Contract Summary: Muskallonge Lake State Park Campground Road Improvements
This Project Manual and bidding document is issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design and Construction Division, in partnership with the Department of Natural Resources (DNR) for the Muskallonge Lake State Park Campground Road Improvements located at 29881 CO RD 407, Newberry, Michigan. The project consists of removal of existing hot mix asphalt (HMA), earth excavation, grading, clearing, select demolition, HMA paving, concrete paving and sidewalks, pavement markings, signage, soil erosion and sedimentation control (SESC), testing, and water and sewer construction within the campground. The campground will remain closed during construction. A mandatory prebid walk-through inspection is scheduled for Monday, August 12, 2024, at 1:00 p.m. at the project site. Bids are due electronically through the SIGMA VSS website by 2:00 p.m. Eastern time on Wednesday, August 28, 2024. The bid hold period is 60 calendar days. Contract time for substantial completion is no later than three months after the on-site construction start date or October 1, 2025, whichever is sooner, with final completion required 30 calendar days after substantial completion. Five alternates are included allowing the Owner to eliminate work at specific areas including ADA campsites, the day use area, Lake Superior Overlook Parking Lot, the sanitation station, and Section 3 campground loops.
Bidders must submit a 5% bid security in the form of a certified check, cashier's check, money order, or bid bond. The contract is a single prime contract with the State of Michigan as owner, and OHM Advisors serving as the professional engineer. Liquidated damages are assessed at $1,000 per calendar day for failure to achieve substantial completion by the specified date and $1,000 per calendar day for failure to achieve final completion. The project requires compliance with prevailing wage requirements, Michigan residency requirements for at least 50% of employees, and nondiscrimination provisions. Contractors must secure all required permits and licenses and comply with soil erosion and sedimentation control regulations under Michigan's Natural Resources and Environmental Protection Act. The project is anticipated to be funded through state resources, and the contractor must provide performance and payment bonds equal to 100% of the contract amount. All bids must be submitted electronically with a maximum of two attachments (each less than 6 MB), and contractors are advised not to wait until the last minute to submit due to system cutoff at the deadline.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
MUSKALLONGE LAKE
STATE PARK
CAMPGROUND ROAD
IMPROVEMENTS
DEPARTMENT OF TECHNOLOGY,
MANAGEMENT AND BUDGET
DTMB FILE NO. 751/22438.ABG
PROJECT NO. 7136-22-0122
Date: July 26, 2024 tnettell Snapshot
DTMB-0415 (R 10/22)
PROJECT ADVERTISEMENT
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE FACILITIES ADMINISTRATION
DESIGN & CONSTRUCTION DIVISION
This form is required for the advertisement of all construction projects. (1984 PA 431)
DTMB FILE NO. 751/22438.ABG
DATE
Friday, July 26, 2024
ADVERTISEMENT DATE
Friday, July 26, 2024
BID DUE DATE
Wednesday, August 28, 2024 @ 2:00 p.m.
EASTERN time
PROJECT NAME AND LOCATION (INCLUDE STREET ADDRESS)
Muskallonge Lake State Park Campground Road Improvements
29881 CO RD 407
Newberry, MI 49868
WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION
A mandatory prebid meeting will be held on Monday, August 12, 2024, at 1:00 p.m., at the project site.
Mandatory Yes No
NOTE: An individual is only permitted to represent one bidder at a mandatory walk-through.
DESCRIPTION OF WORK: The project consists of removal of existing HMA, earth excavation, grading, clearing, select demolition, HMA paving, concrete paving and sidewalks, pavement markings, signage, SESC, testing, and some water and sewer construction within the Muskallonge Lake State Park Campground. The campground will be closed during construction.
Please NOTE:
• Bid responses and bid attachments MUST be uploaded to SIGMA VSS.
• Contractors should only submit a maximum of two (2) attachments (both being less than 6 MB) for bid responses. One attachment is to be bid documents (Bid Summary, Bid Schedule, Bid Bond, Certification forms, Signature Authority, etc.) and if applicable, the other attachment should be Qualified Disabled Veteran (QDV) information (DD214, Proof of 51% Ownership and Proof of Service-Connected Disability)
•• Do not wait until just before the 2:00 p.m. solicitation deadline to submit your bid response.
SIGMA VSS will not allow a proposal to be submitted after 2:00 p.m., even if a portion of the bid response has been uploaded.
•• If you experience issues or have questions regarding your electronic submission, you must contact the SIGMA Help Desk for assistance prior to the 2:00 p.m., solicitation deadline. You may contact the SIGMA Help Desk by telephone at 517.284.0540 or toll-free at 888.734.9749. You may also email the SIGMA Help Desk at sigma-procurement-helpdesk@michigan.gov
• Please email the Design and Construction Contract Specialists if you are having SIGMA VSS issues. Please include your SIGMA ticket number and any supporting documentation (i.e., screenshots) to Anne Watros (WatrosA@michigan.gov) and Don Klein (KleinD4@michigan.gov).
