ATTACHMENT 1 - Performance Work Statement - Yakama Service Unit update.pdf

PDF 524 KB Posted

Attached to
Amendment 3 - Yakama Service Unit Upgrade Stand Alone Closed Circuit Television and Card Access System
Solicitation number
75H71326Q00009
Issued by

About this file

This Performance Work Statement (PWS) details an upgrade project for Closed-Circuit Television (CCTV) security camera and Card Access Systems (CAS) at the Yakama Indian Health Service clinic in Toppenish, Washington. The project aims to replace an obsolete security system to comply with Indian Health Manual Part 3, Chapter 7 Pharmacy Security requirements. Key objectives include installing 29 new high-quality cameras with 5-megapixel resolution, providing complete surveillance coverage of the pharmacy department, and upgrading three existing card reader locations with electric strikes at five pharmacy and three medication room entrances.

The project requires full system compatibility with IHS IDEMIA-ID-One PIV 2.4.1 and HHS 128K PIV II card standards, with a separate physical network for video traffic. The contractor must provide a comprehensive 5-year warranty, deliver on-site training, and complete all work by March 31, 2026. Performance standards include zero blind spots in camera coverage, 24/7 operation with automatic backup power, 45-day video storage capacity, and full integration with the Lenel OnGuard system. The total project will be monitored through a detailed Quality Assurance Surveillance Plan (QASP) with multiple inspection phases and strict performance criteria.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

(PWS)

Upgrade and Install Stand-Alone Closed-Circuit Television (CCTV) Security Camera and Card Access System Upgrade

(CAS)

Portland Area Indian Health Service Clinics

1. INTRODUCTION

1.1 Purpose

This Performance Work Statement (PWS) establishes the performance requirements for upgrading and installing stand-alone Closed-Circuit Television (CCTV) security camera systems and Card Access Systems (CAS) at two Portland Area Indian Health Service pharmacy facilities to ensure compliance with Indian Health Manual Part 3, Chapter 7 - Pharmacy, Sections 3-7.7 Pharmacy Security requirements.

1.2 Background

Portland Area Indian Health Center provides access to health care for an estimated 150,000 American Indian/Alaska Native residents of Oregon, Washington, and Idaho. The Portland Area Indian Health Service operates four Federal Health Facilities in 3 tribal communities and one at Chemawa Indian School. The Yakama Indian Health Center is located in Toppenish, WA on the Yakama Indian Reservation.

All IHS Federal Pharmacy Departments must meet compliance regulations of Indian Health Manual: Part 3, Chapter 7 -- Pharmacy, Sections 3-7.7 Pharmacy Security, E. Access to Controlled Substances, (5) Closed Circuit Television Cameras - a-f.

The Yakama Service Unit currently has an obsolete stand-alone CCTV and CAS system that does not meet Agency standards for Pharmacy Security Surveillance and requires complete upgrade. Facilities layout for Pharmacy Department is provided in Attachments A, referencing existing equipment and overall technical infrastructure (i.e., conduit routes, junctions, circuitry, outlets, switches, etc.).

1.3 Scope of Work

The Contractor shall provide all labor, supervision, materials, equipment, tools, supplies, transportation, and incidental services necessary to successfully upgrade and install fully functional stand-alone CCTV security camera systems and Card Access Systems that meet all specified performance standards and ensure compliance with Indian Health Manual requirements. Contractor should also be aware of existing CAS throughout the Facility that should remain in place and active.

2. APPLICABLE DOCUMENTS

2.1 Regulatory and Compliance Requirements

• Indian Health Manual Part 3, Chapter 7 -- Pharmacy, Sections 3-7.7 Pharmacy Security

• IHS IDEMIA-ID-One PIV 2.4.1 Standards

• HHS 128K PIV II Card Standards

• National Institute of Standards and Technology (NIST) Standards

• Federal Information Processing Standards (FIPS)

• American National Standards Institute (ANSI) Standards

• National Electrical Installation Standards (NEIS)

• Underwriters Laboratories (UL) Standards

• Current National Electrical Code (NEC)

• Current mechanical and electrical codes applicable to project locations

2.2 Reference Documents

• Attachment A: Yakama Service Unit Facility Layouts

3. REQUIREMENTS

3.1 Performance Objectives

The Contractor shall achieve the following performance objectives:

PO-1: Security Compliance - Deliver fully operational CCTV and CAS systems that meet 100% of Indian Health Manual Part 3, Chapter 7, Section 3-7.7 Pharmacy Security requirements at both service unit locations by April 1, 2026.

