obtaining copies of other required documents such as FDOT specifications, etc. The CONTRACTOR shall have available on the work, at all times, one copy each of the plans (including relevant design Standards), and specifications.
01040 - 2.02 County's Plans: The plans furnished by the COUNTY consist of general drawings showing such details as are necessary to give a comprehensive idea of the construction contemplated. Roadway plans will show in general, alignment, profile grades, typical cross sections and general cross sections. Structure plans, in general, will show in detail all dimensions of the WORK contemplated. When the structure plans do not show the dimensions in detail, they will show general features and such details as are necessary to give a comprehensive idea of the structure. Grades shown are finished grades.
01040 - 2.03 Utility Relocation Schedules: Utility relocation schedules are provided in the contract documents for informational/planning purposes only. The COUNTY provides no guarantee or assurances as to the accuracy of the schedules due to the nature of the work and the coordination that is required by the CONTRACTOR and utilities during the execution of the project. The CONTRACTOR is not entitled to any damages or additional compensation from the COUNTY for deviations to the utility relocation schedules that may or may not impact the CONTRACTOR's Schedule within the overall Contract Duration.
01040 - 2.04 Alterations in Plans: All authorized alterations affecting the requirements and information given on the approved plans shall be in writing. No changes shall be made on any plan or drawing after its approval by the PROJECT MANAGER, except by direction of the PROJECT MANAGER.
01040 - 2.05 Working Drawings (For Structures): The CONTRACTOR shall furnish such working, shop and erection drawings as may be required to complete the structure in compliance with the design shown on the plans. The drawings shall be prepared on reproducible permanent transparent material made for the purpose, such as tracing cloth or plastic. The size of the transparent sheets shall be no larger than 24 by 36 inches. Each sheet shall be numbered consecutively for the series and the sheet number shall indicate the total number in the series (VIZ. 1 of 12, 2 of 12,.......12 of 12). Each sheet shall have affixed thereon a title block indicating the name of the series, the subject of the sheet, the state job number designations and
October 2017 Section 01040: Control of the Work | 2 the name of the persons drawing and checking, together with dates on which the WORK was done.
Working, shop and erection drawings submitted for approval by the CONTRACTOR shall be directed as follows with the number of copies indicated:
A. Bridge, Bulkhead and Retaining Wall Structures and Lighting and Signing
Structural Items: The number of and the submittal path to be followed shall be determined dependent upon the identity of the Engineer of Record. The identity of the Engineer of Record is shown adjacent to the title block on the structural plan sheets, and on the key sheets for roadway, signing, and pavement marking and lighting plans. The following signing and lighting items are defined as Structural Items: Lighting- poles, bracket arms, frangible bases and foundations; Signing- Mounting brackets for bridge mounted signs, overhead cantilever structures and footings, overhead truss structures and footings, overhead sequential sign structures and footings and multiple post sign supports and footings.
1. When the Engineer of Record is shown to be the COUNTY, the
CONTRACTOR shall submit one set of prints and one set of reproducible copies of each series of working, shop and erection drawings to the COUNTY with a copy of the letter of transmittal sent to the PROFESSIONAL. WORK requiring catalog data, material certifications, material test results, procedure manuals, fabrication/welding procedures, and maintenance and operating procedures shall be submitted to the COUNTY in sets of 9 of each series.
2. When the Engineer of Record is shown to be a Consulting
Engineer or Firm the CONTRACTOR shall submit one set of prints and one set of sepias or CADD files of each series of working, shop and erection drawings to the Consulting Engineer or Firm with a copy of the letter of transmittal sent to the COUNTY.
WORK requiring catalog data, material certifications, material tests, procedure manuals, fabrication/welding procedures, and maintenance and operating manuals shall be submitted to the Consulting Engineer in sets of 9 of each series. The mailing address of the Consulting Engineer of Record and the appropriate Shop Drawing Review personnel will be furnished by the COUNTY or will be on the plans.
B Signing, Lighting, Drainage Structures and Attenuators and other nonstructural items: The number of and the submittal path to be followed
October 2017 Section 01040: Control of the Work | 3 shall be determined dependent upon the identity of the PROFESSIONAL of Record. The identity of the Engineer of Record is shown on the key sheets for roadway, signing and pavement marking and lighting plans.
1. When the Engineer of Record is shown to be the COUNTY, the
CONTRACTOR shall submit 9 sets of prints and electronic files of each shop drawing to the COUNTY for approval. All submittals and correspondence shall be addressed to the Engineer of Record as noted on the key sheet.
