7565617 SPECS STREAMLINED MACC.pdf
PDF 245 KB Posted
- Attached to
- FRCE Building 137, Hangar 3 Floor Repairs
- Solicitation number
- N400857565617
About this file
This document is a Statement of Work and Specifications for repair and resurfacing of Hangar 3 flooring at MCAS Cherry Point, North Carolina, under Work Order #7565617.
The project encompasses repair and resurfacing of approximately 5,600 square feet of concrete floor in Hangar 3, Building 137, located in the Flight Readiness Center–East (FRCE) area. The work addresses delamination and spalling caused by improper previous surface preparation, creating safety and Foreign Object Damage (FOD) concerns for aircraft operations. The contractor must rectify concrete delamination and resurface the area with a durable urethane slurry topcoat capable of withstanding aircraft rolling loads. Work must occur behind containment screens to prevent construction dust and chemicals from becoming FOD concerns. Two technical specifications govern execution: Section 03 01 00 (Rehabilitation of Concrete) and Section 09 67 23.16 (Fuel Resistive Resinous Flooring, 5-Coat System). The work area will remain operational during construction, requiring minimal interference with normal facility activities. Contractors must comply with extensive security requirements including DBIDS credential registration, FRC East-specific access protocols, and compliance with ISO 9001, AS9100, AS9110, ISO 14001, and OSHAS 18001 standards. The contractor must provide qualified personnel including a Superintendent, Quality Control Manager, and Site Safety Officer (potentially combined roles). Specialized requirements include a minimum 60 percent waste diversion rate from landfills, one-year warranty on materials and workmanship, proper insurance coverage, and detailed submittals including work plans, quality control procedures, and closeout documentation such as spare parts data, warranty management plans, and operation and maintenance manuals.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 7565617 Amendment 0001.pdf | ||
| 7565617 Master PPI Form.xlsx | XLSX spreadsheet | |
| 7565617 RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FRCE B137 HANGAR 3 FLOOR REPAIRS
MCAS CHERRY POINT, NORTH CAROLINA 28533-0006
WORK ORDER #7565617
1.1 GENERAL INTENTION
The work includes repairing and resurfacing the floor of Hangar 3 in Building 137 which is in the Flight Readiness Center – East (FRCE) area. Work is near the building’s large hangar doors on the flightline side. The work area is approximately 5,600 square feet (35 feet x 160 feet) of the floor.
1.2 LOCATION
The work is located at MCAS Cherry Point, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 DETAILED REQUIREMENTS.
The project encompasses resurfacing the damaged floor within the space of Hangar 3 toward the flightline side of the hangar in the red marked aisle way. In a previous repair the surface was not properly prepped and the surface was delaminating.
This part of the hangar floor shows evidence of spalling and has become a safety and Foreign Object Damage (FOD) concern for FRC-East production.
Work must rectify the delamination of existing concrete, repair and resurface it with a durable urethane slurry topcoat such that the resulting slab surface will hold up to the pressures of aircraft rolling on its surface.
Work must occur behind containment screens so that construction related temporary dust/chemicals does not become a safety and FOD concern.
Refer to Specifications Sections attached at the end of this document. Sections include the following:
03 01 00 Rehabilitation of Concrete 09 67 23.16 Fuel Resistive Resinous Flooring, 5-Coat System
1.4 SPECIAL SCHEDULING REQUIREMENTS
Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
The work area will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
Permission to interrupt any activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption and in accordance with section 1.10.
1.5 CONTRACTOR ACCESS AND USE OF PREMISES
1.5.1 ACTIVITY REGULATIONS
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.5.1.1 SUBCONTRACTORS AND PERSONNEL CONTACTS
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
Electronic Security Systems equipment such as processing control units, workstations, field panels, sensors, card readers, cable installation, and system programing, testing and training must be performed by U.S. citizens who have been subjected to a trustworthiness determination or U.S. companies using U.S. citizens who have been subjected to a trustworthiness determination.
1.5.1.3 INSTALLATION ACCESS
Obtain access to Navy and Marine Corps installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/ Operations-and-Management/Base-
Support/DBIDS/. No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.5.1.3.1 REGISTRATION FOR DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/Operations-and-Management/Base- Support/DBIDS/. Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer that provides the purpose for access to the Base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the Base Visitor Control Center representative to obtain a background check.
This form is available for download at https://www.cnic.navy.mil/Operations-and-Management/Base- Support/DBIDS/.
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.5.1.3.2 DBIDS ELIGIBILITY REQUIREMENTS
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification. The Government is the final authority.
1.5.1.3.3 DBIDS NOTIFICATION REQUIREMENTS
Immediately report instances of lost or stolen badges to the Contracting Officer.
Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.5.1.3.4 ONE-DAY PASSES
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation.
The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.5.1.4 NO SMOKING POLICY
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.5.2 WORKING HOURS
Regular working hours shall consist of an 8 1/2 hour period normally between the hours of 7:00 am to 3:30 pm, Monday through Friday, excluding Government holidays.
1.5.3 WORK OUTSIDE REGULAR HOURS
Work outside regular working hours requires Contracting Officer approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours.
During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.5.4 EXCLUSIONARY PERIOD
No work must be performed during weekends or the period of weekdays between the hours of 3:30 PM and 7:00 AM inclusive, without prior written approval of the Contracting Officer.
This period has not been considered in computing the time allowed for the performance of this contract.
1.5.5 OCCUPIED BUILDING[S]
The Contractor shall be working in an existing building which is occupied. Do not enter the building without prior approval from the Contracting Officer.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Relocate movable furniture approximately 6 feet away from the Contractor's working area as required to perform the work, protect the furniture, and replace the furniture in its original locations upon completion of the work. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.
The Government will remove and relocate other Government property in the areas of the building scheduled to receive work.
1.5.6 UTILITY CUTOVERS AND INTERRUPTIONS
Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays.
Conform to procedures required in the paragraph "Work Outside Regular Hours."
Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.6 SECURITY REQUIREMENTS
1.6.1 STATION REGULATIONS
No employee or representative of the contractor will be admitted to the work site without an Identification Badge or is specifically authorized admittance to the work site by the FEAD, Facilities Engineering & Acquisition Division.
IMPORTANT NOTE: FEAD personnel (Construction Managers, Engineers/Architects, Engineering Technicians, Contract Specialists, or Contract Surveillance Representatives) will not receive, process, re-transmit or otherwise handle IN ANY WAY Personally Identifiable Information (PII) related to the badging process. Do NOT forward any of this information to the
FEAD.
1.6.2 CONTRACTOR ACCESS TO MCAS CHERRY POINT AND OUTLYING AREAS
Documentation requirements for granting access to MCAS Cherry Point for commercial and contract employers and employees.
This document is an aid in meeting ASO 5560.6C requirements and is not a substitute for the order.
The Pass & Identification Office at Building 251 will issue credentials to authorized contractors. Sub-Contractors and suppliers must coordinate through the Prime-Contractor.
Criminal Activity. In accordance with ASO 5560.6C, the below list of criminal activities within an applicant's record are considered not in the best interest of the Marine Corps and will be grounds for automatic denial of access aboard the Installation:
a. Conviction for espionage, sabotage, sedition, treason, terrorism, armed robbery, or murder.
b. Felony conviction for a firearms or explosives violation, regardless of the date of conviction.
c. Conviction of crimes encompassing sexual assault or rape.
d. Conviction of crime encompassing child molestation, or the possession or production of child pornography.
e. Conviction of trafficking in persons.
f. Conviction of drug possession with intent to sell or distribute.
g. Convicted of three or more misdemeanor violations, or attempted violations, within the previous 10 years of the following offenses:
(1) Sex crime
(2) Assault
(3) Larceny
(4) Drugs
(5) Weapons
Persons requesting access to MCAS Cherry Point will be denied access based on the following:
a. The individual is a registered sex offender.
b. The individual has an active arrest warrant from Federal, State, local, or other civil law enforcement authorities, regardless of offense or violation.
c. The individual has a felony conviction within the last 10 years, regardless of the offense or violation.
d. The individual's name appears on any Federal or State agency watch list for criminal behavior or terrorist activity.
e. The individual is debarred entry or access to a Marine Corps site, other DoD installations or facilities, or other Federal site or facility.
f. The individual engaged in acts or activities designed to overthrow the U.S. Government by force.
g. The individual is known to be or reasonably suspected of being a terrorist or belongs to an organization with known terrorism links/support.
h. The individual is identified in the National Crime Information Center (NCIC) known suspected terrorist (KST) file, or the Terrorist Screening Database (TSDB) report as known to be, or suspected of being, a terrorist or belonging to an organization with known links to terrorism or support of terrorist activity. If an individual is identified on the NCIC KST files or TSDB, the Provost Marshal's Office (PMO) will immediately call the NCIS Multiple Threat Alert Center (MTAC) for further coordination. The MTAC will coordinate with the Department of Justice or Federal Bureau of Investigation (FBI) and provide handling instructions to MCAS Cherry Point Police, Criminal Investigations Division (CID), or NCIS.
i. The individual is illegally present in the U.S.
j. The individual has knowingly submitted an employment questionnaire with false or fraudulent information.
k. The individual is a prisoner on a work-release program or currently on felony probation or parole.
l. The individual is pending any felony charge.
m. The individual has criminal arrest information that the site commander determines the person presents a threat to good order, discipline, or health and safety on the Marine Corps site.
n. Any reason the Installation Commander deems reasonable for good order and discipline.