PO-2: Complete Coverage - Ensure zero blind spots in pharmacy surveillance coverage through strategic camera placement with overlapping fields of view for all critical areas including medication storage, controlled substance safes, dispensing areas, and entry/exit points.

PO-3: System Reliability - Install systems capable of continuous 24/7 operation with automatic backup power for minimum 24 hours and video storage meeting specified retention periods (45 days at Yakama).

PO-4: Operational Continuity - Complete all work with minimal disruption to pharmacy operations, maintaining pharmacy security and functionality at end of each workday.

PO-5: User Accessibility - Deliver systems that are accessible and operable by both IT staff and non-IT personnel (pharmacists, administrators) following comprehensive on-site training.

PO-6: Long-term Sustainability - Provide comprehensive 5-year warranty and maintenance support ensuring sustained system performance and compliance.

3.2 Performance Standards

3.2.1 Yakama Service Unit - System Upgrade

PS-1: CCTV Camera System Performance

The Contractor shall upgrade the existing obsolete CCTV system to meet the following performance standards:

a. Coverage: Install minimum twenty-nine (29) new high-quality cameras providing complete coverage of the Pharmacy Department with overlapping fields of view eliminating all blind spots.

b. Resolution: Minimum 5 megapixel resolution for all cameras with ability to clearly capture:

• Facial recognition quality imagery

• Prescription label and medication identification

• Personnel activities and movements

• Date/time stamps on all footage

c. Technical Capability:

• IP-based solution compatible with IPv4 and IPv6

• Power over Ethernet (PoE) capability

• Unique IP address for each camera with descriptive location naming

• Auto sensor adjustment for varying light conditions

• Continuous exposure adjustment to optimize image quality

• Night mode/infrared capability for low-light recording

• Live and recorded footage with clear date/time stamps

d. Infrastructure:

• Separate physical network for video traffic (not on data/voice network)

• Utilize existing cable trays and pathways within crawl space where feasible

• Install new cable pathways, j-hook support (above ceiling), and conduit sleeves as needed

• Install tamper-proof mounting hardware/fasteners

• Provide copper and/or fiber drops to support devices

• Install Ethernet copper category cabling (Cat5e or Cat6 minimum)

• Properly label all ports and infrastructure

e. Recording and Storage:

• Lenel Network Video Recorder (latest version) or approved equivalent

• Dell server/desktop hardware

• Storage capacity for minimum 45 days of footage from all cameras

• Equipment/System to be located in secure areas with restricted access.

f. Power and Backup:

• Backup battery system providing minimum 24 hours of operation

• Uninterruptible power supply for critical components

g. Removal of Obsolete Equipment:

• Remove all six (6) existing obsolete cameras

• Properly inventory removed equipment for IHS disposal

• Remove associated obsolete infrastructure as directed

PS-2: Card Access System Performance

The Contractor shall upgrade the existing Card Access System to meet the following performance standards:

a. Compliance: Full compatibility with IHS IDEMIA-ID-One PIV 2.4.1 and HHS issued 128K PIV II cards

b. Coverage: Upgrade three (3) existing card reader locations and install electric strikes/door release mechanisms at:

• Five (5) Pharmacy Department entrances

• Three (3) Medication Room entrances

c. Software Integration: Integration with Lenel OnGuard System (latest version) or approved equivalent

d. Audit Capability: System configured to retrieve minimum 5,000 events or equivalent to 2 weeks of data for each card reader

e. Hardware:

• New door release mechanisms at all designated locations

• Controllers/modules installed in secure location within Pharmacy Department

• Battery backup providing minimum 24 hours operation without external power

PS-3: Documentation and Training Performance (Yakama)

a. Provide comprehensive equipment inventory with make/model/serial numbers and physical locations for IHS Property Officer

b. Provide copy of all End User License Agreements

c. Deliver certified on-site training for IT and Pharmacy staff covering:

• System operation and functionality

• Maintenance procedures

• Troubleshooting procedures

• User access and retrieval of footage

d. Provide Gantt Chart showing project schedule meeting March 1, 2026 deadline

e. Provide all manufacturer operating and maintenance manuals

3.2.2. Yakama Service Unit:

• Normal business hours: Monday-Friday, 8:00 AM - 6:30 PM local time (excluding Federal holidays)

• Submit separate electrical plan if required to support new cameras and endpoints

• Ensure daily disposal of construction debris

• Professional conduct while providing services

3.3 Deliverables

The Contractor shall provide the following deliverables:

Deliverable Due Date/Milestone Project Schedule/Gantt Chart Within 14 days of contract award Site Assessment Report Within 21 days of contract award Pre-Installation Package (35%) Per approved project schedule Pre-Installation Package (65%) Per approved project schedule Pre-Installation Package (90%) Per approved project schedule Pre-Installation Package (100%) Prior to installation commencement Equipment Specifications for Approval 30 days prior to procurement Manufacturer Cut-Sheets 30 days prior to testing System Readiness Checklists At installation completion

