B04 PPI Log 12.12.2025.xlsx

XLSX spreadsheet 54 KB Posted

Attached to
Belcourt RTU & Cabinet Replacement
Solicitation number
75H70126Q00007
Issued by

About this file

The file is a Project/Proposal Information (PPI) Log for a federal construction solicitation by the Indian Health Service (IHS) for the Belcourt RTU & Cabinet Replacement project. The solicitation (75H70126Q00007) involves replacing the HVAC unit and renovating the CT room at the Quentin N. Burdick Memorial Hospital in Belcourt, North Dakota, with a 180-calendar day performance period. The project is a 100% set-aside for Indian Small Business Economic Enterprises (ISBEE) under NAICS code 236220, with a $45 million size standard.

The PPI log contains 25 technical questions and responses from 12/3/2025 to 12/12/2025, addressing various project details such as construction duration, after-hours work permissions, equipment installation, warranty periods, and specific technical requirements. Key clarifications include confirmation of no design requirements, acceptance of using Procore for project correspondence, permission for the contractor's superintendent to serve multiple roles, and specific details about existing equipment and renovation scope. The contract will be awarded as a Firm Fixed Price (FFP) construction contract, with evaluation based on lowest price and conformance to solicitation requirements.

View the file

Other files

File Type Posted
B05 Amendment 4.pdf PDF
B01 Drawing A.2 Revised.pdf PDF
B05 Amendment 3.pdf PDF
B05 Amendment 2.pdf PDF
B05 Amendment 1.pdf PDF
Attachment 4 Drawings RTU.pdf PDF
Attachment 1 Wage Determination ND20250029.pdf PDF
Attachment 5 Drawings Cabinetry.pdf PDF
Attachment 2 SOW.pdf PDF
B01 26Q00007.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PPI Log

