8-Attachment E - Bid-Price Proposal Form.pdf

PDF 296 KB Posted

Attached to
Generator Maintenance (2026 - 2031)
Solicitation number
K27-0009-29
Issued by
Maryland

About this file

Summary

This is a Bid/Price Proposal Form for the Maryland Judiciary Administrative Office of the Courts (AOC) solicitation K27-0009-29 for Generator Maintenance services covering the period from July 1, 2026, through June 30, 2031. The AOC seeks comprehensive maintenance coverage for mechanical, electrical, and control system components across two generator units: MTU 12V1600 DS600 and MTU 1000RXC. The scope of work includes major (full-service) maintenance services, minor (inspection) maintenance services, labor rates for technician work performed during normal business hours, after-hours, weekends, holidays, and overtime periods, mileage charges, and semi-annual full load testing with associated pre-test inspection, load bank mobilization and setup, full load test execution, instrumentation and data logging, post-test report preparation, and travel and per diem expenses. The contract consists of a base year (July 1, 2026 – June 30, 2027) followed by four option years, with identical service line items repeated for each contract period.

Bidders must provide unit pricing for all line items across the base year and option years, with pricing to be entered on the proposal form for each service call, hourly labor rate, and semi-annual testing activity. The form requires bidder identification information including company name, address, Federal Tax Identification Number, telephone, and email, along with certification status for Minority Business Enterprise (MBE) and Veteran-Owned Small Business Enterprise (VSBE) participation. A grand total price must be calculated by summing the totals from the base year, all four option years, resulting in a comprehensive five-year cost proposal. An authorized representative must sign and date the completed proposal form.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment E Bid/Price Proposal Form

Procurement Maryland Judiciary – mdcourts.gov/procurement

Solicitation number: K27-0009-29

Project title: Generator Maintenance (2026 – 2031)

Base Year – Period of Performance 07/01/2026 – 06/30/2027

Line Maintenance Services Unit Price (UP) Qty. Total (UP x Qty.)

1 Major (Full-Service) Maintenance - MTU 12V1600 DS600 $ per service call 1 $

2 Major (Full-Service) Maintenance - MTU 1000RXC $ per service call 1 $

3 Minor (Inspection) Maintenance - MTU 12V1600 DS600 $ per service call 3 $

4 Minor (Inspection) Maintenance - MTU 1000RXC $ per service call 3 $

Line Labor Rates (Outside of Annual Maintenance Services) Unit Price (UP) Qty. Total (UP x Qty.)

5 Service Technician – Normal Business Hours $ per hour 1 $

6 Service Technician – After Business Hours $ per hour 1 $

7 Service Technician – Weekends and Holidays $ per hour 1 $

8 Service Technician – Overtime $ per hour 1 $

9 Mileage Rate $ per mile 1 $

Semi-Annual Full Load Testing MTU 12V1600 DS600 Unit

10 Pre-test inspection and coordination $ per semi-annual test 2 $

11 Load bank mobilization and setup $ per semi-annual test 2 $

12 Full load test execution $ per semi-annual test 2 $

13 Instrumentation and data logging $ per semi-annual test 2 $

14 Post-test report preparation and delivery $ per semi-annual test 2 $

15 Travel and per diem $ per semi-annual test 2 $

Semi-Annual Full Load Testing MTU 1000RXC Unit

16 Pre-test inspection and coordination $ per semi-annual test 2 $

17 Load bank mobilization and setup $ per semi-annual test 2 $

18 Full load test execution $ per semi-annual test 2 $

19 Instrumentation and data logging $ per semi-annual test 2 $

20 Post-test report preparation and delivery $ per semi-annual test 2 $

21 Travel and per diem $ per semi-annual test 2 $

22 Total (Lines 1-21) $

Option Year 1 - Period of Performance 07/01/2027 – 06/30/2028

Line Description Unit Price (UP) Qty. Total (UP x Qty.)

23 Major (Full-Service) Maintenance - MTU 12V1600 DS600 $ per service call 1 $

24 Major (Full-Service) Maintenance - MTU 1000RXC $ per service call 1 $

25 Minor (Inspection) Maintenance - MTU 12V1600 DS600 $ per service call 3 $

Procurement Maryland Judiciary – mdcourts.gov/procurement

26 Minor (Inspection) Maintenance - MTU 1000RXC $ per service call 3 $

Line Labor Rates (Outside of Annual Maintenance Services) Unit Price (UP) Qty. Total (UP x Qty.)