2. The CONTRACTOR shall submit 9 sets of prints and electronic files of each shop drawing to the COUNTY for approval unless a reduced number has been approved by the Project Manager.
For the following categories of working and shop drawings, the CONTRACTOR shall submit for approval permanent reproducible drawings and/or CADD files with one print and nine sets of applicable computations. The print and the cover sheet of each set of applicable computations shall be signed and sealed by the CONTRACTOR's Specialty Engineer:
1. CONTRACTOR originated redesign.
2. Design and/or structural details furnished by the CONTRACTOR in compliance with the contract.
3. For structures that may jeopardize public safety, such as structures spanning functioning vehicular roadways, pedestrian walkways, railroads and channels to navigable waterways and for unusual structures such as cable stayed bridges, post-tensioned concrete box girder bridges, movable bridges, bridges with clear spans in excess of 50 foot or bridges classified as major bridges; the CONTRACTOR shall submit to the COUNTY signed and sealed drawings and calculations of all special erection equipment.
Additionally, prior to its use, the special erection equipment shall be personally inspected by the Specialty Engineer who shall certify to the PROFESSIONAL in writing that the equipment has been fabricated and is being utilized in accordance with the submitted drawings and calculations. The Specialty Engineer shall also sign and seal the letter of certification.
4. For the same structures defined in (3) above, the CONTRACTOR shall submit to the PROJECT MANAGER signed and sealed drawings and calculations of all falsework and/or temporary
October 2017 Section 01040: Control of the Work | 4 supports. Additionally, after its erection and/or installation, but prior to the application of any superimposed load, the falsework and/or temporary supports shall be personally inspected by the Specialty Engineer who shall certify to the PROJECT MANAGER in writing that the falsework and/or temporary supports have been constructed of materials and in accordance with the details shown on the submitted drawings and calculations.
The Specialty Engineer shall also sign and seal the letter of certification.
For Steel Structures: Working Drawings for steel structures shall consist of shop detail, erection details and other working plans, showing details, dimensions, sizes of material, and other information necessary for the complete fabrication and erection of the metal work.
For Concrete Structures: Working drawings for concrete structures shall consist of such detailed plans as may reasonably be required for the effective prosecution of the WORK and which are not included in plans furnished by the COUNTY. These may include details of falsework, bracing, centering and form work, masonry layout diagrams, and diagrams for bending reinforcing steel.
Submission of Working, Shop and Erection Drawings: All working, shop and erection drawings prepared by the CONTRACTOR or his agents (Subcontractor, fabricator, supplier and etc.) shall be reviewed, dated, stamped, approved and signed by the CONTRACTOR prior to submission to the Engineer of Record for review. The CONTRACTOR's signed approval of drawings submitted shall confirm that he has verified the WORK requirements, field measurements, construction criteria, sequence of assembly and erection, access and clearances, catalog numbers and other similar data. Each series of drawings shall indicate the specification Section and page or drawing number of the contract plans to which the submission applies. The CONTRACTOR shall indicate on the working, shop and erections drawings all deviations from the contract drawings and shall itemize all deviations in his letter of transmittal. The CONTRACTOR shall schedule the submission of shop drawings so that approximately 45 days (beginning on the date of receipt) is allowed for review by the COUNTY for routine work. For WORK of more complexity, the time for review by the COUNTY will be increased in proportion to the complexity of the work. The CONTRACTOR shall adjust
October 2017 Section 01040: Control of the Work | 5 his schedules so that an additional approximate 30-day period is provided for each resubmittal.
It is incumbent upon the CONTRACTOR to submit his shop drawings to facilitate expeditious review. Voluminous submittals of shop drawings at one time are discouraged, and may result in increased review time. In no case will the COUNTY accept liability for resulting delays, added costs and related damages when the time required for approval extends beyond the approximate times shown herein. Only COUNTY approvals/stamps on shop drawings are valid and any WORK performed in advance of approval will be at the CONTRACTOR's risk.
Responsibility for Accuracy of Working Drawings: It is understood, however, that approval by the PROJECT MANAGER of the CONTRACTOR's working drawings does not relieve the CONTRACTOR of any responsibility for accuracy of dimensions and details, or for conformity of dimensions and details. The CONTRACTOR shall be responsible for agreement and conformity of his working drawings with the approved plans and specifications.
Cost of Working Drawings: The contract prices shall include the cost of furnishing all working drawings, and the CONTRACTOR will be allowed no extra compensation for such drawings.
01040 - 2.06 Coordination of…
This is the start of the file's text. The full file is on GovTribe.