1.6.4 FLEET READINESS CENTER, EAST (FRC EAST) REQUIREMENTS
Work involved under this contract is in the FRC East Maintenance Depot and Flightline Area. No employee or representative of the Contractor will be admitted to the work site unless they (1) are specifically authorized admittance by the FEAD, and (2) has a security badge. The Contractor shall obtain clearance and FRC East security badges for all personnel required to be on the project site prior to performing any work. The Contractor shall submit a written request for security badges to the FEAD and to FRC East Security. Each employee will be required to go to Trailer 32 to obtain his security badge with FRC East access. A limited number of Contractor vehicles will be allowed access to the site of work subject to meeting regular access requirements. No personal vehicles will be allowed behind the security fence. Parking of vehicles shall be restricted to the immediate project site as determined by the FRC East Security. The security badges issued under this contract are valid for this specific project and are not transferable to another project.
FRC East is registered to the ISO 9001, AS9100, AS9110, ISO 14001, and OSHAS 18001 standards. To adhere to the standards required of these programs, FRC East must ensure that all individuals accessing the facility are aware of the conditions and factors that affect the well-being of all employees, temporary workers, contractor personnel, visitors, and any other person in the workplace.
The following are requirements for granting access to Fleet Readiness Center East (FRC East) for commercial and contract employers and employees.
a. The Contractor shall complete a "Contractor Work Notice- Form FRC-East 5000/10" and provide the Notice to the appropriate shop supervisor for signature and leave the top part of the Notice with the shop supervisor to post in a prominent location in the work area. The Contractor shall keep the bottom portion of the "Contractor Work Notice" for his records and provide a copy to the Contracting Officer.
For projects occurring on facility roofs (roofing repair, HVAC replacement, or similar work), the Contractor shall complete a "Contractor Work Notice" form and provide the Notice to the shop directly under the area being worked, even if no direct impact to the shop is anticipated. A blank copy of this form is included at the end of this section.
b. In the event of an emergency, including hazardous material spills, the individual discovering the emergency shall call 911 from any FRC East phone. Relay the grid number listed on the phone for location assistance. If you are calling from a cell phone, call 252-466-3616 - Fire Department Dispatch.
This does not relieve the Contractor from reporting the situation to the Contracting Officer which is required elsewhere in this specification.
c. Badges will be displayed at all times and shall be returned upon completion of visit/work. Every badge is considered Government Property and all lost badges will be reported to the FRC East Badge and Decal Office located in Trailer 32.
d. Report any injury/illness occurring on site to the FRC East Safety Office immediately by calling 252-464-7015. This does not relieve the Contractor from reporting the situation to the Contracting Officer which is required elsewhere in this specification.
e. The facility must be kept clean and orderly at all times.
Ensure that you place all waste in proper receptacles so that the facility is maintained in a "Clean as you go" condition.
f. When in the FRC East industrial areas, wear the personal protective equipment (PPE) required for that area. PPE requirements are generally marked but if there is uncertainty, check with the area supervisor. Typically, safety glasses with side shields and steel toed shoes are required in most shops.
g. Smoking is NOT authorized while traveling from one facility location to another while walking or in a vehicle being operated anywhere within the FRC East compound.
ABSOLUTELY NO SMOKING on the property except in Designated Smoking Areas.
h. Extra caution shall be taken around the flight line and aircraft turn-up areas to control trash, debris, and materials. Additionally, all personnel on the flight line must be continuously alert and stay clear of helicopter and jet operations in progress.
i. Vehicles must not obstruct aircraft movement or other daily operations.
j. Safety (252-464-7015), security (252-464-7999), and environmental (252-464-8042) infractions shall be reported to the appropriate office immediately. This does not relieve the Contractor from reporting the situation to the Contracting Officer which is required elsewhere in this specification.
k. If an emergency situation occurs which would endanger the health or safety of personnel, the area shall be evacuated.
Re-entry to affected buildings will be at the discretion of uniformed guards, fire department, or safety office personnel only.
l. Decisions to evacuate will be from the FRC East Commanding Officer or his/her representative. Visitors/contractors, along with non-essential facility personnel, south of Harrison Drive, adjacent to Building 4224, will evacuate the facility first. Fifteen minutes later, the visitors/contractors south of Curtiss Road, between Buildings 83 & 84, will evacuate the facility. Fifteen minutes later the visitors/contractors north of Curtiss Road will evacuate the facility.
m. Cellular phones and photographic equipment are not authorized within FRC East unless they are approved in advance by the Security Office (252-464-7999). Cellular phones may be used on roof areas for emergency purposes only.
n. All vehicles must have proper passes, and no pass may be transferred between vehicles.
o. All vehicles will follow posted speed limits which are 5 MPH on the outside of buildings and 3 MPH inside of any building.
p. Vehicle headlights must be on at all times within the facility.
q. All vehicles are required to slow down, sound horn, and proceed with caution at all cross aisles and other locations where vision is obstructed.
r. Personnel are strictly forbidden to introduce any substance into the storm drain system including catch basins, roof drains, and floor drains.
s. All facility entrants are responsible for all materials they bring into the facility and shall handle them in such a manner to ensure they are not left as "foreign objects" anywhere in the facility.
t. In case of a utility emergency on weekends or after normal work hours, call the Public Works Department trouble call desk at 252-466-4363.
u. The use of gasoline is prohibited for any purpose other than fueling motor vehicles. All gasoline-powered vehicles are prohibited inside FRC East buildings.]
