This is an Amendment of Solicitation for construction services issued by the Indian Health Service (IHS), Division of Engineering Services, Dallas, for the ZSU Quarters Sewer Improvements Project (Project AQ18ZS002) at the Zuni Comprehensive Community Health Center in Zuni, New Mexico. The amendment extends the proposal due date from January 26, 2026 at 2:00 PM CT to February 4, 2026 at 2:00 PM CT. Offerors must acknowledge receipt of the amendment either by completing items 8 and 15 on the revised SF1442, by acknowledging receipt on each copy of the offer submitted, or by separate letter/electronic communication referencing the solicitation and amendment number. The solicitation is a 100% Small Business set-aside under NAICS code 237110 (Water and Sewer Line and Related Structures Construction) with a $45 million size standard. The project magnitude is estimated between $100,000 and $250,000, with a mandatory 90-calendar-day period of performance from issuance of Notice to Proceed and a performance bond requirement due within 10 calendar days of award.

The amendment provides scope clarifications and updates to Section C (Description/Specifications/Statement of Work), including construction of two sanitary sewer lines ('A' and 'B') with associated manholes, service lateral reconnections, traffic control planning, demolition and waste disposal, and an all-inclusive one-year warranty on labor and materials. Updated attachments include revised wage determination (NM20260011 dated 01-02-2026), price schedule revision 1, technical provisions, and construction details. Additional requirements include as-built red-line drawings maintained during construction, submittal coordination with the owner during full occupancy, utility mark-up coordination with NM One-Call, and compliance with OSHA standards and noise/vibration restrictions. The contracting officer is Shaukat Syed at Shaukat.syed@ihs.gov; written questions must be received no later than 14 days prior to the proposal receipt date. A pre-proposal site visit was held on January 7, 2026 at 11:00 AM CST with an agenda covering project scope, technical requirements, permits, and utility coordination responsibilities.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

A00001

See Summary of Changes

Indian Health Service (IHS) Division of Engineering Services (DES) - Dallas 1301 Young Street, Suite 840 Dallas, TX 75202

See Item 6

75H70126R00014

AQ18ZS002

1 10

01/21/2026

12/23/2025

SF30 CONTINUATION OF BLOCK NARRATIVE Page 2 of 10

SUMMARY OF CHANGES

The solicitation is hereby amended to address the following:

1. Extend the proposal due date/time from January 26, 2026, 2:00PM CT to February 4, 2026, 2:00PM CT. Offerors are required to submit the attached revised SF1442 when submitting their proposal.

2. Issue the Pre-proposal site visit agenda and sign-in sheet

3. Answer questions from prospective offeror (See B05 Attachment A1-1 Pre-proposal

Inquiries).

4. Issue updated wage determination (See B01 Attachment J02 - Wage Determination

NM20260011 dated 01-02-2026).

5. Issue updated B01 Attachment J03 - Price Schedule_Rev.1 dated January 21, 2026.

6. Add the following attachments as a result of scope clarifications: (1) B01 Attachment J01a -

Technical Provisions; (2) B01 Attachment J01b – Details.

7. Revise Section C – Description/Specifications/Statement of Work

Section C revisions are highlighted below:

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

Construction Services for ZSU Quarters Sewer Improvements Project Project AQ18ZS002

Zuni-Ramah Service Unit

I. GENERAL:

The Zuni Comprehensive Community Health Center (ZCCHC) is currently experiencing aging issues with their Quarters’ Sewer lines. The system has project construction drawings as developed by QA Engineering.

II. PROJECT DESCRIPTION:

A. Title: ZSU Quarters Sewer Improvements Project

B. Description of the Work: The Contractor shall furnish the necessary construction services, labor, equipment, materials and transportation to complete the Scope of Work.

1. Drawings issued for Construction, October 19, 2023 (See B01 Attachment

1 - Plans).

2. Establish a traffic plan for the project;

3. 6th Street Sewer Line ‘A’:

SF30 CONTINUATION OF BLOCK NARRATIVE Page 3 of 10

a. Construct sanitary sewer line ‘A’ as designed; this will also include new inverts, three manholes as identified on drawings as MH#8, MH#7N and MH#6;

b. Reconnect service laterals to housing units;

c. Connect to existing system;

d. Tie-in service downstream of Cleanout, as noted in drawings of

Keyed Note 8

e. Backfill trench with bedding materials, and patch roadway.

