This document contains responses to pre-proposal inquiries for solicitation number 75H701-24-R-00010 from the Indian Health Service seeking demolition and abatement services at health care facilities in Winslow, Arizona and Dilkon, Arizona. The services include demolishing existing buildings, capping utilities, and removing service lines. The estimated period of performance is February/March 2024 through completion. Subcontractor past performance will not be evaluated. The contractor must comply with diverting 50% of waste from landfills or obtain approval to deviate. The contract will cover costs of an archaeological monitor if needed via a contract modification. The helipad at the Dilkon site will remain in place.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment of Solicitation Amendment A00003 under Solicitation 75H701-24-R-00010 Winslow and Dilkon Health Care Facility Demolition/Abatement
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-24-R-00010
PROJECT:
Winslow and Dilkon Health Care Facility Demolition/Abatement
LOCATION: Winslow, AZ & Dilkon, AZ
PROJECT NO:
DOCUMENT
OWNER: Shaukat Syed PHONE: 214-767-3934 DOCUMENTS:
DATE: DEPARTMENT: IHS/DES
Item No.
Reference Drawing, Spec, Page COMMENTS POC IHS Approved Response
Amendment A00003 dated 12/14/2023
1. RFP
I would like to ask if the Indian Health Service would accept the past performance requirements of our subcontractors for Winslow and Dilkon Health Care Facility Demolition/Abatement project.
CO
As stated in the solicitation under Factor 2, “the Government will only evaluate up to four (4) Customer Satisfaction Surveys/ Past Performance Questionnaires (PPQs) combined for the prime contractor.” Therefore, we will not evaluate PPQ for the subcontractors.
2. RFP Do we need to comply with 50% of disposal waste materials being diverted from landfills ? COR Yes, the contractor needs to comply with this requirement. If this is unfeasible, this can be discussed after award.
3. RFP Will WIHCC Hospital will cover the cost of an archaeological monitor if needed ? COR
As stated in the solicitation, if subsurface cultural materials are encountered during demolition of the buildings, an Archaeological Monitor may be required to be onsite during any and all ground disturbance activities. Therefore, Option CLIN 0009 will be exercised via a modification and thus invoiced based on the daily reports submission of hours worked.
4. RFP
If an archaeological monitor is needed will WIHCC Hospital $10,000 allowance cover contractor’s expenses with delays, setting equipment and possible remobilization?
COR
As stated in the solicitation, if an archaeological monitor is needed, Option CLIN 0009 will be exercised via a modification and thus invoiced based on the daily reports submission of hours worked.
5. RFP Will there be hydro-mulch or reseeding required? COR No since the existing conditions do not have vegetation.
6. RFP What are the hours we are allowed to operate equipment? COR Normal business hours and as per contract documents. There are no current limitations for equipment operation.
7. RFP Will this project most likely happen in April? COR Work will commence after contract award and issuance of NTP, which we expect to be around February/March 2024 time frame.
Amendment of Solicitation Amendment A00003 under Solicitation 75H701-24-R-00010 Winslow and Dilkon Health Care Facility Demolition/Abatement
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-24-R-00010
PROJECT:
Winslow and Dilkon Health Care Facility Demolition/Abatement
LOCATION: Winslow, AZ & Dilkon, AZ
PROJECT NO:
DOCUMENT
OWNER: Shaukat Syed PHONE: 214-767-3934 DOCUMENTS:
DATE: DEPARTMENT: IHS/DES
Item No.
Reference Drawing, Spec, Page COMMENTS POC IHS Approved Response
8. RFP Are the Gas lines to be turned off ? unhooked, capped ? or moved ? COR
As stated in the solicitation, all utilities shall be capped at the curb. Contractor to provide plans and specifications for disconnections of all utilities for buildings being demolished.
Only the service lines are required to be removed/capped 5’ from existing building line.
9. RFP Will the block entry wall remain ? COR The block entry wall needs to be removed.
10. RFP Does AB and surface gravel need to be removed? COR AB and surface gravel does not need to be removed.
11. RFP Does the heli pad and fencing need to be demolished and removed? COR The helipad is outside the Dilkon Clinic site and will remain as is.