1.6.4.1 Mandatory Contract Performance Requirements for FRC East
a. All personnel working on site at FRC East under this contract must document their receipt and review of the information listed in FRCEASTINST 5000.1B, annually. The Security Department will provide a means of completing initial review prior to FRC East entrance.
b. Foreign object (FO) is defined as any article or substance alien to the aircraft or assembly which is allowed to invade the product. Foreign Object Damage (FOD) is the damage that occurs due to these FOs. All FRC East work sites will be maintained in such a manner as to prevent FOD to aircraft and/or aircraft components. Work sites shall be kept clean at all times. All debris, scrap material, tools, and equipment will be cleared from the work site as work progresses. At no time will hoses, power cords, materials, etc. be permitted to create tripping hazards in areas of the work site.
c. In those cases where a contractor supervisor determines that solving a safety or health problem is beyond their control, but within the control of FRC East, the contractor shall notify the Contracting Officer.
1.6.4.2 Additional Contract Performance Requirements for FRC East
a. Work above or anywhere near aircraft or passageways shall be avoided whenever possible. If this is not possible, the cognizant shop supervisor will be informed so arrangements can be made to protect, move, or evacuate assets from the area to minimize foreign object debris potential. The area below the elevated work area will be adequately marked and barricaded at all times. Under no circumstances will work be performed over unprotected spaces.
b. Constant control of tools and materials is required at all times in the following critical areas: Shop 94304 (Rotor Head Shop); Shop 94601 (Ordinance/Survival Shop); Shop 93117 (Aircraft Paint Shop); Shop 93111 (Aircraft Clean Shop); Shop 96552, 96555, and 96556 (Aircraft Engine Shops); all shops in Building 4225; and all Shop 95000 Aircraft Hangars.
c. Buildings 137, 188, 245, 4224, and 4247 are classified as hazardous areas and have special requirements. Do not utilize any ignitable items, items powered by electric motors, or internal combustion engines unless they are determined to be suitable to the conditions of the buildings.
d. The recharging of mobile equipment shall not take place inside any FRC-East building.
e. Tools and hardware will be controlled at all times to prevent migration out of the work site. Lost tools shall be reported to the Contracting Officer who will then notify the FRC East Tool Control Manager at 252-464-9741. Tools found unattended will be confiscated and reported to the Contracting Officer.
f. Work requiring any modification to an air pollution control device must be approved in advance by the Contracting Officer, who will obtain approval from the FRC East Air Quality Program Manager. These devices are marked with a 5" x 9" red placard and a contact number, 252-464-7264.
g. Work accomplished that will impact industrial ventilation systems or fans will require prior notification of the Contracting Officer, who will then notify the FRC East Air Quality Program Manager at 252-464-7264. These systems are continuously monitored.]
1.6.6 STAGING AREA
The contractor staging area will be (PM to coordinate). Amount of material on site shall be kept to a minimum and shall only be material that is pertinent to the work currently being performed. All stockpiling of equipment and materials shall be closely coordinated with the Government and shall not disrupt activities at the site.
1.7 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by North Carolina Law.
1.8 SUPERVISION
The complexity of this project will require one person to fill the roles of the Superintendent, Quality Control Manager, and Site Safety and Health Officer.
1.9 SUBMITTALS
None.
1.10 PLANNED OUTAGES AND SERVICE DISRUPTIONS
Planned outages and service disruptions are requested by the contractor for approval by the Government when necessary to facilitate and/or accomplish contract work. Affected services include utilities (steam, water, waste water, and electrical service), communications (telephone, network, industrial control systems, and fire/security alarm systems, fire protection equipment, infrastructure, and road closures.
Disruption of these services cannot be allowed without written approval of the government.
The contractor is required to 1) request the outage in writing and 2) demonstrate sufficient contingency preparedness in the event that service cannot be restored due to a failure in accomplishment of contract work.
All outages require Contractor’s written request fifteen (15) days prior to commencement of such work. The request shall be submitted to the COR with the date, time, duration, and scope of the outage.
As supporting documentation for the request, the contractor is require to submit a contingency plan for all reasonably foreseen risks related to the contractor’s performance of the work that would impact disrupted services in excess of the approved outage. This plan must demonstrate the following at a minimum.
1. Understanding of key personnel and communications methods to include phone numbers.
2. Analysis of reasonable risks during the contract work that would impact disrupted services in excess of the approved outage.