Deliverable Due Date/Milestone UL Certifications At installation completion Equipment Inventory with Serial Numbers At installation completion End User License Agreements At installation completion Operating and Maintenance Manuals At installation completion On-Site Training Prior to final acceptance 5-Year Warranty and Maintenance Agreement At final acceptance Final Completion Documentation April 1, 2026 or earlier

4. PLACE OF PERFORMANCE

Work shall be performed at the following locations:

Yakama Service Unit 401 Buster Rd Toppenish, WA 98948

On-site assessments are strongly recommended and can be coordinated through the Contracting Officer's Representative (COR).

5. PERIOD OF PERFORMANCE

The period of performance shall be from date of contract award through March 31, 2026. All systems shall be completed, tested, accepted, and fully operational by April 1, 2026.

The 5-year warranty and maintenance period shall commence upon final acceptance of the systems.

6. GOVERNMENT FURNISHED

PROPERTY/EQUIPMENT

The Government will not provide any Government Furnished Equipment or Property. The Government will provide:

a. Access to network infrastructure for system integration, software installation, license activation, and system configuration verification

b. Coordination with facility staff for site access and work area coordination

c. Review and approval of submittals and documentation

7. CONTRACTOR FURNISHED

PROPERTY/EQUIPMENT

The Contractor shall provide all personnel, equipment, materials, tools, supplies, transportation, and services necessary to complete the work, including but not limited to:

a. CCTV cameras meeting specified resolution and capability requirements b. Network video recorders c. Servers and desktop computers (Dell) d. Video/audio storage hardware e. Backup battery systems f. Card access readers (PIV 2.4.1 compliant) g. Electric strikes and door release mechanisms h. Software licenses (Lenel OnGuard or equivalent) g. Network infrastructure (switches, cabling, conduit, etc.) j. Cable trays, j-hooks, conduit sleeves, and support hardware k.

Mounting hardware (tamper-proof) l. All necessary hand tools, power tools, and equipment m.

Safety equipment and PPE n. Transportation for personnel, equipment, and materials o. Waste disposal containers and services

8. SECURITY AND ACCESS REQUIREMENTS

8.1 Facility Access

All contractor personnel shall:

a. Check in daily as "visitors" at the facility administration office b. Sign in and out each time entering/leaving pharmacy areas c. Display identification upon request d. Comply with all facility security protocols e. Obtain required clearances or background checks as directed by the Government

8.2 Information Security

The Contractor shall:

a. Protect all sensitive information encountered during performance b. Comply with all applicable privacy and security regulations c. Ensure all personnel are aware of confidentiality requirements d. Report any security incidents immediately to the COR

9. QUALITY ASSURANCE SURVEILLANCE PLAN

(QASP)

9.1 Purpose

This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate contractor performance. The QASP describes the performance standards and quality levels the services must meet, how the Government will assess performance, and the corrective actions available when performance does not meet contract standards.

9.2 Roles and Responsibilities

Contracting Officer (CO): Responsible for contract administration and has authority to make contractual commitments and modifications.

Contracting Officer's Representative (COR): Responsible for monitoring contractor performance and documenting performance in accordance with this QASP. The COR will coordinate with the Project Officer, Pharmacy Manager, and Facilities Management to ensure proper oversight.

Project Officer: Assists the COR in monitoring technical performance and coordinates day-to-day activities with the contractor.

Pharmacy Manager: Provides subject matter expertise regarding pharmacy security requirements and operational needs.

Facilities Manager/Maintenance Mechanic Supervisor: Oversees infrastructure-related work and ensures compliance with building codes and facility requirements.

9.3 Performance Assessment Methods

The Government will employ the following surveillance methods:

Method Description Application Direct Observation

Physical inspection of work in progress and completed installations

Installation phase, final acceptance

Functional Testing

Testing of equipment and integrated systems to verify performance

System commissioning, acceptance testing

Document Review

Examination of submittals, certifications, manuals, reports All project phases

Customer Feedback

Input from pharmacy staff, IT personnel, facility management

Throughout project and post-installation

Random Inspection Unannounced inspections during installation Installation phase

Method Description Application Performance Metrics

Measurement against specific standards (resolution, storage capacity, etc.) Testing and acceptance phases

9.4 Performance Standards and Surveillance

Phase 1: Pre-Installation (Planning and Design)

