7606105 STATEMENT OF WORK.pdf

PDF 2 MB Posted

Attached to
Paint All Exterior and Common Area Doors, Buildings 4166, 4167, 4168, 4169 & 3673
Solicitation number
N400857606105
Issued by

About this file

This is a Statement of Work (SOW) for painting exterior and common area doors, door frames, exterior wall vents, and handrails at five Marine Corps Air Station (MCAS) Cherry Point buildings located in North Carolina.

The contractor shall provide comprehensive surface preparation and painting services for approximately 800 doors and door frames across Buildings 4166, 4167, 4168, 4169, and 3673. Work includes cleaning, degreasing, scraping loose coatings, sanding, rust treatment, priming, and application of finish coatings to achieve a professional, durable, corrosion-resistant finish. Common area, stairwell, mechanical, and storage room doors require refinishing on both sides, while residential/individual room doors need preparation on the exterior/corridor-facing side only. Exterior wall vents, louvers, grilles, and frames must be cleaned and painted while ensuring ventilation openings remain unobstructed and mechanical components are not sealed. Building 3673 exclusively includes approximately 2,350 linear feet of four-tube handrail/railing refinishing requiring minimum one primer coat and two finish coats. All work must be field-verified prior to commencement. The contractor must provide one person serving as superintendent, quality control manager, and site safety officer. Regular working hours are 7:00 a.m. to 3:30 p.m., Monday through Friday, excluding government holidays. Pre-work submittals required include manufacturer technical data sheets, Safety Data Sheets, color and finish samples, work plans, project schedule, and safety documentation. The barracks remain operational during the entire construction period, requiring minimal interference with normal activities and coordination with the Facilities Engineering & Acquisition Division (FEAD).

View the file

Other files

File Type Posted
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
Master PPI Form.xlsx XLSX spreadsheet
7606105 RFP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DISTRIBUTION: DoW COMMUNITY ONLY

Paint all exterior and common area doors, BUILDING 4166,4167,4168,4169 and 3673

MCAS CHERRY POINT, NORTH CAROLINA 28533-0006

WORK ORDER # 7606105

1.1 GENERAL INTENTION

The work includes Paint all exterior and common area doors and incidental related work.

1.2 LOCATION

The work is located at MCAS Cherry Point Building 4166, 4167, 4168, 4169 and 3673 approximately as indicated. The exact location will be shown by the Contracting Officer.

1.3 DETAILED REQUIREMENTS

PREPARATION AND PAINTING OF EXTERIOR/COMMON AREA DOORS, DOOR

FRAMES, EXTERIOR WALL VENTS, AND BUILDING 3673 HANDRAILS

The Contractor shall provide all labor, supervision, materials, equipment, tools, transportation, access equipment, Personal Protective Equipment (PPE), surface protection, and incidental items necessary to clean, prepare, repair minor surface defects, treat corrosion, prime, and paint all designated exterior and common area doors and door frames, exterior wall vents/louvers and associated frames, and designated handrails within the buildings identified herein.

All work shall result in a complete, uniform, durable, and professionally finished coating system.

a. Included Buildings The following buildings are included within this scope of work:

Building 4166

Building 4167

Building 4168

Building 4169

Building 3673

b. Doors and Door Frames There are approximately 800 doors and associated door frames combined throughout Buildings 4166, 4167, 4168, 4169, and 3673 requiring surface preparation and painting.

Door and frame refinishing requirements shall be as follows:

Common Area, Stairwell, Mechanical Room, and Storage Room Doors and Frames:

All designated common area, stairwell, mechanical room, and storage room doors and associated door frames shall be completely prepared and refinished on BOTH SIDES.

Residential/Individual Room Doors and Frames:

All designated residential/individual room doors and associated door frames shall be prepared and refinished on the EXTERIOR/CORRIDOR-FACING SIDE ONLY. The interior/room-facing side is not included unless specifically directed by the Government.

Surface preparation and refinishing shall include, as required:

Cleaning and degreasing all surfaces to be coated.

Removal of dirt, dust, grease, mildew, chalking, biological growth, and other surface contaminants.

Scraping and removal of loose, peeling, blistered, flaking, or otherwise deteriorated coatings.

Sanding and feathering existing coating edges to provide a smooth transition between sound existing coatings and exposed substrate.

Removal of loose and scaling surface rust and corrosion by mechanical means as required.