3. An effective recovery plan to restore minimum essential services in the event of these risks materializing.
4. Requested government support.
The government will similarly produce risk-based contingency plans for restoration of essential services caused by reasonably foreseen factors that are not related to the performance of the contract. In these cases, the government may request the contractor make additional preparations to support essential and high risk services. Such requests are considered within the scope of this contract but will be priced and negotiated via modification as conditions warrant.
Approvals will be issued by the Public Works Officer or his/her designee and transmitted via the COR.
1.11 GOVERNMENTAL SAFETY REQUIREMENTS
Personal protective equipment (PPE) is governed in all areas by the nature of the work the employee is performing. Use personal hearing protection at all times in designated noise hazardous locations or when performing noise hazardous tasks.
Safety glasses must be worn or carried/available on each person. Mandatory PPE includes: hard hats, long pants, appropriate safety shoes, and appropriate class reflective vest.
Comply with the Safety and Health Requirements Manual (EM 385- 1-1), NFPA 70, NFPA 70E, NFPA 241, the Accident Prevention Plan (APP), the Activity Hazard Analysis (AHA), Federal and State OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.
An APP in accordance with EM 385-1-1, Appendix A, is required.
An AHA in accordance with EM 385-1-1, Section 1, is required for each activity or task.
The contractor is responsible for any required permits.
1.12 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
Divert a minimum of 60 percent by weight of the project construction waste and demolition debris/waste from the landfill or incinerator. Follow applicable industry standards in the management of waste.
Implement a Construction Waste Management Program for the project. Establish a process for clear tracking and documentation of construction waste and demolition debris/waste.
Develop and document how the Construction Waste Management Program will be implemented in a Construction Waste Management Plan. Submit a Construction Waste Management Plan to the Contracting Officer for approval. Construction waste and demolition debris/waste materials include un-used construction materials not incorporated in the final work, as well as demolition debris/waste materials from demolition activities or deconstruction activities.
Conduct Construction Waste Management meetings. After award of the Contract and prior to commencement of work, schedule and conduct a meeting with the Contracting Officer to discuss the proposed Construction Waste Management Plan and to develop a mutual understanding relative to the management of the Construction Waste Management Program and how waste diversion requirements will be met.
Submit Construction Waste Management Plan within 45 calendar days after contract award. Revise and resubmit Construction Waste Management Plan as necessary, in order for construction to begin. Execute demolition IAW Specifications Section 02 41 00 Demolition. Manage demolition debris/waste or deconstruction materials in accordance with the approved construction waste management plan. An approved Construction Waste Management Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations or meeting project cumulative waste diversion requirement.
Maintain records to document the types and quantities of waste generated and diverted through re-use, recycling, and sale to third parties; through disposal to a landfill or incinerator facility. Provide Final Construction Waste Diversion Report 60 days prior to the Beneficial Occupancy Date (BOD).
Collect, store, protect, and handle reusable and recyclable materials at the site in a manner which prevents contamination and provides protection from the elements to preserve their usefulness and monetary value.
Control accumulation of waste materials and trash. Recycle or dispose of collected materials off-site at intervals approved by the Contracting Officer and in compliance with waste management procedures as described in the waste management plan.
1.12 EXECUTION
If during the course of the work, conditions are encountered which are not covered in the contract or are different from conditions that would be reasonably anticipated, the contractor shall immediately notify the Contracting Officer. If such conditions are hazardous or the continuation of work would cause a hazardous condition to develop, the contractor shall stop work and proceed as directed by the Contracting Officer as directed by provisions contained in other sections of this specification. This may include modifications to, or the development of a new, Health and Safety Plan for this project, and alternate or additional appropriate abatement procedures.
1.13 CLOSEOUT SUBMITTALS
1.13.1 SPARE PARTS DATA
Submit two copies of the Spare Parts Data list. Indicate manufacturer's name, part number, nomenclature, and stock level required for maintenance and repair. List those items that may be standard to the normal maintenance of the system.
1.13.2 WARRANTY MANAGEMENT PLAN
Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction. Submit two sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan narrative must contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or of engineering background, not necessarily familiar with this contract. The term "status" as indicated below must include due date and whether item has been submitted or was accomplished. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period must begin on the date of project acceptance and continue for the full product warranty period. The warranty management plan must include, but is not limited to, the following:
a. Roles and responsibilities of personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the Contractors, subcontractors, manufacturers or suppliers involved.
b. For each warranty, the name, address, telephone number, and email of each of the guarantor's representatives nearest to the project location.
c. A list and status of delivery of Certificates of Warranty for extended warranty items, including roofs, HVAC balancing, pumps, motors, transformers, and for commissioned systems, such as fire protection and alarm systems, sprinkler systems, and lightning protection systems.
d. As-Built Record of Equipment and Materials list for each warranted equipment, item, feature of construction or system indicating:
(1) Name of item.
(2) Model and serial numbers.
(3) Location where installed.