Performance Standard Acceptable Quality Level Monitoring Method Frequency

Site assessment completed and documented

Complete and accurate assessment submitted within 21 days of award

Document Review Once

Project schedule/Gantt Chart submitted

Realistic timeline showing March 31, 2026 completion; includes all major milestones

Document Review

Within 14 days of award

Equipment specifications submitted for approval

Meets all technical requirements;

submitted 30 days prior to procurement

Document Review

Prior to equipment purchase

Pre-installation package (35% review)

All required elements per Section 3.2.11; accurate and complete

Document Review & Meeting

Per schedule

Pre-installation package (65% review)

All required elements per Section 3.2.11; incorporates feedback from 35% review

Document Review & Meeting

Per schedule

Pre-installation package (90% review)

All required elements per Section 3.2.11; substantially complete

Document Review & Meeting

Per schedule

Pre-installation package (100% review)

Final package complete and approved; ready for installation

Document Review & Meeting

Prior to installation start

Safety and planning documents submitted

Complete Safety Plan, Infection Control Assessment, Debris Disposal Plan

Document Review

Prior to installation start

Performance Rating Criteria:

• Satisfactory: All deliverables submitted on time, complete, and meet requirements

• Marginal: Minor deficiencies or delays up to 5 business days; correctable

• Unsatisfactory: Significant deficiencies or delays exceeding 5 business days

Phase 2: Installation and Implementation

Standard Acceptable Quality Level Monitoring

Method Frequency

Work conducted during approved hours

100% compliance with approved schedule; after-hours work pre-approved

Daily Sign-in/out Logs Daily

Minimal disruption to pharmacy operations

Pharmacy operational; pharmacy work completed by 4:00 PM daily Direct Observation Daily

Site maintained clean and safe

Work area free of debris and obstructions at end of each workday

Visual Inspection Daily

Pharmacy security maintained

Functioning locks and security system at end of each day Direct Observation Daily

Daily progress communication

COR/supervisors notified of daily work status and any issues

Communication Log Daily

All equipment is new 100% new equipment verified by packaging, documentation, serial numbers

Inspection & Documentation

Upon delivery and installation

Wiring concealed from patient view

100% of wiring hidden;

professional appearance Visual Inspection Weekly and at completion

Use of approved equipment/brands

All equipment matches approved specifications (Dell, Cisco, Lenel or approved equivalent)

Inspection & Documentation Upon delivery

Proper installation techniques

Work meets manufacturer specifications and industry standards

Direct Observation & Inspection

Weekly and at completion

Performance Rating Criteria:

• Satisfactory: All daily requirements met; no safety or security issues

• Marginal: Minor issues corrected same day or within 24 hours

• Unsatisfactory: Repeated violations, safety/security compromises, or uncorrected deficiencies

Phase 3: System Performance and Technical Standards

Performance Standard Acceptable Quality Level Monitoring

Method Frequency

Camera resolution meets specifications

Yakama: 5MP minimum all cameras

Testing & Verification

At installation completion

Complete surveillance coverage

Zero blind spots; overlapping coverage verified in all critical areas

Testing & Visual Verification

At installation

Method Frequency

IPv4 and IPv6 compatibility

100% of devices compatible and tested Network Testing At installation completion Power over Ethernet (PoE) functionality 100% operational for all cameras Testing At installation completion

IP addressing and naming

Each camera has unique IP and descriptive location name; properly documented

Documentation & Testing

At installation completion

Video storage capacity

Yakama: 45 days minimum;

verified with actual footage

Testing & Calculation

At installation completion

Backup battery performance

Minimum 24 hours operation verified through testing Load Testing At installation completion

Low-light/night vision capability

All cameras function properly in low-light conditions; clear imagery produced

Testing in Various Lighting

At installation completion

Motion detection (Yakama)

Cameras properly detect motion and initiate recording Functional Testing At installation completion Tamper-proof mounting

All cameras secured with tamper-proof hardware; resistance verified Physical Inspection At installation completion

Date/time stamping accuracy

All footage clearly displays accurate date, time, and camera location

Testing & Verification

At installation completion

Video network segregation

Video traffic on separate physical network verified; no interference with data/voice

Network Testing At installation completion

Performance Rating Criteria:

• Satisfactory: All technical requirements met or exceeded

• Marginal: Minor deficiencies not affecting primary function; correctable within 5 days

• Unsatisfactory: Fails to meet specified standards; significant functionality gaps

Phase 4: Card Access System Performance

Performance Standard Acceptable Quality Level Monitoring Method Frequency

PIV 2.4.1 and HHS PIV II compatibility (Yakama)

100% compatibility verified with actual HHS PIV II cards Testing At installation completion

Card reader functionality (Yakama)