• You may be asked by our contract specialists to email your bid response. Emailed submissions will require DCD approval and will be handled on a case-by-case basis.
• Approved emailed submissions MUST be received prior to 2:00 p.m. deadline to be considered responsive and responsible.
• Bid Responses should not be emailed to the Project Director.
5% Bid
Security: Required Not Required
NIGP CODES: 91327, 91336, 91345, 91360, 91347, 91394, 98814, 98832, 98863, 91275
ACCEPTING QUESTIONS UNTIL: Wednesday, August 21, 2024
Please do not submit online questions via SIGMA VSS. ALL questions should be emailed to Zane Hyrkas at zane.hyrkas@ohm-advisors.com no later than 2:00 p.m., Eastern on Wednesday, August 21, 2024.
Documents may be obtained from:
https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfServi ce
PSC/Agency: OHM Advisors
Address: 424 Hancock Street, Hancock, MI 49930
Phone: 906-482-0535
Email: taylor.nettell@ohm-advisors.com
Approved by:
This is a Cover Sheet to the State’s Owner and Contractor Standard Construction Contract, known as the MICHSPEC Division 0 Specifications. The MICHSPEC Division 0 Specifications have been developed from the FORMSPEC Michigan Model, 1997 Edition. Although the State’s 2008 Version of the Division 0 Specifications are written as simply as practical, it is nonetheless advisable to consult with companion Guide to Specifiers when preparing specifications for a specific project. These Division 0 Specifications were developed by incorporating provisions and requirements furnished by the State into the FORMSPEC Michigan Model. These Division 0 Specifications have undergone detailed technical reviews by Department of Technology, Management and Budget, State Facilities Administration representatives and detailed legal reviews by the Department of the Attorney General for the State of Michigan. Specifiers are encouraged to consult with a Division 0 specifications specialist or an attorney knowledgeable in public contracts when preparing specifications for a specific project.
STATE OF MICHIGAN
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE FACILITIES ADMINISTRATION
MICHSPEC 2008 VERSION, OWNER AND CONTRACTOR
STANDARD CONTRACT FORMS AND CONDITIONS OF THE CONTRACT
MICHSPEC No. 97.0820 − 00020 THROUGH 97.0820 − 00440
RELEASED ON NOVEMBER 1, 1997.
Developed from
Contract Forms and Conditions of the Contract
FORMSPEC Michigan Model and suggested for use with
Bidding Requirements
751/22438.ABG
Department of Natural Resources
Muskallonge Lake State Park Campground Road Improvements
Newberry, MI
July 26, 2024
1997 Edition/R 02/24 Version
STATE OF MICHIGAN (OWNER & CONTRACTOR) TABLE OF CONTENTS
MICHSPEC DTMB 00010 − 1 (R 02/24)
SECTION 00010 TABLE OF CONTENTS
SECTION/PAGE NO.
SUBJECT INDEX
SECTION 00020 GLOSSARY ............................................................................................................................................. 00020 - 1
SECTION 00030 ADVERTISEMENT .................................................................................................................................. 00030 - 1
SECTION 00100 INSTRUCTIONS TO BIDDERS ............................................................................................................... 00100 - 1
ARTICLE 1 BIDDING DOCUMENT INTERPRETATIONS .................................................................................................. 00100 - 1
ARTICLE 2 QUALIFICATIONS OF BIDDERS ..................................................................................................................... 00100 - 1
ARTICLE 3 BIDDING DOCUMENTS; SITE CONDITIONS; SAFETY REQUIREMENTS; LAWS ....................................... 00100 - 2
ARTICLE 4 INTERPRETATIONS; ADDENDA .................................................................................................................... 00100 - 3
ARTICLE 5 BID SECURITY ................................................................................................................................................ 00100 - 3
ARTICLE 6 CONTRACT TIME; LIQUIDATED DAMAGES .................................................................................................. 00100 - 4
ARTICLE 7 MATERIALS AND EQUIPMENT ...................................................................................................................... 00100 - 4
ARTICLE 8 SUBCONTRACTORS ...................................................................................................................................... 00100 - 5
ARTICLE 9 BID FORM AND BID FORM ATTACHMENTS ................................................................................................. 00100 - 5
ARTICLE 10 PREPARATION AND SUBMISSION OF BIDS.................................................................................................. 00100 - 6
ARTICLE 11 BID WITHDRAWAL; BID MODIFICATION ........................................................................................................ 00100 - 6
ARTICLE 12 BID OPENING; OBJECTION TO THE AWARD ................................................................................................ 00100 - 7
ARTICLE 13 BIDS TO REMAIN OPEN .................................................................................................................................. 00100 - 7
ARTICLE 14 AWARD OF THE CONTRACT .......................................................................................................................... 00100 - 7
ARTICLE 15 EXECUTION OF THE AGREEMENT ................................................................................................................ 00100 - 9
ARTICLE 16 MOBILIZATION PAY ITEM ............................................................................................................................. 00100 -10 ARTICLE 17 SOIL EROSION AND SEDIMENTATION CONTROL–FINE FOR NON-COMPLIANCE .................................. 00100 -10 ATTACHMENT A TO SECTION 00100: BIDDER'S CHECK LIST........................................................................................ 00110 - 1
SECTION 00120 SUPPLEMENTARY INSTRUCTIONS ..................................................................................................... 00120 - 1
SECTION 00210 INFORMATION FOR BIDDERS .............................................................................................................. 00210 - 1
SECTION 00300 BID SUMMARY ...................................................................................................................... 00300 - SUMMARY
SECTION 00300 BID FORM ............................................................................................................................................... 00300 - 1
ARTICLE 1 THIS BID IS SUBMITTED TO THE STATE OF MICHIGAN ("THE OWNER"). ................................................. 00300 - 1
ARTICLE 2 THE BIDDER'S REPRESENTATIONS ............................................................................................................... 00300 - 1
ARTICLE 3 TIME OF COMPLETION ..................................................................................................................................... 00300 - 2
ARTICLE 4 ATTACHMENTS INCLUDED WITH THIS BID .................................................................................................... 00300 - 2
ARTICLE 5 DEFINED TERMS ............................................................................................................................................... 00300 - 2
