8-09 Exhibit H SOW HDDR.pdf
PDF 162 KB Posted
- Attached to
- DART CBD TSP Cabinet Power
- Solicitation number
- 2093591
- Issued by
- Dallas County, Texas
About this file
This Statement of Work is an exhibit to Solicitation No. 2093591 issued by the Dallas Area Rapid Transit Authority (DART) in Dallas, Texas, and outlines the electrical scope of work for a power supply replacement project at 13 Traffic Signal Priority (TSP) intersection locations. The project involves three primary tasks: replacement of batteries in signal enclosures, replacement of power supply units in signal enclosures, and replacement of UPS units in signal enclosures. All work must be performed exclusively during scheduled overnight shifts to avoid disruption to DART's revenue service and daytime operations. The document specifies that contractors must attend a Pre-Bid Conference and site visit to assess site conditions, including access constraints and railroad right-of-way protocols. DART will provide flagging support and manage signal flash mode operations during power supply replacements, while temporary power via contractor-provided generators and lighting must be maintained during equipment cutover and installation.
Contractors are responsible for furnishing all tools, equipment, incidental supplies, and materials necessary for execution, with pricing based solely on customary cost elements including labor, materials, equipment usage, and standard industry markups—no mobilization or administrative fees are permitted unless expressly identified in the bid. Contractors must furnish and install all required supports, rails, brackets, mounting hardware, and associated materials for new power supply unit installations in compliance with applicable codes, DART specifications, and industry best practices. Deliverables include installation of all new power supply equipment, removal and proper disposal of replaced components as required by DART, confirmation and documentation of proper installation and functional readiness, and shift reports with final close-out documentation. All work must comply with DART safety requirements, railroad right-of-way rules, and local electrical codes, with any deviations, assumptions, or clarifications to be submitted in writing during the formal question-and-answer period.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No: 2093591
DART Form 33.H 1 of Exhibit H 09 Exhibit H SOW HDDR.docx 3/11/2026 7:33:00 AM
Dallas Area Rapid Transit Authority
Dallas, Texas
EXHIBIT H
STATEMENT OF WORK
The electrical scope of work includes the following tasks at 13 TSP Intersection locations:
1. Replacement of batteries in signal enclosures.
2. Replacement of power supply units in signal enclosures.
3. Replacement of UPS units in signal enclosures.
For Pre-Bid Conference and Site Visit
1. Project Overview The purpose of this project is to replace existing power supply systems associated with DART signal cabinets and related infrastructure. All activities will be performed during scheduled overnight work windows to avoid disruption to revenue service and daytime operations.
This Scope of Work defines contractor responsibilities, DART-provided resources, site access conditions, and performance expectations for all bidders.
2. Work Hours and Access
1. Night Work Requirement
All work under this contract shall be performed exclusively during night shifts as scheduled and approved by DART. No daytime work will be permitted unless explicitly authorized in writing by the DART Project Manager.
2. Site Access DART will ensure the contractor has adequate access to all designated work areas for the full duration of each night shift. Access constraints, railroad right-of-way protocols, and safety briefings will be reviewed during the Pre-Bid Conference and site visit.
3. Flagging Support DART will provide all required flaggers during the contractor’s work hours. Contractors must coordinate staffing and scheduling requirements with DART in advance.
3. Temporary Power and Signal Operations
1. Temporary Power Supply
During power supply replacement activities, the contractor will use temporary generators to maintain power to the signal cabinets. Contractor-provided temporary lighting will also be required to ensure safe and effective night-time operations.
2. Signal Flash Mode Operations During the cutover and replacement process, signal systems will be placed in flash mode. This flash operation and all related signal programming will be provided and managed by others (not the contractor).
Contractors are responsible for planning their work around this operational state.
4. Contractor Responsibilities
1. Tools, Equipment, and Materials
All contractor tools, equipment, and incidental supplies necessary to execute the work shall be included in the contractor’s pricing. Equipment must meet all applicable safety and performance standards.
2. Installation of Supports and Rails The contractor shall furnish and install all required supports, rails, brackets, mounting hardware, and associated materials needed for the installation of new power supply units. All installation methods must comply with applicable codes, DART specifications, and industry best practices.
3. Labor and Cost Basis Pricing shall be based solely on customary cost elements including labor, materials, equipment usage, and standard industry mark-ups. No additional mobilization or administrative fees shall be included unless expressly identified in the bid.
5. Additional Requirements
• Contractors must attend the scheduled Pre-Bid Conference and site visit to assess site conditions firsthand.
DART Form 33.H 2 of Exhibit I 09 Exhibit H SOW HDDR.docx 3/11/2026 7:33:00 AM
• Any deviations, assumptions, or clarifications must be submitted in writing during the formal Q&A period.
• All work must comply with DART safety requirements, railroad right-of-way rules, and local electrical codes.
6. Deliverables (High-Level)
• Installation of all new power supply equipment.
• Removal and proper disposal of replaced components (if required by DART).
• Confirmation and documentation of proper installation and functional readiness.
• Shift reports and final close-out documentation.
********************* End of Exhibit H ********************