4. Existing Sewer Line ‘B’:

a. Remove existing material along path of existing sanitary sewer line ‘B’ in alleyway north of Housing Units 404 and 405;

b. Construct sanitary sewer line ‘B’ as designed; this will also include new manholes as identified on drawings as MH#10 and MH#11;

c. Build 4-foot diameter manhole at MH#11, as directed in drawings per Piping Schedule 2;

d. Reconnect 4-inch service lines for Housing Units 404 and 405, denoted on drawings on Detail 2, page C-1;

e. Connect to existing system at A Avenue located at MH#11

f. Backfill trench with bedding materials;

g. Reconnect 4-inch service lines for Housing Units 2001 and 2002, denoted on drawings on Detail 1, page C-1;

h. Patch roadway to MH# 11 on Sewer Line ‘B’

C. Demolition:

1. The contractor shall remove all existing materials demolished from the site to an off-site solid waste disposal at the contractor’s expense.

2. The contractor shall at the end of the construction project submit a manifest of waste disposal chronicling the total solid waste disposed, location and total weight (mass).

D. Warranty:

1. The contractor shall provide an all-inclusive 1-Year warranty on all parts and labor and all manufacturers’ warranties must be provided in writing.

2. The Contractor shall warranty that all provided materials are new, non-refurbished, and free from defects. The Contractor shall warranty workmanship for a period of one year from date of final acceptance by Owner. If Government provided equipment is damaged by the Contractor during the installation, the Contractor will immediately replace the damaged equipment at no cost to the Government.

III. PERIOD OF PERFORMANCE:

A. The period of performance will be 90 calendar days from issuance of Notice to Proceed. Any changes to the approved construction schedule shall be submitted for review not less than 5 days ahead of schedule.

SF30 CONTINUATION OF BLOCK NARRATIVE Page 4 of 10

B. As-builds red-lines shall be maintained during construction and submitted at the end of the construction period of performance. Submit with Final pay application.

C. Submittals shall be submitted by the contractor for all materials under this work.

IV. COORDINATION WITH OWNER:

A. Full Owner Occupancy: Owner will occupy site and adjacent building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner and patient usage.

Perform the Work so as not to interfere with Owner's day-to-day operations.

Maintain all existing pedestrian and vehicle exits as part of the approved Traffic Control Plan (TCP) or as conditions dictate.

B. Staging and Storage Areas: The Contractor is allowed to utilize a limited portion of the existing parking lots, for the storage of equipment and materials.

The Contractor shall protect all new roadways from damage caused by their equipment and shall repair or pay for the repair of any damaged roads, curbs and sidewalks. The Contractor shall be responsible for all security of his equipment and materials. The Contractor shall be responsible for complying with all OSHA standards for the safe storage of equipment and materials, including the safe handling of flammable liquids under 29 CFR 1926.152(a).

C. Utility Mark-Up: The Contractor is responsible for contacting NM One-Call for utility markup before beginning any excavation work.

D. Contractor to develop a phasing plan of construction during the design phase and obtain concurrence from the owner.

V. WORK RESTRICTIONS:

A. General: Comply with limitations concerning the use of public streets and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Working hour limitations may be imposed by the COR upon the Contractor at the pre-construction conference or during construction.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than three business days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

1. Notify Owner not less than three business days in advance of proposed disruptive operations.

SF30 CONTINUATION OF BLOCK NARRATIVE Page 5 of 10

2. Obtain Owner's written permission before proceeding with disruptive operations.

E. Contractor and its subcontractors are not permitted to use the Owner’s sanitation facilities. The Contractor shall provide and maintain necessary sanitary conveniences (porta-potties) for its employees throughout the duration of the Work. These shall be located away from public observation to the maximum extent possible.

F. Smoking is not permitted anywhere on the project site.

G. Controlled Substances: Use of tobacco products and other controlled substances on Project site is not permitted.

H. Work shall be performed in strict accordance with all terms, conditions, specifications, schedules and drawings. Performance shall be in accordance with the requirements, conditions, terms and representations contained in this solicitation, any pertinent OSHA Occupational and Safety regulations, and any State and/or local regulations, laws and codes.

I. The Contractor shall at all times keep the work area and adjoining areas free from accumulation of excess materials, except in areas that have been approved for stockpiling removed materials. At the completion of the Work, the Contractor shall remove all waste materials and rubbish from the project site as well as all equipment.

END of SOW

As stated in the solicitation, questions are to be sent in writing to the Contacting Officer at at Shaukat.syed@ihs.gov and must be received no later than 14 days prior to proposal receipt date to allow time for response. Therefore, no further questions are guaranteed to be answered.