27 Service Technician – Normal Business Hours $ per hour 1 $

28 Service Technician – After Business Hours $ per hour 1 $

29 Service Technician – Weekends and Holidays $ per hour 1 $

30 Service Technician – Overtime $ per hour 1 $

31 Mileage Rate $ per mile 1 $

Semi-Annual Full Load Testing MTU 12V1600 DS600 Unit

32 Pre-test inspection and coordination $ per semi-annual test 2 $

33 Load bank mobilization and setup $ per semi-annual test 2 $

34 Full load test execution $ per semi-annual test 2 $

35 Instrumentation and data logging $ per semi-annual test 2 $

36 Post-test report preparation and delivery $ per semi-annual test 2 $

37 Travel and per diem $ per semi-annual test 2 $

Semi-Annual Full Load Testing MTU 1000RXC Unit

38 Pre-test inspection and coordination $ per semi-annual test 2 $

39 Load bank mobilization and setup $ per semi-annual test 2 $

40 Full load test execution $ per semi-annual test 2 $

41 Instrumentation and data logging $ per semi-annual test 2 $

42 Post-test report preparation and delivery $ per semi-annual test 2 $

43 Travel and per diem $ per semi-annual test 2 $

44 Total (Lines 23 – 43) $

Option Year 2 - Period of Performance 07/01/2028 – 06/30/2029

Line Description Unit Price (UP) Qty. Total (UP x Qty.)

45 Major (Full-Service) Maintenance - MTU 12V1600 DS600 $ per service call 1 $

46 Major (Full-Service) Maintenance - MTU 1000RXC $ per service call 1 $

47 Minor (Inspection) Maintenance - MTU 12V1600 DS600 $ per service call 3 $

48 Minor (Inspection) Maintenance - MTU 1000RXC $ per service call 3 $

Line Labor Rates (Outside of Annual Maintenance Services) Unit Price (UP) Qty. Total (UP x Qty.)

49 Service Technician – Normal Business Hours $ per hour 1 $

50 Service Technician – After Business Hours $ per hour 1 $

51 Service Technician – Weekends and Holidays $ per hour 1 $

52 Service Technician – Overtime $ per hour 1 $

53 Mileage Rate $ per mile 1 $

Semi-Annual Full Load Testing MTU 12V1600 DS600 Unit

54 Pre-test inspection and coordination $ per semi-annual test 2 $

55 Load bank mobilization and setup $ per semi-annual test 2 $

56 Full load test execution $ per semi-annual test 2 $

57 Instrumentation and data logging $ per semi-annual test 2 $

58 Post-test report preparation and delivery $ per semi-annual test 2 $

59 Travel and per diem $ per semi-annual test 2 $

Semi-Annual Full Load Testing MTU 1000RXC Unit

60 Pre-test inspection and coordination $ per semi-annual test 2 $

61 Load bank mobilization and setup $ per semi-annual test 2 $

62 Full load test execution $ per semi-annual test 2 $

63 Instrumentation and data logging $ per semi-annual test 2 $

64 Post-test report preparation and delivery $ per semi-annual test 2 $

65 Travel and per diem $ per semi-annual test 2 $

66 Total (Lines 45 – 65) $

Option Year 3 - Period of Performance 07/01/2029 – 06/30/2030

Line Description Unit Price (UP) Qty. Total (UP x Qty.)

67 Major (Full-Service) Maintenance - MTU 12V1600 DS600 $ per service call 1 $

68 Major (Full-Service) Maintenance - MTU 1000RXC $ per service call 1 $

69 Minor (Inspection) Maintenance - MTU 12V1600 DS600 $ per service call 3 $

70 Minor (Inspection) Maintenance - MTU 1000RXC $ per service call 3 $

Line Labor Rates (Outside of Annual Maintenance Services) Unit Price (UP) Qty. Total (UP x Qty.)

71 Service Technician – Normal Business Hours $ per hour 1 $

72 Service Technician – After Business Hours $ per hour 1 $

73 Service Technician – Weekends and Holidays $ per hour 1 $

74 Service Technician – Overtime $ per hour 1 $

75 Mileage Rate $ per mile 1 $

Semi-Annual Full Load Testing MTU 12V1600 DS600 Unit

76 Pre-test inspection and coordination $ per semi-annual test 2 $

77 Load bank mobilization and setup $ per semi-annual test 2 $

78 Full load test execution $ per semi-annual test 2 $

79 Instrumentation and data logging $ per semi-annual test 2 $

80 Post-test report preparation and delivery $ per semi-annual test 2 $

81 Travel and per diem $ per semi-annual test 2 $

Semi-Annual Full Load Testing MTU 1000RXC Unit

82 Pre-test inspection and coordination $ per semi-annual test 2 $

83 Load bank mobilization and setup $ per semi-annual test 2 $

84 Full load test execution $ per semi-annual test 2 $

85 Instrumentation and data logging $ per semi-annual test 2 $

86 Post-test report preparation and delivery $ per semi-annual test 2 $

87 Travel and per diem $ per semi-annual test 2 $

88 Total (Lines 67-87) $

Option Year 3 - Period of Performance 07/01/2030 – 06/30/2031

Line Description Unit Price (UP) Qty. Total (UP x Qty.)