Treatment of remaining tightly adhered corrosion with a coating-compatible rust treatment, where applicable.

Spot repair and preparation of minor surface imperfections necessary to provide a paint-ready surface.

Removal of all dust, debris, and residue resulting from surface preparation.

Application of a compatible corrosion-resistant primer to exposed, bare, repaired, or prepared metal surfaces.

Application of the required finish coating system in accordance with the coating manufacturer's written recommendations.

Protection of door hardware, hinges where applicable, locks, cylinders, closers, panic hardware, access-control devices, fire-rating labels, identification plates, weather stripping, seals, and adjacent finished surfaces.

Final touch-up and cleanup of all completed surfaces and surrounding work areas.

Paint shall not be applied over loose or scaling rust, unsound existing coatings, dirt, grease, moisture, or other contaminants that may adversely affect coating adhesion or service life.

Estimated Quantity: Approximately 800 doors and associated door frames.

Quantities are approximate and are provided for estimating purposes. The Contractor shall field verify actual quantities, dimensions, substrate conditions, and access requirements prior to ordering materials and commencing work.

c. Exterior Wall Vents, Louvers, Grilles, and Frames All designated exterior wall vents, louvers, grilles, and associated frames located at Buildings 4166, 4167, 4168, 4169, and 3673 shall be cleaned, prepared, treated for corrosion where required, primed, and painted.

Surface preparation and coating requirements shall be consistent with those specified for other painted metal surfaces within this

SOW.

The Contractor shall ensure that coating operations do not:

Obstruct ventilation openings.

Restrict required airflow.

Seal or interfere with movable louvers.

Coat screens or mechanical components not intended to receive paint.

Interfere with the proper operation of ventilation equipment.

Allow overspray or coating materials to enter the building or ventilation system.

The Contractor shall field verify actual quantities, dimensions, conditions, and access requirements for all vents, louvers, grilles, and associated frames prior to commencing work.

d. Building 3673 – Handrail Refinishing In addition to the doors, frames, vents, and associated components identified above, Building 3673 contains approximately 2,350 linear feet of existing four-tube handrail/railing requiring surface preparation and refinishing.

Building 3673 is the only building included within this project requiring handrail/railing refinishing. Handrail painting is not included for Buildings 4166, 4167, 4168, or 4169.

The Contractor shall prepare and refinish approximately 2,350 linear feet of four-tube handrail/railing at Building 3673. Work shall include, as required:

Cleaning all handrail and railing surfaces to be coated.

Removal of dirt, grease, salts, mildew, biological growth, chalking, and other contaminants.

Scraping and removal of all loose, peeling, blistered, flaking, or otherwise deteriorated coatings.

Mechanical removal of loose and scaling rust and corrosion.

Wire brushing, sanding, grinding, power-tool cleaning, or other approved preparation methods as required to provide a sound substrate.

Feathering edges between sound existing coatings and exposed substrate.

Removal of all dust, debris, and residue generated during surface preparation.

Treatment of remaining tightly adhered corrosion with a coating-compatible rust treatment where required.

Application of a compatible corrosion-resistant primer to exposed, bare, repaired, and prepared metal surfaces.

Application of the specified finish coating system.

Protection of concrete, sidewalks, walls, landscaping, building components, adjacent finished surfaces, vehicles, and other Government property from paint, overspray, grinding debris, and preparation debris.

Final touch-up and cleanup.

Handrails/railings shall receive a minimum of one (1) appropriate primer coat where required and two (2) finish coats, unless the coating manufacturer's specified coating system requires otherwise.

The completed handrails/railings shall have a uniform color, sheen, coverage, and overall appearance. Completed surfaces shall be free of visible rust, exposed bare metal, peeling or loose coatings, runs, sags, drips, holidays, overspray, excessive brush or roller marks, and other visible coating defects.

Estimated Quantity: Approximately 2,350 linear feet of four-tube handrail/railing at Building 3673 only.

e. Estimated Project Quantities Item Building(s) Approximate Quantity Exterior/Common Area Doors and Associated Frames 4166, 4167, 4168, 4169 & 3673 800 EA

Exterior Wall Vents/Louvers, Grilles & Associated Frames 4166, 4167, 4168, 4169 & 3673 Field Verify Four-Tube Handrail/Railing Refinishing 3673 Only 2,350 LF All quantities identified within this SOW are approximate and are intended to establish the general magnitude of work. The Contractor shall verify field conditions, dimensions, quantities, access requirements, substrate conditions, and existing coating conditions prior to commencing work.

Minor variations between the estimated and actual quantities that could reasonably be identified during the pre-work site investigation shall not relieve the Contractor of the responsibility to provide a complete and finished coating system for all surfaces designated within this scope of work.

f. Final Finish and Acceptance Requirements The intent of this SOW is to provide a complete, properly prepared, corrosion-resistant, and professionally applied protective coating system for all designated surfaces.

Application of primer or finish coatings over improperly prepared, contaminated, wet, deteriorated, loose, peeling, or actively corroding surfaces will not be accepted.

Completed surfaces shall provide uniform coverage, color, sheen, and appearance and shall be free of visible rust, bare substrate, peeling, blistering, runs, sags, drips, holidays, overspray, and other coating defects.

Any work determined by the Government to have inadequate surface preparation, untreated corrosion, insufficient coating coverage, poor adhesion, overspray, or other deficiencies attributable to the Contractor's workmanship shall be properly prepared and recoated by the Contractor at no additional cost to the Government.1.4 SPECIAL SCHEDULING REQUIREMENTS

Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.

The barracks will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.

Permission to interrupt any activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption and in accordance with section 1.10.

1.5 CONTRACTOR ACCESS AND USE OF PREMISES

DBIDS has gone live at MCAS Cherry Point. In order to reduce wait time when exchanging your RapidGate credential, it is highly recommended each applicant pre-register at https://dbids-global.dmdc.mil/enroll#!/

Non-DoD cardholding visitors to Marine Corps Installations with a driver's license or ID issued by a state that is not compliant with the Real ID Act of 2005 will now need to provide an alternate form of acceptable identification to gain entry, or be escorted by an authorized patron of the air station.

North Carolina now issues REAL ID compliant driver’s licenses, but many drivers have yet to be issued the new license.

Drivers may get a North Carolina REAL ID driver's license at any NCDMV driver's license office.

The Act established minimum security standards for license issuance and production and prohibits Federal agencies from accepting driver's licenses and identification cards from states not meeting the Act's minimum standards.

In absence of a compliant state issued driver's license or ID, one of the following federally approved forms of identification must also be provided in addition to the non-compliant driver's license or ID:

1. U.S. Passport

2. U.S. Passport Card

3. U.S. Coast Guard Merchant Mariner Card

4. Personal Identity Verification (PIV) Card

5. Personal Identity Verification - Interoperable (PIV-I)

6. U.S. State Department Driver's License

7. Veteran's Health Identification Card (Issued by the U.S.

Department of Veterans Affairs)

8. U.S. Permanent Resident Card (Form I-551)

9. U.S. Certificate of Naturalization or Certificate of

Citizenship (Form N-550)

10. Department of Homeland Security Employment Authorization

Document (Form I-766)

1.5.1 ACTIVITY REGULATIONS

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.5.1.1 SUBCONTRACTORS AND PERSONNEL CONTACTS

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.5.1.2 This section intentionally left blank

1.5.1.2.1 This section intentionally left blank

1.5.1.2.2 This section intentionally left blank

1.5.1.2.3 This section intentionally left blank

1.5.1.3 INSTALLATION ACCESS

Obtain access to Navy and Marine Corps installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html. No fees are associated with obtaining a DBIDS credential.

Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.

1.5.1.3.1 REGISTRATION FOR DBIDS

Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html. Procedure includes:

a. Present a letter or official award document (i.e. DD Form

1155 or SF 1442) from the Contracting Officer that provides the purpose for access to the Base Visitor Control Center representative.

b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.

c. Provide completed SECNAV FORM 5512/1 to the Base Visitor

Control Center representative to obtain a background check.

This form is available for download at https://www.cnic.navy.mil/om/dbids.html.

d. Upon successful completion of the background check, the

Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.

e. Upon successful completion of the enrollment process, the

Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.

1.5.1.3.2 DBIDS ELIGIBILITY REQUIREMENTS

Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.

An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification. The Government is the final authority.

1.5.1.3.3 DBIDS NOTIFICATION REQUIREMENTS

Immediately report instances of lost or stolen badges to the Contracting Officer.

Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:

1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.

2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.

1.5.1.3.4 ONE-DAY PASSES

Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation.

The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.