All readers operational at all designated locations (Yakama: 3

Functional Testing

At installation

Performance Standard Acceptable Quality Level Monitoring Method Frequency readers; access points per specification)

Electric strikes/door releases (Yakama)

100% operational (5 pharmacy entrances, 3 medication rooms)

Functional Testing

At installation completion

Audit capability (Yakama)

System retrieves 5,000 events or 2 weeks data per reader

Testing & Verification

At installation completion

Lenel OnGuard integration (or equivalent) (Yakama)

Software fully integrated and functional

System Testing

At installation completion

CAS backup battery (Yakama) Minimum 24 hours operation verified Load Testing At installation completion

Performance Rating Criteria:

• Satisfactory: All CAS requirements met; full functionality demonstrated

• Marginal: Minor issues not affecting security; correctable within 5 days

• Unsatisfactory: Security compromises or significant functionality failures

Phase 5: System Integration and Testing

Performance Standard Acceptable Quality Level Monitoring

Method Frequency

All devices tested and functional

100% of cameras, recorders, microphones, software, and locks operational

Integrated System Testing

Prior to final acceptance

Camera aim and focus optimization

All cameras provide clear, usable footage of designated areas

Visual Review of Test Footage

Prior to final acceptance

System integration All components work together seamlessly; no compatibility issues Integrated Testing Prior to final acceptance

User accessibility Non-IT staff can successfully access and operate system User Testing Prior to final acceptance

Network performance

No degradation of existing network performance; video network performs as designed

Network Performance Testing

Prior to final acceptance

Stress testing System performs under continuous operation for 72 hours minimum Extended Testing Prior to final acceptance

Performance Rating Criteria:

• Satisfactory: All systems fully integrated and functional; passed all tests

• Marginal: Minor integration issues; resolved within 5 days

• Unsatisfactory: System failures, incompatibilities, or performance deficiencies

Phase 6: Documentation and Training

Performance Standard Acceptable Quality Level Monitoring

Method Frequency

Equipment inventory submitted

Complete list with make/model/serial numbers and locations for all equipment

Document Review At installation completion

End User License Agreements provided

All software licenses documented and copies provided Document Review At installation completion

Operating manuals provided

Complete manufacturer manuals for all equipment Document Review At installation completion Maintenance manuals provided

Complete maintenance documentation for all systems Document Review At installation completion System Readiness Checklists completed

Signed by qualified technician with completion dates Document Review At installation completion

UL certifications submitted All applicable UL listings provided Document Review At installation completion

On-site training conducted

All designated staff trained; training covers operation, maintenance, troubleshooting

Training Attendance & Assessment

Prior to final acceptance

Training effectiveness

Staff demonstrate ability to operate system after training

Practical Demonstration

At training completion

Performance Rating Criteria:

• Satisfactory: All documentation complete and training effective

• Marginal: Minor documentation gaps; additional training session needed

• Unsatisfactory: Significant documentation missing or inadequate training

Phase 7: Warranty and Post-Installation

Performance Standard Acceptable Quality Level Monitoring

Method Frequency

5-year warranty agreement executed

Comprehensive warranty covering all work, materials, equipment, installation

Document Review

At final acceptance

Warranty terms clearly defined

Coverage, response times, maintenance schedule clearly specified

Document Review

At final acceptance

Method Frequency

System defects corrected

All identified defects resolved prior to final acceptance

Inspection & Testing

Prior to final acceptance

Post-installation support responsiveness

Contractor responds to issues within timeframes specified in warranty

Response Time Tracking

Throughout warranty period

Scheduled maintenance performed

Maintenance conducted per agreement; system functionality verified

Inspection & Testing

Per maintenance schedule

Performance Rating Criteria:

• Satisfactory: Warranty comprehensive; all support obligations met

• Marginal: Minor delays in response or service

• Unsatisfactory: Failure to honor warranty terms or provide required support

9.5 Overall Performance Rating System

Performance will be evaluated using the following rating system:

Satisfactory (S): Meets or exceeds all performance standards. Work is complete, functional, and compliant with all requirements. No deficiencies noted or minor issues corrected immediately.

Marginal (M): Minor deficiencies that do not significantly impact system functionality or compliance. Issues are correctable within 5 business days. Does not represent a pattern of performance problems.

Unsatisfactory (U): Fails to meet performance standards. Significant deficiencies affecting system functionality, safety, security, or compliance. Represents pattern of poor performance or failure to correct previously identified issues.

9.6 Corrective Action Process

When performance does not meet acceptable standards, the following corrective action process will be implemented:

Level 1 - Marginal Performance (First Occurrence)

1. COR documents deficiency in surveillance log

2. COR notifies contractor verbally or via email within 1 business day

3. Contractor submits corrective action plan within 2 business days

4. Contractor implements corrections within 5 business days

5. COR verifies correction through re-inspection or testing

6. Performance documented as satisfactory upon successful correction

Timeframe: Issue must be resolved within 5 business days of notification

Level 2 - Unsatisfactory Performance or Repeated Marginal Performance

1. COR documents deficiency in writing with detailed description

2. COR issues formal written notice requiring corrective action plan within 2 business days

3. Contractor submits detailed corrective action plan addressing root cause and preventive measures

4. COR reviews and approves corrective action plan (may require revision)

5. Contractor implements corrective action within timeframe specified by COR (not to exceed 10 business days unless extended for good cause)

6. COR conducts follow-up surveillance to verify effectiveness

7. If not corrected satisfactorily, COR notifies Contracting Officer

Timeframe: Initial corrective action plan due within 2 business days; implementation within 10 business days unless extended

Level 3 - Critical Failure, Safety Issue, or Non-Compliance

1. COR immediately notifies Contracting Officer (within same business day)

2. Contracting Officer may issue stop work order if safety or security is compromised

3. Formal meeting convened with contractor within 3 business days

4. Contractor submits comprehensive corrective action plan within 3 business days of meeting

5. Contracting Officer determines appropriate remedy which may include:

o Formal cure notice o Show cause notice o Withholding of payment o Termination for default o Demand for immediate correction at contractor expense

6. Contractor implements approved corrective action under close Government supervision

7. Independent verification of correction required before work resumes

Examples of Critical Failures:

• Safety violations endangering personnel

• Security breaches compromising pharmacy security

• Use of non-approved or substandard equipment

• Failure to maintain pharmacy functionality at end of workday

• Repeated unsatisfactory performance

• Failure to meet completion deadline

9.7 Performance Documentation

The COR shall maintain a comprehensive performance file containing:

Daily Documentation:

• Contractor sign-in/sign-out logs

• Daily activity logs and progress notes

• Communication records (emails, meeting notes, phone logs)

Inspection Documentation:

• Inspection reports with photos

• Quality control checklists

• Test results and measurements

• Non-conformance reports

Submittal Documentation:

• All contractor submittals and Government responses

• Equipment specifications and approvals

• Pre-installation packages (35%, 65%, 90%, 100%)

• Manufacturer cut-sheets and certifications

Corrective Action Documentation:

• Deficiency notifications

• Corrective action plans

• Verification of corrections

• Follow-up inspection reports

Acceptance Documentation:

• System testing results

• Training attendance and assessment records

• Equipment inventory

• Final inspection reports

• Certificate of Substantial Completion

• Final acceptance letter

Warranty Documentation:

• Warranty agreements

• Maintenance schedules

• Service call records

• System performance tracking

9.8 Inspection and Acceptance Procedures

9.8.1 Inspection Authority

The Government reserves the right to inspect all work at any time during the period of performance. The Contractor shall provide access to work areas and shall not cover or conceal any work until it has been inspected and accepted by the COR, unless otherwise directed.

9.8.2 Staged Inspections

Formal inspections shall occur at the following stages:

1. Pre-Installation Review: 35%, 65%, 90%, and 100% documentation reviews

2. Delivery Inspection: Verification that all equipment is new and meets specifications

3. Rough-In Inspection: Verification of infrastructure (conduit, cabling, mounting) before covering

4. Installation Inspection: Verification of proper installation of all devices

5. Pre-Testing Inspection: Visual inspection of complete installation before functional testing

6. Functional Testing: Comprehensive testing of all system components

7. Integrated System Testing: Testing of complete integrated system

8. Final Inspection: Comprehensive review of all work, documentation, and training

9.8.3 Final Acceptance Criteria

Final acceptance will be granted when all of the following criteria are met:

Installation Completion:

• [ ] All cameras, equipment, and infrastructure installed per approved plans

• [ ] All work completed in accordance with contract requirements and applicable codes

• [ ] Site restored; all debris removed; professional appearance

System Performance:

• [ ] All cameras operational and providing clear footage with no blind spots

• [ ] All recording and storage systems functional and meeting capacity requirements

• [ ] Card Access System(s) fully functional and compliant

• [ ] Backup battery systems tested and verified for 24-hour minimum operation

• [ ] Network segregation verified; no impact on existing data/voice network

• [ ] All systems integrated and working together seamlessly

Technical Compliance:

• [ ] All equipment meets specified technical standards (resolution, PoE, IPv4/IPv6, etc.)