NOTICE TO OFFERORS: Offerors must acknowledge receipt of any and all amendments by number and date on their cover letter in their offer or by submitting a signed copy of the SF30.

All other terms and conditions remain unchanged.

END OF SUMMARY OF CHANGES

mailto:Shaukat.syed@ihs.gov

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

75H70126R00014

Indian Health Service (IHS) Division of Engineering Services (DES) - Dallas 1301 Young Street, Suite 840 Dallas, TX 75202-5433

Project Title: Zuni Quarters Sewer Improvement

Location: Zuni Comprehensive Community Health Center, 12 B Avenue, Zuni, NM 87327-0467

This project will be procured as a 100% Small Business set-aside under North American Industry Classification System (NAICS) code 237110, Water and Sewer Line and Related Structures Construction. The associated size standard for this procurement is $45 million.

Magnitude of Construction: The magnitude of this construction project is anticipated to be between $100,000.00 and $250,000.00.

TERO is applicable. See Section H.48

A site visit has been scheduled. See Section L.6 for site visit Information.

Same as Block 7

Shaukat Syed (516) 361-4989

AQ18ZS002

1 5012/23/2025

2/4/2026

2:00PM CT

F.2 Period of Performance

AWARD (To be completed by Government)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

B.3

Shaukat Syed

LUMP SUM TOTAL $_____________________

AGENDA

Pre-Proposal Site Visit Meeting

Solicitation No. 75H701-26-R-00014 Project Name: Zuni Quarters Sewer Improvement

Location: Zuni Comprehensive Community Health Center Date: January 07, 2026, 11:00AM CST

1. Welcome and Introduction of Government Team:

• Shaukat Syed, Contracting Officer

• Thomas Dodge, Contracting Officer’s Representative

2. Purpose: The purpose of this site visit is a walkthrough of the jobsite.

3. Bidding & Contract Requirements

a. Solicitation No. 75H701-26-R-00014

b. Solicitation Issued: December 23, 2025

c. Proposals Due: January 26, 2026, 2PM CST

d. Project Funded by I.H.S.

e. Instruction to Offerors

• All questions are to be submitted in writing for an official response to the Contracting Officer at Shaukat.Syed@ihs.gov .

• Verbal responses at the pre-proposal conference will not be binding.

4. Contract Overview:

a. Solicitation issued as 100% Small Business set aside

b. Basis for Award: LPTA (Section M of the RFP).

c. Construction contract will be between the Indian Health Service and the successful Contractor.

d. Period of Performance: 90 calendar days from issuance of NTP.

e. TERO fee is applicable (See Section H.48).

f. Items to be submitted with proposal - all documents featured in Section L of the RFP.

g. Daily Reports and Logs – Contractor is required to maintain and submit throughout the entire course of the project.

h. Direct all formal inquiries regarding the bidding documents and technical clarifications in writing to Contracting Officer.

i. Contracting Officer will transmit such amendment necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding. Questions must be submitted in writing to be formally answered in an amendment.

j. All inquiries are due no later than January 16, 2026 (ten days prior to proposal due date).

k. Amendments to date: 0 mailto:Shaukat.Syed@ihs.gov

5. Project Scope:

The purpose of this contract is for the reconstruction of the sewer lines, which will include the demolition, construction and replacement of the existing sewer lines placed along 6th Street and the sewer lines located in the alleyway north of Housing Units 404 and 405 at the Zuni Comprehensive Community Health Center.

The work shall be according to the drawings and specifications.

6. Technical Information/Requirements (Highlights Only)

a. Safety – The successful Contractor will be required to assign a competent safety officer to ensure that construction is performed in accordance with all OSHA safety requirements.

b. Permits – Contractor shall obtain all required permits, insurance, fees, etc. required to work in Pueblo of Zuni, McKinley County, New Mexico. Any cost associated with third party inspection of electrical, mechanical, plumbing, etc. that may be required by the County or State will be the responsibility of the Contractor.

c. Record Drawings (STP 4.0) – The Contractor shall provide two reproducible sets of As- Constructed Drawings (aka Red-Lines)

7. Utility Coordination: Coordinate utility connections with the applicable utility provider. The Contractor shall be responsible for payment of tapping or connection fees. The Contractor shall install utilities as designed and with the approval of the utility provider.

Amendment No. A00001.pdf
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK