This document contains an amendment to a federal solicitation for construction of staff quarters at Peach Springs, Arizona. The amendment provides questions and answers from prospective offerors to clarify requirements. It advises that the solicitation closing date remains November 28, 2023 at 1:00 PM Pacific Time, with all other terms and conditions unchanged. The answers reference environmental clearance documents provided previously, release civil engineering CAD files, and clarify that interior partition walls can be anchored directly to the post-tension concrete slab floor using power-driven fasteners extending into the slab. Substrate material under standing seam metal roofing is left to the contractor's choice, provided it meets specified standards. Only materials shown in drawings and specifications for sprinkler piping will be accepted without substitution at this time.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
A0002
Andrew Hart, Supervisory Contracting Officer
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to Provide Q&A as of Nov 3, 2023, and Question item #4 related attachments.
The Solicitation closing date and time remain November 28, 2023 at 1:00 PM (Pacific Time).
All other terms and conditions of this solicitation remain unchanged.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
Indian Health Service - DES Seattle 701 Fifth Ave, Suite 1600 Seattle, WA 98104
See Item 6
9A. AMENDMENT OF SOLICITATION NUMBER
75H70124R00009
5. PROJECT NUMBER (If applicable)
20-080
1 4
11/3/2023
9B. DATED (SEE ITEM 11)
10/19/2023
Amend No. Item # Date Submitted
Question Type
(Technical or Admin)
Question Response Date Response Responded
By
EXAMPLE 0 11/23/2020 Technical Please provide drawings or plans for ??? 11/23/2020 IHS Response IHS POC
A0001 1 10/25/2023 Technical
1. Can the Government provide the Environmental Assessment and Environmental Clearance documents for the project? Specification Section 01 57 20.00 10 Environmental Protection references the contractor’s responsibility under this section and page 3. 1.7 Environmental Protection Plan and 1.8 Protection Features page 6, references working within areas that have been surveyed/cleared for our planed work area however the area is not referenced on the plans. Also, 1.9 Special Environmental Requirements page 6, Swainson’s Hawk Nesting survey requirements within 10-days of starting on-site work in addition to the February 1 – August 31 nesting season. Additionally, this section references Archaeology, Waters of the US, Wetlands, and other concerns. The clearance documents will help us better understand what the contractor will be required to address under this section and to price the work accordingly.
10/31/2023
The NEPA document was provided with RFC package. Please send to all contractors.
"1.9 Special Environmental Requirements page 6, Swainsons hawk nesting survey requirements" are not pertinent to this project. I am not sure where that is called out in the contract but needs to be removed. This is an oversight by JSRA.
IHS PM
A0001 2 10/25/2023 Technical
2. Can the Government provide the Civil Engineering CAD files?
Attachment B01 DRAWINGS Sheets C001 to C602 show the site civil work to be preformed by the contractor and the CAD file will assist us in provide accurate pricing for the work described in the drawing. 10/31/2023
The following base CAD files have been provided to the Government for distribution: Existing Grade.xml, Finished Grade.xml, MA-CS-SI-41629.06 (10-30- 2023).dwg, MC-VB-41629.06 (10-30- 2023).dwg
Design Firm
A0001 3 10/25/2023 Technical
3. How is the interior wall framing to be attached to the post-tension (PT) slab? Sheet S511, Detail 102 - Perimeter Footing A PT Slab, indicates how the exterior wall framing is to be attached to the PT slab however the interior wall anchoring is not shown or described.
10/31/2023
Non-loadbearing interior partition walls shall be anchored directly to the post-tension slab through use of power-driven fasteners . Power driven fasteners shall be a length that does not extend into the tendon zone of the slab when attached to the wall sill plate. Refer to Detail S512/108 Similar
Design Firm
A0002 4 11/1/223 Technical
My question is regarding what type of substrate are you using under the Standing Seam Metal Roof Panels. This is no call out in the specifications and the only call out on the attached drawings is “WSP” (see attached highlighted drawings). Is this 5/8” plywood or OSB being used. We need to know this for wind loads.
11/2/2023
Refer to Sheet S001 "ROUGH
CARPENTRY AND WOOD
STRUCTURAL PANELS; item 2.
Substrate is Contractors option, provided that substrate conforms to referenced performance standards of stated section.
Design Firm
A0002 5 11/2/2023 Technical
CPVC plastic pipe is UL Listed and FM approved for 13D and 13R wet pipe systems for light and ordinary group 1. Will we be able to use CVPC pipe for this project? 11/2/2023
Provide sprinkler piping listed in drawings and specification. No Substitutions of the sprinkler piping material accepted at this time.
Design Firm
JOHNSON SMITTHIPONG &
ROSAMOND ASSOCIATES, INC.
5210 E Williams Cir Ste 600 Tucson, AZ 85711
(520) 547-7904 www.jsra.com
FOR CONSTRUCTION
Buffkin Highlight
Buffkin Highlight
Buffkin Highlight
Buffkin Highlight
Buffkin Highlight
STRUCTURAL ENGINEERS
CREATING ELEGANT SOLUTIONS
JOHNSON SMITTHIPONG &
ROSAMOND ASSOCIATES, INC.
5210 E Williams Cir Ste 600 Tucson, AZ 85711
(520) 547-7904 www.jsra.com
FOR CONSTRUCTION
/2
6/
T hi s E le ct ro ni c S ig na tu re
H as
B ee n A ut ho riz ed
B y
M e
T hi s
/2 6/
/2
7/
/2
7/
Buffkin Highlight
| B05 Addendum #1 2023 09 26.pdf |
| Subject: Pre-Bid Meeting Minutes & Plan Set Revision, Santa Clara Pueblo – East Housing Lift Station, IHS Project No. AL-18-A86 |
| 2022 10 24 B77 Addendum Drawings.pdf |
| 4 |
| scattered housing b77 Revision #1 1- Drywater (1) |
| scattered housing b77 Revision #1 2 - Hererra (1) |
| scattered housing b77 Revision #1 3 - Sanchez (1) |
| scattered housing b77 Revision #1 5-Pecos & Lewis (1) |
| scattered housing b77 Revision #1 22X34 PLAN (1-40) (1) |
| ADP90E0.tmp |
| SECTION B. PRICE SCHEDULE |
| ADPD131.tmp |
| SECTION B. PRICE SCHEDULE |
| ADP129C.tmp |
| PPI Log |
| ADP619A.tmp |
| PPI Log |
| ADP5719.tmp |
| PPI Log |
File details come from the government source that posted it. Updated .