• [ ] All cameras properly aimed, focused, and optimized

• [ ] Date/time stamping accurate on all footage

• [ ] Low-light/night vision capability verified

• [ ] Motion detection functional (Yakama)

• [ ] Tamper-proof hardware installed and verified

Testing:

• [ ] All functional testing completed satisfactorily

• [ ] Integrated system testing passed

• [ ] 72-hour stress test completed successfully

• [ ] User acceptance testing completed by pharmacy and IT staff

Documentation:

• [ ] All equipment inventoried with make/model/serial numbers and locations

• [ ] End User License Agreements provided

• [ ] Operating and maintenance manuals provided

• [ ] System Readiness Checklists completed and signed

• [ ] UL certifications submitted

• [ ] As-built drawings provided

• [ ] All required project documentation complete

Training:

• [ ] On-site training completed for all designated staff

• [ ] Training effectiveness verified through practical demonstration

• [ ] Training materials provided

Warranty:

• [ ] 5-year comprehensive warranty agreement executed

• [ ] Warranty terms clearly defined and acceptable

Compliance:

• [ ] Systems meet 100% of Indian Health Manual requirements

• [ ] All applicable codes and standards met

Quality:

• [ ] All deficiencies corrected

• [ ] No outstanding punch list items

• [ ] Work meets professional quality standards

• [ ] COR satisfied with overall quality and performance

9.8.4 Punch List Process

If deficiencies are identified during final inspection that prevent final acceptance, a punch list will be created:

1. COR prepares detailed punch list of all deficiencies

2. Contractor acknowledges receipt of punch list within 1 business day

3. Contractor provides schedule for correcting all punch list items within 2 business days

4. Contractor corrects all punch list items within agreed timeframe (typically 10 business days)

5. COR re-inspects corrected work

6. Process repeats until all items are satisfactorily corrected

7. Final acceptance granted when punch list is complete

Critical Punch List Items (affecting safety, security, or core functionality) must be corrected immediately and shall not exceed 5 business days.

Minor Punch List Items (cosmetic or non-critical issues) may be granted longer correction periods but shall not exceed 10 business days.

9.8.5 Substantial Completion

Substantial Completion may be granted when:

• Systems are operational and meet Indian Health Manual compliance requirements

• Only minor punch list items remain

• Training has been completed

• Facilities can use the systems safely and effectively

Substantial Completion does not constitute Final Acceptance and does not trigger the warranty period. The Contractor remains responsible for completing all punch list items.

9.9 Performance Metrics Summary

The following key performance indicators (KPIs) will be tracked throughout the project:

KPI Target Measurement

Project Schedule Adherence 100% completion by March 1, 2026 Gantt Chart vs. actual progress

Daily Schedule Compliance 95% or higher Days working within approved hours

Safety Incidents Zero Incident reports Security Incidents Zero Incident reports Site Cleanliness 100% compliant Daily inspections Equipment Specification Compliance

100% new, approved equipment Delivery inspections

Camera Coverage Zero blind spots Testing and verification System Uptime During Testing 99% or higher 72-hour stress test Technical Standards Compliance 100% Testing and measurement

KPI Target Measurement Documentation Completeness 100% Document review

Training Effectiveness 90% or higher staff competency Post-training assessment

Punch List Completion Rate 100% within timeframes Punch list tracking Warranty Terms 5 years comprehensive Contract review

9.10 Government Surveillance Commitment

The Government commits to:

Timely Review: Review all contractor submittals within 10 business days of receipt (5 business days for time-sensitive items)

Access Coordination: Provide reasonable facility access during normal business hours with 24-hour notice for routine work

Technical Support: Provide access to network and IT resources as needed for system integration and testing

Communication: Maintain regular communication with contractor through weekly progress meetings and daily coordination as needed

Decision-Making: Provide timely decisions on requests for information, change proposals, and technical issues

Fair Assessment: Conduct objective performance assessment based on established standards in this QASP

10.6 Pricing Instructions and Requirements

1. All-Inclusive Pricing: Unit prices and extended prices shall include all costs for labor, materials, equipment, supplies, tools, transportation, mobilization/demobilization, overhead, profit, insurance, bonds, taxes, permits, TERO fees, and all other direct and indirect costs necessary to complete the work as specified.

2. Equipment Specifications:

• Pricing must be based on equipment meeting all specified technical requirements

• Servers/Desktops: Dell manufacture or approved equivalent

• Network Equipment: Cisco or approved equivalent

• Video Management: Lenel OnGuard (latest version) or approved equivalent

• All equipment must be new (no refurbished or reconditioned)

• Provide specific make/model for all major equipment items in proposal

3. Site Visit: Contractors are strongly encouraged to conduct site visits at both locations before submitting pricing. Site visits can be coordinated through the COR. The Government is not responsible for contractor assumptions made without site verification.

