8 - Cost Estimate Worksheet.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Y1PC--930CM3005: Construction, Cemetery Expansion, Fort Jackson National Cemetery (VA-25-00053285)
Solicitation number
36C78625B0020
Issued by

About this file

The file is a Cost Estimate Worksheet for a construction project at Fort Jackson National Cemetery, associated with VA Solicitation Number 36C78625B0020. The worksheet provides a comprehensive template for contractors to detail construction costs across multiple division categories, including general conditions, site investigation, and potential mechanical, electrical, and plumbing work. The template allows offerors to specify unit costs, number of units, and extended total costs for each division, with sections for subtotals, insurance, bonding, overhead, and profit calculations. While many division categories are listed (such as concrete, masonry, metals, electrical, and utilities), only a few initial sections like site investigation and general conditions are currently populated, suggesting contractors will need to complete the detailed cost breakdown for their specific project approach.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

IFB Contractor Cost Estimate Worksheet
Lump Sums are required for each Division that will be utilized in this project to total the Final Lump Sum number.

If a Division is not being used put N/A in that field.

Additional lines/items can be added if needed or appropriate.

Offeror shall use and edit to fit Task Order Project
Project Number:
Solicitation Number:
Project Title:
DivisionUnit of Measure# of UnitsUnit Cost $Extended/Total Cost $Comments / Remarks
Division 0 - Special Sections
General Conditions and AdministrationJB1
Division 01 - General Requirements
MobilizationJB1
Division 02 - Existing Conditions
Site InvestigationJB1
Division 03 - Concrete

Division 04 - Masonry

Division 05 - Metals

Division 06 - Wood, Plastic, and Composites

Division 07 - Thermal and Moisture Protection

Division 08 - Openings (Doors, Windows, etc...)

Division 09 - Finishes

Division 10 - Specialties

Division 11 - Equipment

Division 12- Furnishings

Division 13 - Special Construction

Division 14 - Fire Suppression

Division 22 - Plumbing

Division 23 - Heat, Ventilating, and Air Conditioning

Division 25 - Integrated Automation

Division 26 - Electrical

Division 27 - Communications

Division 28 - Electronic Safety and Security

Division 31 - Earthwork

Division 32 - Exterior Improvements

Division 33 - Utilities

Mechanical, Electrical, Plumbing Subtotal
General Construction Subtotal
Total Base Construction Cost
Insurance (if applicable)
Bonding (if applicable)
Overhead________ %$0.00
Profit________ %$0.00
GRAND TOTALS$

File details come from the government source that posted it. Updated .