This is a Pre-Bid Conference presentation prepared by the City of Fort Worth Transportation and Public Works Department for the 2027 Asphalt Resurfacing Contract 1, City Project No. 106812. The project encompasses milling and overlay work on approximately 60,000 square yards of pavement, including 2 inches of milling with 2 inches of Asphalt Superpave SP-D SAC-A PG70-28, approximately 1,900 cubic yards of base repair, 6,800 square yards of 7-inch concrete base repair flatwork, 7,400 linear feet of concrete curb and gutter, 8,600 square feet of concrete driveway ADA ramps, and 36,000 linear feet of pavement marking. Work locations include Campus Drive North from South Campus Court to Southeast Loop 820 and Belknap Street from Oakhurst Scenic Drive to North Beach Street. The bid opening is scheduled for October 1, 2026, with council bid award targeted for October 20, 2026, a pre-construction meeting by December 2026, and construction to begin in January 2027. Contractors must be available to commence work immediately upon receiving the Notice to Proceed.
The Engineer's Estimate for this project is $4.4 million. Pre-qualification requirements include demonstrated experience with asphalt paving heavy maintenance projects valued at $1,000,000 or more. Required bid proposal submittals include a bid form following Bonfire submission instructions, a conflict of interest statement, a bid bond, proof of workers' compensation coverage, vendor compliance with state law documentation, the proposal form, any applicable addenda, and a completed bid table. Contractors must provide traffic control plan details to obtain a Street Use Permit from the City and a Lane Closure Permit from the Texas Department of Transportation. The small business enterprise goal has been waived for this contract. The project manager is Iretomiwa Otuyelu, P.E., who can be contacted at 817-392-6747 or Iretomiwa.otuyelu@fortworthtexas.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-00 45 26 Contractor Compliance with Workers Compensation Law.doc | DOC document | |
| 10-Submission Instructions - 26-0315 (rev. 092926).docx | DOCX document | |
| 7-CPN 106812 Pre-Bid Meeting Sign in Sheet.xlsx | XLSX spreadsheet | |
| 5-2027 Asphalt Resurfacing Contract 1.xlsx | XLSX spreadsheet | |
| 3-00 45 11 Bidders Prequalifications.pdf | ||
| 4-Bid Documents Package Folder Contents Checklist.doc | DOC document | |
| 6-CPN106812 Project Manual.pdf | ||
| 9-CPN 106812 Asphalt Resurfacing Contract 1 Addendum 1.pdf | ||
| 1-00 45 13 Prequalification Application.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Presented by Iretomiwa Otuyelu, P.E.
Project Manager Transportation & Public Works Department
September 15, 2026 2027 Asphalt Resurfacing Contract 1 City Project No. 106812
Pre-Bid Conference Transportation and Public Works
Project Limits
| Campus Dr | NB | S Campus Court – Southeast Loop 820 |
| Belknap Street | Oakhurst Scenic Drive – N Beach Street |
Project Details Major Work Items:
Paving 60,000 SY: 2” Milling with 2” Asphalt Superpave SP-D SAC-A PG70-28
Approximately 1,900 CY of Base Repair (Ty-B PG64-22)
6,800 SY: 7” Concrete Base Repair
Flatwork 7,400 LF: Concrete curb & Gutter 8,600 SF: Concrete Driveway ADA Ramps
36,000 LF Pavement Marking
Engineer’s Estimate: $4.4 Million
| Street Name | From | To | Scope | Pavement Quantity (SY) |
| Campus Dr NB | S Campus Ct | Southeast Loop 820 | Mill & Overlay | 4320 |
| Belknap Street | Oakhurst Scenic Dr | N Beach Street | Mill & Overlay | 52000 |
Contractor is required to provide traffic control plan details to obtain a Street Use Permit from the City, and Lane Closure Permit from TxDOT.
Anticipated Schedule Schedule:
Bid Opening October 1st, 2026 Council Bid Award – Aiming October 20th, 2026 Pre-construction meeting by December 2026 Begin Construction in January 2027 Selected vendor must have crews available to start work after receiving the Notice to Proceed.
Project Requirements Pre-qualification:
Asphalt Paving Heavy Maintenance ($1,000,000 and OVER) Project Manual available on-line on Bonfire Required in Bid Proposal Submittal Follow Submission Instruction in Bonfire Bid Form Conflict of Interest Statement Bid Bond Contractor Compliance with WC Vendor Compliance to State Law Proposal Form Addendum Bid Table
Small Business Goal is waived for this contract.
Small Business Enterprise:
Questions/Discussion
Fort Worth Project Manager
| Iretomiwa Otuyelu |
| 817-392-6747 |
| Iretomiwa.otuyelu@fortworthtexas.gov |
image1.png image2.png image3.png image4.png image5.png
File details come from the government source that posted it. Updated .