Amend No.Item #Date SubmittedQuestion Type (Technical or Admin)QuestionResponse DateResponseResponded By
EXAMPLE011/23/20TechnicalPlease provide drawings or plans for ???11/23/20IHS ResponseIHS POC
A0001112/3/25TechnicalAs noted in scope of work Item 3 Period of performance “C” on site construction duration not to exceed 30 days, The Solicitation is indicates an 180 day duration. Can you clarify the project duration as 180 days?12/3/25The 180 days includes lead time for equipment, mobilization, and other pre-construction work. The construction will take place in the facilities only CT room. Limiting the down time of the CT is essential for the facility. 30 days is specifically for the between shut down of the room and turn over to the facility. If the bidder believes this to not be feasible please respond in kind.IHS COR
A0001212/3/25TechnicalThe scope of work “L” “Commissioning indicates the design Builder shall commission” can you clarify that the design has already been completed based on the plans and there is no design requirements for this project?12/3/25There are no design requirements for this project. This is simply an error.IHS COR
A0001312/3/25TechnicalCan you provide afterhours work time frame if we require to work after the designated hours?12/3/25After hours work can be permitted on weekends, holidays, and after work hours of 7:30-5:00. We simply as the contractor to request at least a day prior to give the facility time to prepare for any security requirements.IHS COR
A0001412/3/25TechnicalSheet A.2 Note 2 indicates a new door – The scope of work does not include this door, can you provide the specifications and details of this new door including Door Specifications, Finishes and Hardware requirements12/3/25A correction will need to be issued. This door is not to be included in this contract.IHS COR
A0001512/3/25TechnicalSheet A.2 Note 2 indicates a new door – Is the door frame required to be removed and replaced as well?12/3/25See aboveIHS COR
A0001612/3/25TechnicalSheet A.4 new penetration for mechanical, Can you provide dimension from the wall to the opening for clarity?12/3/25Sheet A.4 does not indicate an new penetration for mechanical. There is an existing floor penetration that will be exposed by moving the cabinets. This penetration will need to be filled in as indicated.IHS COR
A0001712/3/25TechnicalCan you provide the riser diagram for the new steam line?12/3/25A steam riser diagram is not available. Elevation can be measured on site during the pre-bid site visit.IHS COR
A0001812/3/25TechnicalCan the submittals, RFI’s and Submittal register, and other project correspondence be utilized thru FTP Procore System?12/3/25Yes, this is acceptable.IHS COR
A0001912/3/25TechnicalDelegated Design Can you clarify if we are required to provide a delegated design for casework, mechanical or electrical systems, Fire Alarm?12/3/25No delegated design work is required for this project.IHS COR
A00011012/3/25TechnicalCan the Contractors Superintendent also serve as the Quality Control Manager and the Site Safety Officer i.e. Triple Hat Functions?12/3/25Yes, this is acceptable.IHS COR
A00011112/3/25TechnicalWarranties Can you clarify the warranty period to be 1 year after substantial completion.12/3/25Yes, upon acceptance of substantial completion by the government, the contractor is to provide a 1-year warranty.IHS COR
A00011212/3/25TechnicalSubmittal Procedures states that the submittal review time is 14 calendar days, does this duration include the IHS, A/E and any consultants?12/3/25YesIHS COR
A00011312/3/25TechnicalAre there any seismic requirements? If there are, have they been incorporated with the design already?12/3/25No seismic requirementsIHS COR
A00011412/3/25TechnicalIs there sprayed fireproofing required to be repaired at existing areas? If so can you provide required specifications?12/3/25No sprayed fireproofing is required.IHS COR
A00011512/3/25TechnicalCan you clarify the existing roof structure will support the new AHU unit without modifications?12/3/25Yes, this was verified by the engineer on plan sheet A.IHS COR
A00011612/3/25TechnicalIs the existing CT Scanner to be removed by others during the construction phase of this work?12/3/25The existing CT scanner cannot be moved and will remain in place during construction.IHS COR
A00011712/3/25TechnicalIs the Existing CT Scanner to reinstalled by others after Construction?12/3/25See above.IHS COR
A00011812/3/25TechnicalCan you provide the required penetration details required for the new steam lines thru the floor?12/3/25Penetration details are not available. The contractor will need to submit a shop drawing as a submittal for approval.IHS COR
A00011912/3/25TechnicalThe plans do not indicate the existing sink although the submittals are requesting sink and faucet can you clarify if we are required to remove and replace sink and Faucets or are we to provide just the removal and re-install of existing sink and faucets?12/3/25Remove and re-install existing sink and faucet.IHS COR
A00012012/3/25TechnicalIs there any requirements for radiation protection to be removed or reinstalled in this scope of work?12/3/25NoIHS COR
A00012112/3/25TechnicalIs there any backing requirements for the new casework?12/3/25The backing requirements will be determined by the cabinet manufacturer.IHS COR
A00012212/3/25TechnicalIs the owner to be responsible to removing and reinstalling equipment and furniture from the existing space?12/3/25YesIHS COR
A00012312/3/25TechnicalThe scope of work is to provide a new AHU and the period of performance is 180 days, can the owner provide an administrative notice to proceed to order the required equipment as the AHU materials are lengthy procurement durations and then provide a Construction Notice to Proceed to commence work?12/3/25Yes, this can be provided.IHS COR
A00012412/3/25TechnicalDue to the short period of time between bid questions due date and when the bid is due we would request a proposal time extension for the proposal to become due.12/3/25This most likely will be acceptable. Please provide a specific request to include the additional number of days.IHS COR
12/9/25TechnicalPlans and SOW are calling for Armstrong Calla Health Zone or equal. Could we get clarification if these will be square edged tile or a tegular?12/12/25The ceiling tile will be square edged.IHS COR
12/12/25TechnicalAre we covering up the access area to cables in the floor behind the CT Machine? Or do you need access to that area?12/12/25The cable raceway behind the CT machine will not be covered up and will be left in its current condition.IHS COR
A00012512/12/25TechnicalCan we do new flooring up to the base of the CT Machine as tight as we can?12/12/25YesIHS COR

Key

Technical
Admin

File details come from the government source that posted it. Updated .