89 Major (Full-Service) Maintenance - MTU 12V1600 DS600 $ per service call 1 $

90 Major (Full-Service) Maintenance - MTU 1000RXC $ per service call 1 $

91 Minor (Inspection) Maintenance - MTU 12V1600 DS600 $ per service call 3 $

92 Minor (Inspection) Maintenance - MTU 1000RXC $ per service call 3 $

Line Labor Rates (Outside of Annual Maintenance Services) Unit Price (UP) Qty. Total (UP x Qty.)

93 Service Technician – Normal Business Hours $ per hour 1 $

94 Service Technician – After Business Hours $ per hour 1 $

95 Service Technician – Weekends and Holidays $ per hour 1 $

96 Service Technician – Overtime $ per hour 1 $

97 Mileage Rate $ per mile 1 $

Semi-Annual Full Load Testing MTU 12V1600 DS600 Unit

98 Pre-test inspection and coordination $ per semi-annual test 2 $

99 Load bank mobilization and setup $ per semi-annual test 2 $

100 Full load test execution $ per semi-annual test 2 $

101 Instrumentation and data logging $ per semi-annual test 2 $

102 Post-test report preparation and delivery $ per semi-annual test 2 $

103 Travel and per diem $ per semi-annual test 2 $

Semi-Annual Full Load Testing MTU 1000RXC Unit

104 Pre-test inspection and coordination $ per semi-annual test 2 $

105 Load bank mobilization and setup $ per semi-annual test 2 $

106 Full load test execution $ per semi-annual test 2 $

107 Instrumentation and data logging $ per semi-annual test 2 $

108 Post-test report preparation and delivery $ per semi-annual test 2 $

109 Travel and per diem $ per semi-annual test 2 $

110 Total (Lines 89 - 109) $

111 Grand Total (Line 22 + Line 44 + Line 66 + Line 88 + Line 110) $

Bidder/Offeror Name:

Bidder/Offeror Address:

Federal Tax Identification No.:

Telephone No.:

Email:

MBE: ☐ No ☐ Yes, Certification No.:

VSBE: ☐ No ☐ Yes, Certification No.:

Signature of Authorized Representative Date

Print name of Authorized Representative

Title of Authorized Representative

Total UP x Qty:
fill_5:
fill_7:
fill_9:
Total UP x Qty_2:
fill_13:
fill_15:
fill_17:
fill_19:
fill_20:
fill_21:
fill_22:
fill_23:
fill_24:
fill_25:
fill_26:
fill_27:
fill_28:
fill_29:
fill_30:
fill_31:
fill_32:
Total UP x Qty_3:
fill_34:
fill_35:
fill_2:
Total UP x Qty_4:
fill_4:
fill_5_2:
fill_6:
fill_7_2:
fill_8:
fill_9_2:
fill_10:
fill_11:
fill_12:
fill_13_2:
fill_14:
fill_15_2:
fill_16:
fill_17_2:
fill_18:
fill_19_2:
fill_22_2:
Total UP x Qty_5:
fill_24_2:
fill_25_2:
fill_26_2:
Total UP x Qty_6:
fill_28_2:
fill_29_2:
fill_30_2:
fill_31_2:
fill_32_2:
fill_33:
fill_2_2:
fill_3:
fill_4_2:
fill_5_3:
fill_6_2:
fill_7_3:
fill_8_2:
fill_9_3:
fill_10_2:
fill_11_2:
fill_14_2:
Total UP x Qty_7:
fill_16_2:
fill_17_3:
fill_18_2:
Total UP x Qty_8:
fill_20_2:
fill_21_2:
fill_22_3:
fill_23_2:
fill_24_3:
fill_25_3:
fill_26_3:
fill_27_2:
fill_28_3:
fill_29_3:
fill_30_3:
fill_31_3:
fill_32_3:
fill_33_2:
fill_34_2:
fill_8_3:
fill_9_4:
Total UP x Qty_9:
fill_11_3:
fill_12_2:
fill_13_3:
Total UP x Qty_10:
fill_15_3:
fill_16_3:
fill_17_4:
fill_18_3:
fill_19_3:
fill_20_3:
fill_21_3:
fill_22_4:
fill_23_3:
fill_24_4:
fill_25_4:
fill_26_4:
fill_27_3:
fill_28_4:
fill_29_4:
fill_30_4:
fill_31_4:
fill_32_4:
BidderOfferor Name:
BidderOfferor Address:
Federal Tax Identification No:
Telephone No:
Email:
Yes Certification No:
Yes Certification No_2:
Date:
Print name of Authorized Representative:
Title of Authorized Representative:

File details come from the government source that posted it. Updated .