ARTICLE 6 BID SCHEDULE .................................................................................................................................................. 00300 - 3
ARTICLE 7 SCHEDULE OF CHANGE ORDER PRICES ...................................................................................................... 00300 - 5
ARTICLE 8 BID SUBMITTED ON ......................................................................................................................................... 00300 - 6
SECTION 00310 BID BOND ............................................................................................................................................... 00310 - 1
SECTION 00320 NONCOLLUSION AFFIDAVIT ................................................................................................................ 00320 - 1
SECTION 00410 BID BREAKDOWN ................................................................................................................................. 00410 - 1
SECTION 00420 QUESTIONNAIRE ................................................................................................................................... 00420 - 1
ARTICLE 1 ORGANIZATION ............................................................................................................................................... 00420 - 1
ARTICLE 2 SPECIALTY CONTRACTOR LICENSES .......................................................................................................... 00420 - 1
ARTICLE 3 EXPERIENCE ................................................................................................................................................... 00420 - 1
ARTICLE 4 ADDITIONAL QUALIFICATIONS ...................................................................................................................... 00420 - 2
ARTICLE 5 REFERENCES .................................................................................................................................................. 00420 - 2 REFERENCES ATTACHMENT ......................................................................................................................... 00420 - 3
SECTION 00430 LIST OF SUBCONTRACTORS ............................................................................................................... 00430 - 1
SECTION 00440 SCHEDULE OF MATERIALS AND EQUIPMENT .................................................................................. 00440 - 1
ARTICLE 1 BID MATERIALS AND EQUIPMENT −LISTED (NAMED OR SPECIFIED) ITEMS ........................................... 00440 - 1 ARTICLE 2 BID MATERIALS AND EQUIPMENT − OPEN SPECIFICATIONS .................................................................... 00440 - 3
SECTION 00500 AGREEMENT .......................................................................................................................................... 00500 - 1
ARTICLE 1 THE CONTRACT; THE PROJECT; THE WORK .............................................................................................. 00500 - 1
ARTICLE 2 CONTRACT DOCUMENTS .............................................................................................................................. 00500 - 1
ARTICLE 3 CONTRACT PRICE ........................................................................................................................................... 00500 - 2
ARTICLE 4 CONTRACT TIME; LIQUIDATED DAMAGES ................................................................................................... 00500 - 2
ARTICLE 5 PAYMENTS TO CONTRACTOR ...................................................................................................................... 00500 - 3
MICHSPEC DTMB 00010 − 2 (R 02/24)
ARTICLE 6 THE PROFESSIONAL SERVICES CONTRACTOR ......................................................................................... 00500 - 3
ARTICLE 7 CONTRACTOR'S REPRESENTATIONS .......................................................................................................... 00500 - 3
ARTICLE 8 MISCELLANEOUS ............................................................................................................................................ 00500 - 3
ARTICLE 9 NOTICE AND SERVICE .................................................................................................................................... 00500 - 4
SECTION 00520 ATTACHMENT “A” TO AGREEMENT ................................................................................................... 00520 - 1
SECTION 00610 PERFORMANCE BOND ........................................................................................................................ 00610 - 1
SECTION 00620 PAYMENT BOND ................................................................................................................................... 00620 - 1
SECTION 00700 GENERAL CONDITIONS ........................................................................................................................ 00700 - 1
ARTICLE 1 INTERPRETATIONS ........................................................................................................................................... 00700 - 1
1.1 Section 00020 Glossary:............................................................................................................................................... 00700 - 1
1.2 Intent of the Contract Documents: ................................................................................................................................ 00700 - 1
1.3 Priority of the Contract Documents: .............................................................................................................................. 00700 - 2
1.4 Interpretation of Indemnification Provisions: ................................................................................................................. 00700 - 2
1.5 Additional Interpretations: ............................................................................................................................................. 00700 - 2
1.6 Ownership and Use of the Contract Documents: .......................................................................................................... 00700 - 3
1.7 Copies of the Contract Documents: ............................................................................................................................... 00700 - 3
ARTICLE 2 THE OWNER−GENERAL PROVISIONS .......................................................................................................... 00700 - 3
2.1 Availability of Lands, Areas, Properties and Facilities: ................................................................................................. 00700 - 3
2.2 Reference Points; Base Lines and Benchmarks: .......................................................................................................... 00700 - 3
2.3 Stop Work Order: .......................................................................................................................................................... 00700 - 3
2.4 Limitations on the Owner’s Responsibilities: ................................................................................................................ 00700 - 4
2.5 Additional General Provisions: ...................................................................................................................................... 00700 - 4
2.6 Partnering Charter: ....................................................................................................................................................... 00700 - 4