(4) Name and phone numbers of manufacturers or suppliers.
(5) Names, addresses and telephone numbers of sources of spare parts.
(6) Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
(7) Cross-reference to warranty certificates as applicable.
(8) Starting point and duration of warranty period.
(9) Summary of maintenance procedures required to continue the warranty in force.
(10) Cross-reference to specific pertinent Operation and
Maintenance manuals.
(11) Organization, names and phone numbers of persons to call for warranty service.
(12) Typical response time and repair time expected for various warranted equipment.
e. Procedure and status of tagging of equipment covered by extended warranties.
f. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty or safety reasons.
1.13.3 OPERATION & MAINTENANCE MANUALS
Provide four electronic copies of the Operation and Maintenance Manual files. Submit to the Contracting Officer for approval 30 days before the Beneficial Occupancy Date (BOD). Update and resubmit files for final approval at BOD.
HANGAR 3 FLOOR REPAIRS, B137, FRCE 7565617
SECTION 03 01 00
REHABILITATION OF CONCRETE
02/18
PART 1 GENERAL
1.1 SCOPE
This specification governs the rehabilitation of structural concrete.
1.2 DEFINITIONS
1.2.1 Bracing
Temporary supplemental members used to avoid local or global instability during construction, evaluation, or repair that are intended to be removed after completion of construction.
1.2.2 Delamination
A planar separation in a material that is roughly parallel to the surface of the material.
1.2.3 Rehabilitation
Repairing or modifying an existing structure to a desired useful condition.
1.2.4 Repair
The reconstruction or renewal of concrete parts of an existing structure for its maintenance or to correct deterioration, damage, or faulty construction of members or systems of a structure.
1.2.5 Shoring
Props or posts of timber or other material in compression used for the temporary support of excavations, formwork, or unsafe structures; the process of erecting shores.
1.2.6 Termination Joint
The interface where a placement of repair material meets existing concrete, the edge of an expansion joint, or other existing surfaces.
1.2.7 Unsound Concrete
Concrete that is fractured, delaminated, spalled, deteriorated, defective, contaminated or otherwise damaged.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
SECTION 03 01 00 Page 1
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 117 (2010; R 2015) Specifications for Tolerances for Concrete Construction and Materials and Commentary
ACI 440.5 (2008) Specification for Construction with Fiber-Reinforced Polymer Reinforcing Bars
ACI 440.6 (2008) Specification for Carbon and Glass Fiber-Reinforced Polymer Bar Materials for Concrete Reinforcement
ACI 440.8 (2013) Specification for Carbon and Glass Fiber-Reinforced Polymer (FRP) Materials Made by Wet Layup for External Strengthening of Concrete and Masonry Structures
ACI 503.2-503.4 (2010, R 2003) Three Epoxy Specifications
ACI 503.3 (2010) Specification for Producing a Skid-Resistant Surface on Concrete by the Use of Epoxy and Aggregate
ACI 503.7 (2007) Specification for Crack Repair by Epoxy Injection
ACI 548.4 (2011) Standard Specification for Latex-Modified Concrete (LMC) Overlays
ACI 548.8 (2007) Specification for Type EM (Epoxy Multi-Layer) Polymer Overlay for Bridge and Parking Garage Decks
ACI 548.9 (2008) Specification for Type ES (Epoxy Slurry) Polymer Overlay for Bridge and Parking Garage Decks
ACI 548.10 (2010) Specification for Type MMS (Methyl Methacrylate Slurry) Polymer Overlays for Bridge and Parking Garage Decks
ACI 548.12 (2012) Specification for Bonding Hardened Concrete and Steel to Hardened Concrete with an Epoxy Adhesive
ASTM INTERNATIONAL (ASTM)
ASTM A775/A775M (2022) Standard Specification for Epoxy-Coated Steel Reinforcing Bars
ASTM A780/A780M (2020) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings
ASTM A934/A934M (2022) Standard Specification for Epoxy-Coated Prefabricated Steel Reinforcing Bars
SECTION 03 01 00 Page 2
ASTM C33/C33M (2024a) Standard Specification for Concrete Aggregates
ASTM C42/C42M (2020) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete
ASTM C496/C496M (2017) Standard Test Method for Splitting Tensile Strength of Cylindrical Concrete Specimens
ASTM C881/C881M (2020a) Standard Specification for Epoxy-Resin-Base Bonding Systems for Concrete
ASTM C882/C882M (2024) Standard Test Method for Bond Strength of Bonding Systems Used With Concrete by Slant Shear
ASTM C1059/C1059M (2024) Standard Specification for Latex Agents for Bonding Fresh to Hardened Concrete
ASTM C1077 (2026) Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation
ASTM C1438 (2013; R 2017) Standard Specification for Latex and Powder Polymer Modifiers for use in Hydraulic Cement Concrete and Mortar
ASTM C1583/C1583M (2013) Standard Test Method for Tensile Strength of Concrete Surfaces and the Bond Strength or Tensile Strength of Concrete Repair and Overlay Materials by Direct Tension (Pull-off Method)
ASTM C1602/C1602M (2022) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete
ASTM D93 (2019) Standard Test Methods for Flash-Point by Pensky-Martens Closed Cup Tester
ASTM D323 (2015a) Vapor Pressure of Petroleum Products (Reid Method)
ASTM D542 (2014) Index of Refraction of Transparent Organic Plastics
ASTM D1078 (2011) Standard Test Method for Distillation Range of Volatile Organic Liquids
ASTM D3418 (2015) Transition Temperatures of Polymers by Differential Scanning Calorimetry
SECTION 03 01 00 Page 3
ASTM D4016 (2014) Viscosity of Chemical Grouts by Brook field Viscometer (Laboratory Method)
ASTM D4580/D4580M (2012) Standard Practice for Measuring Delaminations in Concrete Bridge Decks by Sounding
ASTM E329 (2025b) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection
INTERNATIONAL CONCRETE REPAIR INSTITUTE (ICRI)
ICRI 310.2R (2013) Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, Polymer Overlays, and Concrete Repair
1.4 SUBMITTALS
Government approval is required for all submittals. Submit the following:
SD-01 Preconstruction Submittals
Qualifications
Work Plan
SD-03 Product Data
Conventional Concrete
Polymers
Miscellaneous Materials And Equipment
SD-05 Design Data
Formwork
Repair Procedures
Mixture Proportioning
SD-06 Test Reports
Mixture Proportioning
Quality Control
Conventional Concrete
Polymers
SECTION 03 01 00 Page 4
Miscellaneous Materials And Equipment
SD-07 Certificates
Qualifications
Reinforcement And Reinforcement Supports
Conventional Concrete
Polymers
SD-08 Manufacturer's Instructions Equipment For Concrete Preparation
1.5 QUALITY ASSURANCE
1.5.1 General Requirements
a. Follow the requirements of ACI 301 for Work involving portland cement concrete.
b. To protect personnel from overexposure to toxic materials, conform to the applicable manufacturer's Safety data sheets or local regulations.
Submit manufacturer's Safety Data Sheets for all polymers as well as other potentially hazardous materials.
c. Submit the repair procedures for executing the work as well as the test data and documentation on materials used for repair. Submittal must include component materials, mixture proportions, and supplier's quality control program.
d. Inspection and testing of surface preparation as well as placement of reinforcing steel must be in accordance with provisions included herein and the Contract Document.
e. Sampling and testing of materials, as well as inspection and testing of work, must be in accordance with established procedures, manufacturer's instructions, specific instructions from the Contracting Officer if given, or recommended practices as referenced herein and the Contract Documents.
f. Trial batches and testing requirements for various repair materials specified are the responsibility of the Contractor.
g. The testing agency must inspect, sample, and test repair materials and concrete production as required. When it appears that material furnished or work performed by Contractor fails to conform to Contract Documents the testing agency will immediately report such deficiency.
1.5.2 Qualifications
The submittals must where applicable, identify agencies and individuals who will be working on this contract and their relevant experience. Do not make changes in approved agencies or personnel without prior approval of the Contracting Officer.
SECTION 03 01 00 Page 5
1.5.2.1 Testing Agencies
, Agencies that test concrete materials must meet the requirements of ASTM C1077. Testing agencies that test or inspect placement of reinforcing steel must meet the requirement of ASTM E329. Submit data on qualifications of Contractor's proposed testing agency for acceptance.
1.5.2.2 Quality Control Personnel
Field tests of repair materials required must be made by an ICRI Concrete Surface Repair Technician Tier 2. Submit resumes, pertinent information, past experience, training and education of all operators of specialized demolition equipment if needed for this and the three paragraphs above.
1.5.2.3 Contractor Qualifications
The contractor performing the repair work must have been involved in a minimum of three concrete repair projects similar in size and scope to this project for at least five years. Submit information, including name, dollar value, date, and point-of-contact for similar projects which demonstrates the required experience and/or training.
1.5.2.4 Worker Qualifications
a. Each worker engaged in the use of specialized removal or application equipment, including saw operators hydromilling equipment operators, epoxy injection , must have satisfactorily completed an instruction program and three years of experience in the operation of the equipment. The worker must have active experience with the equipment within five years of the project.
b. Workers installing adhesive anchors must be ACI Adhesive Anchor Installer certified or equivalent.
1.5.2.5 Regulatory Requirements
Perform all work in accordance with applicable Federal, State, and local safety, health, and environmental requirements. The Contractor is responsible for obtaining all permits required by Federal, State, and local agencies for the performance of the work.
1.5.3 Work Plan
Prepare a work plan describing the methods of concrete removal and repair, including methods, equipment and materials to be used for each feature.
