This document contains Pre-Proposal Inquiries related to Solicitation 75H70124R00043 for the Lower Brule IHC Pharmacy Renovation project. The key details are:
The project involves renovating the pharmacy at the Lower Brule Indian Health Center in Lower Brule, South Dakota to meet USP 795, 797, and 800 compounding requirements. The solicitation is a Request for Proposals (RFP) with a single Firm Fixed Price (FFP) contract award. The construction magnitude is anticipated to be between $500,000 and $1,000,000, with a 180-calendar day period of performance. The solicitation is set aside for small businesses under NAICS code 236220 with a $45 million size standard. The solicitation and all amendments will be posted on SAM.gov. The document provides responses to seven pre-proposal inquiries covering topics such as flooring transitions, temporary pharmacy, security systems, exterior siding and roofing, ceiling tile demolition, and self-performed labor calculations.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment of Solicitation Amendment A00002 under Solicitation 75H70124R00043 Lower Brule IHC Pharmacy
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-24-R-00025
PROJECT:
Lower Brule IHC Pharmacy Renovation, LOCATION: Lower Brule, SD
PROJECT NO:
DOCUMENT
OWNER: Erik Lundstrom Email: Erik.Lundstrom@ihs.gov DOCUMENTS:
DATE: DEPARTMENT: IHS/DES
Item No.
Reference Drawing, Spec, Page COMMENTS POC IHS Approved Response
Amendment A00002 dated 07/01/2024
1. Drawings Drawing sheet A4.1- Where are new flooring transitions expected? COR Transitions between different types of flooring will be at the centerline of the door.
2. RFP Phase 1- Does the temporary pharmacy receive any flooring? COR Existing flooring will be used.
3. Drawings Drawing E4.1 What is the new security system spec’d to be? COR
The contractor is not installing any new security system.
From a video and door security standpoint, all that is to be included in this contract is for the contractor to install the data cables for the ceiling mounted video cameras per plan note 5 on sheet E4.1 and detail 2, sheet E7.1. All doors that will have card readers will have the contractor do the door access control rough-ins per detail 3 on sheet E7.1. They will install the conduit accordingly and install the main. The actual installation of the video cameras and door card readers will be handled under a separate contract with the IHS HSPD-12 IDIQ contractor.
4. RFP Exterior- Please provide specs for existing siding and roofing manufacturers. COR
For the siding, refer to the infill window note on sheet A2.1.
The contractor is to match the existing wall construction and use a full sheet of T1-11 siding for the window infill. The roof manufacturer is unknown but the roof is a standing seam metal roof.
5. Drawings Demo A1.2- Will any ACT demo extend into the corridor? COR Some corridor walls are being demo’d and the corridor widths will be narrowed up approximately 1 foot. There will be some ACT demo/patching required as noted on drawing A3.1.
6. RFP Demo- Has the facility been tested for Asbestos and/or lead? COR Hazardous material removal projects have been completed at the facility.
Amendment of Solicitation Amendment A00002 under Solicitation 75H70124R00043 Lower Brule IHC Pharmacy
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-24-R-00025
PROJECT:
Lower Brule IHC Pharmacy Renovation, LOCATION: Lower Brule, SD
PROJECT NO:
DOCUMENT
OWNER: Erik Lundstrom Email: Erik.Lundstrom@ihs.gov DOCUMENTS:
DATE: DEPARTMENT: IHS/DES
Item No.
Reference Drawing, Spec, Page COMMENTS POC IHS Approved Response
7. RFP Self Performed Calc Sheet—Are GC self-performed labor items to be included in E? Please confirm. CO
There is a formula to follow for e) “Offeror’s total estimated cost of contract performance for similar situated entities (a-b-c-d=e).” Therefore, e is determined by the minus of b, c, and