ARTICLE 3 THE PROFESSIONAL − GENERAL PROVISIONS .......................................................................................... 00700 - 4
3.1 Owner’s Representative: ............................................................................................................................................. 00700 - 4
3.2 Clarifications and Interpretations: ................................................................................................................................. 00700 - 4
3.3 Minor Variations and No-Cost Changes; Minor Delays:................................................................................................ 00700 - 5
3.4 Determinations by the Professional: ........................................................................................................................... 00700 - 5
3.5 Limitations on the Professional’s Responsibilities: ....................................................................................................... 00700 - 5
ARTICLE 4 CONTROL OF WORK − GENERAL PROVISIONS ........................................................................................... 00700 - 5
4.1 Review of the Contract Documents: ............................................................................................................................. 00700 - 5
4.2 Management, Supervision, and Personnel: .................................................................................................................. 00700 - 5
4.3 Materials and Equipment: ............................................................................................................................................. 00700 - 6
4.4 Concerning Control of Work: ........................................................................................................................................ 00700 - 6
4.5 Patent Fees and Royalties: ........................................................................................................................................... 00700 - 7
4.6 Use of Premises: .......................................................................................................................................................... 00700 - 7
4.7 Record Documents: ...................................................................................................................................................... 00700 - 7
4.8 Emergencies: ................................................................................................................................................................ 00700 - 8
4.9 Indemnification: ............................................................................................................................................................ 00700 - 8
ARTICLE 5 SUBCONTRACTORS AND SUPPLIERS .......................................................................................................... 00700 - 8
5.1 Employment of Subcontractors: .................................................................................................................................... 00700 - 8
5.2 "Or Equal" and Substitute Materials and Equipment:.................................................................................................... 00700 - 9
5.3 The Contractor’s Continuing Responsibilities: ............................................................................................................ 00700 - 9
ARTICLE 6 SUBMITTALS .................................................................................................................................................... 00700 - 9
6.1 Shop Drawing, Sample and Other Technical Submittals: ............................................................................................. 00700 - 9
6.2 Review and Return of Technical Submittals: .............................................................................................................. 00700 - 10
6.3 Progress Schedule Submittals: ................................................................................................................................... 00700 - 10
6.4 Review and Return of Progress Schedule Submittals: ............................................................................................... 00700 - 10
6.5 Additional Provisions Concerning Submittals: ............................................................................................................ 00700 - 10
ARTICLE 7 LEGAL REQUIREMENTS; INSURANCE ........................................................................................................ 00700 - 11
7.1 Laws; Permits (Which Include Approvals and Licenses): ........................................................................................... 00700 - 11
7.2 Sales and Use Tax and Other Similar Taxes: ............................................................................................................. 00700 - 12
7.3 Safety and Protection: ................................................................................................................................................ 00700 - 12
7.4 Bonds and Insurance - General Requirements: .......................................................................................................... 00700 - 12
7.5 The Contractor’s Liability Insurance:......................................................................................................................... 00700 - 12
7.6 Pollution Liability Insurance: ....................................................................................................................................... 00700 - 13
7.7 Property Insurance (Builder's All Risk Insurance): ...................................................................................................... 00700 - 13
7.8 Waiver of Rights: ........................................................................................................................................................ 00700 - 13
7.9 Receipt and Application of Proceeds: ......................................................................................................................... 00700 - 13
MICHSPEC DTMB 00010 − 3 (R 02/24)
7.10 Unfair Labor Practice: ................................................................................................................................................. 00700 - 13
7.11 Michigan Right-To-Know Law: .................................................................................................................................... 00700 - 13
7.12 Nondiscrimination: ...................................................................................................................................................... 00700 - 14
7.13 Michigan Residency for Employees: .......................................................................................................................... 00700 – 14
7.14 Prevailing Wages: ...................................................................................................................................................... 00700 – 14
ARTICLE 8 PROSECUTION; SUBSTANTIAL COMPLETION ........................................................................................... 00700 - 15
8.1 Starting the Work: ....................................................................................................................................................... 00700 - 15
8.2 Revision 0 (Rev. 0) Schedule and Cost Submittals: ................................................................................................... 00700 - 15
8.3 Compliance with Contract Time Requirements: .......................................................................................................... 00700 - 15
8.4 Substantial Completion: .............................................................................................................................................. 00700 - 15
8.5 Partial Use: ................................................................................................................................................................. 00700 - 16
8.6 Division of Responsibilities: ........................................................................................................................................ 00700 - 16
8.7 Suspension of Work: .................................................................................................................................................. 00700 - 16
8.8 Sharing of Total Float on Non-Critical Paths: .............................................................................................................. 00700 - 16
ARTICLE 9 WARRANTY; TESTS, INSPECTIONS, AND
APPROVALS; CORRECTION OF WORK ....................................................................................................... 00700 - 17
9.1 Warranty: ................................................................................................................................................................... 00700 - 17
9.2 Tests, Inspections and Approvals: ............................................................................................................................. 00700 - 17
9.3 Uncovering Work: ...................................................................................................................................................... 00700 - 17
9.4 Correction of Work: .................................................................................................................................................... 00700 - 17
9.5 Special Correction Period Requirements: .................................................................................................................. 00700 - 18
9.6 Special Maintenance Requirements: ......................................................................................................................... 00700 - 18
ARTICLE 10 CHANGES ..................................................................................................................................................... 00700 - 19
10.1 Changes in the Work: ................................................................................................................................................ 00700 - 19
10.2 Differing Subsurface or Physical Site Conditions: ...................................................................................................... 00700 - 19
10.3 Responsibilities for Underground Utilities: ................................................................................................................. 00700 - 20
10.4 Hazardous Material Conditions: ................................................................................................................................. 00700 - 20
10.5 Incidents with Archaeological Features: .................................................................................................................... 00700 - 20
10.6 Unit Price Work: ......................................................................................................................................................... 00700 - 21
10.7 Cash Allowances; Provisionary Allowances: ............................................................................................................. 00700 - 21
10.8 Change Orders; Change Authorizations: ................................................................................................................... 00700 - 21
ARTICLE 11 CHANGES IN CONTRACT PRICE; CHANGES IN
CONTRACT TIME ......................................................................................................................................... 00700 - 22
11.1 General Provisions: ................................................................................................................................................... 00700 - 22
11.2 Changes in Contract Time: ........................................................................................................................................ 00700 - 22
11.3 Methods for Making Adjustments in Contract Price: .................................................................................................. 00700 - 22
11.4 Labor, Subcontract and Material/Equipment Costs: .................................................................................................. 00700 - 23
11.5 Construction Equipment Costs: ................................................................................................................................. 00700 - 23
11.6 Rented or Leased Construction Equipment: .............................................................................................................. 00700 - 23
11.7 Owned Construction Equipment: ............................................................................................................................... 00700 - 24
11.8 General Conditions Costs: ......................................................................................................................................... 00700 - 24
11.9 Limitations on Allowable Costs: ................................................................................................................................. 00700 - 24
11.10 Costs Covered by the Fee for the Work Involved (and not Allowable as Cost of the Work Involved): ........................ 00700 - 24
11.11 Limits on the Fee for the Work Involved: .................................................................................................................... 00700 - 25
11.12 Fee for Unabsorbed Home Office Overhead: ............................................................................................................. 00700 - 25
11.13 Changes in Contract Time for Early Completion: ........................................................................................................ 00700 - 25
11.14 Access to Records: ..................................................................................................................................................... 00700 - 26
11.15 Price Reduction for Defective Cost and Pricing Data: ................................................................................................ 00700 - 26
ARTICLE 12 PROGRESS PAYMENTS; FINAL PAYMENT ............................................................................................... 00700 - 26
12.1. Schedule of Values: ................................................................................................................................................... 00700 - 26
12.2 Requests for Payment: .............................................................................................................................................. 00700 - 27
12.3 Review of Request for Payment; Intent of Review: .................................................................................................... 00700 - 27
12.4 Refusal to Make or to Recommend Payment: .......................................................................................................... 00700 - 27.
12.5 Final Request for Payment: ....................................................................................................................................... 00700 - 27
12.6 Final Payment and Acceptance: ................................................................................................................................ 00700 - 28
12.7 Contractor’s Continuing Obligation: ......................................................................................................................... 00700 - 28
12.8 Waiver of Claims: ...................................................................................................................................................... 00700 - 28
ARTICLE 13 OTHER WORK .............................................................................................................................................. 00700 - 28
13.1 Related Work at Site: ................................................................................................................................................. 00700 - 28
13.2 Coordination Requirements: ...................................................................................................................................... 00700 - 29
13.3 Claims Between the Contractor and Other Parties: ................................................................................................. 00700 - 29
MICHSPEC DTMB 00010 − 4 (R 02/24)
ARTICLE 14 TERMINATION .............................................................................................................................................. 00700 - 29
14.1 Notice Requiring Assurance of Due Performance: .................................................................................................... 00700 - 29
14.2 Contractor Default and Termination for Cause: ........................................................................................................ 00700 - 30
14.3 Surety Default: ........................................................................................................................................................... 00700 - 31
14.4 Termination for Convenience of the Owner: .............................................................................................................. 00700 - 31
14.5 The Contractor May Suspend Work: ....................................................................................................................... 00700 – 31
ARTICLE 15 DISPUTES .................................................................................................................................................... 00700 - 31
15.1 Claims Under This Article: ......................................................................................................................................... 00700 - 31
15.2 Requirement for Certification of Contractor Claims: ................................................................................................. 00700 - 32
15.3 Recommendations or Decisions from the Professional:........................................................................................... 00700 - 32
15.4 Determinations by the Director-DCD: ....................................................................................................................... 00700 - 32
15.5 Supplements to AAA Arbitration: ............................................................................................................................... 00700 - 33
15.6 Interest on a Judgment; Payment of Judgment: ........................................................................................................ 00700 - 33
15.7 Venue; Flow-Through Provision: ............................................................................................................................... 00700 - 33
SECTION 00800 SUPPLEMENTARY CONDITIONS ....................................................................................................... 00800 - 1
SUMMARY 01 10 00
ALTERNATES 01 23 00
SUBSTITUTION PROCEDURES 01 25 00
PROJECT MANAGEMENT AND COORDINATION 01 31 00
SUBMITTAL PROCEDURES 01 33 00
QUALITY REQUIREMENTS 01 40 00
TEMPORARY FACILITIES AND CONTROLS 01 50 00
PRODUCT REQUIREMENTS 01 60 00
EXECUTION 01 73 00
CLOSEOUT PROCEDURES 01 77 00
OPERATION AND MAINTENANCE DATA 01 78 23
PROJECT RECORD DOCUMENTS 01 78 39
SECTION 01310 PROGRESS SCHEDULE ...................................................................................................................... 01310 - 1
DRAWINGS - BOUND SEPARATELY
TITLE SHEETS THRU
COVER DT
NOTES C-001
LEGEND C-010
BORINGS 1 C-090
BORINGS 2 C-091
BORINGS 3 C-092
BORINGS 4 C-093
BORINGS 5 C-094
EXISTING CONDITIONS – OVERALL C-110
EX CONDITIONS – ACCESS RD, SAN. & CONTACT STATION PARKING LOT C-111
EX CONDITIONS – ACCESS RD & DAY USE AREA C-112
EX CONDITIONS – SECTION 3 C-113
EX CONDITIONS – SECTION 1 & 2 C-114
EX CONDITIONS – OVERLOOK PARKING LOT C-115
REMOVAL PLAN – ACCESS RD, SAN. & CONTACT STATION P. LOTS C-120
REMOVAL PLAN – ACCESS RD, CUL-DE-SAC, AND DAY USE AREA C-121
REMOVAL PLAN – SECTION 3 C-122
REMOVAL PLAN – SECTIONS 1 & 2 C-123
REMOVAL PLAN – OVERLOOK PARKING LOT C-124
SITE PLAN – ACCESS RD, SAN. & CONTACT STATION P. LOTS C-130
SITE PLAN – ACCESS RD, CUL-DE-SAC, & DAY USE AREA C-131
SITE PLAN – SECTION 3 C-132
SITE PLAN – SECTIONS 1 & 2 C-133
SITE PLAN – OVERLOOK PARKING LOT C-134
UTILITY PLAN – ACCESS RD, SAN. & CONTACT STATION P. LOTS C-135
UTILITY PLAN – ACCESS RD, CUL-DE-SAC, & DAY USE AREA C-136
UTILITY PLAN – SECTION 3 C-137
UTILITY PLAN – SECTION 1 & 2 C-138
MICHSPEC DTMB 00010 − 5 (R 02/24)
GRADING PLAN – ACCESS RD, SAN. & CONTACT STATION P. LOTS C-140
GRADING PLAN – ACCESS RD, CUL-DE-SAC, & DAY USE AREA C-141
GRADING PLAN – SECTION 3 C-142
GRADING PLAN – SECTIONS 1 & 2 C-143
GRADING PLAN – OVERLOOK PARKING LOT C-144
GRADING PLAN – ADA SITES C-145
ACCESS ROAD STA 0+00 TO 20+25 PROFILES C-150
DAY USE AREA STA 0+00 TO 7+48 PROFILES C-151
LOOP 1A STA 30+00 TO 48+20 PROFILES C-152
LOOP 1B STA 50+00 TO 61+80 PROFILES C-153
LOOP 2A STA 60+00 TO 70+81 & STA 80+00 TO 89+20 PROFILES C-154
LOOP 3A STA 90+00 – 98+44 & LOOP 3B STA 100+00 – 107+44 PROFILES C-155
LOOP 3C STA 110+00 TO STA 116+55 PROFILES C-156
DETAILS C-501
DETAILS C-502
SANITATION STATION DETAILS C-503
TYPICAL CROSS SECTIONS C-504
TECHNICAL SPECIFICATIONS
SELECTIVE DEMOLITION 02 41 19
CAST-IN-PLACE CONCRETE 03 30 00
SITE CLEARING 31 10 00
EARTH MOVING 31 20 00
ASPHALT PAVING 32 12 16
CONCRETE PAVING 32 13 13
CONCRETE PAVING JOINT SEALANTS 32 13 73
PAVEMENT MARKINGS 32 17 23
TURF AND GRASSES 32 92 00
DISINFECTION OF WATER UTILITY PIPING SYSTEMS 33 01 10.58
AIR TESTING 33 05 05.41
THRUST RESTRAINT FOR UTILITY PIPING 33 05 09.33
SITE WATER SERVICE UTILITY LATERALS 33 14 17
VALVES AND HYDRANTS FOR WATER UTILITY SERVICE 33 14 19
SANITARY SEWERAGE PIPING 33 31 00
STORMWATER CONVEYANCE 33 42 00
STATE OF MICHIGAN (OWNER AND CONTRACTOR) GLOSSARY
MICHSPEC DTMB 00020 - 1 (R 02/24)
SECTION 00020 GLOSSARY
1.1 Defined Terms:
1.1.1. The following terms or relative pronouns used in
Division 0 of the Specifications have these intent and meanings:
Activity− An element in the Progress Schedule establishing a requisite step, or the time and resources required, for completing the part of the Work associated with that Activity.
Addenda− Written instruments that are used by the Owner and/or Professional to incorporate interpretations or clarifications, modifications, and other information into the Bidding Documents. An Addendum issued after Bid opening to those Bidders who submitted a Bid, for the purpose of rebidding the Work without readvertising, is referred to as a post-Bid Addendum.
Agreement− The written agreement between the Owner and Contractor covering the Work to be furnished and performed.
Alternate− Refers to Work specified in the Bidding Documents for which the Bidder shall bid a Bid Price in the space provided in the Schedule of Alternates in Section 00300 Bid Form.
Apparent Low Bidder:- Those Bidders whose Base Bid, when added to those specific Alternates the Owner intends to accept, yields the three lowest sums of Base Bid and Alternates. Additional Bidders may be considered Apparent Low Bidders if their Base Bid, when added to those specific Alternates the Owner intends to accept, yields a sum within 10% of the lowest of the Apparent Low Bidder’s sum. If a qualified disabled veteran meets the requirements of the contract solicitation and with the veteran’s preference is the lowest Bidder is considered the Apparent Low Bidder.
Archaeological Feature− Any prehistoric or historic deposit of archaeological value, as determined by a representative of a State agency that is duly authorized to evaluate such findings and render such judgments. An Archaeological Feature deposit may include, but is not limited to Indian habitations, ceremonial sites, abandoned settlements, treasure trove, artifacts, or other objects with intrinsic archaeological value and that relate to the history and culture of the State of Michigan.
As-Planned Schedule− The Contractor’s Revision 0 Progress Schedule returned to the Contractor as "Resubmittal Not Required," with or without comments or objections noted.
Authorized Technical Data− Information and data contained in a report of exploration and tests of subsurface conditions that are expressly designated in paragraph 2.0 of Section 00210 Information for Bidders. Also, any physical data (dimension, location, conditions, etc.) contained in those drawings of physical conditions of existing surface and subsurface facilities identified in paragraph 3.0 of Section 00210 Information for Bidders.
Bar Chart Schedule− Activity schedule, in a bar chart format, that accounts for the entire Work at a level of detail commensurate with the Progress Schedule requirements of the Contract Documents.
STATE OF MICHIGAN MODEL
Developed from FORMSPEC Michigan Model.
Bid− Written offer by a Bidder for the Work, as specified, which designates the Bidder’s Base Bid and Bid Prices for all Alternates. The term Bid includes a Rebid.
Bidder− The Person acting directly, or through an authorized representative, who submits a Bid directly to the Owner.
Bidding Documents− The proposed Contract Documents as advertised, and all Addenda issued before Bid opening, and after Bid opening, if the Work is rebid without readvertising.
Bid Price− The Bidder's price for a lump sum item of Work, or the product of the Bidder's unit price for an item of Unit Price Work times the quantity given on the Bid Form for that item.
Bid Security− A security serving as a guarantee that the Bidder will conform to all conditions requisite for its return or as liquidated damages in the event of failure or refusal to conform.
Bidding Requirements− The Advertisement, Instructions to Bidders (including Attachment A), Supplementary Instructions, Information for Bidders, Bid Form, Bid Form Attachments and Qualification Submittals, as advertised and as modified by Addenda, and any other Section included within Division 0 of the Bidding Documents for the purpose of governing bidding and award of the Contract.
*AD Board− The Administrative Board of the State of Michigan.