1.5.1.4 NO SMOKING POLICY

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.5.2 WORKING HOURS

Regular working hours shall consist of an 8 1/2 hour period normally between the hours of 7:00 am to 3:30 pm, Monday through Friday, excluding Government holidays.

1.5.3 WORK OUTSIDE REGULAR HOURS

Work outside regular working hours requires Contracting Officer approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours.

During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.5.4 EXCLUSIONARY PERIOD

No work must be performed during the period holidays, or weekends inclusive, without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for the performance of this contract.

1.5.5 OCCUPIED BUILDING[S]

The Contractor shall be working in and around existing buildings which are occupied. Do not enter the building[s] without prior approval of the Contracting Officer.

The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Relocate movable furniture approximately 6 feet away from the Contractor's working area as required to perform the work, protect the furniture, and replace the furniture in its original location upon completion of the work. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.

1.5.6 UTILITY CUTOVERS AND INTERRUPTIONS

This section intentionally left blank

1.6 SECURITY REQUIREMENTS

This section intentionally left blank

1.6.1 STATION REGULATIONS

No employee or representative of the contractor will be admitted to the work site without an Identification Badge or is specifically authorized admittance to the work site by the FEAD, Facilities Engineering & Acquisition Division.

IMPORTANT NOTE: FEAD personnel (Construction Managers, Engineers/Architects, Engineering Technicians, Contract Specialists, or Contract Surveillance Representatives) will not receive, process, re-transmit or otherwise handle IN ANY WAY Personally Identifiable

1.6.2 CONTRACTOR ACCESS TO MCAS CHERRY POINT AND OUTLYING AREAS

Documentation requirements for granting access to MCAS Cherry Point for commercial and contract employers and employees.

This document is an aid in meeting ASO 5560.6A requirements and is not a substitute for the order.

The Pass & Identification Office at Building 251 will issue credentials to authorized contractors. Sub-Contractors and suppliers must coordinate through the Prime-Contractor:

Criminal Activity. In accordance with ASO 5560.6A, the below list of criminal activities within an applicant's record are considered not in the best interest of the Marine Corps and will be grounds for automatic denial of access aboard the Installation:

a. Conviction of any felony offense.

b. Conviction of any misdemeanor offense, which was the result of a plea bargain of a felony offense.

c. Conviction of any offense involving a weapon.

d. Conviction of any drug offense involving manufacturing or trafficking.

e. More than one misdemeanor conviction of drug related offenses over the applicant's lifetime or one misdemeanor drug related offense within the last five years.

f. Conviction of any assault charge.

g. Conviction of any offense involving theft or larceny.

h. Conviction of any offense of domestic violence.

i. Conviction of any offense related to the abuse/neglect of a child.

j. Conviction of any sexual in nature related offense or registration as a sex offender.

k. Commission of any grievous criminal offense/misconduct while aboard any Federal installation, including blatant disregard for rules and regulations of the Installation, but excluding minor traffic offenses.

l. Other than Honorable, Bad Conduct, and Dishonorable discharges from the U.S. Military.

m. Those identified as undocumented citizens.

n. Those on the National Terrorist Watch List.

o. Any individual who attempts to hide or purposely fails to disclose all past criminal history during the vetting process.

p. Any individual that the Provost Marshal's Office determines to present a risk to the security and safety of the Installation and whose access is deemed not in the best interest of the Marine Corps.

q. Any individual who has been debarred from the

Installation by the Installation Commander or is currently listed as debarred from any other Federal installation.

r. Any individual with an outstanding warrant for their arrest or apprehension.

s. Any individual with a pending criminal court case that, if convicted, would result in access denial in accordance with the criteria listed above.

1.6.3 This section intentionally left blank

1.6.4 This section intentionally left blank

1.6.4.1 This section intentionally left blank

1.6.4.2 This section intentionally left blank

1.6.5 This section intentionally left blank

1.6.6 STAGING AREA

The contractor staging area will be PM to coordinate. Amount of material on site shall be kept to a minimum and shall only be material that is pertinent to the work currently being performed. All stockpiling of equipment and materials shall be closely coordinated with the Government and shall not disrupt activities at the site.

1.7 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by North Carolina Law.

1.8 SUPERVISION

The complexity of this project will require one person to fill the roles of the Superintendent, Quality Control Manager, and Site Safety and Health Officer.

1.9 SUBMITTALS

The following items shall have submittals delivered to the COR for approval by the government prior to the commencement of site work.

a. Product Data Manufacturer's technical data sheets for all proposed cleaners, rust treatments, primers, paints/coatings, and repair products.

Products shall be compatible with the existing substrate and proposed coating system.

b. Safety Data Sheets (SDS) Current SDS for all paints, primers, cleaners, solvents, rust treatments, and other chemical products proposed for use.

c. Color and Finish Paint manufacturer, product line, color, and sheen/finish for Government approval. Where matching other existing BEQ finishes, provide a color chip or sample for approval.

d. Work Plan Brief description of proposed surface preparation, rust/corrosion treatment, priming, painting methods, protection of adjacent surfaces, overspray control, and cleanup procedures.

e. Project Schedule Proposed start/completion dates, sequence of buildings, work hours, and anticipated duration of work at each building.

f. Safety Documentation Site-specific safety plan and applicable certifications for equipment/operators, fall protection, scaffolding, aerial lifts, respiratory protection, or other requirements associated with the work.

g. Field Verification Contractor shall field verify quantities, existing conditions, and access requirements prior to commencing work and notify the COR of any significant discrepancies.

No on-site work shall commence until required submittals have been reviewed and approved by the Government. Government approval does not relieve the Contractor of responsibility for compliance with all contract requirements and manufacturer's written instructions.

1.10 PLANNED OUTAGES AND SERVICE DISRUPTIONS

Planned outages and service disruptions are requested by the contractor for approval by the Government when necessary to facilitate and/or accomplish contract work. Affected services include utilities (steam, water, waste water, and electrical service), communications (telephone, network, industrial control systems, and fire/security alarm systems, fire protection equipment, infrastructure, and road closures.

Disruption of these services cannot be allowed without written approval of the government.

The contractor is required to 1) request the outage in writing and 2) demonstrate sufficient contingency preparedness in the event that service cannot be restored due to a failure in accomplishment of contract work.

All outages require Contractor’s written request fifteen (15) days prior to commencement of such work. The request shall be submitted to the COR with the date, time, duration, and scope of the outage.

As supporting documentation for the request, the contractor is require to submit a contingency plan for all reasonably foreseen risks related to the contractor’s performance of the work that would impact disrupted services in excess of the approved outage. This plan must demonstrate the following at a minimum.

1. Understanding of key personnel and communications methods to include phone numbers.

2. Analysis of reasonable risks during the contract work that would impact disrupted services in excess of the approved outage.

3. An effective recovery plan to restore minimum essential services in the event of these risks materializing.

4. Requested government support.

The government will similarly produce risk-based contingency plans for restoration of essential services caused by reasonably foreseen factors that are not related to the performance of the contract. In these cases, the government may request the contractor make additional preparations to support essential and high risk services. Such requests are considered within the scope of this contract but will be priced and negotiated via modification as conditions warrant.

Approvals will be issued by the Public Works Officer or his/her designee and transmitted via the COR.

1.11 GOVERNMENTAL SAFETY REQUIREMENTS

Personal protective equipment (PPE) is governed in all areas by the nature of the work the employee is performing. Use personal hearing protection at all times in designated noise hazardous locations or when performing noise hazardous tasks.

Safety glasses must be worn or carried/available on each person. Mandatory PPE includes: hard hats, long pants, appropriate safety shoes, and appropriate class reflective vest.

Comply with the Safety and Health Requirements Manual (EM 385- 1-1), NFPA 70, NFPA 70E, NFPA 241, the Accident Prevention Plan (APP), the Activity Hazard Analysis (AHA), Federal and State OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.

An APP in accordance with EM 385-1-1, Appendix A, is required.

An AHA in accordance with EM 385-1-1, Section 1, is required for each activity or task.

The contractor is responsible for any required permits.

1.12 EXECUTION

If during the course of the work, conditions are encountered which are not covered in the contract or are different from conditions that would be reasonably anticipated, the contractor shall immediately notify the Contracting Officer. If such conditions are hazardous or the continuation of work would cause a hazardous condition to develop, the contractor shall stop work and proceed as directed by the Contracting Officer as directed by provisions contained in other sections of this specification. This may include modifications to, or the development of a new, Health and Safety Plan for this project, and alternate or additional appropriate abatement procedures.

File details come from the government source that posted it. Updated .