Submit the work plan for approval at least 30 days prior to the start of the work. The plan must include, but not be limited to, repair materials to be used with specific information on products and/or constituents, and requirements for handling, storage, etc., equipment to be used, surface preparation, and requirements for placement, finishing, curing and protection specific to the materials used. Include a description of field demonstrations in the work plan. Do not commence work until the work plan and field demonstration representative of the type of work are approved.
1.6 ACCEPTANCE OF REHABILITATION WORK
1.6.1 General Requirements
a. Completed concrete rehabilitation work must conform to applicable
SECTION 03 01 00 Page 6 requirements of Contract Document and this specification. The Contractor is responsible to bring Work into compliance with requirements of Contract Documents if the Concrete repair work fails to meet one or more requirements of Contract Documents.
b. Correct rejected repair work by removing and replacing or by strengthening with additional construction acceptable to the Contracting Officer. Use repair methods that meet applicable requirements for function, durability, dimensional tolerances, and appearance.
c. Submit proposed work plan , repair methods, materials, and modifications to the Work needed to correct rejected repair work to meet the requirements of Contract Documents.
1.6.2 Tolerances
a. Construction tolerances for repairs must conform to ACI 117 . Where existing conditions do not allow tolerances to conform to ACI 117 , use the details and materials for such conditions as indicated in the Contract Documents. For conditions not shown or that are different than indicated in the Contract Documents, notify the Contracting Officer before proceeding with the work at those locations.
b. Inaccurately formed concrete surfaces resulting in concrete members with dimensions that exceed ACI 117 tolerances are subject to rejection.
1.6.3 Appearance
Concrete surfaces not meeting the requirements of the Contract Documents must be brought into compliance.
1.7 PROTECTION OF COMPLETED REHABILITATION WORK
a. Do not allow construction loads to exceed the loads that a structural member or structure is safely capable of supporting without damage.
Provide supplemental support if construction loads are expected to exceed safe load capacity.
b. Protect repaired and adjacent areas from damage by construction traffic, equipment, and materials. During the curing period, protect repair materials from damage by mechanical disturbances, including load-induced stresses, shock, and vibration.
c. Protect repair materials from environmental damage by weather events during the length of the curing period.
PART 2 PRODUCTS
Products or materials used must conform to the requirements included herein as well as the Contract Documents. The usage of other products or materials not covered by this requirement or specified in the Contract Documents are permitted upon approval by the Contracting Officer.
Additional information and submittals for products and materials not included in this document including product data, samples, design data, test reports, certificates, manufacturer's instructions, and field reports must be submitted as requested by the Contracting Officer.
SECTION 03 01 00 Page 7
2.1 EQUIPMENT FOR CONCRETE PREPARATION
Means and methods used for concrete removal and surface preparation must be selected and used such as to minimize damage to the structure and to the concrete substrate that remains.
2.1.1 Equipment for Concrete Removal
Removal equipment and techniques must be suitable to produce concrete surface profiles and level of cleanliness in designated areas as required by this specification and the contract Documents.
2.1.1.1 Cutting Equipment
a. The following cutting equipment are permitted: High-pressure water jet without abrasives Saw cutting Diamond wire cutting Stitch drilling.
b. Cutting, lifting, and transporting equipment must be adequate to cut, support, and transport concrete sections without incurring any damage to the existing structure.
2.1.2 Surface preparation and cleaning equipment
2.1.2.1 Low Pressure Water Cleaning
Use equipment capable of delivering 1000 psi to to 5000 psi at 2 gal/min to 10 gal/min for cleaning loose material from repair areas.
2.1.2.2 Other Cleaning Equipment
Use equipment that delivers oil free air capable of cleaning loose material and debris from repair areas. If necessary to dry the concrete surface, clean, dry, compressed air may be used. Also, use vacuums capable of removing loose material and debris.
2.2 MATERIALS FOR FORMWORK AND EMBEDDED ITEMS
a. Formwork and embedded items must meet the requirements specified in
ACI 301 .
b. Install and remove formwork without damaging or staining the existing structure or repair material.
c. Forms used for polymer concrete/mortars must be tight enough to hold the material that is used without leaking. All surfaces where bond is not desired, but which are exposed to the monomer or resin, must be treated with a form release agent.
2.3 REINFORCEMENT AND REINFORCEMENT SUPPORTS
2.3.1 Steel Bars, Wires, and Fiber-reinforced Concrete
a. Reinforcement and reinforcement support must meet the requirements specified in ACI 301 .
b. Repair coating damage incurred during shipment, storage, handling, and placing of reinforcing bars in accordance with ASTM A780/A780M ASTM A775/A775M ASTM A934/A934M as appropriate . Damaged areas must not
SECTION 03 01 00 Page 8 exceed 2 percent of surface area in each linear foot of each bar.
c. Mechanical splices for coated reinforcement must have compatible coatings, in accordance with…
This is the start of the file's text. The full file is on GovTribe.