4. Approval Process: All equipment specifications must be submitted for Government approval before procurement. Allow sufficient time in project schedule for approval process (minimum 30 days).

5. Labor Rates: If required in proposal, provide fully-burdened labor rates by labor category (e.g., Project Manager, Installation Technician, Network Engineer, Electrician).

6. Warranty: The 5-year comprehensive warranty must include:

• All equipment, materials, and workmanship

• Remote and on-site technical support

• Preventive maintenance (specify frequency)

• Repairs and replacement of defective components

• Labor for warranty service calls

• Response time commitments (specify)

• Annual system inspection and optimization

7. Payment Terms:

• Progress payments based on completion of major milestones (to be negotiated)

• Final payment upon successful completion and acceptance

• Retainage as specified in contract (typically 10%)

8. Period of Performance: All work must be completed and systems operational by March 31, 2026.

9. Price Validity: Prices shall remain firm and fixed for 90 days from date of proposal submission.

10. Contingency Allowance: Line item 3.11 is a not-to-exceed allowance for unforeseen site conditions discovered during installation that require additional work beyond the scope. This allowance:

• Will only be utilized if approved in writing by the Contracting Officer

• Requires documented justification and detailed cost breakdown

• Does not constitute a guarantee of additional work or payment

• May not be used for contractor errors, omissions, or failure to conduct adequate site assessment

11. Deliverables Included: All pricing includes delivery of all required documentation, manuals, training, and services as specified in Section 3.3 Deliverables.

12. Alternative Solutions: If proposing equipment or solutions other than specified (e.g., equivalent to Lenel OnGuard, alternative to Cisco), clearly identify in proposal with:

• Detailed justification for equivalency

• Technical specifications demonstrating compliance with all requirements

• Comparative analysis to specified products

• Any cost differential

13. Pricing Format:

• Use pricing schedule format provided

• Show unit prices and extended prices for all line items

• Calculate subtotals and total accurately

• Identify any assumptions or clarifications

• If "TBD" quantities listed, provide unit price and estimated total

14. Exclusions: Identify any exclusions or items not included in pricing that might normally be expected as part of the work.

11. ATTACHMENTS

Attachment A: Yakama Service Unit Facility Layouts (Includes overall facility layout and pharmacy-specific layout showing existing camera and card reader locations)

END OF PERFORMANCE WORK STATEMENT

Attachment A (Yakama Service Unit) – overall facility

Attachment A (Yakama Service Unit Pharmacy Only)

PERFORMANCE WORK STATEMENT (PWS)
Upgrade and Install Stand-Alone Closed-Circuit Television (CCTV) Security Camera and Card Access System Upgrade (CAS)
1. INTRODUCTION
1.1 Purpose
1.2 Background
1.3 Scope of Work
2. APPLICABLE DOCUMENTS
2.1 Regulatory and Compliance Requirements
2.2 Reference Documents
3. REQUIREMENTS
3.1 Performance Objectives
3.2 Performance Standards
3.2.1 Yakama Service Unit - System Upgrade

3.3 Deliverables

4. PLACE OF PERFORMANCE
5. PERIOD OF PERFORMANCE
6. GOVERNMENT FURNISHED PROPERTY/EQUIPMENT
7. CONTRACTOR FURNISHED PROPERTY/EQUIPMENT
8. SECURITY AND ACCESS REQUIREMENTS
8.1 Facility Access
8.2 Information Security
9. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
9.1 Purpose
9.2 Roles and Responsibilities
9.3 Performance Assessment Methods
9.4 Performance Standards and Surveillance
Phase 1: Pre-Installation (Planning and Design)
Phase 2: Installation and Implementation
Phase 3: System Performance and Technical Standards
Phase 4: Card Access System Performance
Phase 5: System Integration and Testing
Phase 6: Documentation and Training
Phase 7: Warranty and Post-Installation
9.5 Overall Performance Rating System
9.6 Corrective Action Process
Level 1 - Marginal Performance (First Occurrence)
Level 2 - Unsatisfactory Performance or Repeated Marginal Performance
Level 3 - Critical Failure, Safety Issue, or Non-Compliance
9.7 Performance Documentation
9.8 Inspection and Acceptance Procedures
9.8.1 Inspection Authority
9.8.2 Staged Inspections
9.8.3 Final Acceptance Criteria
9.8.4 Punch List Process
9.8.5 Substantial Completion
9.9 Performance Metrics Summary
9.10 Government Surveillance Commitment
10.6 Pricing Instructions and Requirements