Bonds− Section 00310 Bid Bond, Section 00610 Performance Bond and Section 00620 Payment Bond are security furnished by the Contractor, as required by the Contract Documents.
Business Day− Any Day except Saturdays, Sundays and holidays observed by the Owner.
Bulletin− A standard DTMB or other PSC form used by the PSC & Owner to describe a change in the Work under consideration by the Owner and to request the Contractor to submit a proposal for the corresponding adjustment in Contract Price and/or Contract Time, if any.
Calendar Day− Every day shown on the calendar, Saturdays, Sundays, and holidays included.
Cash Allowance− An Owner-specified sum included within the Contract Price to reimburse the Contractor for the actual purchase/furnished cost of materials and/or equipment or other designated items, as specifically provided in the Contract Documents. Although the scope (e.g., the required quantity) of any Work covered by a Cash Allowance is sufficiently
MICHSPEC DTMB 00020 - 2 (R 02/24)
detailed in the Contract Documents for the purposes of bidding the required labor costs, Subcontract costs, construction equipment costs and general conditions costs and Fee, it is understood that the required materials, equipment or other designated items are of uncertain purchase cost at the time of Bid or are yet to be specified in more detail by the Professional as to quality, appearance, durability, finish and such other necessary features affecting purchase price.
Change Authorization− A written order issued and signed by the Professional, which directs changes in the Work that require no adjustment in Contract Price or Contract Time, or which allows for variations in the quantities of Unit Price Work.
Change Order− A written order issued and signed by the Owner, which amends the Contract Documents for changes in the Work or an adjustment in Contract Price and/or Contract Time, or both.
Construction Mechanic− A skilled or unskilled mechanic, laborer, worker, helper, assistant, or apprentice working on a state project but shall not include executive, administrative, professional, office, or custodial employees
Contact Person− Individual in the employ of the Professional or the Owner who is designated as the sole point of contact for prospective Bidders for requests or inquiries concerning the Work and/or the Bidding Documents.
Contract− Refer to the definition in paragraph 1.1 of Section 00500 Agreement. The term “Contract” encompasses the legal obligations of the Owner and Contractor, as defined by the Contract Documents.
Contract Award− The official action of the Board, the Director-SFA or the Director-DCD awarding the Contract to the Contractor.
Contract Documents− Those documents itemized or designated in paragraphs 2.2 through 2.4 of Section 00500 Agreement.
Contract Float− Calendar Days between the Contractor's anticipated date for early completion of the Work, or of a specified portion of the Work, if any, and the corresponding Contract Time.
Contract Price− The Contract price for the Work, or a designated portion of the Work, as designated in Section 00500 Agreement or elsewhere in the Contract Documents, is the total compensation, including authorized adjustments, payable by the Owner to the Contractor (subject to provisions for Unit Price Work).
Contract Times− The Contract Times for the entire Work are the periods allowed, including authorized adjustments, for Substantial Completion and final completion of the Work. The Contract Times for a designated portion of the Work are the periods allowed for Substantial Completion and final completion of any such portion of the Work, as specified in the Contract Documents.
Contractor− Person named "the Contractor" in Section 00500 Agreement with whom the Owner has entered into the Contract.
Correction Period− The period during which the Contractor shall, in accordance with the Contract Documents, (a) correct or, if rejected, remove, and replace Defective Work, and (b) maintain warranties for materials and equipment in full force and effect.
Cost of the Work Involved− The sum of all costs that would be, or were, necessarily incurred by the Contractor in providing any Work Involved with the related change, less the costs that would be, or would have been, incurred by the Contractor to provide such Work without the related change.
CPM Schedule− Computerized, Activity-based Progress Schedule, using Critical Path Method (CPM) techniques, and accounting for the entire Work at a level of detail commensurate with the Progress Schedule requirements of the Contract Documents.
Critical Path Method (CPM)− The Critical Path Method of planning and scheduling. The term “Critical Path” denotes a sequence of Activities controlling achievement of a specified Contract Time.
Date of Commencement of the Contract Time− The date when the Contract Time starts to run.
Defective− An adjective which when referring to or when applied to the term “Work” refers to (a) Work not conforming to the Contract Documents or not meeting the requirements of any inspection, test, or approval, or (b) Work itemized in a Punch List which the Contractor fails to complete or correct within a reasonable time after issuance of the Punch List by the Professional.
Defective Work/Non-Compliance Notice – A DTMB-0499 form or equivalent issued to identify defective or non-compliant conditions requiring response and remedy by the Contractor.
Delay− Any act or omission or other event that in any manner adversely affects or alters the schedule, progress or completion of all or any part of the Work. Delay is a generic term intended to include deferral, stoppage, slow down, interruption and extended performance, and all related hindrance, rescheduling, disruption, interference, inefficiency and productivity and production losses.
*Department (DTMB)− Department of Technology, Management and Budget of the State of Michigan. Director is the Director of the Department.
Director-SFA- The Director of DTMB State Facilities Administration.
Director-DCD-…